RFI HPR FORM - 12E-C01-CE-0084 - 3rd LAYER BACFILLING AT PROJECT F 9 AROUND OFFICE AND LAY DOWN AREA

The document is a request for inspection from Mofarreh Marzouq Al-Harbi & Partners Co. Ltd. for the third layer backfilling at the office and lay-down area of Area F-9 in Ras Alkhair Industrial City. The request details the contract and location information, references relevant documents, and specifies a field density test and survey inspection are required for the third layer backfilling.

Uploaded by

Abdul Hannan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
265 views4 pages

RFI HPR FORM - 12E-C01-CE-0084 - 3rd LAYER BACFILLING AT PROJECT F 9 AROUND OFFICE AND LAY DOWN AREA

The document is a request for inspection from Mofarreh Marzouq Al-Harbi & Partners Co. Ltd. for the third layer backfilling at the office and lay-down area of Area F-9 in Ras Alkhair Industrial City. The request details the contract and location information, references relevant documents, and specifies a field density test and survey inspection are required for the third layer backfilling.

Uploaded by

Abdul Hannan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

ROYAL COMMISSION

RAS ALKHAIR INDUSTRIAL CITY

REQUEST FOR INSPECTION (RFI)

INSPECTION REQUEST NUMBER:CE-0084 REVISION NO.: DATE: 15-JAN-23

CONTRACTOR NAME:
CONTRACT NO.: 12E-C01
MOFARREH MARZOUQ AL-HARBI & PARTNERS CO. LTD.
LOCATION :- ( 12E-C01 - AREA-F- 9) DATE & TIME OF INSPECTION: 16-JAN-2023,
AROUND OFFICE AND LAY-DOWN AREA

REFERENCE DOCUMENT NO.: RC Spec.Sections: 02310 par3.05,2315 par. 3.05,Section 02310 par. 3.07

DRAWING NO.: (12E-035-20UT-CE-216)

ITP NO. & ACTIVITY NO.: MMAH-CE-002_2.2 & 2.3REV.00

ITEM TO BE INSPECTED: FDT & SURVEY INSPECTION FOR 3RD LAYER BACKFILLING L AT ( 12E-
C01 - AREA-F- 9) AROUND OFFICE AND LAY-DOWN AREA

LOCATION: ( 12E-C01 - AREA-F- 9) AROUND OFFICE AND LAY-DOWN AREA

TYPE OF INSPECTION
(circle applicable) Witness Hold

ADDITIONAL INFORMATION/COMMENTS:

REQUESTOR: QCI. ABDUL HANNAN SIGNATURE: DATE: 15-JAN-23

RECEIVED BY: ENGR.TURKI AL MUTAIRI SIGNATURE: DATE: 15-JAN-23

PAGE 1 OF 1
ROYAL COMMISSION
for Jubail and Yanbu
MOFARREH MARZOUQ AL-HARBI & PARTNERS CO. LTD.

HOLD POINT RELEASE


CONTRACT NO. : 12E-C01
SITE PREPARATION FOR INDUSTRIAL WASTE MANAGEMENT FACILITY IN RIC (IWMF)

HPR NO.: CE-0070 DATE: 16-JAN-23

Work Type : Pay-Item No.: SW-31 23 00-01 Zone No.:

CIVIL WORKS Activity Descriptions :


FDT & SURVEY INSPECTION FOR 3RD LAYER BACKFILLING L AT ( 12E-C01
- AREA-F- 9) AROUND OFFICE AND LAY-DOWN AREA
ELECTRICAL WORKS
MECHANICAL WORKS

OTHERS : _______________ Work Area / Location : ( 12E-C01 - AREA-F- 9) AROUND OFFICE AND LAY-DOWN
AREA

Attachment/s : IFC Drawings Shop Drawings As-Built Drawings Calculations


Drawing Reference No. : ( 12E-035-20UT-CE-216) Revision No. :
Inspection for : Materials / Delivery INSTALLATION HOLD POINT

QUANTITY RECORDS
Measured Qty.
Pay-Item No. Unit B.O.Q. Previous Qty. To Date Under Run Over Run
this Period

SW-31 23 00-01 mᶟ

TOTAL

WORK : MAY PROCEED MAY NOT PROCEED QUALITY : POOR GOOD

FIELD COORDINATION APPROVAL: REMARKS:


CIVIL
ELECTRICAL
MECHANICAL
STRUCTURAL
SPECIALIST

Inspected by MMAH Quality Control Department: Hold Point Released by RC Representative:


Q.C. Engineer QCI. Abdul Hannan Name: ENGR.TURKIAL MUTAIRI
Signature Signature
Q.C. Manager Engr. Najamuddin Ahamed Date:
Signature DATE: 16-JAN-23 Time: DATE: 16-JAN-23
EXCAVATION AND BACKFILLING CHECKLIST
Contract No.: 12E-C01 MMAH-CE-CL-001
Project Name:
SITE PREPARATION FOR INDUSTRIAL WASTE MANAGEMENT FACILITY IN RIC (IWMF)

Project Location: Ras Alkhair Industrial City Date: 16-Jan-23

Drawing No.:
12E-035-20UT-CE-216
Specification No.:
RC Spec.Sections: 02310 par3.05,2315 par. 3.05,Section 02310 par. 3.07

FDT & SURVEY INSPECTION FOR 3RD LAYER BACKFILLING L AT ( 12E-C01 - AREA-F- 9) AROUND OFFICE
Location: AND LAY-DOWN AREA

Item No. Inspection Attributes Accept Reject Not


Applicable

1 Excavation cleared of foreign and loose material

2 Slopes shored or correctly stepped

3 Access are properly provided and identified

4 Fill Material cleans and conforms to requirements

5 Lift thickness and compaction procedures in accordance with specifications

6 Final elevation in accordance to drawings

7 Moisture control acceptable

8 Compaction method and equipment

9 Soil Density Test Reports filed


REMARKS:

Prepared by:QCI. Abdul Hannan Approved by: ENGR.TURKIAL MUTAIRI

Signature & Date: 16-Jan-23 Signature & Date: 16-Jan-23

MMAH QA/QCI RC FIELD ENGINEER


SITE PREPARATION CHECKLIST
Contract No.: 12E-C01 MMAH-CE-CL-002
Project Name:
SITE PREPARATION FOR INDUSTRIAL WASTE MANAGEMENT FACILITY IN RIC (IWMF)

Project Location: Ras Alkhair Industrial City Date: 16-Jan-23

Drawing No.:
12E-035-20UT-CE-216
Specification No.:
RC Spec.Sections: 02310 par3.05,2315 par. 3.05,Section 02310 par. 3.07

FDT & SURVEY INSPECTION FOR 3RD LAYER BACKFILLING L AT ( 12E-C01 - AREA-F- 9) AROUND OFFICE
Location: AND LAY-DOWN AREA

Not
Item No. Inspection Attributes Accept Reject
Applicable

1 All backfilling layer should be as of indicated in the Contract Drawing

2 Select fill is of Client Specification or as approved by the client

3 Do not allow layers to exceed 300mm in thickness before compaction

4 Compact each layers in accordance with Royal Commission for Jubail & Yanbu Standards

5 The bottom of the trench shall be free of sharp or loose rock, debris or foreign matter

6 Cable or pipe shall be laid on a 150mm thick clean sand bed

7 The bed should be compacted uniformly to provide even bearing for pies
REMARKS:

Prepared by: QCI. Abdul Hannan Approved by: ENGR.TURKIAL MUTAIRI

Signature & Date: 16-Jan-23 Signature & Date: 16-Jan-23

MMAH QA/QCI RC FIELD ENGINEER