Bottom Up and Top Bottom
Bottom Up and Top Bottom
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5844
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
construction sequence of top-down construction is as Keep constructing the superstructure until it gets
follows: finished.
Construct the embedded retaining wall (usually a Design and construction principles for the top-down
diaphragm wall). method primarily call for two major structural elements.
Construct piles. Place the steel columns where the Columns with sufficient capacity must be pre-founded in
piles are constructed. bored piles or diaphragm wall panels to sustain the
Proceed to the first stage of excavation. construction load and to utilize as part of the bracing system.
Cast the floor slab of first basement level with the
opening to allow machines to be lowered to 2. Case Study
excavate level below and for excavation material to
be removed. An ongoing bottom-up construction of a G+4 residential
Proceed to the second stage of excavation; cast the apartment at Trivandrum, Kerala is taken for comparison
floor slab of the second basement level. study. It is a rectangular plot surrounded with buildings, the
Repeat the same procedure until the desired depth main constraints of the site are limited space for parking and
is reached. others activities and water table level. Considering these
Construct the foundation slab. Complete the constraints the ongoing construction is theoretically
converting into top-down construction method and
basement.
comparing the activities and time of construction.
The construction activities from ancient age have a typical stage of commencement during the execution phase i.e. the first
activity starts from the foundation of the structure. The conventional method of construction of structures is based on Bottom-
Up method in which the sub-structure and super-structure floors are constructed sequentially from the bottom of the sub-
structure or lowest level of basement to the top of the super-structure. This method is suitable for small scale works, as there is
rapid change in patterns of use of land available like use of underground basements for parking, underground metro stations the
volume of works at the foundation level of the structures has increased to manifolds The top-down method is an another
construction method that can be used for structures with basement floor and having space and other constraints.
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5845
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
Here the all the activities in a construction project management such as project duration, resources, labor etc., are scheduling
using primavera in both the above construction methods with respect to our project site (residential building (G+4)).
Bottom-up Construction Schedule
Using primavera all the activities such as project duration, resources, labor, cost etc. for the proposed residential
apartment with G+4 in bottom-up construction is scheduled. The residential building project is situated in Trivandrum,
Kerala. The residential building is 926.112square feet with G+4 structure without providing required parking facilities.
Construction schedule is as shown in the Table.
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5846
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5847
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
Activity ID Activity Name Original Duration Start Finish Budgeted Total Cost
Activity ID Activity Name Original Duration Start Finish Budgeted Total Cost
Wood work for joinery (teak wood) 25d 14-Mar-2020 13-Apr-2020 Rs6,987,236.00
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5848
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5849
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 05 | May 2020 www.irjet.net p-ISSN: 2395-0072
Theertha S.L
Department of Civil Engineering
Saintgits College of Engineering
Sujithmon S
Department of Civil Engineering
Saintgits College of Engineering
Joseph Zacheriah
Department of Civil Engineering
Saintgits College of Engineering
© 2020, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 5850