4 Properties of Formaldehyde
4 Properties of Formaldehyde
CONTENTS
1. Acknowledgement
2. Summary
3. Introduction
4. Properties of Formaldehyde
Physical properties
Chemical properties
Method of analysis
ACKNOWLEDGEMENT
This project is the result of the continuous guidance and encouragement of the
teachers of The Department of Chemical Engineering and Technology, IIT-BHU.
I express my deep sense of gratitude and reverence to Prof. A.S.K. Sinha, Head of
Department, Department of Chemical Engineering and Prof. P. Ahuja, Prof. KK
Singh, Dr. VL Yadav and Dr. Pradeep Kumar, Project Coordinators, for providing
us the opportunity to work in this project, for their scrupulous supervision and
being available for us to sort out any kind of trouble in the way.
Finally, I would like to thank all my batch-mates for their unalloyed helping hands
which provided us with both material and moral support throughout the project.
Shivam Singh
10102EN067
B.Tech. Part-IV
During this study we will consider many aspects including the entire plant‟s process
unit design, process flow diagrams, cost estimations, operation parameters,
equipment sizing, construction materials and environment/safety precautions.
This project requires the theoretical and practical application of mass transfer,
heat transfer, fluid dynamics, unit operations, reaction kinetics and process
control. There are several tasks that are crucial to the completion of the project
outlines including mass and energy balances, design of the reactor, design of heat
exchangers, design of the absorber and distillation column, energy optimization,
economic analysis and hazard analysis.
PROBLEM INFORMATION
The standard enthalpies of these two reactions are ΔHo1 = -156 KJ and ΔHo2 = 85
KJ respectively. The first exothermic reaction produces around 50 % -- 60 % of the
total formed formaldehyde. The rest is formed by the second endothermic
reaction.
The reactor in this project‟s problem is to receive two streams; the first is a
mixture of fresh methanol and recycled methanol. The second stream to the
reactor mixed with the first is compressed fresh air.
The absorber receives the reactor‟s outlet and afresh stream of water. Absorption
of 99% is expected. The distillation column receives the liquid then separates the
overhead methanol stream then recycles it back to methanol fresh feed mixing
point.
The bottom formaldehyde stream is pumped and mixed with deionized water
forming (37 wt. % formaldehyde) formalin stream which sent for storage. The
mixing is presented as follows:
The catalyst to be implemented in the reactor‟s design is silver wired gauze layers
or catalyst bed of silver crystals. The catalyst is spherical with 1mm diameter and
a void fraction or porosity of 0.5. The common design of the silver catalyst is a thin
shallow catalyzing bed with a thickness of 10 to 55 mm.
The usual life span of this catalyst is three to eight months, where the silver can
be recovered. The purity of the feed flow rates is very crucial due to the fact that
the catalyst is very receptive to poisoning that would kill the reaction and reduces
the production to zero if traces of sulfur or a transition metal are present.
This section includes all the major participating materials to the production plant.
These properties are based upon operating conditions of the plant‟s design:
In the mid-1970s, the production was 54% of capacity. Annual growth rate of
formaldehyde was 2.7% per year from 1988 to 1997. In 1992, formaldehyde ranked
22nd among the top 50 chemicals produced in the United States. The total annual
formaldehyde capacity in 1998 was estimated by 11.3 billion pounds. Since then
and the production capacity around the globe is expanding exponentially reaching
a world‟s production of 32.5 million metric tons by 2012.
Due to its relatively low costs compared to other materials, and its receptivity for
reaching high purities, formaldehyde is considered one of the most widely
demanded and manufactured materials in the world. It is also the centre of many
chemical researches and alternative manufacture methods.
This also explains the vast number of applications of this material including a
building block for other organic compounds. Formaldehyde is a very versatile
chemical and it is used in many industries, including -
One of the main use of Formaldehyde is formaldehyde based resins. Most of the
formaldehyde produced in the world is used for this. Different resins are made
from formaldehyde using different substrates. One of the most popular is Urea-
Formaldehyde resin. Its major use is as adhesives and it is also used as a binder for
glass fibre roofing materials. We will now discuss the various productions methods
available.
HCHO → CO + H2
This process is based on the air oxidation of the methanol under “Lean”, i.e. low
methanol concentration, conditions to avoid the explosive range.
The reactions occur over a mixed oxide catalyst containing molybdenum oxide and
iron oxide in the ratio 1.5 to 3. The reaction temperature is around 550o F and the
reaction is slightly over atmospheric pressure. An excess air is used to ensure a
near complete and to avoid the explosive range for methanol.
Fresh methanol is mixed with air plus recycled gas in a steam-heated vaporizer.
The effluent from this device is fed to the reactor, which is of the vertical packed-
tubular type. The reacting gas mixture flows downward through the tubes and
transfers its heat of reaction to a circulating heat transfer medium on the shell
side of the reactor.
The heat transfer medium in turn vaporizes the feed water to produce steam at
pressures up to about 25 atmosphere .The catalyst is granular or spherical
supported Fe/Mo and has aging characteristics such that over the period of its life
(12-15 months) the bed temperature must be increased from about 450 – 550 o F.
The exit gases from the reactor pass through a heat recovery exchanger, where
low pressure steam is generated, and thence to the absorption column where
water is used as the scrubber column.
The absorber can be either of the packed or the tray type. The top of the absorber
is kept at a low temperature in order to ensure adequate removal of formaldehyde
from the overhead gases. The bottom stream from the absorber represents the
final product. Because the reaction conditions promote more formic acid than do
those for the silver process, it is necessary to remove this acid by ion exchange
method.
A large portion of the absorber overhead is recycled back to the feed system. This
permits the methanol content of the reactor feed to be as high as 9.0 volume%
and causes a dilution of the gas from the absorber to the point that is not always
necessary to provide further treatment of the gas discharged from the system. For
this reason, the absorption column in this process is higher than that foe silver
catalyst process.
Studies of the two processes based on the nominal size of 100,000,000 lb/yr of 37%
formaldehyde solution showed that the silver process was far economical than the
oxide process. It was found that the capital cost of the silver process was about
20% lower than the oxide process with manufacturing cost essentially the same.
The conversion of methanol to formaldehyde in the improved silver process is
normally between 77% and 95%, while in the older it is about 55%. So, conversion is
also not a problem anymore.
The most radical improvements in the silver catalyst process have been made by
BASF and are now used commercially. A different form of the catalyst, a higher
reaction temperature, and changes in reactor feed composition have made
possible a high methanol conversion; thus, it is no longer necessary to recover
unreacted methanol. Maximum size of a production unit has also been increased by
these changes.
This process is based on partial oxidation and reduction process at 600 °C on silver
grains, works with the excess of methanol above the upper explosion limit of the
mixture methanol-air.
HCHO → CO + H2
The reaction occurs over a silver catalyst at typical conditions of (560-620oC) and
pressure slightly over atmosphere. Methanol conversion is 65- 75 % per pass. Since
the reactor feed is kept on the rich side of the explosive limit, all the oxygen is
converted .Unreacted methanol is separated from the reaction mixture and
recycled.
A flow diagram is shown. Fresh Methanol, which must be free from iron carbonyls
and sulphur compounds (catalyst poison), is combined with recycle methanol and
pumped through a steam-heated vaporizer. An additional heat exchanger for super
heating the methanol may also be used. Air is drawn through a filter and
compressed in a blower for feed to the process. An air washer is provided for
removal of possible catalyst poisons, and while water is usually sufficient for the
scrubbing liquid, caustic solutions are sometimes needed. The washed air is pre
heated and mixed with fresh feed methanol to give a combined feed temp. of
about 150o C. Provision is made for the addition of up to 0.75 lb steam /lb
methanol to serve as thermal ballast for reaction control.
The absorber bottoms stream is pumped to the still where methanol is separated
overhead and the product formaldehyde solution is the bottom stream. The water
content of the bottoms is controlled by the amount of makeup water added at the
top of the absorption column, and thuds there are definite upper limit for the
water content in the bottoms.
The methanol still typically is a tray column with conventional refluxing and re-
boiling. For reduction of the bottom to 1.0 wt% methanol, 40 bubble cap trays are
used. Residence time distribution can depend on the shifting equilibrium
composition of the liquid, and the controlled residence time characteristics of the
bubble cap tray appear advantageous. The methanol net distillate is recycled back
to the fresh feed of methanol. The recycle is done in vapor phase to conserve
energy. Also, some design employs vacuum distillation of methanol still to
discourage the formation of higher products like acetaldehyde.
If the formic acid content is higher then the distillate bottom is passed through
deionizer. Also a certain amount of product is left in distillation column for
stabilization.
LIST OF EQUIPMENTS
CONTROLLING PARAMETERS:
5. Composition of the feed entering the reactor. Maintained at 80% methanol &
controlled indirectly by controlling the composition of the feed entering the
evaporator. It is important as it controls the composition of formaldehyde
formed.
6. Phase of the feed entering the reactor. No liquid should enter the reactor
dome as it could spoil the silver bed. To ensure this feed is passed through
superheater before it enters the reactor so that no condensation takes
place. In addition to this another separator is employed just before the feed
enters the reactor which filters out any liquid & send it back to the
evaporator.
The abrupt decrease of the formaldehyde yield above 923 K was accompanied by a
yield increase of CO and H2, suggesting a gas phase decomposition of formaldehyde
to CO and H2 at the high temperature. Formic acid appeared only in a limited
temperature region (approximately 570–850 K) and could not be observed in the
high temperature region before the deactivation of catalyst
However, the longer residence time was not beneficial for the formaldehyde
formation: its selectivity decreased apparently under the longer residence time,
which may be partly due to the fast decomposition of formaldehyde in the gas
phase to H2 and CO at high operation temperatures. The H2 selectivity did increase
with residence time, albeit not to the extent that the formaldehyde selectivity
decreased.
The influence of water vapor in the reaction gas on the formaldehyde selectivity
was estimated. Water vapor content was varied in the region of H 2O/CH3OH molar
ratio of 0–2.0. The space velocity was kept constant by varying the N2 flow
accordingly. This led to a constant CH3OH/O2 molar ratio. Each result was an
average over a 15 h lasting stationary test.
The conversion of methanol increased with the H2O/CH3OH molar ratio, however,
the selectivity to formaldehyde passed through a maximum around a H2O/CH3OH
molar ratio of about 0.75, which corresponds basically well with the above-
mentioned molar ratio of 0.67 in industrial formaldehyde manufacture (indicated
by the vertical dashed line). Because of the experimental error in the
formaldehyde detection, the experiment was reproduced at different feed
concentrations, supporting the conclusions reported above.
It is also show that the selectivity to CO2 decreased with the molar ratio of
H2O/CH3OH. The more water vapor was fed in the reaction gas, the less CO2 was
detected.
METHANOL
EXPOSORE
Exposure to methanol can be treated fast and efficiently. If the contact was
to the eyes or skin, flushing with water for 15 minutes would be the first
course of action. Contaminated clothing or shoes are to be removed
immediately. If the contact is much more series, use disinfectant soap, then
the contaminated skin is covered in anti-bacteria cream. Inhalation of
methanol is much more hazardous than mere contact. If breathing is
difficult, oxygen is given, if not breathing at all artificial respiration
REACTIVITY
Methanol has an explosive nature in its vapor form when in contact with
heat of fires. In the case of a fire, small ones are put out with chemical
powder only. Large fires are extinguished with alcohol foam. Due to its low
flash point, it forms an explosive mixture with air. Reaction of methanol and
Chloroform + sodium methoxide and diethyl zinc creates an explosive
mixture. It boils violently and explodes.
STORAGE
FIRE HAZARDS
Formaldehyde is flammable in the presence of sparks or open flames.
EXPOSURE
Exposure to methanol can be treated fast and efficiently. If the contact was
to the eyes or skin, flushing with water for 15 minutes would be the first
course of action. If the contact is much more series, use disinfectant soap,
then the contaminated skin is covered in anti-bacteria cream. Inhalation of
methanol is much more hazardous than mere contact. The inhalator should
be taken to a fresh air.
MATERIAL BALANCE
In this section, material balance over some important units has been performed
manually. The final stream tables give the composition in all streams.
Equation used
as accumulation = 0
equation given above can be applied for mass balance.
ASSUMPTIONS
Total molar conversion of methanol is 81%.
60% of formaldehyde is formed via reaction 1 and remainder is formed
by reaction 2.
Conversion values for reaction 1 and 2 are obtained by using literature
survey on the formaldehyde production process.
Since,the ratio of methanol to oxygen for this process in industrial reactors is 2.5.
Amount of oxygen required = 87.5/2.5 = 35 Kmol/hr
REACTOR
F ORMALIN ABSORBER
REACTOR
The reactor used in the formaldehyde plant utilizes catalyst bed and has the shell
and tube heat exchanger located in it. The catalyst bed actually lies on the shell
and tube heat exchanger. The reaction takes place on the exchanger and as can be
seen from the rate equation is actually very fast. So, the diffusion or mass transfer
resistance is not considered in the reaction.
6 copper screens and two silver screens at bottom. 1 silver screen is kept at top.
The temperature of the catalyst bed is maintained at about 600C. The heat
evolved from the highly exothermic reaction raises the temperature to 670-700C.
Also initially passing steam in the outer jacket raises the temperature. Air required
for the reaction is provided from the air valve provided near the reactor.
Here, the methanol vapours are converted into formaldehyde by an oxidation
reaction in the presence of silver catalyst.
The methanol vapours enter the reactor dome at a temperature of about 120C.
The methanol vapours are then converted into vapours of HCHO in the reactor in
the presence of high-pressure air and the high temperature of about 700C. The
vapours go down into the steam generator and then to the condenser.
II Method.
Using Heat Of Reaction Cumulatively
heat of
reaction 116.6 Kj/Kmol
1663.29
heat released 9 Kj/sec
0.09610
CH3OH 0.61 8
0.15755
HCHO 1 5
0.06585
H2 0.418 8
0.03466
CO2 0.22 2
0.02048
CO 0.13 2
0.13266
H2O 0.842 1
0.00141
O2 0.009 8
0.49125
N2 3.118 6
Total 6.347
05 05 05
1.01E-
d -2.8497E-08 09 7.69E-10 9.8E-09 -4.7E-09 -4.5E-09 -3.9E-09
Inlet
Temperature deg. C 373 in K 646.13
Outlet
Temperature deg. C 170 in K 443.13
Energy Calculations
(Sp. 6164.37
Heat Required Heat.* KJ/Kmol 9
Flow Rate of 90.5399
Gases Moles/sec 6
(flow Rate*Sp. 558.122
Heat Required Heat.* KW 6
Cooling Medium is Water
Inlet Temperature of Water deg. C 25 in K 298.13
Outlet Temperature of Steam deg. C 204.44 in K 477.57
Specific Heat Of Water KJ/KgK 4.184
2221.42
Total Heat To Be Quenched KW 2
(Total heat is equal to latent heat and sensible heat)
Steam
Enthalpy Btu/lb 826
Steam 1920.00
Enthalpy KJ/Kg 6
Flow Rate of Water is calculated by dividing the heat load by the temp. difference of
water and
the specific heat of water
Flow Rate of 0.83174
Water Kg/sec 9
Catalyst Calculations
Consatnts K1 K2
a 8.52 3810
b 10.79 7040
Reactor
Conditions
Temp. 873.13 K
Pressure 1.1 atm
Partial Press. Of Methanol 0.476395
Area Calculation
LMTD deg. C 358.05
R 1.39
S 0.318
Correction Factor (from graph) 0.92
Corrected LMTD 329.406
Kg/m^3 1601.85
Volume of Catalyst m^3 0.015808958
Dia of Catalyst Bed mm 992 inch 39.05512
Height of Catalyst Bed m 0.204519026
Lemgth of Tube m 4.88
Total m 5.084519026
ABSORPTION COLUMN
ABSORBER DESIGN
One of the most common unit operations in the industry is the absorption process.
Absorption is the mechanism of transporting molecules or components of gases into
liquid phase. The component that is absorbed is called the solute and the liquid
that absorbs the solute is called the solvent. Actually, the absorption can be either
physical where the gas is removed due to its high solubility in the solvent, or
chemical where the removed gas reacts with the solvent and remains in solution.
PACKED-BED ABSORBER
The packed-bed absorbers are the most common absorbers used for gas removal.
The absorbing liquid is dispersed over the packing material, which provides a large
surface area for gas-liquid contact. Packed beds are classified according to the
relative direction of gas-to-liquid flow into two types. The first one is co-current
while the second one the counter current packed bed absorber. The most common
packed-bed absorber is the counter-current flow tower. The gas stream enters the
bottom of the tower and flows upward through the packing material and exits from
the top after passing through a mist eliminator.
Liquid is introduced at the top of the packed bed by sprays or weirs and flows
downward over the packing. In this manner, the most dilute gas contacts the least
saturated absorbing liquid and the concentration difference between the liquid
and gas phases, which is necessary or mass transfer, is reasonably constant through
the column length. The maximum (L/G) in counter-current flow is limited by
flooding, which occurs when the upward force exerted by the gas is sufficient to
prevent the liquid from flowing downward. The minimum (L/G) is fixed to ensure
that a thin liquid film covered all the packing materials.
PACKING MATERIAL
The main purpose of the packing material is to give a large surface area for mass
transfer. However, the specific packing selected depends on the corrosiveness of
the contaminants and scrubbing liquid, the size of the absorber, the static pressure
drop, and the cost. There are three common types of packing material: Mesh,
Ring, and Saddles. In our project Ceramic Berl Saddles packed was selected since it
is good liquid distribution ratio, good corrosion resistance, most common with
aqueous corrosive fluids and Saddles are beast for redistributing liquids low cost.
Also we use 2 inches diameter packing.
S I ZI N G O F P A CK E D T O W E R
ASSUMPTIONS
2. x and y are for the mole fraction of Methanol in liquid and gas respectively.
Where
G' = mass flow rate of gas per unit cross-sectional area of column, g/s•m2
ρ_g = density of the gas stream
G‟flooding = 9.323643
G‟ operating = 0.55 (G‟ flooding) = 5.128
area of packing = 0.361348 (G/G‟operating)
D_packing = 0.6784m
PACKING HEIGHT
C ALCULATING N O G AND Z
Z= HOG *NOG
yA,in = 0.27778
yA,out = 0.007
Y* A,in = 0.20
Y* A,out = 0.0001
NOG = 9.2540
Z_column = Z_packing*(1+0.25)
Z_column = 10.41m
DISTILLATION COLUMN
KEY COMPONENTS
The light key will be the component that it is desired to keep out of the bottom
product, and the heavy key the component to be kept out of the top product.
Here the light component is Methanol while the heavy component being Water.
Hengstebeck‟s Method:
For any component i the Lewis-Sorel material balance equation and equilibrium
relation can be written in terms of individual component molar flow rates; in the
place of component composition:
vn+1,i = ln+1 + di
l’n+1, i = v’n, 1 + bi
where :
ln+1 = the liq. flow rate of any component i from the stage n,
vn, i = the vapour flow rate of any component i from the stage n,
di = the flow rate of the component i in the tops,
bi = the flow rate of the component i in the bottoms,
Kn, i = the equilibrium constant for component i at the stage n.
Le = L - ∑li
Ve = V - ∑vi
L’e = L’ - ∑l’i
V’e = V’ - ∑v’i
Where
Ve and Le are the estimated flow rates of the combined keys.
li and vi are the limiting liquid and vapour rates of the components lighter than the
keys in the rectifying section.
L‟i and v‟i are the limiting liquid and vapour rates of the components heavier than
the keys in the stripping section.
Then we have:
li = di/(αi-1)
vi=li + di
v’i = αibi/(αLK-αi)
l’i = v’i + bi
y= αLKx / ( 1 + (αLK-1)x )
where x and y refers to the liquid and vapour concentrations of the light key.
The Fenske equation have been used to estimate the minimum number of stages at
the total reflux condition. The equation is:
[ xi / xr ] = αiNm [ xi / xr ]b
If the number of stages is known then the above equation can be used to estimate
the split of components between the top and the bottom at total reflux. Thus we
have:
di/ bi = αiNm [ dr / br ]
Where di and bi are the flow rates of the component i in the tops and the
bottoms.
And dr and br are the flow rates of the reference component in the tops and the
bottoms.
where xi,f = the concentration of the component i in the feed and q depends upon
the condition of the feed.
EFFICIENCY
Feed Specifications
COMPONENT Xd Xb Xf
0.4 0.592514 X Y X Y
0.5 0.685644 0.013 0.0133 0.249776 0.4
0.6 0.765899 0.013 0.02856 0.249776 0.4
0.7 0.835776 0.023 0.02856 0.325915 0.4
0.8 0.897166 0.023 0.048442 0.325915 0.5
0.9 0.951527 0.035 0.048442 0.434847 0.5
1 1 0.035 0.073698 0.434847 0.6
0.051 0.073698 0.568191 0.6
Line: Y=X 0.051 0.104778 0.568191 0.7
X Y 0.07 0.104778 0.703466 0.7
0 0 0.07 0.141559 0.703466 0.8
1 1 0.093 0.141559 0.81692 0.8
0.093 0.18313 0.81692 0.9
0.119 0.18313 0.897845 0.9
0.119 0.22774 0.897845 1
Sample Point calculations 0.147 0.22774 0.949137 1
EQUIL. POINT 0.147 0.273025 0.949137 1
X Y 0.175 0.273025
0.949137 0.97602 0.175 0.316474
0.202 0.316474
BOTTOM OPERATING LINE POINT 0.202 0.355965
X Y 0.25 0.355965
0.202175 0.316474
TOP BOTTOM
MOLE/S Ai Li Vi MOLE/S Ai Vi Li
8.151891 2.181109 6.901898 15.05379 14.25074 0.6 4.965182 19.2159
xb 0.0133
xd 0.957699
xf 0.177376
3.22521
MIN. NUMBER OF STAGES NUM. 7
0.33867
DEN. 7
9.52297
NO. 8
THET
Xd Ai Xd*Ai A 1.84
6.06243
TOTAL 5
5.06243
MIN. REFLUX RATIO 5
Xb(LK) 0.00989
0.04223
Xd(HK) 1
0.13741
Xf(LK) 8
0.63730
Xf(HK) 7
Method Employed is Kirkbride equation
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0 0.2 0.4 0.6 0.8 1
mole fraction of Formaldehyde in Water
Column Efficiency in % 60
Real Stages 28.33333 or 29
Base Densities:
Liquid Density 1111
Vapor Density 0.695
Surface Tension 0.018
Top Densities:
Liquid Density 792
Vapor Density 1.13073
Surface Tension 0.0469
Tray Spacing taken to be 0.5 m
Column Diameter: K1
F(LV) at Bottom 0.040147 0.08
F(LV) at Top 0.032117 0.08
At Top 0.094868
Base Velocity: in m/sec 3.130886
Top Velocity: in m/sec 2.508947
Column Diameter:
1.23775
Base m 7
1.17598
Top m 2
Height Claculation:
Totla Number of Trays 29
Crude Hright for Column m 14.5
(number of stages * tray spacing)
CONDENSER
Shell and tube exchangers can be effectively used as condensers which are
employed more preferably than direct contact condensers. There are 4 types of
condenser configurations available. They are :
Of which horizontal shell side and vertical tube side are the most commonly used
ones. A horizontal exchanger with condensation in tubes is rarely used as a process
condensers but is the usual arrangement for heaters and vaporizers using
condensing steam as the heating medium.
In the formaldehyde process, the condenser used is total condenser. The outlet
stream is condensed methanol which is recycled back to the fresh feed. Thus the
overall economy of the process increases. The reflux ratio of 1.5 times the
minimum is utilized in the distillation column which gives the amount of methanol
recycled and produced.
COMPONENT TOP Xd
LMTD Calculations:
Temp. correction factor R 1.65
S 0.240964
LMTD Temp. deg. C 28.12493
Correction Factor Ft 0.96
Corrected LMTD Ft*LMTD 26.99993
Choosing 20 mm O.D. 16.8 mm I.D. 4.88 m (16 ft) long brass tubes
Tube ID mm 16.8
Tube OD mm 20
Tube Length m 4.88
Mean Temp.
Shell-side deg. C 58.25
Tube-side deg. C 30
(H51-Tw) deg. C 4.035714
Tw 54.21429
(inverse of
U 1/U) 638.9926
REBOILERS
TYPES OF REBOILERS
SELECTION OF REBOILER
In our case, Thermosyphon reboiler is used. In this type, the heat available in
bottom feed is utilized. This type of reboiler requires a minimum head so that it
can take advantage of density difference thus the support of distillation column
and reboiler needs to be elevated and the cost increases. But the higher cost is
offset by the economic usage of available heat which otherwise would have been
lost.
BOILER DESIGN
COMPONENT Xd Xb Xf
Critical
Temperature deg. C 586.0482
(Ref: J. H. Perry)
Choosing 20 mm O.D. 16.8 mm I.D. 4.88 m (16 ft) long brass tubes
Tube ID mm 16.8
Tube OD mm 20
Tube Length m 4.88
Area of one tube m^2 0.303
The plant has beside the major equipments like reactor, distillation column and
absorber column several other heat tansfer and mass transfer equipments. For
example; heat exchangers are used extensively in the chemical plants. These heat
exchangers are required for utilising the heat in the effluent gases. Furnaces are
there to provide extra heat needed and which is not available in the process
streams. Likewise, pumps, compressors and blowers are used to transfer solid,
liquid and gases. A sample designing of some them used in the formaldehyde plant
is given here.
PUMPS
S ELECTION OF PUMP
Using graph between flow rate on x axis and pressure required on y axis from
Donald R Woods suitable pump is Centrifugal Pump.
Choosing from pump-heat exchanger combination pipe size available from [ fig 2-
30 , Page 2-28 ,D.R. Woods]
Pressure loss
Material K K /D f
BLOWER
Taking air to be an ideal gas amd air entering at the room temp. and at a pressure
of 14.7 psia.
ρ1= MP1/RT
ρ2= MP2/RT
Thus we have d2= d1 ( P1 / P2)1/2
hence d2 = 10 (35 / 14.7) cm = 15.43 cm.
PRESSURE DROP
Reynolds no. = d1 v ρ1 / µ
d1 = 10 * 10-2 m
v = 20 m /sec.
µ= 0.185 * 10-4 pa
(reference : J.H. Perry , Table 2.229)
VALVE DESIGN
Valves are used to control pressure condition of flowing streams. Valves and vents
are needed as the as like in the reactor, the reactions might be occuring at the
high pressure. But the downstream gases, in this case going to absorber needs to
be brought down in the pressure.
ρ = 25.68 * 25 / 14.7
0.0821 * 616
ρ = 0.864 Kg/m3
k = 6.08
AIR FILTER
Air-Filter Types Air filters may be broadly divided into two classes:
(1) Panel, or unit, filters;
(2) Automatic, or continuous, filters.
Panel filters are constructed in units of convenient size (commonly 20- by 20-in or
24- by 24-in face area) to facilitate installation, maintenance, and cleaning. Each
unit consists of a cleanable or replaceable cell or filter pad in a substantial frame
that may be bolted to the frames of similar units to form an airtight partition
between the source of the dusty air and the destination of the cleaned air. Panel
filters may use either viscous or dry filter media. Viscous filters are so called
because the filter medium is coated with a tacky liquid of high viscosity (e.g.,
mineral oil and adhesives) to retain the dust. The filter pad consists of an assembly
of coarse fibers (now usually metal, glass, or plastic). Because the fibers are
coarse and the media are highly porous, resistance to air flow is low and high
filtration velocities can be used. Dry filters are usually deeper than viscous filters.
The dry filter media use finer fibers and have much smaller pores than the viscous
media and need not rely on an oil coating to retain collected dust.
Automatic filters are made with either viscous-coated or dry filter media.
However, the cleaning or disposal of the loaded medium is essentially continuous
and automatic. In most such devices the air passes horizontally through a movable
filter curtain.
TABLE 9.
Other table presents the relative performance of Group I, II, and III filters with
respect to airflow capacity, resistance, and dust holding capacity. The dust-
holding capacities correspond to the manufacturers‟ recommended maximum
allowable increases in airflow resistance. The values for dust-holding capacity are
based on tests with a synthetic dust and hence are relative. The actual dust-
holding capacity in a specific application will depend on the characteristics of the
dust encountered. In some instances it may be appropriate to use two or more
stages of precleaning in air-filter systems to achieve a desired combination of
operating life and efficiency. In very dusty locations, inertial devices such as
multiple small cyclones may be used as first-stage separators.
Table 10 : Air Flow Capacities and Resistance Holding Capacity for different
Filters
MECHANICAL DESIGN
Reactor Data
Diameter = 1.2 m
Height =6m
Top and Bottom: Toro spherical head
Operating Pressure of Reactor: 1.1 atm.
Operating Temperature of Reactor: 873 K
where D is 1200 mm
l= 74.58 mm
hence vh = 0.4 m3
Thickness of head
t=p * w /(2fE-0.2* p) + c
where t = thickness of head.
P = pressure inside vessel.
W = stress intensification factor for torospherical dished head.
c= corrosion allowance
w = ¼ * ( 3 + ( rc / ri)1/2)
w = ¼ * ( 3 + ( 960 /120)1/2) = 1.46
p= 1.68 kg/mm2
hence t = 1.68 * 960 * 1.46 / (2 * 13.37 * 0.85 –0.2 * 1.68) = 2.14 mm
but the minimum thickness has to be taken = 3 mm
corossion allowance = 3 mm
hence total thickness = 6 mm
t = D * (∆p / fall)0.5
=0.05 mm
but the minimum thickness has to be taken = 3 mm
corrosion allowance = 3 mm
Hence total thickness = 6 mm
2 openings are to be provided for water inlet and steam outlet.
And 2 openings are to be provided for inlet gases and outlet reactor effluent stream.
Velocity of gases maintained :
Velocity in tube = tube length / residence time = 6 / 0.02 = 300 m/ sec.
But due to some velocity head loss and since the velocity of gases before entering the
reactor was 2 m/sec it is not changed and kept as it is. Also high velocity in the shell
means correspondingly high velocity in tubes so the mean residence time will further
decrease from 0.02 sec to some lower value which is highly desirable because it will
reduce the amount of formic acid formed.
NOZZLE DESIGN
Calculation of diameter
∏*D2 * v / 4 = Volumetric flow rate of the mixture.
D = ( 71.11 * 10-3 * 14.265 * 4 / ( 2 * 3.142))0.5 = 80.45 cm.
Optimum diameter for nozzle:
-
dopt = 282 * G0.52 * ρ 0.37
Similarly the design was done for the liquid water inlet. Whose diameter comes out to be 80
mm.
Support Design
(Reference Process Equipment Design – 2nd Edition by M.V. Joshi Page 367).
Diameter of vessel = 1.2 m
Height of vessel = 6 m
thickness of vessel = 10 mm (shell)
For head
thickness = 6 mm
Straight portion of head = 0.5m
effective height of head = .4123m
density of carbon steel = PS = .286 lb/ Cu-1n
= .286 (12)3 lb/ cu – ft
= 494 .208 lb/ cu-ft
= 16.018 494 – 208
= 7916 K S /m3
D
Di = 1.2m D0 = 1.22 cm, H = 9.6 m
Di H Ps
2 2
weight of shell =
1.002
0
4
.992 7.36 7916
2 2
=
4
D
= 915 .3 kgf
Di hs p s
2 2
weight of head =
0
4
r0 r1 ps
2 3 3
1.002
3
.992 0.5 7916
2 2
2
3
.1072 .0992 7916
3 3
=63 Kgf
weight of liquid (EDC) filled in reactor
height of liquid
weight
4
D 4 p
i
2
0 H
0.992 2 4 1.000 10 3 4.88 0.4
4
= 4526 Kgf
Total weight of Reactor = 915.3 + 63 + 4526
5500 kgf (indudiny wt. of nozzle & other aceessories)
Total Weight = Weight of Vessel + Attachments + Catalyst Weight
Since this weight is much appreciable so lug support will not work here, so we go for
skirt support.
Skirt
Stress due to dead weight (draw diagram on page 367 M.V. Joshi)
f0
w
D0 k t s k
f0
99 .2 t s k
5525 17 .73
kg / cm 2
ts k
Stress due to wind load
fwb
4 Mw
D0 k 2 t s k
m kp1 h1 D0
H
2
f wb
4.kp1 h1 D0 H / 2
D0 k 2 t s k
31 .27
kg / cm 2
ts k
fsb
3 Rok 2 .t s k
2 CW
2
.03813
kg / cm 2
ts k
f t max max f w b or fs b f a b
Maximum tensile stress at bottom of skirt
31 .27 17 .77 13 .5
kg / cm 2
ts k ts k ts k
Permissible tensile stress = 1400 kg /cm2
ts k cm .00964 cm
13.5
1400
.0964 mm
max f wb or fsb f ab
Maximum compressive stress on skirt from equation
fs permisssib le
1
yield po int
3
666 kg / cm 2
2000
3
ts k cm 0.0721 cm
48.09
666
Use a minimum thickness of 6 mm.
fc
w Mw
A Z
w = weight of vessel, contents & attachment
A = area of contact between bearing plate & foundation
Mw = bending moment due to wind
Z = Section modulus of area’
Pe k p1 h1 D0
Mw plw k p1 h1 D0
H H
2 2
109 .95
5525 4 0.7 128 .5 0.992 11 .5
fc
109 .95 99 .2 99 .2
2 2 4 4
32 109 .95
= 33.123 + .018 = 33.14 kg/cm2
which is less than the permissible value for concrete.
Maximum bending moment in bearing plate
M max f c
bl 2
2
l = difference between outer radius of beaving plate and outer radil of skirt
2
6 420 .35 b
Stress f
6 M max
2 2
b tB b. t B
2522 .09
2
kg / cm 2
tB
Permissible stress in bending is 1575 kg/cm2
tB Em 2 0.0166 cm 2
2 2522 .09
1575
t B .16
1.6 mm
cm
Since the calculated thickness is less than 12 mm a steel rolled angle may be used as a
beaqring plate. Bolting chair need not be used.
FLANGE DESIGN:
do/di = ((y-pm)/(y-p(m+1)))0.5
Assuming a gasket thickness of 1/16 = 1.58 mm
y = 1600
m = 2.00
Suppose di = 11.02
So do = 11.08
Hp = 2bGmp
= 2 * 0.5 * 3.14 * 11.52 * 2.00 * 16.17
= 1170 lb
So,
B = 11.02” =0.280 m
A = 20.87” = 0.530m
C = 16.92” = 0.430 m
E =13/16” =0.8125” = 0.0206m
go = 0.236” = 0.006 m
R = 9/8 = 0.033 m
G = 3.425” = 0.087 m
t = 0.096 m
h = 0.175 m
Calculate Di =2.56 m
Shell thickness
4
= 63.44 KN/m2
Design Pressure = 1.05137 .86 .104 .182 .3.44 103 N / m2
= 320.71 KN/mm2
t
PDi
2fJP
Material Selection – Stainless Steel
for this material fall 300C = 165 106 N/m2
Assuming Double welded butt joint with spot radiography J = 0.85
= 4.1 mm
Ref. (Coulson & Richardson Volume – 6 , Page 641)
Minimum practical wall thickness (including corrosion allowance = 3 mm)
So, t = 8mm
Thickness of wall = 5 mm (including corrosion allowance = 2 mm)
Do 3.56 2.008 m
= 3.576 m
Torispherical Head design
Do = 3.576 m
Let Ri = inside crown radius = Do = 3.576 m
ri = inside knucelete radius = .06 Di
= .06 * 3.56 = .2136 m
Assuming thickness t = 8mm
ro = outside knuclde radius = ri + t
= .2136 .008 .2144 m
Ro = Outside crown radius = r1 +1 = 3.576 + .008
= 3.584 m
Do
Ro Ro R o o 200
D
2
(From geometry)
2
Do 2 3.576
= 0.636 m
.901
4 Ro 4 3.584
2
.685
D0r0 3.576 * .2144
2 2
o
h
hE = effective height of head = minimum of D o / 4R o
2
D o ro
2
hE = .636 m
C = shape factor determined by graph
.174
hE .636
Do 3.576
.174
t .008
Do 3.576
from graph C = 1.40
1.44753 10 5 N / m2
NOZZLE DESIGN
Moler flow rate = 2 mole/sec (approx)
Density of Water = 990 K/m3
So, Voumetric Flow Rate = Flow Rate of formaldehyde * molar flow rate of
water* mol. Wt. *density
= 14.265 * 2 *18 *990/1000
= 508.40 Kg/sec
dopt = 282 * G0.52 * ρ-0.37
= 282 * 508.40.52 * 990-0.37
= 318 mm
Taking nozzle dia. = 320 mm or 32 cm
Similarly Nozzle Dia for gas comes out to be 48 cm
Nozzle Reinforcement Design
Nozzle is provided on the head and it is welded there internal design pressure
= 3.2071 105 N/m2
3.2071 10 5
= 4
/ 10 kg / cm2
10
= 3.2071 kg/cm2
3.2071 3560 mm
thickness of nozzle = tn
PDi
2 f J P 2 1300 1 3.2071
= 4.39 mm
No corrosion allowance, since the material is stainless stell.
Actual thickness = 5 mm
Area to be compensated = d tRS
trs = thickness cale for shell
d = 5 cm (internal dia) + 8.4 10-3 (thickness) = 5 cm
= d tRS = 320 5
= 1600 mm2
Area available for compensation As = d t s t rs c (of shell)
= 320 5 8.4 10 3 3
= 640 mm2
Ao 2H1t n t rn C
Area available for compensation (external branch)
Reference Book
Support Design : Process Equipment Design (second editor) By M. V. Joshi
Since on absorber is not large, as result we can safely chose bracket or lug support for
vertical cylindrical vessels.
Data : -
Diameter of vessel =3.56 m
Height of vessel = 10.62 m
Clearance from vessel both of foundation = 1.5m
Weight of vessel
Weight of vessel = weight of absorber + weight of pacing
weight of absorber = Do 2 Di 2 H s
3.576
4
.3.56 10.62 7500
2 2
4
= 7142.5 Kg
from Page 23-35 John H. Perry.
for Stainless steel 201 s .28 lb / Cu in .
.28 12 3
lb
Cu ft
483 .84
lb
Cu ft
16 .018 483 .84 kg / m3
7500 .14 kg / m3
Mass of packing = 2 Di 2 H b
4
3.56 2 7.62 609 kg
4
= 4532 kg.
Total weight of Tower
with contents = 7142.5 + 4532 + 500 Kg extra
= 12174.5 Kg
wind pressure = 128.5 kg/m2
Skirt
f0
w
D0 k t s k
f0
3560 ts k
12174 .5 10 .885
kg / cm2
ts k
fwb
4 Mw
D0 k 2 t s k
m kp1 h1 D0
H
2
f wb
4.kp1 h1 D0 H / 2
D0 k 2 t s k
18 .14
kg / cm 2
ts k
fsb
3 Rok 2 .t s k
2 CW
2
.03813
kg / cm 2
ts k
18 .14 10 .885 7.255
kg / cm2
ts k ts k ts k
ts k cm .005282 cm
7.255
1400
.
=
05282 mm
max f wb or fsb f ab
Maximum compressive stress on skirt from equation
fs permisssib le
1
yield po int
3
666 kg / cm 2
2000
3
ts k cm 0.0721 cm
29.025
666
Use a minimum thickness of 6 mm.
fc
w Mw
A Z
w = weight of vessel, contents & attachment
A = area of contact between bearing plate & foundation
Mw = bending moment due to wind
Z = Section modulus of area’
Pe k p1 h1 D0
Mw plw k p1 h1 D0
H H
2 2
391 .6
12174 .5 4 0.7 128 .5 3.56 10 .62
fc
391 .6 356 356
2 2 4 4
32 391 .6
= 0.582 + .001 = 0.583 kg/cm2
which is less than the permissible value for concrete.
Maximum bending moment in bearing plate
M max f c
bl 2
2
l = difference between outer radius of bearing plate and outer radii of skirt
M max 92 .98 b
2
6 92.98 b
f
6 M max
Stress : 2 2
b tB b. t B
557 .8
2
kg / cm 2
tB
tB Em 2 0.3541 cm2
2 557 .8
1575
t B .59cm = 5.9 mm
Since the calculated thickness is less than 12 mm steel rolled angle may be used as a bearing
plate. Bolting chair need not be used.
EFFLUENT TREATMENT
WASTE CHARACTERSTICS
The major waste stream from the process is the "formaldehyde in water" and
formaldehyde vapors released into atmosphere. Beside formic acid, Carbon-mono-oxide
etc., which need to be treated before disposal. Carbon-mono-oxide and other gases are
in low concentration, so they are not treated as such but released at high elevation in
atmosphere.
Formalin is a highly toxic gas, and strict precautions are necessary to minimize risk
to workers and possible released during its handling. Major sources of fugitive air
emissions of chlorine and hydrogen are vents, seals, and transfer operations. Acid
and caustic wastewaters are generated in both the process and the materials
recovery stages.
Scrubber systems should be installed to control gas effluent emissions from condensers
and at storage and transfer points for liquid chlorine. Sulfuric acid used for drying
chlorine should be neutralized before discharge.
KEY ISSUES
The following summarizes the key production and control practices that will lead to
compliance with emissions guidelines.
1) Give preference to the effluent gases.
2) Adopt the following pollution prevention measures to minimize emissions.
3) Use scrubbers at the absorber to minimize the off-gases from it.
4) Recycling of water in air washer should be treated.
5) Recycling of dust containing water should be from suitable pumps.
In the effluent treatment plant, the formic acid going along with the water is passed
through an ion exchange bed. A sample design fo a deionizer for the treatment of formic
acid from the formalin stream is given below. A similar treatment can be devised for
outlet water stream.
Secondly, the settling tank can be designed for the treatment of rundown water from the
air washer.
DEIONIZER
For ion exchange system sizing, the quantity of liquid to be processed in a period
of time must be determined. The processing rate if often expressed in gallons per
day or pounds per day.
Processing rate = quantity to be processed / time period minus regeneration time
Equipment must be sized such that the service time is sufficient to allow a unit in
regeneration to be completed prior to the exhaustion of the usable capacity of the
unit in service. The service time of a single unit in a multiple unit system is usually
designed for a service time, which exceeds the sum of the regeneration time
required for all of all the units in service. Having the required feed processing rate
per fixed-bed ion exchanger and the required length of the service period, the
exchanger or adsorption load to each unit for a service period can be calculated.
For continuous ion exchange equipment, the load is calculated on the basis of
exchange load per unit time. Generally, the capacities of an ion-exchange material
to remove a given component are determined experimentally. But the data is
available on common materials.
Variables on which the amount of ion-exchange bed required depends are
conc. of the component to be removed, process flow contact rate, regenerant
chemical conc., etc. Ion-exchange capacities are affected by the rate of mass
transfer between the process fluid and ion-exchange resin.
Typically, a tank diameter which will allow service operation at flows that will
exceed 2 gpm/ft2 of tank area and not exceed 12 gpm/ft2 are acceptable. Once
the vessel diameter is determined, the ion-exchange media bed depth can be
calculated (media volume divided by area = bed depth). The resin bed depth in a
fixed-bed-ion-exchange unit usually should exceed 30in. and be limited to a
maximum depth of 96 in.. High flows per unit area and deep ion-exchange resin
depths may result in high-pressure drops. Pressure losses across a resin bed are
normally limited to 10-20 lb/in2. Large pressure losses can, in combination with
exchange media volume changes (result from ionic or osmotic changes), causes
physical damage to the exchange media, the exchanger, and the internals of the
exchanger.
The chemicals that are used to regenerate the resins or the nature of the liquid
being processed dictate the use of interior coating or linings in an ion-exchanger
tank.
F L O W D I S TRI B U TI O N
For efficient working of ion-exchange resins, plug flow is generally preferred. Well-
distributed liquid flow distributors are required for that.
DESIGN
d= 1.000 + 0.003*W
d= 1.000 + 0.003*37
d= 1.111
d= 1111 Kg/m3
Volume of solution = weight/density
Volume of solution = 300*1000/1111
volume of solution = 270.03 m3/day
conc. of formaldehyde = 120Kg/day
270.03 m3/day
= 0.444 gm/lt
= 444 mg/lt
Eq. Wt. Of HCOOH =46/1(mol.wt./bascity)
=46
meq/lt of HCOOH = 444 mg/lt / 46
= 9.65
Total meq treated per day = 9.65 * 270.03 * 103
= 2605.79 eq/day
Resin Requirement:
Regenrant Reqd.
SAFETY POLICY
E F F E CI TVE S AF E TY AN D LOSS PRE VE N TI O N IS E S S E N TI AL FOR A CO M P AN Y ’ S
P RO S PE RI TY
Hazards in the chemical industry are much more than in any other industry.
Besides mechanical and electrical hazards, chances of fire explosion, inhalation
of toxic gases, handling of corrosive and poisonous substances are encouraged in
chemical industry. Thus it is important that the employee should recognize safety
and fire hazards in the manufacture of soda ash.
Objectives of industrial safety program are: -
a) To lessen human sufferings.
b) To prevent damage to plant and machinery.
c) To reduce the amount of time lost due to accidents.
d) To hold the expense of workman compensation to minimum.
GENERAL SAFETY
ELECTRICAL HAZARDS:
PROCESS UTILITIES
Process utilities are a major necessity for any chemical plant. The following are
usually considered utilities although in some companies one or more are treated
under other categories on the cost sheet. The utility cost for the whole plant (from
coat estimation sheet) is Rs.1.97412×108
Steam, Cooling water, Deionized water, Electric power, Refrigeration ,
Compressed air , Instrument air, Effluent treatment. Their effect on the cost of
the production will naturally depend on the process involved Occasionally the
costing of the utilities will be intricate because utilities require other utilities for
their own manufacture.
STEAM
A steam generation unit should be present which is a source of steam where ever
it is required .It is measured in thousands of pounds or for small boilers it may be
measured in boiler horse power(33,749 BTU/hr).A pound of steam generated may
have 1200 to1600BTU/lb.Most plants use several stem pressure levels . In many
plants waste heat boilers are additional source of steam at intermediate pressure
levels .
Steam is available at following rating in our plant
Pressure ----------- 400 Kpa
Temperature-------- 204.44 oC
Latent heat -------------826 Btu/lb or 1920 Kj/kg
WATER
Water requirements fall under three categories, cooling, process, and
miscellaneous such as washing or drinking. For cooling purpose it is usually
uneconomical and occasionally violation of conservation laws to use to use a
treated water in once through basis , although untreated river or sea water may
be used in this manner.
Recycled water returns to a cooling tower, where its temperature is lowered
mainly through evaporation. At the tower water is subjected to minor chemical
control for pH adjustment and to suppress the build up of salt.
The temperature difference between the incoming out going water will be a
complex function of ambient and return temperature and humidity .The expense
to operations of cooling or process is usually not significant in the overall
economics of the plant.
COOLING WATER
Cooling water is required to cool hot gases and liquids mainly in the condensers
and heat exchangers. So there should be a source of water nearby, it may be a
pond or a river. Cooling tower is used mainly at the following points in the plant:
1. Reactor Effluent Cooling
2. Absorber Water
Cooling towers should be installed in order to reuse water.
Cooling water is available at 25 oC and the maximum temperature allowed to be
elevated for water is 350 C.
Total quantity of cooling water required =
ELECTRICAL ENERGY
Electric power is required to run motors, pumps, compressors, blowers etc.
It is very necessary to have a reliable power resource.
Normally big plants have their own thermal power station, in which there are huge
boilers, in which steam is generated, which is used to run turbines. This generated
steam can be used in reboilers and heat exchangers
In most cases it represents a modest part of total operating cost. Electrical power
in India is mostly purchased from a public utility. All major contracts contain a
demand component, an energy component and a variable fuel-cost component.
The Demand charge is based on the maximum power requirement drawn by the
plant during a measurable period. The demand charges represents fixed charge
switch must be payed by the utility for generation, transmission and distribution
facilities.
The Energy charge is based on kilowatt used. It can be used as a flat unit cost per
kilowatt –hour. Because of the demand charge a maximum utilization of the
demand capacity will result in the lower units of electricity.
The Fuel Adjustment charge reflects the increased or decreased cost of fuel to the
power company.
In addition of of the cost of power from the utility company, the power must be
transformed and distributed through the plant properly. For a chemical plant these
distribution charges may be 50% of the purchased price of the power from the
utility.
WASTE DISPOSAL
It may be a major or minor cost. In a large plant, effluents from spills, discarded
fractions, etc are run together into a tank or a pond, neutralized aged, and
perhaps diluted until they are very innocuous to the body of water into which they
are eventually drained. Cost of a plant depends on the maintenance depreciation
and operating labor facility.
CONTROL OPERATIONS:
Selecting a Controller
Selection criteria
To solve a control task it is required that the controlled system be analyzed
and
a suitable controller be selected and designed.The most important properties of
the widely used P, PD, I, PI and PID control elements are listed in the following
table:
1)Is the system based on integral or proportional control action (with or without
self-regulation)?
2)How great is the process lag (time constants and/or dead times)?
3)How fast must errors be corrected?
4)Is steady-state error acceptable?
According to the previous chapters (see also above table), controllers and
systems can be assigned to each other as follows:
P controllers are employed in easy-to-control systems where steady-state error
is acceptable. A stable and dynamic control response is reached at minimum
effort.
Ratio control
Ratio control is a special type of follow-up control and is used to maintain a
fixed ratio between two quantities. This requires an arithmetic element (V). Its
input variable is the measured value of the process variable 1(q1) and its output
variable manipulates the process variable 2 (q2) in the secondary control loop.
Q. Fire extinguishers and Fire Hoses are made readily available in respective
areas and steam lancers are positioned at critical areas.
R. Tempered water system is commissioned.
S. All the interlocks function is to be checked as per the details given in
manual.
T. Steam Tracers are commissioned.
6. Close discharge valve at mixing receiver and feed valve at level regulator
LGV 207.
7. Disconnect instruments by actuating corresponding switches in control and
instrumentation board, and switch main switches for electric current and
compressed air.
8. Close main valves for cooling water, cold water, steam and compressed air.
EMERGENCY SHUTDOWN
1. Disconnect rotary blower after opening vent valve and ventilate reactor and
condenser.
2. Shut off heating of methanol evaporator and close cooling water.
3. Shut off process feed water for absorption and washing column.
4. All other plant equipment is put of operation in same sequence as being
done for normal shutdown.
5. In case of sudden failure of compressed air, steam or cooling water it will be
better to affect an emergency shutdown.
condenser.
2. Shut off process feed water for absorption and washing column.
3. All other plant equipment is put off operation in same sequence as being
4. In case the power failure lasts only for a minute, it can be started by
turning blower ON and then process water pump, controlling temp in
evaporator. As soon as an increase in temp of contact reactor is noticed, all
pumps and machines are connected again. Cooling water supply must be
available at once.
COST ESTIMATION
Acceptable plant design must present a process that is capable of operating under
conditions, which will yield profit. Since net profit equals total value minus all
expenses, it is essential that the chemical engineer be aware of the many different
types of cost involved in the manufacturing processes. Capital must allocate for
the direct, plant expenses, such as those for raw material, labor and equipment.
Besides direct expenses many others indirect expenses are incurred, and these
must be included if a complete analysis of the total cost is to be obtained. Some
examples of these indirect expenses are administrative salary, product distribution
cost and cost for interplant communication. A capital investment is required for
every industrial process and determination of necessary investment is an important
part of a plant design process. The total investment for any process consist fixed
capital investment for practical equipment and facilities in the plant plus working
capital, which must be available to pay salaries, keep raw material and products
on hand, and handle other special items requiring the direct cost outline.
When the cost for any type of commercial process is to be determined, sufficient
accuracy has to be provided for reliable decision. There are many factors affecting
investment and production cost. These are;
1. source of equipment
2. price fluctuation
3. company policies
4. operating and rate of production
5. governmental policies
Before an industrial plant can be put into operation, a large sum of money mustbe
supplied to purchase and install the necessary machinery and equipment.
Land and service facilities must be obtained, and the plant must be erected
completely with all piping, controls and services. The capital needed to supply the
DIRECT COST:
1. purchased equipments
2. purchased equipment installation
3. instrumentation and control
4. piping
5. electrical equipment and material
6. building (including services)
7. yard improvement
8. land
INDIRECT COST:
1. engineering supervision
2. construction expenses
3. contractor‟s fee
4. contingency
1) Direct cost:
a) Purchased equipment cost:(15 – 40% of FCI )
Assume 40% of FCI=Rs 2.59×108
b) Installation cost:(35 – 45% of PEC)
Assume 45%=Rs 1.17×108
c) Instrument and control installed:(6 –30% of PEC)
Assume 30% of PEC=Rs 0.78×108
d) Piping installation cost:(10 –80% of PEC)
Assume 80%=Rs.2.07×108
e) Electrical installation cost:(10 – 40% of PEC)
Assume 40% of PEC=Rs 1.036×108
f) Building process and auxilliary:(10-70% of PEC)
Assume 70%=Rs 1.813×108
g) Service facilities:(30-80% 0f PEC)
Indirect cost:
Expenses, which are not directly involved with material and labour of actual
installation or complete facility
Fixed charges:
a) Depreciation:(10% of FCI for machinery)
=Rs 2×108
b) Local taxes:(3-4% of FCI)
Assume 4%=Rs 0.8×108
c) Insurances:(0.4-1% of FCI)
Assume 0.9%=Rs 0.18×108
d)Rent:(8-12% of FCI)
Assume 12%=Rs 2.4x108
Direct production:
a) Raw material:(10-50% 0f TPC)
Assume 20%=Rs 5.38×108
b)Operating labour(OL):(10-20% of TPC)
Assume 15%=Rs 4.035×108
b) Utilities:(10-20% of TPC)
Assume 15%=Rs 4.035×108
c) Maintainence:(2-10% of FCI)
Assume 5%=Rs 1.8×108
General expenses:
Tax =45%
Net profit =Rs 7.93265x108
Plotting the graph on excel, we get break-even point at: 670 tons/day]
Rs.
FIXED COST 865960000
0 0 0 865960000 865960000
100 1045900000 11.7 865960000 1.912E+09
200 2091800000 23.5 865960000 2.958E+09
300 3137700000 35.2 865960000 4.004E+09
400 4183600000 46.9 865960000 5.05E+09
500 5229500000 58.6 865960000 6.095E+09
600 6275400000 70.4 865960000 7.141E+09
700 7321300000 82.1 865960000 8.187E+09
800 8367200000 93.8 865960000 9.233E+09
900 9413100000 106 865960000 1.028E+10
1000 1.0459E+10 117 865960000 1.132E+10
BREAK-EVEN
1.2E+10
1E+10
8E+09
COST , Rs.
6E+09
4E+09
2E+09
0
0 100 200 300 400 500 600 700 800 900 1000
CAPACITY, tons/day
PLANT LOCATION :
The location of the plant can have a crucial effect on the profitability of a project,
and the scope for future expansion. Many factors must be considered when
selecting a suitable site, and only a brief review of the principal factors will be
given in this section. The principal factors to be considered are:
Location, With Respect To The Marketing Area.
Raw Material Supply.
Transport Facilities.
Availability Of Labour.
Availability Of Utilities: Water, Fuel, Power.
Availability Of Suitable Land.
Environmental Impact, And Effluent Disposal.
Local Community Considerations.
Climate.
Political Strategic Considerations.
Marketing Area
Raw Materials
The availability and price of suitable raw materials will often determine the site
location. Plants producing bulk chemicals are best located close to the source of
the major raw material; where this is also close to the marketing area.
Formaldehyde plant should be located near the industries producing methanol in
large quantities, since then it would be easier and cheaper to transport raw
material from supplier to the processing site.
Transport
The transport of materials and products to and from plant will be an overriding
consideration in site selection. If practicable, a site should be selected that is
close at least two major forms of transport: road, rail, waterway or a seaport.
Road transport is being increasingly used, and is suitable for local distribution from
a central warehouse. So, it will be better to have plant location on near highway.
Rail transport will be cheaper for the long-distance transport of bulk chemicals.
So, it should be connected to all major cities by rail.
Availability Of Labour:
Labour will be needed for construction of the plant and its operation. Skilled
construction workers will usually be brought in from outside the site, but there
should be an adequate pool of unskilled labour available locally; and labour
suitable for training to operate the plant. Skilled tradesmen will be needed for
plant maintenance. Local trade union customs and restrictive practices will have
to be considered when assessing the availability and suitability of the labour for
recruitment and training.
The proposed plant must fit in with and be acceptable to the local community. Full
consideration must be given to the safe location of the plant so that it does not
impose a significant additional risk to the community.
Sufficient suitable land must be available for the proposed plant and future
expansion. The land should be ideally flat, well drained and have load-bearing
characteristics. a full site evaluation should be made to determine the need for
piling or other foundations.
Climate
Capital Grants, Tax Concessions, and other inducements are often given by
governments to direct new investment to preferred locations; such as areas of high
unemployment. The Availability of such grants can be the overriding consideration
in site selection.
SITE SELECTION
Location of a plant has crucial impact on profitability and future expansion
PLANT LAYOUT
The management of equipment and facilities specified from process flow sheet
considerations is a necessary requirement for accurate pre construction cost
estimation or for future design involving piping, structural and electrical facilities.
Careful attention to the development of plots and elevation plans will point out
unusual plant requirements and therefore, give reliable information about building
and site costs required for precise pre – construction cost accounting. Rational
design must include arrangements such as processing areas, storage areas and
handling areas in efficient coordination and with regards to such factors are given
below.
• Storage layout: storage facilities for raw materials and products may be located
in isolated areas or in adjoining areas. Hazardous materials become a decided
menace to life and should be isolated when stored. Storage tanks must be
separated to facilitate suitable quantity. Process water may be drawn from river,
wells or purchased from local authority. Electrical power will be needed at all
sites. So plant should be located close to a cheap source of power. A competitively
priced fuel must be available for steam and power generation.
• Effluent disposal: Effluent disposal should be according to the Indian standards.
The appropriate authorities must be consulted during the initial site survey to
determine the standards that must be met.
• Local community considerations: The local community must be able to provide
adequate facilities for the plant personnel: schools, banks, housing and
recreational cultural facilities etc... Also the plant should be located so that the
local community is not harmed. The proposed plant must fit in with and be
acceptable to the local community.
• Availability of suitable land: Sufficient suitable land be available for the
proposed plant and for future expansion. The land should be ideally flat, well
drained and have suitable load bearing capacity. A full site evaluation should be
made to determine the need for pining or other special foundations. It should also
be available at low cost.
• Political and strategic consideration: Capital grants, tax concessions and other
incentives provided by governments to direct new investment to preferred
locations, such as areas of high un-employment should be the overriding
considerations in the site selection.
• Climate: Adverse climatic conditions at a site will increase costs. Abnormally low
temperatures will require the provision of additional insulation & special heating
for equipment & pipe runs. Stronger structures will be needed at locations subject
to high winds or earthquakes.
Sample plant layout given here is taken from the Korea Plant Industries Association
based in Seoul, Korea.
Construction Schedule
About eighteen (18) months after receipt of the down payment, the plant will be
completed. However, this proposed schedule may be extended or shortened
according to onsite construction circumstances.
Operation Manpower
A sample requirement of manpower for the formaldehyde plant of capacity 400
m3/day is given below. Similarly the manpower requirement for 100 tones/day
plant can be drawn.
Classification No of Persons
Plant Manager 1
Engineer 1
Production Operator 3
General Worker 5
Total (based on Korean) 10
BIBIOLGRAPHY
(In alphabetical order)
2. Brownell, L.E. and Young, E.H., Process Equipment Design,1st edition, Wiley,
Prentice Hall (1962)
6. Kern, D.Q, Process Heat Transfer , J. A., 4th Edition , McGraw Hill
International Edition
8. McCabe, Warren L., Smith, Julian C., and Harriot, Peter, Unit Operations of
Chemical Engineering, 5th edition, Pergamon Press (1983)
10. Perry, J.H., Chemical Engineer‟s Handbook, 7th edition, McGraw Hill, Inc.
(1985)
11. Peters, Max S. and Timmerhaus, Klaus D., Plant Design & Economics, 4 th
edition, McGraw Hill, Inc. (1980)
12. Shreve R . N. & Brink J A , Chemical Process Industries , 5th Edition , McGraw
Hill International Edition .
14. Wilbrant, Frank C. & Dryden, Charles E., Chemical Engineering Plant Design,
4th edition, McGraw Hill, Inc. (1980)
1. http://www.sciencedirect.com
2. http://www.onesmartclick.com
3. http://www.chemical-engineering-design.com
4. www.udhe.com
5. www.SRIconsultant.com
NOMENCLATURE
Symbol Significance
ρ Density
Viscosity
M Molecular weight
H Height
D Diameter
T Absolute Temperature
P Pressure
Γ Residence Time
X Fractional Conversion
V Volume
Vo Volumetric flow rate
h Local Heat transfer coefficient
U Overall heat transfer coefficient
Q Heat
Cp Heat Capacity
Latent heat of vaporization
t Time
L Length
k Thermal Conductivity
NRe Reynolds Number
NPr Prandlt Number
Dt Diameter of tank
W Width
Z Height
ΔTm Logrithmic mean temperature
difference
O.D. Outside diameter
I.D. Inside diameter
Db Bundle diameter
Ds Shell diameter