Management and Construction of The Three Gorges Project
Management and Construction of The Three Gorges Project
Abstract: The owner-responsibility system is conducted for implementation of the Three Gorges Project 共TGP兲. For the construction
management of the project, the contracting system, the contract administration system, and the construction supervision system are
executed for the project management. Contractors for civil projects are determined through bidding and contracting. The permanent
equipment and construction materials are purchased through bidding. Some of large-sized construction machines and mechanical and
electrical equipment are procured by the international competitive bids. Qualified engineers from qualified engineering bodies, scientific
research organizations, and construction companies are selected for the construction supervision. This paper covers the construction of the
TGP in some detail, particularly the main dam structure, diversion work, the construction program, and management, project cost, and
financing.
DOI: 10.1061/共ASCE兲0733-9364共2006兲132:6共615兲
CE Database subject headings: Construction management; Contract management; Project management; Water resources.
compacted concrete 共RCC兲 cofferdam is constructed in the tenance after the completion of the project, and is also responsible
construction pit. Meanwhile, the construction of the temporary for the financing and reimbursement of investment including the
shiplock on the left bank of the river is constructed. In this con- fund for resettlement.
struction phase, the river flow and navigation went through the As determined by the State Council, the principles of the so-
main river course. cialist market-oriented economy and the common international
In the second construction stage, the construction is started practice are adopted in TGP’s construction. That is, the bidding
with building the transverse cofferdams, so as to form, together management, contract management, and construction supervision
with the completed RCC longitudinal cofferdam, into the phase II system centering on the project’s legal entity responsibility are
construction pit. The construction of the spillway, intake dam, and carried out for the project construction and management.
power plant on the left bank has begun. Simultaneously, the per- The headquarters of CTGPC is located in Yichang City. There
manent shiplock and shiplift are constructed on the left bank. In are several departments and subsidiaries under the CTGPC such
this stage, the river flow is diverted through the open diversion as planning, financing, scientific management, Gezhouba power
channel, and barge fleets and passenger boats pass through either plant, etc. In the dam site, the project construction department has
the open channel or the temporary shiplock. been established which is in charge of the overall coordination
In the third construction stage, the upstream phase III RCC and management of the construction. Under this department, the
cofferdam is built in the open channel, and the impoundment of subproject departments take the responsibility for management of
the reservoir is up to the elevation of 135 m. The left bank power individual construction items.
station and permanent shiplock is put into operation. In the mean- The Resettlement Bureau under TGPCC was established,
time, the phase III cofferdams together with the longitudinal cof- which is responsible for setup of resettlement policies, resettle-
ferdam, form the phase III construction pit for the construction of ment planning, supervision on resettlement progress, and quality
the right bank dam and power plant. During this period, the river and coordination of the issues arising from the resettlement ex-
flow is discharged through the outlets in the spillway dam, while ecution. The local governments of Chongqing and Hubei Prov-
the boats pass through the permanent shiplock. ince are in charge of the resettlement practice specifically includ-
ing resettlement, industry relocation, and household rebuilding.
Scheduling
The total duration of construction was divided into three construc- Project Management
tion stages.
1. Stage I, from 1993 to 1997, is for the construction prepara-
tion and the phase I works, which is marked with the river Design Management
closure; The design of TGP is undertaken by the Yangtze Water Resources
2. Stage II, from 1998 to 2003, is for phase II works, which Commission under the Ministry of Water Resources. The techni-
marked the generation of electrical power by the first batch cal design is reviewed and approved by the Technical Committee
of generating units and the operation for ship traffic of the of the CTGPC by means of panels of experts. The bidding design
permanent shiplock; and is reviewed and approved by the CTGPC. The detailed construc-
3. Stage III, from 2004 to 2009, is for phase III works, which is tion drawing design is reviewed and approved by the Construc-
marked with the operation of all generating units and tion Department under CTGPC in conjunction with various super-
completion of the project. vision units. Expert comments and ideas are widely called for by
CTGPC on the key technical issues arising from the project to
encourage innovation, give full play to collective wisdom, and
Basic Management Frameworks for Construction avoid incorrect decisions.