U N I V E R S I T Y O F C A L O O C A N C I T Y
G R A D U A T E S C H O O L
P U B L I C - P R I V A T E P A R T N E R S H I P
A L L E Z A E B A G N O L J D , M S C A
Agenda 1. Meaning
2. Advantages & Disadvantages
3. Diesel Power Plants in the Phils.
4. MAIN TOPIC
Project Description
Agenda Project Rationale
Project Components
Process/Technology
Development Plan, Description of
Project Phases
Project Cost
Preliminary Identification of
Environmental Impacts
Diesel Power Plant
an electrical installation
equipped with one or
several electric current
generators driven by diesel
engines.
ADVANTAGES
favorable stable easy and
economy of operating
operation quick start-
characteristics up
DISADVANTAGES
Compaarativ used mainly usually
ely short for servicing
equipped
interval areas remote
between from with
major transmission synchronous
overhauls lines generators.
THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF
CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)
1.Bataan EPZA Diesel Plant;
2. Bauang La Union Diesel Power Plant;
3. Bunker-Fired Diesel Generator Power
Station Project; (Pinamucan, Batangas Diesel
Power Plant);
4.Calaca, Batangas Diesel Power Barges;
5.Cavite EPZA Diesel Plant;
6.Clark Air Base Diesel Plant
THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF
CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)
8.General Santos 50 MW Bunker C-Fired Diesel
Power Plant;
9. Iligan City Diesel Plant I (58 MW Bunker-Fired
Diesel Generating Power Station in Mindanao);
10.Iligan City Diesel Plant II (40 MW Bunker-Fired
Diesel Generating Power Station in Mindanao);
12. Mindanao Diesel Power Barges (Davao)
THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF
CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)
13. Navotas Diesel Power Barge 1 & 2;
14. North Harbor Diesel Power Barges;
15. Subic, Zambales Diesel Power Plant I
16.Subic, Zambales Diesel Power Plant II;
17Zamboanga Diesel Power Plant
300 MW Diesel Power Plant Project
Ingrid2 Power Corporation (the “Proponent”) will be developing a
300 MW modular diesel engine
power plant (the “Generation Facility”) in Barangay Batangas II,
Mariveles, Bataan.
Basic Information on the Proposed
Project
PROJECT NAME: 300 MW Diesel
Power Plant
Project
PROJECT Brgy. Batangas II,
LOCATION: Mariveles, Bataan
PROJECT AREA: 6 hectares
PROJECT TYPE: Diesel-Fired Power
Plant
PROJECT
SIZE/CAPACITY 300 megawatts
Basic Information on the Proposed
Project
INGRID2 Power
Corporation
Office Address: 4/F,
6750 Office Tower, Ayala
PROJECT Avenue, Ayala Center,
PROPONENT: Makati City Tel. No.: (02)
7730-6300
Authorized
Representative:
Atty. Rodrigo M. San
Pedro, Jr. (Attorney-In-
Fact)
PROJECT LOCATION AND AREA
The project will be utilizing a portion
(approximately 6 hectares) of a 14.3-
hectare leased private property
along the Roman Superhighway in
Brgy. Batangas II, Mariveles, Bataan
and in the vicinity of the PNOC
Compound.
LANDMARKS & STRUCTURES ADJACENT TO THE
PROPOSED PROJECT SITE
NORTH
Residential area;
Batangas II Elementary SOUTH
School ;
SMC Consolidated Power
Corporation and Petron Commercial and
Bataan Ref residential areas
within Brgy.
Batangas II;
Brgy. Lucanin
LANDMARKS & STRUCTURES ADJACENT TO THE
PROPOSED PROJECT SITE
WEST
EAST Brgy. Alion
Philippine National Oil
Company (PNOC) Industrial
Park
VICINITY MAP OF THE PROPOSED PROJECT
AERIAL PHOTOGRAPH OF THE PROPOSED PROJECT LOCATION
PROJECT RATIONALE
Ancillary services help Mid-merit and peaking/
sustain the load-following plants,
transmission capacity on the other hand, are
and are essential to operated with flexibility
maintaining the power to respond to varying
quality, reliability and demand for electricity
security of the grid . throughout the day.
.
SITE SELECTION
Technical, environmental, and land use
considerations were taken in the selection of
the site for the proposed project. The
absence of critical habitats within the project
site and its proximity to possible tapping point
(230 kV TeaM Energy Substation in PNOC
Compound) were some of the main factors
that contributed to its selection. No other sites
were considered for the proposed project.
ENVIRONMENTAL IMPACT
Diesel oil is much cleaner as compared to coal
and bunker fuel oil, the use of which are proven
to result in more carbon dioxide (CO2) per kWH
of energy than other methods; increased sulfur
content in some types of coal and bunker fuel
oil may also produce sulfur dioxide and
eventually sulfuric acid that can cause acid
rain.
Availability:
Diesel fuel is obtained almost
exclusively from crude oil/petroleum
and availability of diesel is relatively
stable.
SAMPLE MODULAR DIESEL POWER PLANT TECHNOLOGY
DEVELOPMENT PLAN, DESCRIPTION OF PROJECT
PHASES, AND CORRESPONDING TIMEFRAMES
Pre-Construction Construction
Decommissioning/aban
Operation donment/Rehabilitation
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Conduct complete Specialized
feasibility study; technical
Prepare detailed skills/expertise
PRE-
~30
engineering on various
CONSTRUCTION designs and
drawings;
engineering
Facilitate permit and scientific
requirements and fields.
tender documents
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Perform civil, Engineers,
CONSTRUCTION ~110 architectural, project
and electro- managers, skilled
mechanical works and non- skilled
laborers
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Oversee the entire Management and
operations of the administration
OPERATION ~60 proposed project, skills; over-all
including emergency knowledge on the
situations; Ensuring operation including
the safety and key environmental,
welfare of its labor, and local
personnel ordinances
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Maintain conformity
of the proposed
OPERATION ~60 project to relevant
government
regulations,
including tax
payments, ECC
compliance, etc
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Promote and
OPERATION ~60 uphold a
harmonious
relationship with
the host
community
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Abandonment ~110 Implement the
As required
abandonment plan
PROJECT COST
is estimated at PHP 2,500,000,000.00
(2.5 Billion Pesos)
including:
Conduct of feasibility study,
preparation of detailed engineering
design, acquisition of necessary
government permits and licenses;
• Site development;
PROJECT COST
is estimated at PHP 2,500,000,000.00
(2.5 Billion Pesos)
including:
• Leasing/construction of power plant
components;
• Procurement of necessary equipment and
materials;
• Environmental management and protection,
pollution control facilities; and
• Environmental monitoring activities.
PRELIMINARY IDENTIFICATION OF ENVIRONMENTAL
IMPACTS
To address the potential environmental impacts of the
proposed project, an environmental management plan will
be prepared, presenting the proposed mitigation and/or
enhancement measures that can be employed during the
different phases of the project development.
Construction Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR
Operation Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR
Abandonment Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR