TransCoil ESP System Testing Analysis Report WHTP
TransCoil ESP System Testing Analysis Report WHTP
rigless-deployed
ESP system
Product testing and analysis report
Executive summary
36-in. (914-mm) radius and
then returned to straight using
a bending fatigue test machine
This report outlines the equipment tests and calculated (see Figure 1).
tests used to validate the TransCoil™ rigless-deployed Test results showed that the
electrical submersible pumping (ESP) system. Included are power cable can withstand the
component testing and in-house system integration testing equivalent of more than 180
(SIT), with the following primary areas of focus: trips in and out of a well before
• Thermal expansion during operation being compromised. Test failure
was noted when the cable was
• Tensile strength of all components
no longer able to contain its 500
• Bending stresses of the TransCoil system power cable psi preload (see Figure 2).
• Fatigue testing
Tensile testing (production)
• Finite element analysis (FEA)
The strip material in the power Figure 2: Sample of a failure
cable used with the TransCoil point after the equivalent of
180 trips in and out of the well
ESP system was in the
Component testing un-annealed condition. Some
cold work hardening occurs during the forming process.
Due to the materials that make up the power cable,
This section deals with all of the parts and sub-assemblies
it cannot be annealed like normal coiled tubing.
included in the final TransCoil system assembly.
Tensile tests were completed for each run of cable.
TransCoil system power cable testing These tests provided material strength for the
Each new design and material used in the TransCoil system as-manufactured condition.
power cable was subjected to a battery of tests carried out The tensile strength has to be sufficient for the power cable
at both the Baker Hughes, a GE Company (Baker Hughes), to support its own weight, the weight of the ESP system, and
Artificial Lift Research and Technology Center (ALRTC) the weight of other tools that may be in the string. Pump
in Claremore, Oklahoma, and the Baker Hughes thrust acting on the string also adds to the weight carried by
Coiled Tubing Research and Engineering Center in the coiled tubing. These factors control the depth of install.
Calgary, Alberta, Canada.
Pressure testing (Production)
Bending fatigue testing (prototype) The proprietary manufacturing process includes a pressure
During installation, the power cable used with the TransCoil test to ensure that there are no leaks before the deployment
ESP system was subjected to low-cycle bending fatigue cable leaves the factory (see Figure 3).
(similar to a coiled tubing string). Bending fatigue testing
was required in order to obtain a baseline fatigue life for the
materials selected.
Samples of the power cable were cut to 8-ft (2.43-m) lengths
and capped at both ends. 500 psi (34.48 bar) internal
pressure was applied and the cable was bent around a
Figure 1: Bending fatigue test machine Figure 3: Pressure test setup for the power cable
This analysis is critical in finding high stress areas of a design This testing allows us to define proper torque settings for
that can be corrected before the design is prototyped. tightening the slips nut during installation.
It can also help with reducing weight and saving costs in
part design. Electrical connection (installation)
Typical items that an FEA are run on include bolted or The electrical connection between the motor and the
threaded flange connections, coiled tubing hanger bodies, power cable sets the TransCoil system apart from all
slips, and splices (see Figure 8). rigless-deployed ESP systems available in the market.
With the power cable encased inside a protective enclosure,
the electrical connections are entirely sealed off from well
fluid (see Figure 10), completely eliminating the need for a
traditional ESP motor connector.
Figure 10: Electrical connection from the ESP motor to the power cable, with
the shear sub shown in blue
Figure 8: FEA snapshot showing slips tooth penetration of the tubing at Shear sub design and testing (prototype)
95,000 lb (43 090 kg) loading
The shear sub is tailored for each application. The shear
force required is determined by the weight of the ESP and the
tools hanging from it.
Shear pins can be added or removed to achieve the desired
shear force. The shear sub is set to shear at a weight that is
greater than that of the equipment below it and less than the
yield strength of the tubing.