The document discusses a proposed 300 MW diesel power plant project in the Philippines. It would utilize 6 hectares of leased land in Bataan and use modular diesel engine technology. The project aims to provide ancillary services to support grid reliability. It is expected to have less environmental impact than coal or bunker fuel. The development plan involves pre-construction, construction, operation, and decommissioning phases requiring around 30, 110, and 60 personnel respectively.

Uploaded by

Caz Vinoya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
268 views35 pages

University of Caloocan City Graduate School: Public-Private Partnership

The document discusses a proposed 300 MW diesel power plant project in the Philippines. It would utilize 6 hectares of leased land in Bataan and use modular diesel engine technology. The project aims to provide ancillary services to support grid reliability. It is expected to have less environmental impact than coal or bunker fuel. The development plan involves pre-construction, construction, operation, and decommissioning phases requiring around 30, 110, and 60 personnel respectively.

Uploaded by

Caz Vinoya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

U N I V E R S I T Y O F C A L O O C A N C I T Y

G R A D U A T E S C H O O L

P U B L I C - P R I V A T E P A R T N E R S H I P

A L L E Z A E B A G N O L J D , M S C A

Agenda 1. Meaning
2. Advantages & Disadvantages

3. Diesel Power Plants in the Phils.


4. MAIN TOPIC
Project Description

Agenda Project Rationale

Project Components
Process/Technology

Development Plan, Description of


Project Phases

Project Cost
Preliminary Identification of

Environmental Impacts

Diesel Power Plant


an electrical installation
equipped with one or
several electric current
generators driven by diesel
engines.
ADVANTAGES
favorable stable easy and
economy of operating
operation quick start-
characteristics up
DISADVANTAGES
Compaarativ used mainly usually
ely short for servicing
equipped
interval areas remote
between from with
major transmission synchronous
overhauls lines generators.
THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF
CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)

1.Bataan EPZA Diesel Plant;


2. Bauang La Union Diesel Power Plant;
3. Bunker-Fired Diesel Generator Power
Station Project; (Pinamucan, Batangas Diesel
Power Plant);
4.Calaca, Batangas Diesel Power Barges;
5.Cavite EPZA Diesel Plant;
6.Clark Air Base Diesel Plant
THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF
CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)

8.General Santos 50 MW Bunker C-Fired Diesel


Power Plant;
9. Iligan City Diesel Plant I (58 MW Bunker-Fired
Diesel Generating Power Station in Mindanao);
10.Iligan City Diesel Plant II (40 MW Bunker-Fired
Diesel Generating Power Station in Mindanao);
12. Mindanao Diesel Power Barges (Davao)

THE PHILIPPINE PUBLIC-PRIVATE PARTNERSHIP (PPP) OF


CONCLUDED AND/OR TURNED OVER Diesel power plant in the
phils. (as of February 2022) (DBM)

13. Navotas Diesel Power Barge 1 & 2;


14. North Harbor Diesel Power Barges;
15. Subic, Zambales Diesel Power Plant I
16.Subic, Zambales Diesel Power Plant II;
17Zamboanga Diesel Power Plant
300 MW Diesel Power Plant Project
Ingrid2 Power Corporation (the “Proponent”) will be developing a
300 MW modular diesel engine
power plant (the “Generation Facility”) in Barangay Batangas II,
Mariveles, Bataan.

Basic Information on the Proposed


Project

PROJECT NAME: 300 MW Diesel



Power Plant

Project

PROJECT Brgy. Batangas II,


LOCATION: Mariveles, Bataan

PROJECT AREA: 6 hectares


PROJECT TYPE: Diesel-Fired Power

Plant
PROJECT
SIZE/CAPACITY 300 megawatts

Basic Information on the Proposed


Project

INGRID2 Power
Corporation
Office Address: 4/F,
6750 Office Tower, Ayala
PROJECT Avenue, Ayala Center,
PROPONENT: Makati City Tel. No.: (02)

7730-6300
Authorized
Representative:
Atty. Rodrigo M. San
Pedro, Jr. (Attorney-In-
Fact)

PROJECT LOCATION AND AREA

The project will be utilizing a portion


(approximately 6 hectares) of a 14.3-
hectare leased private property
along the Roman Superhighway in
Brgy. Batangas II, Mariveles, Bataan
and in the vicinity of the PNOC
Compound.
LANDMARKS & STRUCTURES ADJACENT TO THE
PROPOSED PROJECT SITE
NORTH

Residential area;
Batangas II Elementary SOUTH
School ;
SMC Consolidated Power

Corporation and Petron Commercial and


Bataan Ref residential areas

within Brgy.
Batangas II;
Brgy. Lucanin
LANDMARKS & STRUCTURES ADJACENT TO THE
PROPOSED PROJECT SITE

WEST

EAST Brgy. Alion



Philippine National Oil


Company (PNOC) Industrial
Park

VICINITY MAP OF THE PROPOSED PROJECT


AERIAL PHOTOGRAPH OF THE PROPOSED PROJECT LOCATION
PROJECT RATIONALE

Ancillary services help Mid-merit and peaking/


sustain the load-following plants,
transmission capacity on the other hand, are
and are essential to operated with flexibility
maintaining the power to respond to varying
quality, reliability and demand for electricity
security of the grid . throughout the day.
.

SITE SELECTION

Technical, environmental, and land use


considerations were taken in the selection of
the site for the proposed project. The
absence of critical habitats within the project
site and its proximity to possible tapping point
(230 kV TeaM Energy Substation in PNOC
Compound) were some of the main factors
that contributed to its selection. No other sites
were considered for the proposed project.
ENVIRONMENTAL IMPACT
Diesel oil is much cleaner as compared to coal
and bunker fuel oil, the use of which are proven
to result in more carbon dioxide (CO2) per kWH
of energy than other methods; increased sulfur
content in some types of coal and bunker fuel
oil may also produce sulfur dioxide and
eventually sulfuric acid that can cause acid
rain.
Availability:

Diesel fuel is obtained almost


exclusively from crude oil/petroleum
and availability of diesel is relatively
stable.
SAMPLE MODULAR DIESEL POWER PLANT TECHNOLOGY
DEVELOPMENT PLAN, DESCRIPTION OF PROJECT
PHASES, AND CORRESPONDING TIMEFRAMES

Pre-Construction Construction

Decommissioning/aban
Operation donment/Rehabilitation
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Conduct complete Specialized
feasibility study; technical
Prepare detailed skills/expertise
PRE-
~30
engineering on various
CONSTRUCTION designs and
drawings;
engineering
Facilitate permit and scientific
requirements and fields.
tender documents
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT

Perform civil, Engineers,


CONSTRUCTION ~110 architectural, project
and electro- managers, skilled
mechanical works and non- skilled
laborers
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Oversee the entire Management and
operations of the administration
OPERATION ~60 proposed project, skills; over-all
including emergency knowledge on the
situations; Ensuring operation including
the safety and key environmental,
welfare of its labor, and local
personnel ordinances
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Maintain conformity
of the proposed
OPERATION ~60 project to relevant
government
regulations,
including tax
payments, ECC
compliance, etc
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT
Promote and
OPERATION ~60 uphold a
harmonious
relationship with
the host
community
MANPOWER REQUIREMENT PER PROJECT PHASE
ESTIMATED TASK TO BE SKILLS
PROJECT PHASE
MANPOWER PERFOREMED REQUIREMENT
REQUIREMENT

Abandonment ~110 Implement the


As required
abandonment plan
PROJECT COST

is estimated at PHP 2,500,000,000.00


(2.5 Billion Pesos)

including:

Conduct of feasibility study,


preparation of detailed engineering
design, acquisition of necessary
government permits and licenses;
• Site development;

PROJECT COST
is estimated at PHP 2,500,000,000.00
(2.5 Billion Pesos)

including:

• Leasing/construction of power plant


components;
• Procurement of necessary equipment and
materials;
• Environmental management and protection,
pollution control facilities; and
• Environmental monitoring activities.
PRELIMINARY IDENTIFICATION OF ENVIRONMENTAL
IMPACTS

To address the potential environmental impacts of the


proposed project, an environmental management plan will
be prepared, presenting the proposed mitigation and/or
enhancement measures that can be employed during the
different phases of the project development.
Construction Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR
Operation Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR
Abandonment Phase
LAND
Environmental
Prevention/Miti
Environmental Component Potential
WATER gation/Enhance
Aspect Likely to be Impact/s
ment Measures
Affected
AIR