0% found this document useful (0 votes)
597 views

Check List For Beam & Slab

This document is a checklist for inspecting beams and slabs before pouring concrete. It contains 4 sections to check: 1) formwork, 2) steel reinforcement, 3) materials on site, and 4) equipment. The inspector is to verify that the formwork is properly supported and sealed, reinforcement is installed as specified, required materials are on hand in the needed quantities and quality, and all necessary equipment like vibrators, mixers, and lifts are present and in working condition. Signatures are required from the inspector and another witness after completing the checks.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
597 views

Check List For Beam & Slab

This document is a checklist for inspecting beams and slabs before pouring concrete. It contains 4 sections to check: 1) formwork, 2) steel reinforcement, 3) materials on site, and 4) equipment. The inspector is to verify that the formwork is properly supported and sealed, reinforcement is installed as specified, required materials are on hand in the needed quantities and quality, and all necessary equipment like vibrators, mixers, and lifts are present and in working condition. Signatures are required from the inspector and another witness after completing the checks.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CHECKLIST FOR BEAMS AND SLABS

Site: __________________________ Building:__________________________


Position & location of Concrete Work : __________________________
A) CHECKS BEFORE CONCRETING: Date : _______________
Sr. Item Satisfactory Signature
No
1 Formwork
No of props and condition
Level checked at locations:-

Maximum level difference :-


Gaps in plates sealed by :-

Gaps in beam bottoms sealed by :-


Shikanja Spacing confirmed
Beam Side supports
2 Steel
Checked as per schedule
Cover blocks spacing & thickness for beams
Cover block density & thickness for slabs
3 Materials Quantity Quantity Quality
stacked in brass Requir
ed
Cement
N.Sand
S. dust
M.sand
10 mm Agg.
20 mm Agg.
Plasticiser
Water
4 Instruments and Machinery reqd.
a) Punjas  b)Dhummas  c) Ghodis  d) Floats 
e)Thapi, 
Vibrator (No. ) & Condition
Needles Size & No.
Mixer Operating condition and fuel
Lift Operating condition and fuel
Weigh batcher Error L. Hopper _______R. Hopper ________
Weigh batcher Level
Farmas Available at site Size & No
Slope of chute above lift
Walking platforms provided

Signature Signature