Ac tcp2022
Ac tcp2022
FOR
IN
GOVERNMENT BUILDINGS
OF
2022 EDITION
This Testing and Commissioning (T&C) Procedure aims to lay down the minimum testing and
commissioning requirements to be carried out on Air Conditioning, Refrigeration and Mechanical
Ventilation Installation in Government Buildings of the Hong Kong Special Administrative Region
(HKSAR). Such requirements are applicable to both new installations upon completion and existing
ones after major alteration.
The present edition was developed from the General Specification for Building Services
Installation in Government Buildings of the Hong Kong Special Administrative Region 2022 Edition
that was established by the Architectural Services Department (ArchSD).
Electronic version of this T&C Procedure is to be viewed on and free for download from the
ArchSD Internet homepage. As part of the Government’s efforts to limit paper consumption, hard copies
will not be put up for sale.
The ArchSD welcomes comments on this T&C Procedure at any time since the updating of this
T&C Procedure is a continuous process to tie in with technological advances.
DISCLAIMER
This T&C Procedure is solely compiled for Air Conditioning, Refrigeration and Mechanical
Ventilation Installation carried out for or on behalf of the ArchSD in Government premises of the
HKSAR.
There are no representations, either expressed or implied, as to the suitability of this T&C
Procedure for purposes other than that stated above. Users who choose to adopt this T&C Procedure for
their works are responsible for making their own assessments and judgement of all information contained
here. The ArchSD does not accept any liability and responsibility for any special, indirect or
consequential loss or damages whatsoever arising out of or in connection with the use of this T&C
Procedure or reliance placed on it.
The materials contained in this document may not be pertinent or fully cover the extent of the
installation in non-government buildings and there is no intimated or implied endorsement of the sales,
supply and installation of the materials and equipment specified in this T&C Procedure within the
territory of the HKSAR.
TABLE OF CONTENTS
Page
1. Introduction 1
Annex
Annex I Testing and Commissioning Progress Chart for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation
Annex II Testing and Commissioning Certificate for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation
Annex III List of Calibrated Equipment/Instruments Necessary for the Testing and
Commissioning Works
1. Introduction
The procedures stated in this Testing and Commissioning (T&C) Procedure cover the activities in
preliminary tests and inspections, functional performance tests and the commissioning of newly
completed Installations and existing ones after major alteration. They are so compiled to facilitate
the work of Project Building Services Engineer (PBSE) and Project Building Services Inspector
(PBSI) / Project Electrical and Mechanical Inspector (PEMI), who are appointed as the Supervising
Officer’s Representatives, in the following aspects with respect to testing and commissioning:
(a) to vet and approve the T&C procedures for Air Conditioning, Refrigeration and Mechanical
Ventilation Installation;
T&C works shall be carried out as detailed in this T&C Procedure. Supplementary T&C plans may
be proposed as appropriate and agreed by PBSE.
The administrative requirements for T&C works are in general as specified in the General
Specification for Building Services Installation 2022 Edition and all current corrigenda/amendments
thereto published before the date of first tender invitation for the Contract issued by the ArchSD (the
General Specification).
All words and expressions shall have the meaning as assigned to them under the General Specification
unless otherwise specified herein.
(b) to verify that the performance of the installed equipment/systems meet with the specified design
intent, statutory requirements and energy performance, if any, through a series of tests and
adjustments; and
(c) to capture and record performance data of the whole installation as the baseline for future
operation and maintenance.
For the avoidance of doubt, depending on the specific demands of individual installation, the PBSE
may require additional or substitute T&C works in regard to any elements in the Installations other
than those indicated in this T&C Procedure.
The purpose of these tests is to ensure that all components and systems are in a satisfactory and
safe condition before start up. Preliminary adjustment and setting of equipment at this stage
shall also be carried out at the same time to pave way for the coming functional performance
tests.
Before carrying out any test, it shall ensure that the Installations comply with all relevant
statutory requirements and regulations. The T&C works shall also comply with all site safety
regulatory requirements currently in force. In particular, the Contractor shall note the statutory
requirements listed in the General Specification in carrying out the works.
The purpose of functional performance tests is to demonstrate that the Installations can meet
the functional and performance requirements as specified in the Contract. Functional
performance tests should proceed from the testing of individual components to the testing of
different systems in the Installations.
Temporary modifications may be made as the tests proceed. The specific tests required and the
order of tests will vary depending on the type and size of systems, number of systems, sequence
of construction, interface with other installations, relationship with the building elements and
other specific requirements as indicated in the Contract. The testing of systems may have to be
carried out in stages depending on the progress of work or as proposed.
Part of the tests may be required to be carried out in suppliers’ premises in accordance with the
provisions in the Contract.
Any performance deficiencies revealed during the functional performance tests must be
evaluated to determine the cause. After completion of the necessary corrective measures, the
tests shall be repeated as appropriate.
If any test cannot be completed because of circumstances that are beyond the control, it shall
be properly documented and reported to the PBSE, who shall then liaise with the relevant
parties to resolve the situation. The testing shall be resumed immediately upon the attainment
of a suitable testing environment.
Commissioning is the advancement of the Installations from the stage of static completion to
full working conditions and to meet the performance requirements as specified in the Contract.
This will include setting into operation and regulation of the Installations. Fine-tuning of the
commissioned system shall be carried out to match system performance to the actual needs of
the building occupier more closely.
Tests to meet statutory requirements shall be carried out. After the proper testing and
commissioning of the Installations, the relevant authorities shall be notified through the PBSE
Proposed T&C procedures together with the Testing and Commissioning Progress Chart shown
in Annex I shall be submitted to PBSE for approval.
All inspection and T&C results shall be recorded in the appropriate test record forms. A
complete set of these forms can be found in Annex II.
Data recorded in other formats may also be accepted subject to prior approval of the PBSE.
Upon completion of all the required T&C works, a testing and commissioning certificate shown
in Annex II shall be completed and signed to ensure that the agreed T&C works have been
duly carried out.
A functional performance test report covering all measured data, datasheets, and a
comprehensive summary describing the operation of the system at the time of the functional
performance tests shall be prepared and submitted to the PBSE. Deviations in performance as
specified in the Contract or the design intent should be recorded, with a description and analysis
included.
A final performance evaluation of the Installations, where required in the Contract, shall be
included in the commissioning report.
Systems shall be properly commissioned to demonstrate that all the equipment delivers
the designed capacities and that air and water flow rates are balanced in accordance with
the design.
Since the air systems are usually completed ahead of the hydraulic systems,
commissioning of the air systems will commence earlier than the water systems.
Prior to any commissioning works, the completion of the associated builder’s work and
the building services installations of the air-conditioning and ventilation system shall be
checked to ensure that commissioning can proceed without obstruction.
(iv) All builder’s work and building services installations in association with air-
conditioning systems are satisfactorily completed;
(v) All glazing works are completed and all windows closed;
(vi) All curtain walls and the building fabric are completed and reasonably water-
tight;
(vii) All external doors, all stairs and lobbies, and toilet doors are completed and
securable;
(viii) All ceiling works are completed, unless specifically agreed, with the
exception of those access areas required to be left open for final adjustment
and testing of high level building services equipment during the
commissioning period.
All dust generating activities by other trades are finished and all areas are
thoroughly cleaned and sealed to prevent ingress dust from getting into the
ventilation and air-conditioning systems during operation; and
(ix) All builder’s work in association with pressurised and depressurised areas
are completed.
(i) Air intake screens and louvres are unobstructed and clean;
(ii) Fan and other equipment chambers are clean and free of construction debris;
(iv) Fans are checked for impeller housing clearance and free of foreign objects;
(v) Heater batteries and cooler batteries are clean and fins are combed;
(vi) Condensate drain trays for cooling coil and drains for humidifier are
unblocked;
(ix) All electrical wiring circuits (power, lighting and controls) are completed, or
will be completed at the correct stage during the commissioning period;
(xii) Permanent power supply is available at the electrical panels, and all the
connected equipment can be switched on;
(xiv) All outside air, return air and spill air dampers are operative;
(xv) All fire and volume control dampers are fitted and left in the fully open
position;
(xvii) All VAV and CAV terminals are installed, together with grilles and diffusers;
(xx) All water systems are flushed, vented and filled and chemical cleaning
process is completed;
(xxiv) All functional and safety devices are installed and operational.
All aspects of the commissioning procedure shall follow the recommendations in the
relevant Commissioning Codes or Guides published by the CIBSE, ASHRAE or the
relevant Code of Practices issued by the Government. It shall include, but not limited to:-
(a) Preliminary checks to ensure that all systems and system components are in a
satisfactory and safe condition before start-up;
(b) Preliminary adjustment and setting of all plant and equipment consistent with
eventual design performance;
(d) Final regulation and demonstration that the installation delivers the correct flow
rate of fluids and air at the conditions specified in the Contract Documents.
Any specialist plant or equipment such as Central Control and Monitoring System
(CCMS) shall be commissioned and tested by the skilled commissioning engineer and/or
technician of the specialist equipment manufacturer.
3.6.1 Cleaning
Equipment or installation shall be kept clean internally and externally before testing and
commissioning.
(i) The system (new or old) shall be flushed using an appropriate chemical
dispersant of a type and strength recommended by a reputable chemical
water treatment manufacturer and guaranteed in writing by that company as
suitable for the application in question.
(ii) The quality of cleaning water discharged shall comply with EPD
requirements or be treated if needed as stated in Sub-section 6 of the General
Specification.
(iii) The chemicals shall remain in the system for 48 hours, including a minimum
of 12 hours with the pumped circulation in operation, unless otherwise
recommended by the supplier with substantiated technical support accepted
by the Supervising Officer.
(v) The success or failure of the above operation will depend on a high-speed
rate of draining down which is entirely related to the size of the drain points
and the ability of air to enter the system from the top.
(viii) Subsequent to the flushing operations, the large drain down points shall be
reduced to 15 mm valves or cocks or the sizes as indicated in the Contract
Drawings.
(i) Ductwork systems shall be cleaned by purging using the supply air fan, or
robot duct cleaning as recommended by the ductwork system cleaning
specialist. No fan shall be started until cleaning is commenced.
(ii) All submitted proposals for arrangements to ensure cleanliness of air and
water systems shall follow the recommendations in the relevant
Commissioning Codes or Guides published by the CIBSE, ASHRAE or the
relevant Code of Practice issued by the Government.
The piping system shall be welded by flow of dry nitrogen through the tube or
welding method recommended by the Manufacturer’s before pressure test and
evacuation test.
The refrigerant pipework when completed shall be pressure tested by nitrogen gas
in two or more steps up to manufacturer recommendation.
Hydraulic and functional performance tests shall be included under operating conditions,
on the Installations to the entire satisfaction of the Supervising Officer.
3.6.3.1 The proposed list of testing equipment/ instruments to be used for T&C (Annex
III) must be agreed with the PBSE prior to commissioning the work.
(a) sound level meter to BS EN 61672-1 [2013] with built-in octave filter and
sound level calibrator, Microphone Sensitivity: 2dB, Resolution: 0.1dB;
(c) a tachometer, which should be the high quality, direct contact, self-timing
type;
(d) multi-tester;
(a) Work tests shall be carried out in accordance with the type normally associated
with the specified item of equipment and to the standards as laid down in the
Contract.
(b) Static pressure tests shall be carried out on items such as pressure vessels, water
coils, plate type heat exchangers, radiator and convector elements, and all items of
plant or equipment, as laid down in the Specification and Drawings.
(c) Dynamic rotation tests shall be carried out on items such as fan impellers and drives,
compressor, pump impellers and drives. Tests shall be conducted through the
entire rotational speed range up to a maximum of 150% design operating speed if
such provisions have been made in the Contract. When items of plant are
purchased ex-stock, manufacturer’s test certificate will suffice.
(d) Rotational test on electric motors will not be carried out if the equipment is
constructed to the related content of IEC standard, or any other approved standards.
Attention shall be drawn to the magnitude of this task, the constraints of the water
mains, and the time frame within which testing must be carried out.
(b) PBSE reserves the right, at an early construction stage, to carry out destructive
inspection for a randomly selected sample of up to 2% of the total welded joints.
Should any of the above welds prove faulty in materials or workmanship, a further
2% of the welded joints may be ordered for destructive inspection. If any of the
additional welds inspected still found unsatisfactory, PBSE may order any number
of welds to be removed. The works shall include the removal and repair of the
unsatisfactory welds.
(c) The PBSE may conduct visual inspection for at least 2 welds done by each welder.
The welds for inspection shall be randomly selected by the PBSE. Each welder
shall be allocated an identification number. Each weld shall be stamped or marked
with the appropriate identification number to identify the welder. Repair of welds
if any defects are found.
(d) The following test standards, or any standards as deemed appropriate by the PBSE,
shall be followed:-
4.1.3.1 Before carrying out pressure test, spotted open-up inspection for joints shall be
required to inspect the internal finishing after brazing to ensure the quality of
the workmanship.
Refrigerant systems and circuits shall be pressure tested with nitrogen gas to test
pressures as indicated below: -
The method of recording the pressure tests shall be all as indicated in Clauses
4.1.6.6.5 and 4.1.6.6.6.
(a) Prior to application of insulation and painting to the welded pipe joints
and cleaned pipe surfaces, all water pipework shall be hydraulically
pressure tested to 1.5 times the maximum working pressure of the system
for not less than 2 hours or otherwise specified, without leakage or loss of
pressure. The maximum working pressure shall be deemed to be the static
head plus the total pump head. The minimum test pressure for water pipe
is 1,000 kPa.
(b) The pressure test shall be carried out in different sections of the hydraulic
systems in such zoning approved by the PBSE.
(c) Where any plant cannot withstand the maximum pipework test pressure,
it shall be isolated during the pipework tests, and then the isolated plant
shall be tested at its test pressure.
(d) All plugs, caps, tees and drain fittings shall be provided to enable the
pressure tests to be carried out.
(e) Before hydraulic pressure tests are carried out, all safety valves, gauges,
etc., shall be effectively isolated or removed. For all safety equipment,
these shall be effectively tested at their design working pressure during
commissioning of the Installations.
(g) The pressurised section shall then be left fully isolated without further
strokes of the pump and all joints must remain watertight for a period of
at least 2 hours. As to whether or not the section is sound shall be
governed by the rate at which the pressure falls. The PBSE acceptable
percentage of pressure falls shall be agreed with the SOR.
(i) Upon completion of the test, the water shall be released and drained away
as rapidly as possible, the section being then thoroughly sluiced through
to ensure the removal of as much dirt and dross as possible before being
refilled and put into service.
4.1.4.1 All ductwork shall be tested for air leakage in accordance with Clause 6.1.2 of
the General Specification.
4.1.4.2 The joints on ductwork shall be tested for air leakage. All openings such as fan
outlets, grilles, access panels, test holes, etc. shall be sealed before test:
(b) For preliminary and visual test, the method will include using chemical
“white” smoke generator. All openings in the ductwork shall be properly
sealed followed by the introduction of smoke.
Prior to the initial running of any electrically driven pump, fan, valve, electric heater or
automatically advancing filter, the following procedures should be adopted.
(b) that there are no unshrouded live components within the panels;
(c) that the panels and switchgears and heaters are clean;
(d) that the motor and surrounding areas are clean and dry;
(e) that the transit packing has been removed from contactors and other
equipment;
(g) that all mechanical checks on the pump, fan, motor, valve or automatic
filter, where appropriate, are completed;
(j) that all power and control wirings have been completed in detail to the
circuit diagram, paying special attention to circuit for star-delta connected
or specially wound motors;
(k) that the fuse and circuit breaker ratings are correct;
(l) that the starter overloads are set correctly in relation to the motor name-
plate full load current;
(m) that the dashpots are charged with the correct fluid and the time
adjustments and levels are identical;
(n) that insulation tests on the motor have been performed satisfactorily;
(o) that the adjustable thermal cut-outs are set correctly (check manufacturers’
test certificates);
(q) The power metering and monitoring devices are installed correctly, if any;
and
(r) The energy metering and monitoring devices are installed correctly, if any.
(a) check that the declared voltage range is available on all supply phases;
- the control circuit logic and the starter operation shall be tested before
the motor is rotated;
(c) where small motors have direct-on-line starting and simple control
circuits, the starter operation, etc., should be checked when first starting
the motor; and
(d) never energise electronic valve motors until the checks specified have
been completed.
Irrespective of the precautions taken during the construction stage to keep the
internal surfaces of pipework clean, the following procedures shall be used to
clean the system.
4.1.6.1.1 Flushing
(c) where make-up or feed tanks are used for flushing, ensure that
the maximum possible pressure is sustained on the system
during the flushing process. This may necessitate the provision
of a temporary parallel feed of mains water into the tank where
the ball valve has limited capacity. This T&C Procedure
assumes that the connection of the section from the tank is at a
high point in the section being flushed. The flushing water
wherever appropriate, shall be recirculated with suitable
filtration to reduce the water demand and wastewater discharge.
(d) Ensure:
(i) that flushing is carried out from the upper to the lower
sections of a multi-section system, flushing with the
lowest point; initial flushing should always be from small
bore to large bore pipe. Particular care is required on
reverse return systems and systems with roof-top chiller or
boiler plant;
(iii) that the maximum possible flow rates are used; and
Check:
(a) that where special valve packing is required, e.g. grease in medium or high
temperature system, this shall be in accordance with manufacturer’s
instructions;
(c) that the system has been cleaned in accordance with Clause 4.1.6.1.1;
Check:
(a) that probes, pockets, pressure gauges, siphons, orifice plates and taps, and
air vents are installed;
(b) that drains and overflows are connected and free from blockage;
(c) that connections to heating and cooling coils and all other heat exchangers
are correct in relation to the design water flow direction;
(e) that relief valves are installed as specified and are free to operate;
(f) that relief valve outlets are piped away to suitable drain points;
(g) the expansion devices for alignment and freedom from obstruction;
(i) that the strainer meshes are of the correct grade and material;
(j) that the changeover devices for duplex strainers are operative and that
there are means of isolation for single strainers;
(m) that drain cocks are closed and other valves are left open or closed
according to the plan for filling;
(o) that all pipework and fittings are adequately supported, guided and/or
anchored where applicable.
4.1.6.4.1 Pumps
Check:
(a) the external cleanliness of the pumps, remove and clean and
replace all strainers;
(c) that all components, bolts, fixings, tie bars etc., are secured;
(e) the level and plumb of pump and motor shaft and slide rails;
(direct drive pumps require particular attention in this respect);
(n) that glands are correctly packed and the gland nuts are finger-
tight only, pending adjustment to correct drip rate after start-up;
and
(o) that drive guards are fitted and the access for speed
measurement is provided.
Check:
(a) that the valves are installed the correct way round;
Check:
(b) that interior filling of cooling tower is clean and free of foreign
materials such as scale, algae, or tar;
(c) that the cooling tower fans are free to rotate and the tower basin
is clean; and
4.1.6.5.1 All water tanks shall, after erection, be filled with water and shall
remain filled for at least 24 hours during which all joints shall be
carefully examined. Any defect shall be rectified immediately and
the test repeated.
4.1.6.5.3 Charge the system with water by filling from the bottom upwards
forcing the air to high points – for venting to atmosphere. Careful
consideration should be given to the stage of valves and automatic
air vents before and during filling to avoid air-locks and excessive
spillage. Take care not to exceed the working pressure of the
system when filling from a high pressure source. When the whole
system is filled, disconnect the filling source, open the permanent
supply and adjust the tank levels.
4.1.6.6.1 General
4.1.6.6.3 Precautions
Before hydraulic tests are carried out, all safety valves, gauges, etc.
shall be effectively isolated or removed. These safety equipment
shall be effectively tested at their design working pressure during
commissioning of the Installations.
All test certificates shall be signed by the contractor varying out the
T&C and by the Supervising Officer or his Representative who has
witnessed the test. All test certificates shall contain the following
particulars: -
- Date of test
- Apparatus or section under test
- Makers number (if any)
- Nature, duration and conditions of test
- Result of test
- Name of contractor’s representative (in block letter) in charge
of test
- Name of Supervising Officer or his Representative at witness
the test
Dust and debris should be prevented from entering the duct system
as far as possible and the system inspected and cleaned as part of
pre-commissioning steps.
(b) temporary filter media shall be used where building work is still
in progress during T&C, and replaced with clean filters for final
measurements of flow rates;
4.1.7.1.3 Prior to the fitting of air cleaning equipment, ensure that the
environment is clean and then proceed to check the following for
cleanliness:
(h) humidifiers;
(i) eliminators;
(b) that heater and cooler batteries, humidifiers, filters, silencers, fire dampers,
sail switches, volume control dampers etc., are installed correctly in relation
to air flow;
(e) that dampers throughout the system are secured in open/close position, as
desired, with damper actuators locked;
(f) the free movement of fire dampers together with the location of, access to
fit the of fusible link assembly and the correct rating of fusible link; all fire
dampers are finally secured in open position;
(g) that all adjustable louvers are set without deflection, i.e. normal to face of
grille. Adjustable cones on diffusers are set either all in the fully up or all in
the fully down position; and
(h) that test holes are provided at strategic points for the measurement of branch
and total air volume flow.
Check:
(a) the builder's work for ducts and shafts are completed with air sealed;
(b) access doors to plant equipment are sealed around the whole periphery;
(d) axial-flow-type fans installed for correct air flow direction and,
where compounded, in correct order;
(e) level and plumb of fan and motor shaft and slide rails;
(n) drive guards fitted and access for speed measurement provided;
(c) that the transit packing has been removed from contactors and
other equipment;
(d) any safety switches fitted to access doors break the Low
Tension (L.T.) interlock circuit and destroy.
(e) H.T. potential before the door is open wide enough to allow an
arm or leg to reach a H.T. component within the filter casing;
also check that switches are held positively open to prevent
manual closure or closure by spring failure whilst access door
is open;
(f) check that H.T. potentials are reduced to a safe level within the
time it takes to open the door and reaches any H.T. component.
This will be of particular importance when door safety switches
do not merely augment a mechanical interlock earthing system
but are also the sole safety interlock, the value of bleed resistors
connected across each capacitor holding H.T. charge will be
critical; and
(d) that the wash water and f1uid coating systems are completed;
reservoir is charged with correct f1uid and drainage systems are
completed and free from blockage; connection is provided for
manual wash; and
(e) that fabric alter sections are loaded with media; if automatic
advancing then checks listed in Clause.4.1.7.4.2 shall be
carried out.
(b) that all safety and failure alarm systems and function correctly.
4.2.1.1 General
The system as detailed in Annex V Fig.V includes only those plant items
necessary for clarification of the regulation method described. The procedure
given here may have to be adapted to suit the particular arrangement.
4.2.1.2 Procedures
This section defines the procedures to be carried out in order to achieve a water
distribution system, which works satisfactorily and is regulated appropriately.
These works should normally be carried out with the medium at ambient
temperature and therefore there is no need for heated or chilled water to be
(a) check that all normally open isolating and regulating valves are fully open
and that all normally close valves are closed. In the case of thermostatic
valves it is essential that provision for fully opening of the valves is
available. Most electric motorised valves have either provision for
manual override of normal control using a switch on the main control box
or a facility to position the valves seat mechanically;
(b) check that the direction signs of all valves are the same as the water flow
direction;
(c) check that the horizontal or vertical alignment of all flexible joints is
within the tolerances recommended by manufacturers’ installation
guideline;
(d) open all control valves to full flow to heat exchangers of branch circuits;
and
(e) fully open the return and close the flow valve on the pump, close valves
on standby pump. Closing the flow valve on the duty pump will limit the
initial starting current, which is usually excessive at the first time a pump
is running due to bearing stiffness.
(a) the direction and speed of rotation of the motor shaft are correct;
(b) the motor, pump and drive are free from vibration and undue
noise;
(d) the motor running current on all phases are balanced and do not
exceed motor nameplate rating The flow valve can be opened
at this point to raise the running current to say 50 per cent of the
name-plate full load current;
(j) the motor running current are correctly matching with the speed
as specified by manufacturer’s pump data sheet on multi-speed
motors.
(b) gradually open the discharge valve from closed position until
the motor current reaches either the design value or the motor
full load current, whichever is the lower;
(c) check that the bearings and motor temperature remain steady,
that no noise or vibration develops and that no bolts or fixing
works is loose;
(e) vent all high points from time to time. When possible the
medium should be heated to maximum permissible levels to
assist in removing air from the heating system;
(f) adjust the gland nuts of the pump glands to give the correct drip
rate; (not applicable to mechanical seals.) and
(g) after 8 hours of running, check all strainers. If these are clean,
regulation can commence. Otherwise, clean the strainers and
run again for at least 8 hours and then re-check.
(b) this pump can be checked against the other duty pump. In the
unlikely event of failure of the duty pump, commissioning can
continue using standby pump; and
(c) carry out a full diagnosis of the reasons for the failure of the
duty pump before energising the standby pump to ensure that
any contributory causes are remedied.
(b) isolate the secondary system during this period to prevent any
accumulated deposits not removed during the flushing process
being carried over into the secondary services;
(d) only after a final check of both primary and secondary strainers
should actual regulation commence.
(b) referring to Fig. 4.2.1.5.1, the pressure drop across the device is
proportional to the square of the water flow rate. Hence the
actual-to-design water flow is given by;
Q1 P1
Q2 P2
where P1 = Actual pressure drop in kPa
P2 = Design pressure drop in kPa
Q 1 = Actual water flow rate in m3/s
Q 2 = Design water flow rate in m3/s
Pi Po
ΔP = Pi - Po
DEVICE
The AWB system shall perform 3 main functions, namely, (1) water balancing
for system commissioning, (2) monitoring of the flow rates and (3) re-balancing
of water due to change of load profile. The AWB shall be so designed to achieve
a fully automatic control in performing the water balancing. No on-field
adjustment, measurement and testing during the water balancing shall be
required. The only step is to input the design flow rates to the CCMS and
observe the change from the monitor and revise input data if any.
The AWB system shall balance all water circuit as specified in the
Particular Specification or the Contract Drawings to a steady
balanced state. The CCMS system shall coordinate with the control
of all other system such as chiller plant to complete the balancing.
The input design flow data and balancing point of each motorised
balancing valve shall be logged and password protected in the
CCMS. Power shall not be required to maintain motorised
modulating control valves at the balancing point.
Only the person with authority shall change the flow rates and re-
balance the water circuit. The password shall be at least 64-bit
encrypted and stored in the CCMS. The flow rate and temperature
at each motorised balancing valve shall be displayed with colour
graphic layout diagram on the computer monitor and updated at
intervals agreed by PBSE.
The colour graphic layout diagram shall show the location and
number of motorised balancing valves on the background of the
schematic water flow diagram with floor level and room name.
The CCMS shall generate and print out, if requested, tables showing
the actual flow rates, design flow rates and the corresponding
percentage difference of the water passing through motorised
modulating control valves against their location and floor level. The
difference between the input design flow rates and actual flow rates
shall be in accordance with Clause 4.2.1.5.1.
4.2.1.6.4 Demonstration
The system should have been cleaned internally in accordance with Clause
4.1.7.1 but further precautions shall be taken before starting the fans for the first
time:
(c) check that suitable temporary protection has been provided for anything
within the spaces served by the system which could be damaged by initial
discharge of dust from supply outlets at first starting;
(d) install main inlet filter cells, properly coated as necessary, to avoid
introducing additional dirt into the ductwork system after start-up;
The scope of the test is to verify effective performance of the automatic fabric
roll filter in accordance with the manufacturer’s technical information and/or
the stated requirements in the Particular Specification. The general test
procedures for the unit is:
(a) preliminary checks in accordance with Clause 4.1.7.4.2 shall have been
completed;
(d) with the differential pressure control device looped out, close the isolator
controlling supply to filter and test operation by the manual advance switch;
(e) leave the filter on manual advance until the correct total air flow through
the filter is established;
(f) the correct total air flow through the filter shall be established as part of the
procedure for regulation of air flow (see Clause 4.2.2.5 below);
(h) an inclined manometer with pressure sampling points adjacent to the filter
fabric will be used to measure the prevailing static pressure drop across the
clean filter and this will be recorded;
(i) the filter may then be progressively blanked off (e.g. with cardboard) until
the manometer indicates the design ‘dirty filter’ pressure drop;
(j) the differential pressure control will be adjusted to start advancing the filter
at this ‘dirty filter’ pressure drop and to stop advancing the filter at the
design clean filter pressure drop; and
(a) only Registered Electrical Worker(s) with recognised training from the
filter supplier on maintenance of high tension portion of the equipment
should be allowed to enter the filter casing;
(b) the responsible person/team should have the interlock key which controls
the opening of the access door to the section of filter which he is entering or
a fuse link or other item to prevent the filter being energised;
(c) a second person should be stationed outside the door as an observer and he
will normally also be in control of the operation of the power pack from this
position;
(e) where the power pack is remote from the filter a shorting bar should be
securely fixed between earth and each H.T. feed to the filter.
(a) check that no one is inside filter casing, that access doors are
closed and that no entry can otherwise be made to the filter
interior;
(b) cancel and lock out any remote control system for filter;
(f) restore full automatic control sequence and make it ready for
the establishment of air flow through the filter.
When air flow is established through the filter (see Clause 4.2.2.4.5):
(g) readings should normally be made with the meter placed within
the filter casing and observed from the outside through the
observation window;
(h) the correct total air flow through the filter shall be established
as part of the procedure for regulation of total air flow (see
Reference no. 4 of Annex V);
(i) the uniformity of air velocity distribution across the face of the
de-energised filter bank should be checked using an
anemometer after the regulation of total air flow (see Reference
no. 4 of Annex V). To do this, it will be necessary to override
the interlock with the supply fan;
(k) the mean indicated velocity is then calculated and each of the
point readings is expressed as a percentage of this mean. The
(l) upper limits will always be critical and a failure to meet the
specified tolerances must be rectified.
(a) wherever possible the first start of any motor should be on light
load;
(a) that the direction and speed of rotation of motor shaft are
correct;
(b) that the motor, drive and fan are free from vibration or undue
noise;
(j) note the reduced speed rev/s and the motor running current on
multi-speed motors;
(a) after the initial light load run, the machine shall be stopped and
restarted at normal starting load, and the checks listed in Clause
4.2.2.4.2 repeated; and
(a) after a short run at normal load (a few minutes’ run will
normally suffice) flexible connections to terminal units, etc.,
and terminal filters (which were removed in Clause 4.2.2.1)
shall be restored to position;
(d) the dynamic balance of the fan and motor shall be investigated
and corrected if necessary; and
(e) the requirements of checks listed in Clause 4.1.7 have been met;
(g) the associated air supply or extract system that has not been
regulated should normally be shut down and the duct system
under regulation shall be balanced against atmosphere i.e. with
doors or windows open (or purpose-made provisions) to
maintain the relevant spaces under atmospheric pressure.
(b) All air diffusers and grilles shall be balanced by regulating the
dampers provided. Each system of ductwork shall be balanced
so that every branch duct, diffuser, grille and pressure relief
valve shall carry the required quantity of air;
(a) the self-balancing system characteristic requires little actual air balancing
work. The exercise is targeting on verifying the performances of the VAV
boxes and fan airflow discharge in response to changes in controlling
parameters;
(b) check that the system is clean, to avoid damage to VAV box components.
Check that Site conditions in Clause 4.2.2.5.1 are met, unless otherwise
stipulated below;
(c) fully review the recommendation from supplier in the setting to work and
commissioning of both VAV box and variable airflow device. Adhere to
these recommendations to avoid damages due to improper handling;
(e) for a variable speed drive operating on variable frequency control, obtain
data pertaining to the change of fan motor speed and corresponding airflow
with the change of frequency. For a vortex damper control, obtain similar
data against the change of damper setting. Determine the maximum and
minimum fan speed or damper settings;
(f) construct a theoretical system curve with approximate surge area. The
system curve initiates at the minimum inlet static of the boxes, plus system
loss at minimum flow and terminates at design maximum flow;
(g) for variable speed control, the operating range is between “the minimum
speed that can produce the necessary minimum box static at lowest flow
while still remaining in the fan’s stable range” and “the highest speed
necessary to obtain maximum design flow”;
(h) for inlet vane damper control, the operating range is between “the surge line
intersection with the system curve” and “the maximum design flow”;
(j) set the supply and extract fans systems to their minimum speed conditions.
Start the fans, and gradually increase the airflows. Motor running current
checks should be made at various increments, to prevent overloading.
Check that the fans are operating within the extreme conditions identified
from (e);
(k) check system static pressures at or close to the positions specified for the
pressure sensor for automatic regulation of fan speed, and at VAV boxes
near to the fan. This is to prevent over-pressurisation of system components;
(l) should abnormal excessive current or pressure are detected in (j) or (k)
above, check for any improper settings. Refer to the designer for unresolved
problem;
(m) with fan motor current and system pressure not being exceeded, increase
the airflow to the maximum design condition;
(n) verify the VAV box factory settings on maximum and minimum flows with
change in controlling parameter (e.g. actuator responses to voltage
fluctuation according to temperature change). Also check intermediate
settings. This must be done according to the VAV manufacturer’s
recommendations;
(o) in conducting the exercise in (n) for a particular box, it may be necessary to
throttle airflow to other boxes/branches in order to bring the one at test with
sufficient pressure and flow;
(q) check that the least favoured VAV box is also operating at the system’s
minimum design airflow;
(r) for VAV box delivering air to a number of secondary terminals, air
balancing of these terminals should be carried out according to Reference
no. 4 of Annex V;
(s) repeat (h) to (n) for different design conditions dictating the flows of fresh
air and recirculation;
(t) in the above processes, the fan drive mechanism will have to be repeatedly
adjusted. Do this in accordance with the fan drive manufacturer’s
recommendations;
(w) it is important to ensure that pressure sensors for fan airflow control are so
located that they offer responsive, stable and reliable regulation across the
full range of fan operation. Should the pre-determined positions not be
appropriate, reflect this to the PBSE.
(a) check that Site conditions in Clause 4.2.2.5.1 are met, unless otherwise
stipulated below;
(b) check that suitable paths for make-up or spill air are provided. Open all
doors and hatches between the pressurised spaces;
(d) balance the air terminals in accordance with Reference no. 4 of Annex V;
(f) close all doors and hatches so that the space is in its normal operating
condition;
(g) run the other extract or supply fan previously not in operation;
(l) if the flow rates are within specified tolerance, the balancing work is
completed;
(m) if the readings are not within tolerance, re-check the system balance
described in (d) & (e) above and, where necessary, make adjustments to
reinstate the balance of the previously set total volume flow rate. Reiterate
this step until no further adjustment is required;
(o) verify that airflow indicator i.e. Inclined Tube Air Flow Indicator (ITAFI)
between spaces served are fixed and of correct size and type; and
(a) dual duct system comprises a cold duct and a hot duct, respective air to be
mixed in a mixing box before discharging to air-conditioned space at the
appropriate dry and wet bulb temperatures. The cold duct usually can
handle 85% to 100% of system flow, and the hot duct 40% to 80% flow;
(b) check that Site conditions in Clause 4.2.2.5.1 are met, unless otherwise
stipulated below;
(c) start balancing by setting all room control thermostats for maximum cooling,
fully opening the cold air valves;
(d) proceed to the extreme end of the system (longest duct run) and check the
static pressure drop across the box. The reading should exceed or equal the
minimum static pressure recommended by the manufacturer of the box
(about 185 Pa static pressure is common for the mechanical regulator);
(e) for mixing boxes that are not factory preset, set the mechanical volume
regulator in accordance with manufacturer’s recommendation. Refer to
calibration curve wherever appropriate;
(g) for mixing box delivering air to a number of secondary terminals, air-
balance them according to Reference no. 4 of Annex V;
(h) air-balance the flow from boxes to Reference no. 4 of Annex V should
relevant dampers be available and the readings in (f) indicate unacceptable
tolerances. Make adjustment to box air valve if necessary in accordance
with manufacturer’s recommendation;
(i) change the control settings to full heating and make certain that the controls
and dual-duct boxes function properly; and
(j) measure airflow from all air terminals and check against design. For out-of
range mixing box, make adjustment to the air valve if necessary in
accordance with manufacturer’s recommendations.
The AAB system shall perform 3 main functions, namely, (1) air balancing for
system commissioning, (2) monitoring of the airflow rates and (3) re-balancing
of air due to change of load profile. The AAB shall be so designed to achieve a
fully automatic control in performing the air balancing. No on-field adjustment,
measurement and testing during the air balancing shall be required. The only
step is to input the design airflow rates to the CCMS and observe the change
from the monitor and revise input data if any.
(b) The AAB system shall balance all air circuit as specified in the
Particular Specification or the Contract Drawings to a steady
balanced state. The CCMS system shall coordinate with the
(c) The colour graphic layout diagram shall show the location and
number of each motorised volume control damper on the
background of the airflow schematic diagram with floor level
and room name. The CCMS shall generate and print out if
requested tables showing the actual flow rates and design flow
rates of the air passing through motorised volume control
dampers against their locations and floor level. Suitable
hardware and software such as flow meter, actuators, DDC and
the operating system shall be selected to achieve overall
performance of the AAB in accordance with Reference no. 4 of
Annex V.
4.2.2.9.4 Demonstration
The T&C of air handling units should be carried out in line with the General
Specification and the items as specified below.
4.2.2.10.1 Operation
4.2.2.10.2 Inspection
(b) verify that the drives are installed properly and are of the correct
size and type. Verify that the inlet vanes are working;
(d) verify that the fan wheels are on a single shaft. If they are on a
split shaft, then verify that the shafts are properly connected to
the drive end; and
(e) verify that the filters are clean and of correct size and type.
4.2.2.10.3 Procedures
(a) check the fan for proper operating condition and the fan motor
shall be below the full-load current rating;
(e) adjust fan speed to obtain 100 to 110% of design airflow (m3/s);
4.2.2.10.4 Compliance
(a) to comply with this T&C Procedure, complete all of the above
steps and record all data on the report forms; and
(b) all deficiencies that affect the above T&C works should be
resolved by the installing contractor(s) and well include the
deficiencies into the report.
All the procedures are similar to Clause 4.2.2.10 for AHUs except the testing is
for constant outside air coming directly into contact with the units.
4.2.2.11.1 Operation
4.2.2.11.2 Inspection
(b) verify that the drives are installed properly and are of correct
size and type;
(d) verify that the fan wheels are on a single shaft. If they are on a
split shaft, then verify that the shafts are properly connected to
the drive end;
4.2.2.11.3 Procedures
(a) set and test the outside air quantity that could meet the
minimum requirement as specified;
(b) balance the systems that distribute outdoor air directly to the
space to the quantities specified;
(d) verify that the outside air quality remains constant under all
modes of operation;
(e) test and set the outside air and verify that the minimum airflow
rate (m3/s) stays constant. Verify that the outside system air
operates when occupied and when the exhaust system is on; and
4.2.2.11.4 Compliance
(a) to comply with this T&C Procedure, complete all of the above
steps and record all data on the report forms; and
(b) outside air which makes up with the return air is also a
consideration required in balancing the outside air, and should
be reported if not included in the minimum outside air
requirement.
4.2.2.12.1 Operation
4.2.2.12.2 Inspection
4.2.2.12.3 Procedures
(a) use manufacturer’s rated airflow unless ducted, then use a duct
traverse to determine airflow. If duct traverse is impossible,
then use summation of the outlet readings;
(c) measure entering and leaving air dry and wet bulb temperatures;
(g) measure and record the water pressure drop across the coil and
compare to the design. Only rely upon pressure drop for flow
determination if other means noted are impossible to obtain;
(j) verify that controls operate properly and are in correct sequence.
Note any deficiencies and record.
4.2.2.12.4 Compliance
The scope of the test is to verify effective performance of the water scrubber /
kitchen exhaust hood and its associated facilities in accordance with the
manufacturer’s technical information and the stated requirements in the
Particular Specification. The general test procedures are:
(a) the mechanical and electrical installations shall be visually inspected, tested
in conformance with manufacturer’s technical installation guide and
information;
(b) re-sealing test holes shall be provided at the main discharge duct for total
air flow and static pressure measurements. The test hole position shall be
determined on the Site. Test holes usually shall not be drilled on the bottom
side of air duct;
(c) the exhaust air fan shall be generally tested in accordance with relevant
sections for fan, and noise measurement shall be in accordance with relevant
section;
(d) the water circulating pumps should be generally tested in accordance with
relevant section for pumps;
(e) the capture velocity or slot velocity at the hood face or entry slots shall be
measured according to the appropriate standards; such as ANSI/ASHRAE
41.2-2018 and ANSI/ASHRAE 70-2006 (RA2021) on the
recommendations by the Associated Air Balance Council (AABC) U.S.;
(f) water curtain profile at the hood entry shall be visually checked and water
consumption shall be metered throughout the test period;
(g) the mist eliminators shall be installed in correct position and excessive air
mists shall not be allowed;
(i) when the whole installation is featured with two speed flow control modes,
the test procedures shall be carried out for both modes;
(j) after completion of test, the air flow pattern around the hood entry shall be
further verified with smoke candle. The smoke candle shall be positioned
300 mm below hood face and 150 mm around the hood periphery;
(k) during test of hood exhaust system, the general kitchen ventilation systems
shall be put in operation;
(m) Oil mist and odour removal performance shall be verified by recognised
testing laboratory and equipment shall be tested to meet Underwriters
Laboratories UL Standard 710 [2012] - Exhaust Hoods for Commercial
Cooking Equipment.
4.2.2.14 Outdoor Air Pre-conditioner, Heat Wheel and Air Heat Exchanger
(a) verify that all seals are properly installed and adjusted;
(b) measure and record the flow rate of air entering the exhaust
section;
(c) measure and record the flow rate of air leaving the outside air
section;
(d) measure and record the dry and wet bulb temperature of air
entering and leaving the exhaust side;
(e) measure and record the dry and wet bulb temperature of air
entering and leaving the outside air side;
(f) calculate and record the sensible and total capacity of each
airstream;
(g) measure and record the pressure drop on each side of the heat
exchange section;
(h) measure and record the starting and running current of the
equipment; and
(a) The following tests shall be carried out where applicable: static
pressure test, dynamic rotation tests and inspection of welds in
piped services;
(a) check that the indoor and outdoor units are installed according
to supplier’s instructions and recommendations including
maximum pipe run, etc;
(b) check that the safety devices and necessary operational control
are provided as per requirements of the General Specification;
(c) check that pipeworks of correct pipe sizes are installed and
insulation is completed;
(f) ensure that the system has been properly evacuated and leak-
tested;
(i) measure the following and note down in the record sheet:
4.2.3.1 General
T&C of refrigeration system shall be carried out by the skilled and experienced
persons preferably assigned by the original manufacturer.
Normally the refrigeration systems are categorised by the following species (not
exhaustive).
The following points are common to all systems and require careful handling:
For chilled water and condenser water systems, carry out the
T&C procedures as listed in Clauses 4.1.6 and 4.2.1 in addition
to the following.
Check :
(ii) that where chilled water tank is provided the tank lid is
fitted and secured;
(iv) that any splash guards for cooling towers and evaporative
condensers are fitted properly.
For air handling systems and any airways associated with the
air-cooled condensers, evaporative condensers and cooling
towers, carry out the following checks.
Check:
Check:
(iii) that the safety and control devices are fitted : such as the
low pressure and high pressure cut-out, oil pressure cut-
out (where fitted), chilled water low temperature
thermostat, low water flow safety device and any
protective solenoid valves being specified;
(a) Fans
(b) Compressors
Check:
(iv) level and plumb of compressor and motor shaft and slide
rails (applicable to open type compressor only);
(viii) that drive guards are fitted, the access for speed
measurement is provided and nipple extension for motor
lubrication is provided (if applicable);
(c) Drives
Check:
(i) wiring from all safety devices and liquid line solenoid
valve are completed; and
(ii) charge the entire system to the desired test gauge pressure
in accordance with manufacturer’s instructions using dry
nitrogen;
(v) repair any leaks found in the system. Leaks must not be
repaired while the system is under pressure;
(a) setting to work and adjusting air handling plant shall be carried
out in accordance with Clauses 4.1.7 and 4.2.2; and
(b) for systems employing direct expansion air coolers, check that
commissioning of the main air distribution plant has progressed
sufficiently through Clause 4.2.2 so as
4.2.3.2.4 Charging
(a) Procedures
(v) check that the condenser water valves are open and the
pressure or temperature actuated valves (where fitted) are
operative;
(c) Start-Up
(i) test and ensure free movement of all rotating parts of each
compressor. Disconnect drive coupling or vee-belt.
Check the correct direction of motor (applicable to open
type compressor only);
(iii) start the compressor and observe for plant with both
‘manual’ and ‘auto’ selection, after 2 or 3 successful
‘manual’ operations change over to automatic control
and check:
(d) Shut-Down
(e) Running-In
(xii) Low pressure cut-out: Close the liquid line shut off valve
(isolating valve on liquid receiver or cause the liquid line
solenoid valve to close). Isolating valves shall be opened
and closed as slowly as possible and then
This cannot be carried out until the plant has been in operation
for at least 72 hours. By the end of the running-in period any
improper adjustments or sources of potential troubles shall
become apparent.
(vi) Check the drive belts for proper tension and alignment;
and
This shall be carried out after the system has been in operation
for not less than 1 week:
Check that:
(b) all flanged connections are correctly aligned and tightened, with proper
gaskets in place;
(c) the liquid line and float valve assembly are completed;
(f) the purge unit for negative pressure refrigerant systems, and small-bore
accessory piping are completed, including cooling water connections where
specified;
(i) temperature control bulbs/sensors are correctly located, space between bulb
and well is filled and suitable heat conducting fluid, and capillary tubes are
free from damage or distortion.
These are factory pressure and leak tested, often insulated, and
delivered to site with a holding charge of refrigerant /nitrogen.
(v) charge the purge unit to the desired test pressure with
proper type of refrigerant in accordance with the
manufacturer’s instructions;
(vi) check the entire purge unit for leaks using a halide torch
or electronic leak detector. Tap all joints with a mallet
and remove any flux that may be adhering to them;
(vii) repair any leaks and retest the unit. Leaks must not be
repaired while the system is under pressure;
(xiii) check all joints for leaks by electronic leak detector, then
followed by using a soap solution “bubble” test and
(xiv) repair any leaks found in the system. Leaks must not be
repaired while the system is under pressure;
4.2.3.3.4 Charging
(a) Procedures
The chilled water and condenser water systems must have been
thoroughly checked in accordance with Clauses 4.1.6 and 4.2.1,
and be ready for operation. For this section to be carried out
completely, some load on the chilled water plant (probably at
least 50%) is necessary.
(i) Controls
pneumatic/electric switches;
Check:
Check:
(c) Start-Up
(iv) start the chilled water and condenser water pumps and
cooling tower fans;
(vi) start the oil pump and allow the main compressor to run;
- Compressor type
Energise the purge heater and after 30 minutes, start
purge compressor, or in accordance with
manufacturer’s instructions. The longer in time is
better;
- Thermal type
Start in accordance with manufacturer’s instructions;
(d) Shut-Down
(i) stop the compressor and then the chilled water pumps,
condenser water pumps and cooling tower fans in
sequence;
(iii) check that the operation of oil pump continues until the
time delay relay causes it to stop;
(e) Running-In
(ix) take the gauge and other readings and compare them with
design figures, typically;
- evaporator pressure;
The charging operations are usually carried out on the Site. In addition,
cleanliness, stage of system and mechanical and electrical components must be
checked.
Check:
(b) that the chilled water and condenser water circuits are complete and are
ready to operate. Water treatment is available if specified;
(c) that the steam and condensate, or hot water piping system are completed
with adequate pressure gauges, thermometers, and test points;
(e) for hot water piping system: control valve is correctly installed;
(g) that auxiliary water piping and drains are completed (as may be required for
pump motor and cooling during start-up periods);
(h) that all electrical wiring, starters, motors, and controls are completed;
(i) that pneumatic controls (where used) are installed, pneumatic piping is
completed and tested, air pressure is available;
(j) that all gauges and thermometers (or test points) are installed on water inlets
and outlets to evaporator, absorber and condenser;
(k) that dry nitrogen and refrigerant are available for pressure and leakage
testing (when carried out on the Site);
(l) that lithium bromide solution and chemical oils are available for charging,
together with necessary equipment;
(m) that for the system to be operated and properly commissioned. It is usually
necessary to have at least 75% of the cooling load available;
(i) isolate the purge unit (manual valve between purge drum
and purge pump);
(iii) raise the gauge pressure within the unit to test figure
(typically 0.75 bar) with dry nitrogen;
4.2.3.4.2 Evacuation
4.2.3.4.4 Charging
(a) Procedures
(ii) the chilled water and condenser water systems must have
been thoroughly checked in accordance with Clauses
4.1.6 and 4.2.1 and be ready for operation. The heating
(v) check the settings and the functional operation (by raising
and lowering the temperature of water at sensing element
if necessary) of the following items as appropriate to the
system under consideration;
(c) Start-Up
(v) start the chilled water and condenser water pumps, and
cooling tower fans; and
(d) Shut-Down
(ii) check that the time delay relay permits the chilled water
pumps and the solution pumps to continue operation
for the period of time specified by the manufacturer
(typically about 7 minutes).
(e) Running-in
(i) with purge unit operating allow the system to operate for
approximately 8 hours and at the same time observe the
performance and make any necessary adjustments.
Ensure purge unit operates satisfactorily;
(a) Check:
(i) that the unit refrigerant and oil charges are intact. If unsatisfactory,
arrange for checks and repair leaks; pressure test, dehydrate and
recharge by the manufacturer;
(vii) repair any leaks and retest the system. Leaks must not be
repaired while the system is under pressure;
(a) Procedure
- pressure switches;
- temperature switches;
- timing relays;
- anti-recycling relay;
- flow switches;
- other adjustments;
- this includes:
(c) Start-Up
Manual sequence
(v) if oil pressure does not reach the required pressure the
system will automatically shut down (in approximately 5
seconds). Controls must be reset and/or fault rectified
before proceeding;
(xi) check the oil gauge pressure and level at 100 per cent
capacity (typical 2.0 bar with level to bottom of upper
sight glass in sump); and
(d) Shut-Down
Automatic Sequence
(i) check that the large expansion valve (if provided) closes
at approximately 25% capacity (may be activated by cam
switch in relation to unloader slide valve travel);
General criteria for setting up the ground rules for proper T&C of cooling towers
are as described below.
(a) the water system serving the tower has been thoroughly cleaned,
preliminary checks and setting to work and balancing have
been carried out in accordance with Clauses 4.1.6 and 4.2.1;
(b) the fan serving the cooling tower has been set to work in
accordance with Clauses 4.1.7 and 4.2.2 noting any permanent
obstruction and removing all foreign obstructions;
(c) the interior fills of the tower are properly cleaned and free from
foreign materials such as scale, algae or fur;
(d) the water level in the tower basin is maintained at the proper
level, making sure by visual check of the basin sump that the
centrifugal action during full flow does not cause any
entrainment of air which may cause pump cavitation;
(e) all valves except balancing valves in the water system are in
full open position; and
(e) measure inlet and outlet dry and wet bulb temperatures;
(f) use entering & leaving wet bulb temperatures to determine the
tower performance against design;
(g) use entering and leaving dry and wet bulb temperatures to
determine the rate of evaporation involved;
(h) measure wet and dry bulb temperatures between 1 and 1.5
metre from the tower on all sides. These readings should be
taken half-way between the base and the top of the inlet louver
at not more than 1.5 metre spacing horizontally and averaged
out;
(i) note any unusual inlet conditions, wind velocity and wind
direction at the time of test;
(a) the recommended procedures state the ways to undertake automatic testing,
monitoring and commissioning of the refrigeration system in achieving the
designed functions and performance specified;
(b) these procedures shall not be treated as the starting-up T&C for individual
refrigeration machines such as chillers, pumps, cooling towers, etc., which
require to be closely monitored, aligned, adjusted, tuned and balanced by
skilled and experience technicians in accordance with the
(c) the chiller & CCMS shall have a high level integration.
(j) fault signal(s) from each chiller, cooling tower, variable speed
controller and other refrigeration machines;
DDC
Ts Ts
Tl1 Te1
CCMS
CHILLER
m1
DDC
Ts Ts
Tl2 Te2
CHILLER
m2
DDC
Ts Ts
Tl3 Te3
CHILLER
m3
DDC
M COMMON PIPE
BY-PASS
m4
MODULATING
VALVE m5
FLOW METER
(c) for full load performance test, the following procedures are
used:
(ii) at the same time, the testing chiller will sense the
substantial temperature difference between the entering
and leaving chilled water. The compressors of the testing
chiller will cut-in one by one until the testing chiller
reaches the full load condition; and
(b) the chilled water energy output will then be plotted against the
actual power consumption under different load profile in order
to work out performance curves for each chiller;
(c) for a full range of performance data, the test should be carried
out for a sufficient long period of time (say 12 months or within
the whole Maintenance Period) such that data can be obtained
from each chiller from its full load condition to the lowest
partial load condition; and
Detailed requirements relating to IAQ shall be under Section 6.3 of the General
Specification. IAQ parameters and their level of control are specified in the
Particular Specification.
(b) HCHO and O3 may use passive sampling methods but real-time monitoring
is still preferred to passive sampling methods.
(c) All builder’s works associated with the IAQ systems must be completed
and painted with dust preventing compound;
(e) All dust generating activities by other trades are completed and all areas
thoroughly cleaned to prevent ingress of building dust and debris into the
return air or fresh air intake systems;
(f) Air intake screens and louvres are unobstructed and clean;
(i) Floor gullies and drainage traps are clear and operational;
(j) All condensate drains and trays are clear and water can be drained away
satisfactorily;
(m) All outside air, return air and spill air dampers are operative;
(n) All volume control dampers are fitted and are at appropriate opening
positions;
(o) Ductwork systems are cleaned by purging of the supply air fan, or by robot
duct cleaning recommended by the ductwork cleaning specialist;
(p) All VAV and CAV terminals are installed, together with grilles and
diffusers;
(r) Air conditioning systems and the building indoor area are purged to the
standard acceptable by the Supervising Officer.
(a) All air handling : Fans, AHUs, FCUs, water scrubbers, Terminal Air
equipment Control devices, grilles and diffusers.
(b) Air cleaning : All pre-filters, main filters, high efficiency filters
equipment and chemical filters, UV sterilising light assembly
and activated oxygen air purifier
IAQ assessment shall be performed as the last part of the testing and
commissioning process upon completion of the ACMV installation. Further
assessments shall also be done six months after the building has been occupied
and at two months before the expiry of the certified Maintenance Period, i.e.,
For measuring IAQ compliance, assessment shall be carried out by the real-time
monitoring method, the integrated sampling method or airborne bacteria
sampling method. Real-time monitoring shall be used for detection of pollutant
sources and provide information on variation of pollutant levels throughout the
day. The integrated sampling method, either active or passive sampling, shall
be carried out by taking samples of a particular pollutant over 24-hour basis to
obtain the total exposure level data. If it is not practicable to have 24-hour
samples, short-term sampling to cover the worst scenarios shall be considered
subject to approval of the Supervising Officer. All measurements shall be
conducted with the use of calibrated instruments and equipment, standards and
reference materials with traceability to international or national standards. The
corresponding reporting forms of these three methods are as follows:
The sample method, location of measuring & monitoring IAQ parameters and
measurement method of IAQ parameters shall refer to Part D and as detailed in
the Particular Specification requirement.
All air samples shall be collected at 1.0 - 1.2 m above the floor level.
(a) real time monitors shall be incorporated with data logging facilities. The
logged data shall be uploaded to suitable devices for storage and data
analysis. The measurement principles of the monitors are provided at
Reference no. 1 of Annex V. Alternative measurement principles shall be
allowed subjected to the approval of the PBSE;
(b) except air velocity, the measurement time at each sampling position shall
be of minimum 8 hours and covering the whole normal operation hour of
the building, at least one reading should be taken every 5 minutes. Shorter
sampling time shall be allowed subject to the approval of the PBSE;
(e) after logging data for the required sampling period, upload the data to
suitable devices for storage and data analysis. Ignore the readings of the
initial 10 minutes, and then obtain the highest value of 8-hour average;
(f) sample the outdoor air condition in parallel with the sampling of the indoor
condition, the minimum sample of outdoor shall be 4 number 5-minutes
samples taken at 4 time slots distributed within an 8-hour sampling period;
(g) report and record the results, a record form is provided at Reference no. 4.26
of Annex II; and
(h) since the air velocity usually will not fluctuate with time, therefore a shorter
sampling time can be allowed and to be determined by the qualified
examiner.
(b) the sampling time at each sampling position shall be of minimum 24 hours
and covering a normal operation day of the building;
(c) take a 24-hour sample of the outdoor condition in parallel with the sampling
of the indoor condition;
(d) send the samples to the laboratory for analysis within 5 days. Before
analysis, the sampling tubes / filters / bags / canister should be treated and
stored as per manufacturers' recommendations. The laboratory results
should be signed by an approved signatory; and
(e) report and record the results, a record form is provided at Reference no. 4.27
of Annex II.
(b) at each sampling position collect 5-minute samples using Andersen multi-
hole impactor samplers with Tryptic soy agar plates at 4 time-slot evenly
distributed within an 8-hour sampling period covering periods of highest
number of occupancy of a normal operation day;
(d) send the plates for incubation in less than 24 hours. Incubate the plates at
30C for 48 hours, and then perform bacterial count. Standard aseptic
techniques should be practised throughout the whole process; and
(e) report and record the results, a record form is provided at Reference no. 4.28
of Annex II.
4.3.1.10 10% of the integrated samples shall be performed for quality control including
duplicate samples, and field blanks.
4.3.1.11 Report the T&C Result of IAQ measurement by using the report form provided
at Reference no.4.25 of Annex II.
T&C shall be demonstrated by carrying out that the installed air-conditioning and
ventilation equipment and system can satisfactorily perform to the requirements on
energy efficiency and energy conservation as stipulated in the Code of Practice for
Energy Efficiency of Building Services Installation issued by the Electrical and
Mechanical Services Department (EMSD), hereinafter referred to as the “Building
Energy Code” or “BEC”.
T&C should be properly carried out before the handover of projects in order to verify that
the energy efficiency performance of the following equipment and system, but not limited
to, based on technical documents and calculations submitted, can be adequately achieved.
(d) optimum working performance of motion detecting sensing device, enthalpy control
device of free cooling, heat pipe installation, solar heating installation, dehumidifiers
and outdoor air pre-conditioners.
(a) factory test on equipment should be conducted according to the recognised testing
standards such as AHRI, ISO, BS EN and so on. Certificates should be issued in
order to demonstrate that the technical requirements on energy efficiency as laid
down in the Particular Specification are being complied with satisfactorily;
(b) field test should only be conducted after a set of working details agreed between the
contractor and PBSE. Full set of calibrated instruments should be provided for taking
record on design temperature, volumetric and mass flowrate and pressure of air and
water at relevant locations, air relative humidity, equipment operating current and
voltage and overall power input to the air-conditioning and mechanical ventilation
installations (ACMV);
(c) before the commencement of actual T&C works, the relevant forms specified by the
EMSD under the Buildings Energy Efficiency Ordinance should be updated and
submitted;
(d) factory endorsed T&C guidelines for illustrating the compliance of energy efficiency
performance requirement should be submitted for checking and agreement;
(f) initial visual inspection of the installed air conditioning and ventilation equipment
and system shall be carried out;
(g) if the actual site condition could not allow full load for system testing, a simulated
load shall be agreed and generated for testing;
(h) run in the installed air conditioning and ventilation equipment and system for a short
period of time before it becomes steady;
(j) measure relevant system performance parameters such as air and water temperature,
flowrate, pressure, relative humidity, on/off position of dampers and valves and so
on. Based on those measured data and valid scientific equations to verify if the
attained energy efficiency performance of the equipment and system is acceptable
according to the Particular Specification;
(k) results of T&C works should be properly documented and certified by the contractor
and PBSE; and
(l) post-occupation energy efficiency and consumption audit has to be held before the
issuance of Maintenance Certificate for deciding on whether there is any adjustment
and correction to the system operation logic to be made in order to maximise the
working efficiency of the system.
The T&C of CCMS and Building Automation System (BAS) should be carried out by
specialists. Control systems as defined herein relate to ‘on the plant’ control systems,
including pressure/temperature sensing points, motorised valves, dampers, etc. with
which the CCMS/BAS may interface.
It is essential that all wirings within the control panel should be checked to avoid any
loose connections and to ensure correct terminations in compliance with wiring diagrams.
In addition, it is also assured that functional checks to ensure that all interlocking and
sequencing have been carried out in accordance with the requirements and specifications.
It is also critical that the procedures described elsewhere relating to the regulation of air,
water, refrigeration systems and any other connected equipment/systems have been
carried out prior to commissioning the control system.
Generally, the commissioning procedure shall comply with that set out in the CIBSE
Commissioning Code "C" - Automatic Control.
(i) that at full rated flow of the controlled media, the pump
and fan pressures are within design tolerances
immediately prior to setting-up;
(ii) that the input temperature of the controlled media and the
pressure at the input of the controlled device at full design
flow condition are each within specified design limits and
that the pressure difference across the device comply to
design requirements;
Check:
(i) that the actuator has the correct movement so that it will
give the required travel of the final control device;
(c) Controllers
Calibrate as follows:
(vii) cancel any measures that may have been taken to stabilise
the conditions at the detector thus returning the plant
ready for normal working; and
(iii) verify the time and date of the real time clock;
Page 100 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(vi) check the performance of the controller and calibrate the
input and output points as follows:
1. Analogue input
2. Digital input
3. Analogue output
4. Digital output
Page 101 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• force the controller to send OFF or CLOSE
signal; and
Pre-commissioning
The test equipment and instruments shall have been calibrated within
the specified period according to the manufacturer’s
recommendations. The calibration certificates shall be submitted to
PBSE for record;
Page 102 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
All physical adjustments to the CCMS field devices shall be marked.
Volt free and control terminals shall be checked such that they are
separated from mains voltage.
Page 103 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
Level 3 – Level 2 – Sub-system and Level 1 –
Building/Zone equipment Component
Digital inputs
Relays
Switches
Analogue outputs
Actuators
Digital outputs
Relays
Page 104 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(ii) Preliminary check
1. CCMS wiring;
2. Field devices;
4. CCMS Workstation/Server;
5. Wiring
• identification of cables;
• correct location/orientation;
• type as specified;
• identification correct;
Page 105 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
7. Digital inputs/outputs
• identification correct
8. Controller/Router/Gateway/Interfacing Unit
• type as specified;
• identification correct;
• wiring diagram;
9. CCMS workstation/server
• type as specified;
• correct input/output;
Page 106 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(b) Component and System Checking
1. Set Points
2. Time Control
3. Interlocks
4. Control Loops
5. Sequencing
Page 107 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• The automatic change over of plant on plant failure
or when a specified number of hours run has been
reached should be checked by failing plant or
“manually” increasing the hours run;
8. Alarm Function
9. Graphics
6. Check that: -
Page 108 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• connections between panel sections are numbered
as specified, accessible and physically simple to
connect / disconnect.;
Page 109 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• Check the position indication signal that agrees with
the analogue output signal to the actuator;
12. Interlocks
Page 110 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• Check when one particular activity happens, all
related and interlocked activities also occur
(positive checks); and
• Set up trend logs for the input and output of the loop;
Page 111 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
• Monitor (trend-log) the transient behaviour and
check if it is acceptable (i.e. the initial time taken
for the response to settle to a steady level);
Commissioning
(a) commissioning involves completing all the checks and the settings
of control values to ensure the correct operational state of the
Installations;
Page 112 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(e) CCMS workstation/server shall be used to check the
communication networks, such as graphic functions, CCMS
software, etc; and
(i) Installation
Page 113 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
2. Check the sensors, transducers, valves, actuators, AHU,
PAU, FCU, VAV, ventilation fans, frequency inverters
are properly installed according to drawings, etc.;
7. Put the system into an auto mode and test if the program
can run properly; and
Page 114 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
alarm delays, actuator movement, control loop settings plus input
and outputs.
the back-up copies of the latest version of all the software shall be
made. After changes have been made in the software following
the performance tests, a new back-up copy of the software shall be
made, while still retaining a copy of the previous version shall
problems arise;
since the control strategies, set points, alarm levels etc. are
software based, an up-to-date hard copy needs to be kept in the
Operating and Maintenance Manual for permanent reference and
easy access.
Before noise level tests are undertaken, the following preliminary checks shall
be carried out:-
(b) All building works are completed and areas under test are vacated or under
control for carrying out the noise test;
(c) All other noise generating activities and equipment are stopped.
(d) All areas under test are provided with safe access.
Screening test on all noise emitting plant and machineries shall be carried out
during the pre-commissioning phase of the installation work to identify potential
problems that might infringe the Noise Control Ordinance.
Page 115 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
The test results shall be submitted to the Supervising Officer and notify the
Supervising Officer on any likely problematic areas so that prompt action could
be followed up.
Site ambient noise levels shall be recorded prior to the commencement of tests.
In order to minimise the effect of background noise, noise levels at external
areas shall be measured at night or at other representative time as agreed with
the Supervising Officer.
Prior to measurement of noise levels, all the plants in the air system and the
water system are running shall be checked.
If any item of plant is not running during the test, it shall be clearly identified on
the test sheets.
Noise levels shall be measured by an approved noise level meter (or sound meter)
capable of measuring noise levels in the frequency range of 63 Hz to 8 kHz.
Noise level tests of the selected A/C system shall include sound pressure
readings relating to the NC levels in each room where stated in the Contract
Drawings or in the Particular Specification.
In each selected area, noise levels shall be measured at 1.5 metres above the
finished floor level and at a distance of 1.5 metres from the walls or doors of the
areas.
In large areas, the floor area shall be divided into equal areas and readings
carried out in each area.
External noise level tests shall be carried out in locations at agreed boundary
positions.
Upon completion of the noise level tests, a further set of noise level
measurement shall be carried out with all plant off, so as to verify again the level
of background noise.
In cases where measured noise levels are in excess of the specified criteria,
additional checks shall be carried out to identify the sources of excessive noise
generation.
All noise level readings are to be recorded and plotted on octave wave band
frequency charts.
Page 116 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
The date and time of test are also to be recorded together with any relative
comments.
All the effort in designing the indoor ACMV system with care and thought might
be wasted if installation and commissioning of the equipment is not proper. The
following check points shall be followed to determine if the total noise level in
occupied areas within the building exceed the limits as specified in the
Specification.
(a) calibrate the sound level meter with sound level calibrator supplied with the
meter according to the procedures specified in the operation manual of the
meter;
(b) switch on the ACMV equipment or plant serving the area in which noise is
to be assessed. The corresponding fan coil units, ventilation fans and other
sound source(s) affecting the area shall also be turned on;
(c) measure Sound Pressure Levels (SPLs) in dB. Measurement shall be made
as close to the diffuser as possible and the position of the sound level meter
shall be at a height of 1.5 m above floor level is considered appropriate for
general situations;
(d) indicate clearly the locations of measurement on a floor layout plan for the
area(s) concerned;
(e) record the SPLs measured from the 63 Hz octave band through the 8000 Hz
octave frequency band in Certificate no. 21.1 of Annex II;
(f) plot the SPLs on typical Noise Criteria (NC) curves to determine the
measured NC level in each area;
(g) also indicate other relevant information including date and time of
measurement; type, model and calibration date of the meter used as well as
other observations during the measurement process in Certificate no. 21.1
of Annex II;
(h) re-calibrate the meter with the calibrator after the noise measurement; and
(i) measure background noise level only if the ambient noise level in the area,
with the ACMV equipment not operating, exceeds the NC limits as
specified in the Specification.
The noise level measurement is performed to assess the noise generated from
ACMV equipment like chillers, ventilation fans, etc., which may cause nuisance
to noise sensitive receivers outside the building in which the equipment is placed.
Page 117 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
The procedures below are generally in compliance with those set in the
requirements in the Noise Control Ordinance:
(a) calibrate the meter with sound level calibrator supplied with the meter
according to the procedures specified in the operation manual of the meter;
(c) indicate clearly the locations of the noise emitting source and measuring
point(s) on a site plan.
(e) measure the Equivalent Continuous Sound Level (Leq) in dBA over a
period of 30 minutes according to the TM. Measurement can be made over
any shorter period when the EPD is satisfied that the noise under
investigation is essentially steady over a 30-minute period;
(f) record the figures of Leq measured together with the corresponding time
period at which the measurement is conducted in Certificate no. 21.2 of
Annex II;
(i) re-calibrate the meter with the calibrator after the noise measurement.
Page 118 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(a) record the operating speeds of the equipment (i.e. driving speed of motor and driven
speed of fan wheel, rotor or impeller) indicated on the nameplates, drawings or
measured by speed-measuring device in Certificate no. 22 of Annex II;
(b) determine acceptance criteria from the Particular Specification or as indicated below;
(c) perform visual and audible checks for any apparent rough operation of the equipment
or any defective bearings, misalignment, etc;
(d) calibrate the vibration measuring instrument according to the user’s manual;
(e) measure and record in Certificate no. 22 of Annex II vibration at bearings of driving
and driven components in horizontal, vertical and, if possible, axial directions. There
should be at least one axial measurement for each rotating component (fan motor,
pump motor);
(f) indicate other relevant information including date of measurement, type, model and
calibration date of the instrument used as well as other observations in the
measurement process in Certificate no. 22 of Annex II; and
(a) The tests shall be carried out before and after connection of power supply.
The tests shall follow the requirements for L.V. Cubicle Switchboard as
stipulated in the General Specification for Electrical Installation in
Government Buildings of the HKSAR issued by ArchSD; and
(b) The tests to be carried out for the high voltage motor control switchboard
shall strictly follow the tests as recommended by the equipment
manufacturer.
The following tests on all electrical motors shall be carried out and test
certificates shall be provided in duplicate:-
Page 119 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
(i) Check motor nameplate characteristic such as voltage and frequency
& etc.;
(ii) Check motor rotation and speed, prior to connection of the driven
equipment;
(iv) Check the earth continuity loop resistance for every motor starter;
(v) Check the insulation to earth resistance for every motor starter taken
with 500 V "Meggar" tester;
(vi) Test the full load current taken by all motors on each phase;
(vii) Test the tripping time of starter overloads set to 10% above the motor
nameplate rating;
(viii) Test the function of each control unit in accordance with the
specification (e.g. selector switches correctly wired, high or low
circuit cut-out operates, level switches correctly operating);
Type tests and abbreviated tests shall meet the requirements of IEC 60072-
1 [1991], IEC 60072-2 [1990] and IEC 60072-3 [1994]. The Supervising
Officer has the discretion to agree or accept type-test results for
performance in place of individual unit tests but these will not be accepted
in place of practical on the Site, pressure, insulation, resistance tests which
shall still be carried out on individual units.
Approval of test certificates shall not absolve the contractor from providing
motors capable of driving the various items of plant under the conditions of
loading stated in the tender documents.
4.3.7.1 General
On completion of all inspections and tests, a final overall performance test shall
be carried out on the air-conditioning installation.
4.3.7.2 Instruments
Page 120 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
The following calibrated instruments shall be provided for this test:-
(c) Where specified, multi-point recorders with service devices for monitoring
temperature, humidity, current, voltage, etc.;
(e) A sound meter capable of reading the noise level at 62.5, 125, 250, 500,
1000, 2000, 4000 and 8000 Hertz; and
During this test, the air conditioning systems shall be operated for a period of 5
days minimum. During which time, the following shall be noted and the results
compared with the design criteria:-
(a) Note occupation rates, internal heat and humidity loads, and external
conditions at time of test;
(d) Record exhaust and outdoor air extract system ventilation rates;
(f) Check capability of chilled water system to maintain chilled water flow and
return temperature under full load conditions; and
(g) Check electrical loadings of all plants when operating under both full load
and part load conditions.
When full load conditions cannot be achieved during the commissioning tests,
returning to site shall be allowed to carry out a full load test when the desirable
external and internal design conditions occur at the first opportunity during
the Maintenance Period.
Page 121 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
For particularly sensitive areas such as computer rooms, simulated full load
tests shall be carried out at the time of commissioning using electric heaters
to simulate the sensible load and electric steam pan humidifiers to simulate
the latent load.
4.3.7.5 When calculating the required simulated load, the following shall be taken into
account.
(b) the extra heat gain through the structural fabric due to the difference
between the design external air temperature and the external air temperature
at the time of the tests;
(c) the extra solar heat gain at maximum design conditions over that
experienced at the time of the tests;
(d) the extra heat gain from the fresh air quantity due to the difference between
the design external air temperature and the external air temperature at the
time of the tests;
(e) the extra sensible and latent (if significant) heat gains due to the increase in
the number of occupants normally present (i.e. allowed for in the design)
over the number present at the time of the tests; and
(f) NOTE: The areas where simulated load tests are to be carried out shall be
clearly indicated in the Particular Specification.
Page 122 of 122 T&C Procedure for Air Conditioning, Refrigeration and
Mechanical Ventilation Installation 2022 Edition
(TCP-AC-2022)
Annex I
Contract Number :
Contract Title :
Name of Sub-contractor :
Name of Main Contractor :
Contract Period: __/__/20__ to __/__/20__ *Revised /Actual Completion Date: __/__/20__
dd/mm/yyyy dd/mm/yyyy
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
1. Chillers
1.1 Cleanliness & Clause
State Check 4.2.3.1.1
1.1.1 Air System Clause
4.2.3.1.2(b)
1.1.2 Water System Clause
4.2.3.1.2(a)
1.1.3 Refrigeration Clause
System 4.2.3.1.2(c)
Submission of
test record
Submission of
test record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
1.3 Electrical Check Clause
4.2.3.1.5
1.3.1 Electrical Supplies Clause
Isolated 4.2.3.1.5(a)
1.3.2 Electrical Supplies Clause
Connected 4.2.3.1.5(b)
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
1.6 Test of Screw Clause
Compressor System 4.2.3.5
1.6.1 Pressure & Leakage Clause
Test 4.2.3.5.1
1.6.2 Evacuation & Clause
Dehydration 4.2.3.5.2
1.6.3 Charging of Clause
Refrigerant 4.2.3.5.4
1.6.4 Setting to Work & Clause
Adjusting 4.2.3.5.5
Submission of test
record
Submission of test
record
1.8 Functional Test for Clause 4.2.3 Setting to work & record
Air & Water Cooled &
Chillers Annex II
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
1.8.1 Chilled Water Leaving
Temperature
1.8.2 Chilled Water
Entering Temperature
1.8.3 Chilled Water Flow
Rate
1.8.4 Condenser Entering
Temperature (Water
Cooled Chillers)
1.8.5 Condenser Leaving
Temperature (Water
Cooled Chillers)
1.8.6 Compressor Motor
Speed
1.8.7 Compressor Running
Current
1.8.8 Air Flow Rate (Air
Cooled Chillers)
1.8.9 Fan Speed (Air
Cooled Chillers)
1.8.10 Fan Motor Speed (Air
Cooled Chillers)
1.8.11 Fan Motor Running
Current
1.8.12 Supply Voltage
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
2. Chilled Water System
2.1 Cleanliness & State Clause
Check 4.1.6.1
G/F
1/F
2/F
3/F
4/F
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
2.4 Electrical Check Clause 4.1.5
(Pumps)
2.4.1 Electrical Supply Clause
Isolated 4.1.5.1
Pri.
Sec.
Submission of test
record
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
2.5.3 Pump discharge Clause
Pressure 4.2.1.4
Pri.
Sec.
Submission of test
record
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
3. Air Distribution
System
3.1 Cleanliness & State Clause
Check 4.1.7.1
G/F
1/F
2/F
3/F
4/F
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
3.5 Mechanical
Ventilation System
Check
3.5.1 Cleanliness & State Clause
Check 4.1.7.1
G/F
1/F
2/F
3/F
4/F
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
3.6 Check of
Conditioned Air
Distribution
3.6.1 Cleanliness & State Clause
Check 4.1.7.1
G/F
1/F
2/F
3/F
4/F
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
3.7.3 Electrical Check Clauses
4.3.1.1.3
4.3.1.3
G/F
1/F
2/F
3/F
4/F
Submission of test
record
Submission of test
record
Submission of test
record
T&C Progress Chart for Air Conditioning, Refrigeration and Mechanical Ventilation Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference to S A S A S A S A S A S A S A S A
T&C
Procedure
Notes
* Delete as appropriate
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion
A - actual % completion
Contract Number :
Contract Title :
1.4 Sub-contractor :
Part 2 Declaration
2.1 I certify that the Air Conditioning, Refrigeration and Mechanical Ventilation Installation as
specified in the Contract/Sub-contract/Quotation at the above location has been inspected,
tested and commissioned in accordance with this Testing and Commissioning (T&C)
Procedure and/or any other procedures as agreed between the *PBSE and the Contractor.
The results are satisfactory in the aspects as mentioned in Part 3 and/or as recorded in Part 4
of this Certificate, except that indicated in the COMMENTS items.
2.2 I also certify that site tests have been performed in accordance with the requirements set in
this T&C Procedure and that the results are satisfactory. A record of the tests has been
prepared and submitted to the *PBSE.
Note:
Plant performance can be substantiated only when the test data have been recorded and validated against the design data. Proforma for
recording such data can be found in the succeeding pages and these should be properly filled in before submission to the designers with
any relevant comments related to site conditions. Peak Load Test shall be carried out for the entire system with test record submitted
accordingly
(a) The system has been properly cleaned, flushed and filled with water. *Yes/No/N.A. *Yes/No/N.A.
(b) The equipment associated with the system has undergone the *Yes/No/N.A. *Yes/No/N.A.
mechanical and electrical checks and the results are satisfactory.
(a) The system has been properly cleaned and usually checked for air *Yes/No *Yes/No
tightness.
(b) The equipment associated with the system has undergone mechanical *Yes/No *Yes/No
and electrical checks and the results are satisfactory.
(a) The water pumps have been commissioned in accordance with this *Yes/No/N.A. *Yes/No/N.A.
T&C Procedure and the pumps are operating satisfactorily.
(b) The water flow rates of the system have been regulated and balanced *Yes/No/N.A. *Yes/No/N.A.
in accordance with this T&C Procedure. The results are satisfactory
meeting the specified requirements.
(a) The filters have been commissioned according to *this/manufacturer’s *Yes/No/N.A. *Yes/No/N.A.
procedure and the results are satisfactory, meeting the specified
requirements.
(b) The fans have been commissioned according to *this/manufacturer’s *Yes/No/N.A. *Yes/No/N.A.
procedure and the results are satisfactory meeting the specified
requirements.
(c) The air flow rates of the system have been regulated in accordance with *Yes/No/N.A. *Yes/No/N.A.
this T&C Procedure and the system is delivering the designed air
volumes at the terminal outlets.
3.3.3.1 Method A
Compartment: ____________________________________________________
(a) The compartment is provided with a smoke detector automatic fire *Yes/No/N.A. *Yes/No/N.A.
alarm system.
(b) Any smoke detector of the compartment is activated; all fans severing *Yes/No/N.A. *Yes/No/N.A.
the compartment shall be shut down.
(c) All fans unable to restart while fire signal exist. *Yes/No/N.A. *Yes/No/N.A.
(d) Manual Override Switch shall be installed adjacent to the Fire Control *Yes/No/N.A. *Yes/No/N.A.
Panel of the building and easy to operate.
(e) All fans involved in the VAC system shall be shut down when Manual *Yes/No/N.A. *Yes/No/N.A.
Override Switch is activated.
(f) Fail Safe test for the circuit of Manual Override Switch. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.2 Method B
(b) The fan shut down by probe-type smoke detector. *Yes/No/N.A. *Yes/No/N.A.
(c) Fail Safe test for the circuit of probe-type detector. *Yes/No/N.A. *Yes/No/N.A.
(d) The fans unable to restart while fire signal exists. *Yes/No/N.A. *Yes/No/N.A.
(e) Manual Override Switch shall be installed adjacent to the Fire Control *Yes/No/N.A. *Yes/No/N.A.
Panel of the building and easy to operate.
(f) All fans involved in the VAC system shall be shut down when Manual *Yes/No/N.A. *Yes/No/N.A.
Override Switch is activated.
(g) Fail Safe test for the circuit of Manual Override Switch. *Yes/No/N.A. *Yes/No/N.A.
(h) All fans serving the same compartment shall be interlocked *Yes/No/N.A. *Yes/No/N.A.
3.3.3.3 Method C
(a) All fans involved in the VAC System shall be shut down when building *Yes/No/N.A. *Yes/No/N.A.
fire alarm system is achieved.
(b) All fans unable to restart while fire signal exists. *Yes/No/N.A. *Yes/No/N.A.
(c) Manual Override Switch shall be installed adjacent to the Fire Control *Yes/No/N.A. *Yes/No/N.A.
Panel of the building and easy to operate.
(d) All fans involved in the VAC System shall be shut down when Manual *Yes/No/N.A. *Yes/No/N.A.
Override Switch is activated.
(e) Fail Safe test for the circuit of Manual Override Switch. *Yes/No/N.A. *Yes/No/N.A.
3.3.4.1 The system has been satisfactorily cleaned and the equipment has *Yes/No *Yes/No
undergone electrical and mechanical checks.
(a) The refrigeration system has been commissioned by a specialist in *Yes/No/N.A. *Yes/No/N.A.
accordance with the manufacturer’s recommendations.
(b) The refrigeration system has satisfactorily completed the running-in *Yes/No/N.A. *Yes/No/N.A.
period as specified in this T&C Procedure and all necessary
adjustments/ repairs/ replacements have been carried out.
(a) The refrigeration system has been commissioned by a specialist in *Yes/No/N.A. *Yes/No/N.A.
accordance with the manufacturer’s recommendations.
(b) The refrigeration system has satisfactorily completed the running-in *Yes/No/N.A. *Yes/No/N.A.
period as specified in this T&C Procedure and all necessary
adjustments/ repairs/ replacements have been carried out.
(a) The refrigeration system has been commissioned by a specialist in *Yes/No/N.A. *Yes/No/N.A.
accordance with the manufacturer’s recommendations.
(b) The refrigeration system has satisfactorily completed the running-in *Yes/No/N.A. *Yes/No/N.A.
period as specified in this T&C Procedure and all necessary
adjustments/ repairs/ replacements have been carried out.
(a) The refrigeration system has been commissioned by a specialist in *Yes/No/N.A. *Yes/No/N.A.
accordance with the manufacturer’s recommendations.
(b) The refrigeration system has satisfactorily completed the run-in period *Yes/No/N.A. *Yes/No/N.A.
as specified in this T&C Procedure and all necessary adjustments/
repairs/ replacements have been carried out.
(a) The cooling tower(s) of the installation *has/have been field tested in *Yes/No/N.A. *Yes/No/N.A.
accordance with this T&C Procedure and the results are satisfactory,
meeting the specified requirements.
(b) All the safety devices including circuit interlocks and cut-outs have *Yes/No *Yes/No
been checked for correct installation and operation.
(c) Demonstration that sensors and actuators are correctly connected and *Yes/No *Yes/No
addressed.
(d) Demonstration of the physical and logical integrity of the system. *Yes/No *Yes/No
Comments :
(i) From 'Switch On' Central reaches operational state *Yes/No/N.A. *Yes/No
unaided
The noise and sound levels in areas as specified have been checked *Yes/No/N.A. *Yes/No/N.A.
in accordance with this T&C Procedure and are found in compliance
with the Specification.
The vibration tests for equipment as specified have been carried out *Yes/No/N.A. *Yes/No/N.A.
in accordance with this T&C Procedure and the results are
satisfactory, meeting the specified requirements.
(a) A full-load performance test has been carried out and the results, *Yes/No/N.A. *Yes/No/N.A.
which were recorded separately, were found meeting the specified
requirements.
(b) a full-load performance test has NOT been carried out but it will be *Yes/No/N.A. *Yes/No/N.A.
carried out during the free-maintenance period.
Machine Type
Refrigerant Type
Capacity (kW)
Motor Type
Starting Method/Type
Drive Arrangement
Machine Mountings
Emergency Stop
Note: Full load and part load (40% ~ 60% of full load) tests of the chillers shall be carried out at different
seasons separately.
Compressor
Refrigerant Type
Capacity (kW)
Motor Type
Drive
Emergency Stop
Condenser
Capacity (kW)
Sub-cooling (oC)
Fan Type
Drive
Motor Type
Anti-Recycle Logic
Emergency Stop
Fan Type
Fan Drive
Motor Type
Emergency Stop
4.4 Pumps
Location: _____________________ No.: ____ Design Test Result Test Result
Data (full load) (part load) Remarks
Motor Type
Location: _____________________________
Pump No.
Pump No.
Pump No.
Remarks:
T : Top Reading
B : Bottom Reading
L : Left Hand Side Reading
R : Right Hand Side Reading
Maximum allowable misalignments refer to the recommendation in
the General Specification or Manufacture’s Recommendation.
Condition (Cloudy/Sunny)
Fan
Type
Speed (r/s)
Drive
Emergency Stop
Filter
Type :
Velocity (m/s)
Cleanliness
Alarm Buzzer
Cooling Coil
Velocity (m/s)
Velocity (m/s)
No. of steps
Medium
Velocity (m/s)
No. of Steps
Use the air flow sheets and indicate the design and test figures as indicated in Annex V Section 2.
Location: _____________________________
High Side Test Pressure, kPa Low Side Test Pressure, kPa
Refrigerant Specification Specification
Test Result Test Result
Requirement Requirement
R 134a (Air-cooled)
R 134a (Water-cooled)
Others
In performing pressure test for refrigerant system and circuit containing blend refrigerant, e.g.
R407C and R410a, manufacturer’s recommended procedures and test pressure shall be followed.
(Remark: The evacuation shall be pulled down to between absolute pressure of 170 Pa and
340 Pa)
Location: _____________________________
Total
Location: _______________________
No.: _______________________
Test
Description: Design Result Remarks
Result
Manufacturer
Model No.
Serial No.
Country of Origin
Motor Type
Supply Voltage (V)
Rated Power (kW)
Cooling Coil Valve Operate in Normal Condition *Yes/No/N.A.
No. of Blower(s)
Air Flow Rate (l/s)
Water Flow Rate (l/s)
Chilled Water Entering Temperature (oC)
Chilled Water Leaving Temperature (oC)
Hot Water Entering Temperature – if any (oC)
Hot Water Leaving Temperature – if any (oC)
Supply Air Temperature (oC)
Return Air Temperature (oC)
Heating Element (oC)
Electric Heater (oC)
Maximum Output Power (kW)
Overheat Cut-off Operate within 90sec at 50°C ±10% *Yes/No/N.A.
Air Flow Switch *Yes/No/N.A.
Manual Reset Switch Installed *Yes/No/N.A.
Warning Label Provided *Yes/No/N.A.
A Small Hole Provided for Inserting a Testing *Yes/No/N.A.
Thermometer
Heater and Blower Interlock *Yes/No/N.A.
No Internal Insulation within 1m from Heater *Yes/No/N.A.
Assess Panel for Maintenance Provided *Yes/No/N.A.
Warning Label Provided *Yes/No/N.A.
Location: _______________________
No.: _______________________
Test
Description: Design Result Remarks
Result
Manufacturer
Model No.
Serial No.
Country of Origin
Air Flow Rate (max. flow and min. flow) (l/s)
Pressure (kPa)
Supply Air Temperature Setting Point (oC)
Supply Air Temperature (oC)
Air Flow Control Damper operate in Normal Condition *Yes/No/N.A.
CCMS Control in Normal Condition *Yes/No/N.A.
Electric Heater
Output Power (kW)
Temperature (oC)
Maximum Current (A)
Overheat Cut-off Operate within 90sec at 50°C ±10% *Yes/No/N.A.
Air Flow Switch *Yes/No/N.A.
Manual Reset Switch Installed *Yes/No/N.A.
Warning Label Provided *Yes/No/N.A.
Heater and Blower Interlock *Yes/No/N.A.
No Internal Insulation within 1m from Heater *Yes/No/N.A.
Emergency Stop Provided *Yes/No/N.A.
Assess Panel for Maintenance *Yes/No/N.A.
Assess Panel Provided *Yes/No/N.A.
Location: _______________________
No.: _______________________
Test
Description: Design Result Remarks
Result
Manufacturer
Model No. (Indoor Unit)
Serial No.
Model No. (Outdoor Unit)
Serial No.
Country of Origin
Supply Fuse
Control Fuse
Compressor Rated Current (A)
Condenser Fan Rated Current (A)
Evaporator Fan Rated Current (A)
Cooling Capacity
Overload Setting
Refrigerant Type
Starting Current (A)
Running Current (A)
High Pressure Cut-out (kPa)
Low Pressure Cut-out (kPa)
Compressor Suction Pressure (kPa)
Compressor Discharge Pressure (kPa)
Evaporator Entering Coil Dry Bulb (DB-oC)
Temperature
Evaporator Entering Coil Wet Bulb (WB-oC)
Temperature
Evaporator Leaving Coil Dry Bulb Temperature (DB-oC)
Evaporator Leaving Coil Wet Bulb Temperature (WB-oC)
Condenser Entering Coil Dry Bulb Temperature (DB-oC)
Condenser Entering Coil Wet Bulb Temperature (WB-oC)
Condenser Leaving Coil Dry Bulb Temperature (DB-oC)
Condenser Leaving Coil Wet Bulb Temperature (WB-oC)
Emergency Stop
Pressure Gauge(s) Installed *Yes/No/N.A.
Refrigerant High Side Test Pressure, kPa Low Side Test Pressure, kPa
In performing pressure test for refrigerant system and circuit containing blend refrigerant, e.g. R407C and R410a,
manufacturer’s recommended procedures and test pressure shall be followed.
Evacuation Test - (Remark: The evacuation shall be pulled down to between absolute pressure of 170 Pa and
340 Pa)- Refer to the General Specification
1st Duration of Test
4 hours
nd
2 Duration of Test
3 hours
rd
3 Duration of Test
2 hours
Refrigerant Type:
Manufacturer: Location
Air Distribution System:
Pressure testing of pipe servicing system or any section of a *Yes/No/N.A. *Yes/No/N.A.
completed system, shall be completed prior to the application
of any thermal insulation to the cleaned pipe surfaces. The
pressure test for this system is recommended by the
Manufacturer’s.
The system is required to vacuum by a vacuum pump. *Yes/No/N.A. *Yes/No/N.A.
Add the refrigerant to the indoor unit through the refrigerant *Yes/No/N.A. *Yes/No/N.A.
pipe.
The refrigerant is extracted by the new vacuum pump. *Yes/No/N.A. *Yes/No/N.A.
High Side Test Pressure, kPa Low Side Test Pressure, kPa
Refrigerant General General
Specification Test Result Specification Test Result
Requirement Requirement
R22 (Air-cooled) 2950 1780
R22 (Water-cooled) 1900 1360
R134a (Air-cooled) 2080 1190
R134a (Water-cooled) 1270 880
Others
In performing pressure test for refrigerant system and circuit containing blend refrigerant, e.g. R407C and R410a,
manufacturer’s recommended procedures and test pressure shall be followed.
Evacuation Test - (Remark: The evacuation shall be pulled down to between 170 Pa absolute and 340 Pa
absolute)- Refer to the General Specification
1st Duration of Test
4 hours
nd
2 Duration of Test
3 hours
rd
3 Duration of Test
2 hours
Refrigerant Type:
Centrifugal Fan
Motor Power (kW/hp)
Overload Setting (A)
Starting Current (A)
Running Current (A)
Motor Speed (r.p.m.)
Fan Speed (r.p.m.)
Circulating Pump
Motor Power (kW/hp) No.1 No.2 No.3
Overload Setting (A)
Starting Current (A)
Running Current (A)
Pump Head Pressure (kPa/Bar)
Pump Flow Rate (l/s)
pH Meter / Sensor
Set Point
Alarm
ORP Meter / Sensor *Yes/No/N.A.
Set Point (mV)
Alarm
Chemical Dosing Pumps operate in normal *Yes/No/N.A.
condition
Scrubber
Scrubber High level sensor interlock with water *Yes/No/N.A.
supply valve
Scrubber Low level sensor interlock with *Yes/No/N.A.
circulating pump
Chemical Tank Low Level Sensor interlock *Yes/No/N.A.
with Chemical Pump
Sample Inlet
Initial time for sampling
Final time for sampling
Total sampling time (Min)
Pump Flow Rate (l/ min)
Volume of absorbent used (ml)
Sample Outlet
Initial time for sampling
Final time for sampling
Total sampling time (min)
Pump Flow Rate (l/ min)
Volume of absorbent used (ml)
Sample Inlet
Initial time for sampling
Final time for sampling
Total sampling time (min)
Pump Flow rate (l/ min)
Sample Outlet
Initial time for sampling
Final time for sampling
Total sampling time (min)
Pump Flow rate (l/ min)
Location: _______________________
No.: _______________________
Others
Make-up water tank size (m3 or litre)
All valve is/are open *Yes/No/N.A. *Yes/No/N.A.
Waste oil is through a Grease / treatment tank to *Yes/No/N.A. *Yes/No/N.A.
floor drain
4.18 Ventilation and Air-conditioning (VAC) Control Systems interfacing with Fire Alarm Signal
Location: ____________________________
No.: ________________________________
Model No.:
Serial No.:
Motor Supply Voltage (V)
Running Current (A)
Supply fuse (A)
Total Air Flow Rate (l/s)
Supply Air Flow Rate (l/s)
Return Air Flow Rate (l/s)
(a) Outdoor Intake Temperature (c)
(b) Indoor Intake Temperature (c)
(c) Exchanged Air Temperature (c)
(d) Indoor Exhaust Temperature (c)
(a) (c)
Outdoor Intake Exchanged Air
Temperature Heat Temperature
Outside Room
Exchange
Indoor Exhaust Indoor Intake
Temperature
r Temperature
(d) (b)
Name of Project :
Measuring Instrument used : Model No.:
Serial No.:
Last date of calibration:
Measured by :
Weather Conditions :
Observations/Remarks:
Attachments include: (1) NC curves for individual location; (2) floor layout plan indicating locations of noise
measurements
Name of Project :
Measuring Instrument used : Model No.:
Serial No.:
Last date of calibration:
Measured by :
Weather Conditions :
* The measurement shall be made over any 30-minute period according to the Technical Memorandum
for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction
Sites (TM) issued by the Environmental Protection Department (EPD). Measurement can be made over
any shorter period when the EPD is satisfied that the noise under investigation is essentially steady over
a 30-minute period.
Attachments include: (1) calibration results of the measuring instrument; (2) site plan indicating locations of
noise source & noise level measuring point(s)
Name of Project :
Measuring Instrument used : Model No.:
Serial No.:
Last date of calibration:
Measured by :
Weather Conditions :
Indicated operation speed (rev/s) Measured speed (rev/s) Visual/ audible Vibration acceptance Vibration measured (mm/s) Other observations/
Equipment
Motor Equipment Motor Equipment check criteria (mm/s) Horizontal Vertical Axial remarks
Attachment includes a sketch showing the positions of measuring points for each equipment.
4.22 Room Temperature Record – Handover/ Peak Load /Wet & Humidity Season/ Expiry of
Maintenance Period
Name of Project :
Measuring Instrument used : Model No.:
Serial No.:
Last date of calibration:
Measured by :
Weather Conditions
Dry Bulb Temp (oC) : Wind Speed (m/s) :
Wet Bulb Temp (oC) : Atmospheric Pressure (kPa) :
1/F Room 2 A
B
C
D
E
Observations/Remarks:
Attachments include: (1) test certificate of measuring instrument (if any);(2) site floor layout plan indicating
locations of temperature measurements; (3) measuring point shall be indicate on attached layout plan; (4)
numbering of points to be agreed by PBSE/PBSI.
4.22 Room Temperature Record – Handover/ Peak Load /Wet & Humidity Season/ Expiry of
Maintenance Period (Cont’d)
A B A B
Open Area Office
Room 1 Room 2
E E
C D C D
Lift Lobby
Lift 1 Lift 2
Location: _______________________
No: ___________________________
Designed Test
Description Remarks
Data Results
Visual Inspections
Pipe Work Pressure Test Records Acceptable (Yes/No)
Panels Securely Fixed on Support (Yes/No)
Panel Absorber Surfaces Has Obvious Sign of (Yes/No)
Oxidation or De-colourisation
Pipe Work, Heat Exchangers and Solar Hot Water (Yes/No)
Calorifier Are Well Insulated and With UV
Protection Layer
Hydraulic System Has Been Balanced (Yes/No)
All Valves Setting Are Appropriate (Yes/No)
All Electrical/Signal Connections of Sensors, (Yes/No)
Controllers and Data Acquisition Devices Are
Properly Connected
All Sensors Are Properly Installed (Yes/No)
All Sensors Have Been Calibrated (Yes/No)
All Sensors’ Location Appropriate (Yes/No)
Automatic Air Vent Location Appropriate (Yes/No)
All Labels & Signages Are Provided (Yes/No)
Location: _______________________
No: ___________________________
Designed Test
Description Remarks
Data Results
Measurements
Location: _______________________
No: ___________________________
Designed Test
Description Remarks
Data Results
System Controller
Circulation Pump Auto Start-Stop Setting (C)
- Temperature Different Between Solar
Panel Output and Water Tank for Pump
On
Calorifier
Calorifier Storage Volume (m3)
Vent Type (Vented/
Unvented)
Calorifier Shell/lining Materials
Pressure/Temperature Relief Valve Setting
- Purging Temperature (C)
- Purging Pressure (kPa)
Auxiliary Heater Type
Auxiliary Heater Rating (kW)
Over Temperature Thermostat Setting (C)
Calorifier Maximum Heat Transfer Capacity (kW)
Pressure Drop of Calorifier Heating Loop (kPa)
Insulation Type
Insulation Thickness (mm)
Circulation Pumps
Voltage (V)
Current (A)
Power (W)
Flow Rate (l/s)
Pump Head (kPa)
The walkthrough inspection is used to identify areas with a high potential for IAQ problems.
4.24.1 The following general requirements should be met before IAQ measurement:
(c) All builder’s works associated with IAQ systems completed and painted with dust preventing
compound;
(e) All dust generating activities by other trades are completed and all areas thoroughly cleaned to
prevent ingress of building dust and debris into the
(f) Air intake screens and louvers are unobstructed and cleaned;
(g) Fan and other equipment chambers are clean and free of construction debris;
(i) Floor gullies and drainage traps are clear and operational;
(j) All condensate drains and trays are clear and water can be drained away satisfactorily;
(m) All outside air, return air, and spill air dampers are operative;
(n) All volume control dampers are fitted and are at appropriate opening positions;
(o) Ductwork systems are cleaned by purging of the supply air fan, or by robot duct cleaning
recommended by the ductwork cleaning specialist;
(p) All CAV and VAV terminals are installed, together with grilles and diffusers;
(r) Air conditioning systems and the building indoor area are purged to the standard acceptable by
the Supervising Officer
(a) Odour;
(c) Visible fungal growth or mouldy odour (often associated with problem of too much moisture);
(e) Sanitary conditions in equipment such as drain pans and cooling towers;
(j) Overcrowding;
(a) Check for any evidence of high or low temperature. Are these due to occupant
interference, such as installation of new equipment?
(b) Check for evidence of thermal gradients; the floor-to-ceiling differential should not
exceed 3C.
(c) Check for any obstruction of air circulation, such as partitions, taped diffusers, or
blocked by paper, books, or cabinets.
(d) Ensure that thermostats are functioning, calibrated, correctly located, and not
obstructed or enclosed.
(a) Enquire about any recent change in the physical set-up and use of the space (e.g.
open office space converted to closed offices, transformation of office space into a
waiting room, computer room etc.).
(b) Inspect the loading dock and car parks connected with the premises:
• Are stairways, elevator shafts, and ducts acting as pathways for automobile
exhaust and diesel fumes?
• Are carbon monoxide sensors (for ventilation control) and alarms installed in the
garage calibrated and operating properly?
(c) Are stoves and other sources fitted with exhaust system?
(d) Is the building less than a year old, or has any area been renovated, redecorated or
newly furnished within the past month?
(e) Are suitable cleaning products being employed? Is time of use optimum, so as to
reduce exposure of occupants?
(f) Do any activities involve the use of large amounts of chemicals, especially highly
volatile solvents? Is solvent odour present? Are soaked materials and solvents
being disposed of properly?
(i) Is extra ventilation or a separate ventilation system being used where there are
localised sources? Is the ventilation system recirculating volatile organic
compounds from a source throughout the building?
(j) Any mouldy, damp odour, evidence of a previous flood or water leak?
(l) Are there dirt marks or white dust on diffusers, indicating particulates entering from
the ventilation system?
(m) Is smoking only restricted to designated areas with independent ventilation system?
(a) Is the amount of fresh air provided to the premises in line with the
"ANSI/ASHRAE Standard 62.1-2019: Ventilation for Acceptable Indoor Air
Quality"?
(b) Where is the fresh air intake duct located? Is it blocked up? Is it near the cooling
tower? Is it at street level or near a car park (Air intakes located below third-floor
level can conduct fumes from vehicular traffic, parking garages)? Are heavy
industries located nearby? Is there any construction work going on nearby?
(c) Are the outside air controls and dampers functioning properly?
(d) Is the minimum outside air damper opening set at approximately 15%?
(e) Are all air distribution dampers functioning properly and cleared of obstruction?
(f) Are filters installed and maintained properly (e.g. no bypassing, not overloading
with dust)?
(g) Is the filtering system designed for primary filters, rated between 10% and 30%
dust-spot efficiency, and for secondary filters, rated between 40% and 85% dust-
spot efficiency?
(h) Are the drain pans clean, properly drained, and without visible mould growth?
(j) Are diffusers and exhaust outlets close together, thereby causing short-circuiting?
(k) Is the air-conditioning system turned off any time during the day?
(l) Is there a regular schedule for cleaning and maintenance of the ACMV system in
the building?
(m) Are all the components of the ACMV system regularly inspected for leaks,
breaches, etc.?
(n) Do the cooling towers treated according to the "Code of Practice for Prevention of
Legionnaires' Disease" published by Prevention of Legionnaires' Disease
Committee, Hong Kong?
(o) Are the mechanical rooms clean and free of contaminant (e.g. refuse, chemicals)?
4.24.3.4 Other Conditions not mentioned above but considered as relevant to IAQ
Site/Project: _____________________________
Control level
Date/time
IAQ specified at Measured outdoor
of the Methodology Remark
Parameter Particular result level
sampling
Specification
4.26 Testing and Commissioning Records of IAQ Measurement by Real Time Monitor with Data
Logger
Total average:
Outdoor air:
Sample no. 1 2 3 4
Date/time of
the sampling
Average value Total average:
Printout of logged data and calculations should be attached to the copy submitted to the PBSE
4.27 Testing and Commissioning Records of IAQ Measurement by Integrated Sampling Method
Total average:
Outdoor air:
Identification and Batch no. of sampler:
Date/time of the sampling:
Average value:
The Original of Laboratory Report should be attached to the copy submitted to the PBSE.
4.28 Testing and Commissioning Records of IAQ Measurement by Airborne Bacteria Sampling
Site/Project: _____________________________
(Prepare the following data entry table for each Sampling position: - )
Impactor model and serial no: ____________ Last calibration date: _______________
Agar type: ____________ Agar Batch no.: _______________
Name of technician /Supplier preparing the Agar: _________________
Date of agar prepared: _________________
List of Calibrated Equipment/ Instruments Necessary for the Testing and Commissioning Works
Note: The measuring and testing equipment shall be calibrated by laboratories accredited by the Hong
Kong Laboratory Accreditation Scheme (HOKLAS) or other recognised accredited laboratories.
Flow Charts
START
(A) Submission of T&C equipment (B) Submission of T&C (C) Submission of T&C
c/w calibration records by procedures by Contractor programme by Contractor
Contractor
Y Y Y
N
Inspection passed
Y
Request for witness (RFWT) shall be submitted by Contractor
(T&C to be carried out by Contractor and draft record to be
attached with the relevant RFWT.)
T&C Works
- witnessed by PBSE & PBSI
N
T&C passed
Y
(E) T&C certificate and test record
- shall be submitted by Contractor.
- shall be up-dated & checked by PBSI.
END
START
Is sensor reading N
within expected
range?
Is reading similar N
to those in same
zone?
Can this N
difference be
Y explained?
Y Proceed to visual
check of sensor
Y
Is sensor type N
correct? Is sensor at N
correct location? Position
correctly
Configure sensor for
Y correct type
Y
Repair
Y
Check sensor against
calibrated instrument
Is sensor N
acceptable?
Complete checklist
N
Next sensor Repeat test
All completed?
Y
END
START
Is there a N
feedback signal
for the DO?
N Y Is there an input to N
monitor the effect of
the DO?
Y
All completed?
Y
N Is CCMS Y
Set switch to auto on hand, off
or auto?
N Is controller
relay
Repeat test Y operating?
N Is DO Y
overridden?
Check Check device
controller under control
Is DO N
interlocked? Y
Check reason for
Change strategy overridden Rectify
Y configuration fault
Delete if not
required
START
Is there a N
feedback signal
for the AO?
N Y Is there an input to N
monitor the effect of
the AO?
Y
All completed?
Y
N
N Does this input give N
correct indication of
END the operation of AO?
Does a visual check N
indicate correct
operation of the AO?
Y
Y
Next AO Does CCMS AO
indicator lamp show
N correct operation of
Repeat test AO?
N Is CCMS Y
Set switch Check why hand/off/auto on
to auto not on auto auto?
Is device
Set switch hand/off/auto on
to auto Y auto?
N Is AO Y
overridden?
Is AO N
interlocked? Y Is controlled device
ON, i.e. power supply?
Check reason for relay operating?
Change strategy overridden
Y configuration
Delete if not
required
START
Y
Check consequence of
forcing an alarm
Y
N
Is it safe to force
an alarm?
Y
N Is sensor type
correct? Adjust alarm level to
force alarm
Enable Y
alarm
Is alarm message N
category destination Set correct alarm message
correct? destination etc.
Cancel alarm
N
All completed?
Y
END
START
N
Is response Time loop
steady?
Y
Alter set point
Log change in
controlled variable
over time
N Is control plant Y
operating efficiently?
N
Next loop
All completed?
Y
END
IAQ
Measurement Principle Accuracy Example of Calibration Method
Parameter
Temp. Thermistor 0.6C Platinum PRT's calibrated against NIST
primary cells
RH Thin-film capacitive 5% Environmental chamber with extreme accurate
RH control traceable to international or
national standards
Air Hot-wire anemometer The larger of Flow tubes as primary standards with their
movement 5% or flowrate calibrations directly traceable to
0.1m/s length and time standards
CO2 Non-dispersive infrared The larger of Bottled Standard Reference gas traceable to
5% or international or national standards
50 ppm
CO Electrochemical The larger of Bottled Standard Reference gas traceable to
5% or international or national standards
2 ppm
NO2 Chemiluminescence 1% Bottled Standard Reference gas traceable to
international or national standards
TVOC Photo-ionisation sensor with The larger of Bottled Standard Reference Isobutylene gas
super bright 10.6eV calibrated 10% or traceable to international or national standards
against Isobutylene 20 ppb
HCHO Electrochemical or Electrolysis Environmental chamber with known HCHO
concentration traceable to international or
national standards
Rn Electrostatic collection of alpha- Environmental chamber with known Rn
emitters with spectral analysis concentration traceable to international or
looks at the 6 MeV alpha national standards
particles from the Polonium-218
decay.
RSP 90 degree light scattering The larger of Arizona Road Dust (ARD) compared with
laser photometer fitted with 0.1% or NIOSH Method 0600 for respirable dust
filter for measurement of PM10 1 m/m3
particles
O3 Heated metal oxide 10% Comparison with an NIST traceable UV
semiconductor / Electrochemical analyser
The calibration of all monitors shall be traceable to international and/or national standards
(e.g. National Institute of Standards and Technology standards).
v a
v = velocity
Design vol. a = area
vol. = volume
Test vol.
Design vol.
Test
FEED AND
EXPAN SION
TANK
CO NSTANT/ VARIABLE EVAPO RATO R
SPEED SECO NDARY PUM P
EVAPO RATO R
6
DIFFERENTIAL
BY-PASS FLOW
VALVE SET SECO NDARY F M ETER
VENTURI ENTHALPY
(SEE NO TE) CO NSTANT
M ETER
PR IM ARY PUM P
PRIM AR Y
VENTURI
7
C
C2
C'
KEY
C1
G ATE VALVE
G LO BE VALVE
AIR/ W ATER HEAT EXCH ANGER
B1 (TERM INAL UNIT)
4 A4
3 A3
2 A2
1 A1
(a) chilled water system as shown in Fig. V will be used to illustrate the balancing procedures.
The procedures for chilled water circuitry are equally applicable to heating and
condensing water circuitry;
(b) the performance of terminal plant in chilled water systems is considerably more sensitive
to any deviations from the design water flow rate. Hence, the T&C procedure for chilled
water systems requires more exacting tolerances than heating system when balancing;
(c) the flow to each branch circuit is controlled by a two-way motorised on/off control valve;
(d) the return line from each terminal unit is fitted with a motorised modulating valve.
Downstream in series is a regulating valve which has built-in pressure tapings. This valve
is used for both the water flow regulations and measurement. This valve is locked in
position after the balancing procedure is completed.
(a) check the pressure drop across the associated flow regulating valve of each terminal unit
and branch by connecting a manometer between points a and b of the regulating valve
with built-in pressure tapping. (Refer to Fig. V);
(b) compute the square root of the ratio of the actual-to-design pressure drop for each branch
and terminal;
(c) determine which is the least favoured (index) branch and which is the most favoured
branch. The branch with the highest ratio is taken as the most favoured branch, whereas
the branch with the smallest ratio is the least favoured branch, i.e. the index branch.
(b) balance the water flow rate of each terminal unit to the water flow rate of the index
terminal unit in that branch;
(c) balance the water flow rate of each branch independently. (The main branch valves A,
A’, B, B’, C, C’ regulating valves with built in pressure tappings and motorised
modulating valves of terminal units in Fig. V are all fully open at this stage);
(d) assume branch A-A’ has the highest ratio (i.e. the most favoured) and unit A1 (remote in
hydraulic terms relative to the circulating pump) is the least favoured. If it is not, connect
1 manometer across valve No. 1 and a second manometer across the regulating valve at
the least favoured terminal unit; (take regulative valve No. 2 in this case for illustration)
(e) regulate valve No. 2 until the percentage of design water flow rate across the 2 valves is
equal (or within the designer’s tolerances);
(f) leave the first manometer connected across valve No. 1 (a and b) while the rest of the
branch A-A’ is balanced;
(g) connect the second manometer across valve No. 3. Regulate valve No. 3 until the
percentage of design water flow rate is the same (or within the designer’s tolerances) as
valve No. 1;
(h) repeat this T&C Procedure for all valves on branch A-A’;
(i) remove both manometers and start on the next most favoured branch;
(j) repeat until the water flow rates of all terminal units on all branches are balanced within
each branch.
(a) for this stage, the branch regulation valves (A, B and C) will be the measuring stations;
(b) check the percentage of design water flow rate across each branch regulating valve and
determine which is the index branch (say branch B-B’);
(c) set the first manometer across valve No. B’ and the second manometer across valve A’
until the percentage of design water flow rates across the valves A and B are equal (or
within the designer’s tolerances for branch balance);
(d) leave the first manometer connected across valve B. Repeat this T&C Procedure for all
branches (in this example for branch C-C’) working back from the most remote branch
to the branch nearest the pump. (Where, at the start of branch balancing, if the most
remote branch is not the index or least favoured branch, it should be made so, in the
manner described for terminal balance.)
(a) set the pump speed at designed maximum flow conditions for variable speed pump;
(b) measure the water flow by connecting a manometer across the regulating valve No.6.
Adjust the regulating valve until the pressure drop across the valve equals the design
pressure drop;
(c) counter check the flow by using the secondary venturi or other flow meters in the circuit;
(a) measure the water flow by connecting a manometer across the primary venturi. Adjust
the regulating valve or globe valve No.7 until the pressure drop across the venturi equals
the design pressure drop;
(b) counter check the flow by referring to other flow meters in the circuit;
(d) re-scan all measuring stations for record and monitoring purposes including the pump
differential pressures.
This is demonstrated in Table V1, X is the main flow, and Y and Z the branch-offs. The essence
of the method is to regulate flow by targeting on the ratio between branch-offs Y and Z.
Balancing is done by taking Y as the reference point.
X Y Z
Y m3/s
% of
m3/s m3/s % of Y
design
X Z
Design flow 3 1 2 200%
Measurement and Regulation
Initial condition before balancing with
3.43 1.58 1.85 117%
Dampers at Y and X fully open
Carry out Balancing by Regulating Damper
at Y to bring the flows at Y and Z to the same 3.3 110% 1.1 2.2 200%
proportion as at design (i.e. Z at 200% of Y)
Finally Regulate Damper at X to bring all 3 1 2
flows to design condition
Note: Device at X may be a fan speed controller (e.g. variable speed drive) instead of
damper
4.1 Preparation
The proportional balancing method, including preparatory work, is illustrated below in the
following typical low velocity supply air system diagram (Fig. V1).
(a) check that dampers on all terminal grilles/diffusers A11, A12, A13, A14, A21 to 24, A31
to A34, A41 to A44, B11 to B44 and C11 to C44 are fully open, adjustable louvers without
deflection, and adjustable cones fully open;
(b) set all Branch dampers BA, BB, BC, and Sub-branch dampers SA1 to SA4, SB1 to SB4
and SC1 to SC4 fully open;
(c) set OA and RA to opposite extreme positions, either OA fully open with RA fully closed
or vice versa. Set main duct damper (M) if available to fully open;
(d) carefully monitoring the running current, start the fan. It will deliver a higher than design
airflow since all the dampers are open. Avoid overloading the fan motor. If the current
appears to be excessive, stop the fan. Simulate an increase in system losses before restart.
This can be done by slightly throttling OA (or RA, depending on which has been chosen
to be fully open) or M;
(e) measure the air flow rates of all air Terminals. The measurement shall be carried out
preferably using the same measuring device (for Terminals in the same system). This is
to avoid irregularity between different measuring devices;
(f) for the purpose of having truly comparable readings, these measurements shall be made
in one quick continuous operation to avoid change of operating conditions and site
environment over time;
System flow
% of design flow
(g) prepare a table (similar to Table V2) readily indicating the initial measured flows of each
Terminal, Sub-branch, Branch and Main. Express the measurements as percentages of
design values;
(h) study the general pattern of these initial readings. Check for any abnormalities:
abnormalities may indicate excessive leakage, improper closing of dampers and other
problems. Refer unresolved problems to the PBSE if necessary;
(i) for Branches, the preferred sequence is in descending order of measurement to design
ratio, i.e. start balancing with the Branch having the highest measurement to design ratio.
Usually, the Branch nearest (duct run distance) to the fan would have the highest ratio;
(j) for Sub-branches, the preferred sequence is again in descending order of measurement to
design ratio. Usually, the Sub-branch nearest (duct run distance) to the fan would have
the highest ratio;
(k) for Sub-branches, the preferred sequence is again in descending order of measurement to
design ratio. Usually, the Sub-branch nearest (duct run distance) to the fan would have
the highest ratio;
(l) should there be inadequate airflow in a Sub-branch for measurement taking, the dampers
in other Sub-branches may be slightly closed so as provide more flow to the Sub-branch
in question.
(a) determine the Terminals on each Sub-branch with the lowest measurement to design ratio.
This Terminal (T) is to be used as the Index Terminal (IT) during balancing of the
corresponding Sub-branch. It is usually the farthest Terminal downstream;
(b) for each Sub-branch, prepare a table listing the ratio of measurement to design flow rates
of all Terminals, such as the one shown in Table V3;
(c) assuming that Sub-branch SA1 has the highest measurement to design flow ratio, it shall
be the one to be balanced first (according to (k) in section 4.1 above);
(d) assuming that Terminal A14, the one farthest away from the fan, has the lowest
measurement to design flow ratio, it is taken as the IT;
(e) should A14 turns out not to be the Terminal with minimum measurement to design ratio,
gradually close A14’s damper until it has the lowest ratio. Take A14 as the IT;
(f) proceed with the reiteration steps according to the flow chart in Fig V2. Start off with a
Terminal adjacent to IT, in the direction of duct path towards the fan;
#
No (5) Close damper on T by a
Within small amount (usually the least
Range? amount, as determined by
experience, below the upper
limit)
Yes
(g) it is impractical to have identical measured flows from 2 identical Terminals with same
design flow. Tolerance in measurement is allowed in accordance with section 4.6 below;
(h) it is preferable to use the same set of measuring device to avoid irregularities. For the
purpose of having truly comparable readings, these measurements shall be made in one
continuous operation to avoid change of operating conditions and site environment over
time;
(i) it is preferable to use the same set of measuring device to avoid irregularities. For the
purpose of having truly comparable readings, these measurements shall be made in one
continuous operation to avoid change of operating conditions and site environment over
time;
(j) lock (or mark, if locking not practical) the positions of dampers of regulated Terminals;
(k) after setting of dampers of all Terminals in the Sub-branch, carry out the same for all
other Sub-branches;
(l) after setting of dampers of Terminals in all Sub-branches, carry out the same balancing
work for all other Branches;
(m) throughout the process, maintain the balanced Sub-branches at between 70% and 130%
of design flow rate. (This can be done by adjusting OA/RA or M. However if such an
adjustment is made whilst regulating the Terminals in a certain Sub-branch,
measurements have to repeat for all Terminals of the Sub-branch in question.);
(n) throughout the process, make sure that dampers in all Sub-branches and Branches are not
disturbed;
(o) it should be noted that the Terminals are still not operating at their design flow rates at
this stage. However, all Terminals are handling the same ratio of flow to their
corresponding design values;
(p) only after completing the regulating works for all Terminals can the balancing of Sub-
branch is proceeded.
(a) the method is similar to section 4.2 above, except this time it is the dampers in Sub-
branches that are to be regulated. Start off by measuring the flow in each Sub-branch;
B1 B2 B3 B4 Branch B
C1 C2 C3 C4 Branch C
System flow
% of design
Table V4A – Measured Flows of Sub-Branches
(b) prepare a table (similar to Table V4A) readily indicating the measured flows of each Sub-
branch, Branch and Main. Express the measurements as percentages of design values;
(c) should there be inadequate test holes for measurement in Sub-branch, measurement can
be taken at the Index Terminal. The Index Terminal’s measurement to design ratio in
percentage can be used to represent the percentage of measurement to design flow of the
Sub-branch;
(d) assuming that Branch A has the highest ratio, it shall be the one to be balanced first
(according to (a) in section 4.1 above);
(e) determine the Sub-branch on each Branch with the lowest measurement to design flow
ratio. This Sub-branch (SB) is to be used as the Index Sub-branch (IS) during balancing.
Assuming SA4 has the lowest measurement to design ratio, it is taken as the IS;
(f) for each Branch, prepare a table listing the ratio of measured flow rates of all Sub-branch
to their corresponding design flow rates, such as the one shown on Table V4B;
(g) proceed with the reiterative steps of balancing according to the flowchart in Fig. V3 Start
off with an adjacent Sub-branch.
#
No (5) Close damper on SB by a
Within small amount (usually the
Range?
least amount, as determined
by experience, below the
upper limit)
Yes
(h) it is preferable to use the same set of measuring device to avoid irregularities. For
purpose of having truly comparable readings, these measurements shall be made in one
continuous operation to avoid change of operating conditions and site environment over
time;
(k) after setting of Dampers on all Sub-branches in the same Branch, carry out the same for
all other Branches;
(l) throughout the process, maintain the balanced Sub-branches at between 70% and 130%
of design flow rate;
(m) throughout the process, make sure that dampers in all Branches are not disturbed;
(n) it should be noted that the Sub-branches are still not operating at their design flow rates
at this stage. However, all are handling the same ratio of flow to their corresponding
design values;
(o) only after completing the air balancing works for all Sub-branches can the balancing of
Branch is proceeded.
(a) branch Dampers BA, BB & BC are to be regulated. The method is same as for balancing
for Sub-branches;
(b) determine the Branch with the lowest measurement to design flow ratio. This Branch is
to be used as the Index Branch (IB) during balancing. Assuming BC has the lowest
measurement to design ratio, it is taken as the IB;
(c) carry out similar exercise as described in (g) in section 4.3 above, and take note of the
pre-cautions and remarks in (h) to (o).
(a) after completing air balancing of all Branches, it is time to regulate the total system flow;
(b) measure the total airflow in the main duct. Where it is not practical to do so, Branch flow
rates can be added together to establish the total flow;
(d) compare the measured figure with the corresponding design value. Regulate the fan
output until the measured value is within the tolerance of the total flow;
(e) where the system contains automatically operated dampers for varying proportions of
fresh/exhaust/recirculation or face and by-pass dampers, measurement of the total air flow
and regulations of the fan output should be conducted with these dampers in the full fresh
air, full exhaust or full face positions, in accordance to the different design modes of
operation. Measurement of flow with damper positions at the other design extremes
should be taken. These measured results should be compared to corresponding design
values;
(f) wherever a system is directly connected with another system, e.g. supply connected with
an extract via a recirculation duct with fixed or variable mixing dampers, first
proportionally balance the duct run of both systems independently. Then regulate the total
airflow in both systems with the dampers set as described in (e). Care should be exercised
to mark or register on the damper linkage mechanism the established settings;
(g) take measurements and record readings of all Terminals, Sub-branches, Branches and
system after air balancing. Use the same set of measuring devices preferably and complete
the work in a continuous manner;
(h) finally, set the adjustable louvers, diffuser and cones to desired positions.
Performance
System type Terminal Branch Total air flow
effect
Mechanical ventilation, Low +20% of design +10% of design +10% of design
Comfort cooling value value value
Process air conditioning, Medium +15% of design +8% of design +10% design
Escape route value value value
pressurisation
Close control air High +10% of design +5% of design +5% of design
conditioning value value value
Notes:
Where the supply flow tends towards a tolerance limit, the associated extract flow should be regulated
towards the same limit.
Tolerances shown for Terminal are those accumulated during Terminal and Sub-branch regulation.