Week 2 - Historical Project Plan - Gantt Chart PDF
Week 2 - Historical Project Plan - Gantt Chart PDF
1 Project Initiation
Research data points on reservation
1.1 Carmen 1/8/18 1/15/18 7 100%
systems and enhancement
Gather historical data on booking
1.1.1 Carmen 1/15/18 1/15/18 0 100%
process
1.2 Align and evaluate stakeholders Alex 1/15/18 1/17/18 2 100%
Calculate projections and
1.3 Carmen 1/17/18 1/18/18 1 100%
enhancements
1.4 Interview members of the staff Alex 1/18/18 1/19/18 1 100%
1.4 Create project charter (scope and goals) Carmen 1/22/18 1/26/18 4 100%
1.5 Schedule kick off meeting Carmen 1/29/18 1/29/18 0 100%
2 Sourcing
2.1 Research reservation system options Carmen 2/2/18 2/2/18 4 100%
2.2 Generate quotes and review costs Carmen 2/5/18 2/5/18 3 100%
2.3 Test out reservation systems Makayla 2/5/18 2/9/18 4 100%
2.4 Choose a reservation system Carmen 2/5/18 2/9/18 4 100%
Vendor timeline and deliverables
2.5 Carmen 2/6/18 2/10/18 4 100%
schedule
3 Planning
Create contracts and statements of work
3.1 Vince 2/12/18 2/15/18 3 100%
for vendors
Message about launch date to
3.2.1 Alex 2/13/18 2/13/18 0 100%
stakeholders
3.3 Project Plan Updates Carmen 2/15/18 2/28/18 13 100%
Update marketing/social media
3.4 Alex 2/15/18 2/25/18 10 100%
plan/calendar
Create launch day plan: staffing,
3.5 Alex 2/18/18 2/25/18 7 100%
troubleshooting, etc.
4 Training
Map out seating chart/upload into
4.1 Makayla 2/20/18 2/22/18 2 100%
software
4.2 Train GMs on new software Makayla 2/23/18 2/23/18 0 100%
4.3 Train staff on new software Makayla 2/24/18 2/24/18 0 100%
4.4 Test run reservation system Makayla 2/25/18 2/25/18 0 100%
4.5 Create troubleshoot/support plan Makayla 2/20/18 2/25/18 5 100%
4.6 Launch day Carmen 3/1/18 3/1/18 0 100%