2021 Pumped Storage Report NHA
2021 Pumped Storage Report NHA
EXECUTIVE SUMMARY
Executive Summary
PREFACE
T his White Paper was prepared by theis the third
An essential attribute of our nation’s electric power
This Pumped Storage Report prepared
system is grid reliability - ensuring that electric supply
National Hydropower Association’s
by the National Hydropower
securely matches electric Association’s Pumped
demand and in real-time. The
A primary goal of
Pumped Storage Development primary
Storage Development
challenge in
Council
ensuring reliability is that electric
supply has no shelf life - it(Council).
must be generated Thewhen
this paper
Council. Theisprimary
to author is Michael
first report was
neededprepared in 2012
- and electricity demandandcontinually
the second changes,
Manwaring
offer (Council
the reader a Chair, Stantec)in 2018. This report focuses on energy markets,
as do the system conditions impacting secure delivery
of that generation. Electric transmission grid operators
with significant
pumped storageinput provided by Kelly
energy storage havepolicy,
long met development opportunities
the challenge of aligning energy supply and
Rodgers (Council Co-Vice Chair, Sanand challenges, technological advancements,in and
demand and responding to steep increases demand on
hydropower (PSH) a real-time basis with a limited number of long-life, proven
Diego County Water Authority), Scott
the Council’s recommendations
generation to unlock
technologies - specifically the and
hydropower
handbook of historic
Flake (Independent Pumped Storage gas-fired combustion turbines - that have the ability to
full value ofstart
thisuplong duration
quickly and/or vary renewable
their electricstorage
output as the
Consultant), Don
development andErpenbeck (Stantec), demand changes. Large reservoir hydropower, thermal
resource. We have designed the 2021 report so that
Rick Miller (HDR), as
current projects, new well NHA staff (generally coal and gas) and nuclear resources have
it can be easily updated
commonly servedinasresponse to an evolving
baseload resources, providing the
and numerous industry participants. stabilizing backbone to grid reliability. As greater amounts
project opportunities grid and changing storage needs. The report can
of renewable energy resources are integrated into the
and challenges, as be easily referenced forand
energy supply, advocating
recent energyand educating
policy decisions and
regulation have impacted coal and nuclear resources,
at the federal, state and local levels and ultimately
well as technological pumped storage and other energy storage technologies
— be the go-to resource
will continue for new
to emerge pumped
as critical storage
resources to provide
advancement and flexible solutions to meet grid reliability challenges.
development. A new addition in this report is the
resource capabilities. “frequently asked questions” section.
A
s the United States grid continues its rapid evolution to meet ambitious
clean energy goals, the electric industry must manage this change while
maintaining reliability, keeping energy costs competitive and ensuring
that capital is directed toward technologies that can meet all these
goals. The EIA projects the share of electricity from renewables will
grow from 21% in 2020 to 42% in 2050.1 These percentages are much
greater in states with aggressive Renewable Portfolio Standards (RPS),
Clean Energy Standards (CES) or greenhouse gas (GHG) reduction
targets. Many states are now adopting CES goals targeting 100% carbon
free emissions by mid-century. These goals are not limited to state
policies. In some areas, utilities are investing in cleaner assets based on
ESG (Environmental, Social and Governance) issues. Likewise, utility
customers and investors are supporting clean energy through choice
of suppliers, deciding where to locate businesses and purchasing green
energy directly through power purchase agreements. In some ways,
customer and investor driven ESG priorities are incenting change faster
than regulation.
1U.S. Energy Information Administration, Annual Energy Outlook 2021 (AEO 2021)
EXECUTIVE SUMMARY 3
above-mentioned models are forecasting the need
for flexibility, fast ramping, capacity, and both short 40
and long duration energy storage. PSH’s existing
2DOE Water Power Technologies Office, Hydropower Vision Report, October 21, 2016.
3U.S.Energy Information Administration, Battery Storage in the United States: An update on market trends, July 2020
4Storage Futures Study (SFS), Economic Potential of Diurnal Storage in the U.S. Power Sector, NREL
description will be to integrate solar and wind to help Current Challenges to PSH Development
maintain a low carbon reliable grid. In some areas of the
As of the publication of this report, three new PSH
country this is already occurring. Existing PSH units are
projects totaling 1.8 GWs have received all permitting
not only pumping at night but also throughout the day
to match energy demand when there is excess solar on authorizations including a Federal Energy Regulatory
the grid. As load demand grows in the late afternoon, Commission (FERC) license but have yet to commence
PSH plants (or water batteries) can return the excess construction. In addition, FERC reports that over
solar energy to the grid when it is needed most. 50 GWs of pump storage development have been issued
a preliminary permit or are in the process to receive
As state clean energy goals ramp up to reduce climate a permit. Unfortunately, current market and energy
impacts, many gas turbines will likely retire. These policies do not fully value the critical services that PSH
gas turbines have been providing flexible capacity and can provide to the grid. Many challenges faced by PSH
ramping services. The retirement of these units will developers include the following:
make it more challenging for grid operators to maintain
reliability with a more variable energy mix. PSH is • Tax policy – Current Federal tax policy provides
poised to play an even greater role in this future grid that some energy storage technologies receive a 30%
scenario, especially with its highly flexible capability investment tax credit (ITC) while pumped storage
to provide long duration storage and rapid response to does not. This can make a substantial difference
changing energy demands. within a competitive utility procurement setting.
In California’s most recent Integrated Resource • State Procurement policy – Most states that have
Plan developed by the California Public Utilities RPS (renewable portfolio standard) mandates
Commission (CPUC), there is a recognition of the or energy storage procurement targets either
different attributes between 4-hour battery energy implicitly or explicitly exclude pumped storage.
storage and the need for longer duration energy storage, Even “technology neutral” policies can include short
typically 8 hours or more5. The state has several large development timelines or contracting structures that
PSH plants in operation that can supply long duration exclude PSH and favor other storage technologies.
energy storage. During times of stress, these plants are
relied on to help stabilize the grid. As GHG emissions • Market policy – Many of the grid services that
are reduced to meet low carbon emissions targets in PSH provides are either undercompensated or not
2030, significant amounts of 4-hour energy storage will compensated at all. Compensation mechanisms
be used to help flatten the gross peak demand and net for frequency response, inertia, flexible ramping,
peak demand (load minus solar and wind generation). condensing, voltage control and blackstart are
As GHG emissions are further reduced and natural undervalued. Additionally, PSH can provide broader
gas plants are retired, long duration energy storage system benefits that are hard to quantify and measure
provided by PSH is needed to extend the delivery leading to subpar compensation.
5CPUC 2019-2020 Electric Resource Portfolios to Inform Integrated Resource Plans and Transmission Planning
EXECUTIVE SUMMARY 5
• Utility Procurement policy – Most utilities do not • State Procurement policy – States need to send
accurately model the full benefits of PSH including a market signal that long duration storage will be
the full range of services provided by advanced needed to meet aggressive climate goals. Legislatures
turbine technologies. Additionally, when comparing should adopt robust long duration storage targets
PSH to other alternatives utility planners often fail to with long lead times to ensure that the demand
account for the long-life span differences. is met and that all technologies have a chance to
compete.
• Federal permitting policy – Although recent
changes created a two-year expedited licensing • Market policy – All grid services need to be fully
process for closed-loop or “off-river” pumped valued. Many of the grid services that PSH provides
storage, the implementation of this process has made are either undercompensated or not compensated
it difficult for projects to qualify. As of the date of at all. In regional markets, FERC should ensure
this publication, no PSH project has successfully there are sufficient compensation mechanisms
navigated the expedited process. for frequency response, inertia, flexible ramping,
condensing, voltage control and blackstart and
other services provided by PSH. In addition,
NHA Recommendations to Address some renumeration should be provided to those
PSH Development Challenges technologies like PSH that can provide broader
system benefits that are hard to quantify and
Pumped storage technologies are already providing
measure.
essential value to an evolving grid. For new pumped
storage development to occur, U.S. policymakers • Utility Procurement policy – Utilities should work
need to appropriately value all the services PSH can with the Department of Energy, PSH developers and
provide including long duration storage. NHA supports the national labs to ensure that the full benefits of
competitive and technology neutral mechanisms that PSH, including the full range of services provided
will level the playing field for all storage options. These by advanced turbine technologies, are accurately
include: modeled in IRP settings.
• Tax policy – Several proposals in Congress would • Federal permitting policy – FERC and other
create a stand-alone ITC for all storage technologies stakeholders should work to reform the licensing
including PSH. A technology neutral ITC would process, including allowing projects with minimal
ensure that PSH can compete with other storage environmental impacts to be expedited.
resources on a level economic playing field.
P
umped storage hydropower (PSH) has played an important role in
America’s reliable electricity landscape. The first PSH plant in the U.S.
was constructed nearly 100 years ago. Like many traditional hydropower
projects, PSH provides the flexible storage inherent in reservoirs. And
with its pumping mode, PSH brings the added benefit of absorbing
off-peak and excess electric generation and is an important asset in
integrating renewable energy resources.
Today, in the U.S. there are 67 new PSH projects across 21 states
representing over 50 GWs of new long duration storage (see Figure 2).
Many of these projects are located in the west and are off-river or
closed loop meaning they have fewer environmental impacts. Existing
and proposed PSH projects are poised as a perfect complement to the
significant amounts of wind and solar energy being ushered to the grid
to reduce greenhouse gas emissions and combat climate change.
electricity from the grid to pump water from a lower administrations conceived, designed, permitted, and
elevation, PSH creates potential energy in the form of constructed PSH plants to make more efficient use of
water stored at an upper elevation, which is why it is large steam-powered generating plants. These large
often referred to as a “water battery”. thermal plants operate most efficiently when run
continuously. PSH was an ideal technology to absorb
During periods of high electricity demand, the stored electricity being generated at night when demand for
water is released back through the turbines to generate electricity was low and return electricity to the grid
electricity like a conventional hydropower station. during the daytime peak hours. A large PSH plant
Current pumped storage round-trip or cycle energy can store energy to support 8-16 hours of full load
efficiencies often exceed 80% and do not degrade over operation, and a week or longer at the largest plants.
the lifetime of the equipment, comparing very favorably
to other energy storage technologies. With these PSH plants in place, grid operators
recognized the value of PSH to not only pair with large
Beginning in 1929 and for 60 years thereafter, vertically load thermal in a 24-hour cycle, but to meet increased
integrated utility companies and the federal power
800 18000
700 16000
600 14000
12000
500
10000
400
8000
300
6000
200 4000
100 2000
0 0
2012 2013 2014 2015 2016 2017
Pumping GW Hours 1:00 AM–7:00 AM Pumping GW Hours 9:00 AM–5:00 PM
Figure 3. Helms PSH ratio of pumping nighttime and daytime hours with solar and wind overlay.
Source: PG&E, as filed with DOE April 2018 and California Energy Commission.
0.35 3500
0.30 3000
0.25 2500
0.20 2000
0.15 1500
0.10 1000
0.05 500
0.00 0
2015 2016 2017 2018 2019 2020
Ratio of MW hours used for pumping Duke Energy Solar Installed Capacity (MW)
1100-1300 hours compared to hours 0100-0300 hours
Figure 4. Jocassee and Bad Creek PSH ratio of pumping GWH daytime and nighttime.
6Aclosed-loop pumped storage project is generally defined as a pumped storage project that utilizes reservoirs situated at locations other than natural waterways, lakes,
wetlands, and other natural surface water features, and may rely on temporary withdrawals from surface waters or groundwater for the sole purpose of initial fill or the
periodic recharge needed for project operation. “Federal Energy Regulatory Commission Office of Energy Projects Division of Hydropower Licensing. “Guidance for
Applicants Seeking Licenses or Preliminary Permits for Closed-Loop Pumped Storage Projects at Abandoned Mine Sites”. October 2019.
7 “Developing Valuation Guidance for Pumped Storage Projects”, Vladimir Koritarov, Presented April 17, 2019, at EPRI hydropower Flexibility Workshop
3.1 V
ALUING ENERGY STORAGE —
A COMPLEX UNDERTAKING
When discussing the value of energy storage, the conversation typically
revolves around the project cost and the monetized benefits the project
provides. While project costs can be ‘fairly’ straightforward, the benefits
of energy storage have proven very challenging to quantify. A primary
challenge to the ‘value’ picture is that energy storage technologies offer
multiple services, and therefore should be eligible for multiple value
streams. Most market designs are based in energy sales and do not
fully recognize the value of capacity-based services like inertia, voltage
support, etc. Energy based market designs pose a challenge to attract
the necessary investment to develop large capital energy storage projects
like PSH by not providing value to a significant portion of PSH services
Bear Swamp Pumped Storage that are critical for grid resiliency.
Hydropower facility in northern
Massachusetts is jointly owned by To best represent the value of an energy storage project, most developers
Brookfield Power and Emera Energy. try to stack, or combine, various revenue streams to more accurately
8 https://irecusa.org/resources/key-takeaways-for-policymakers-and-regulators/
FERC Order 1000 introduced robust regional planning When evaluating energy storage systems, the dollar
into the transmission process. It also mandated per kilowatt hour ($/kWh) is a helpful illustration of
coordination among neighboring transmission the competitiveness of each storage technology. This
planning regions within their interconnection. Because metric considers the cost of the technology, lifetime and
Order 1000 establishes requirements for reforming amount of energy storage. As Figure 5 shows, pumped
transmission cost allocation processes, it creates an storage hydropower has a much lower $/kWh than
opening for energy storage to be included in the lithium-ion batteries, and is nearly 2 to 3 times less
transmission planning process. If, as a result of the expensive. Also, pumped storage hydropower’s annual
transmission planning process, a project is accepted operations and maintenance, $20/kWh-yr costs are also
into a regional plan, or incorporated as a resource three times lower than batteries9.
supporting the regional plan, it would appear to meet Development of modern PSH project costs can
the threshold requirements of Section 219 of the vary based on site-specific conditions such as the
Federal Power Act, making it eligible for incentive availability of existing civil and generation/transmission
rate treatment. In addition, having storage included in
350 P80
300 x x Average
Median
P20
250 Min
x
200
x
150
100
x x
50
0
Energy-$/kWh
PHS-Fixed speed PHS Variable speed Batteries 2020
Batteries 2025 Batteries 2030
9 DOE Energy Storage Technology and Cost Characterization Report, July 2019
3.3 N
EW TECHNOLOGY ADVANCEMENTS
AFFECTING PSH PROJECTS
infrastructure, land, and water, as well as project PSH is a proven, reliable technology that currently
size, environmental regulations, site geology, water represents more than 95% of all energy storage
availability, and overall construction cost. A feasible solutions globally. Pumped storage technology
project site would include an approximate cost estimate advancements include: improved efficiencies with
ranging from $1,700/kilowatt (kW) to $2,500/kW, based modern reversible pump-turbines, adjustable-speed
on an estimated 1,000 MW sized project. A smaller pumped turbines, advanced equipment controls
project typically does not have the same economies of such as static frequency converters and generator
scale and could result in higher unit costs (in $/kW) insulation systems, as well as innovative underground
than a large project, but the overall project costs would construction methods and design capabilities. The
be much less. These costs are representative for all PSH benefit of these advances is faster response time
project aspects except land acquisition, transmission which enables load following to integrate intermittent
interconnection charges, and some owner’s costs, which renewables more efficiently and cost effectively.
can range from very minor charges to significant, based
on site specific conditions. 3.3.1 A
dvanced Pump-Turbine
According to a 2016 Electric Power Research Institute Equipment Technology
(EPRI) report, the levelized cost of PSH represent Globally, there are approximately 270 pumped
one of the lowest cost forms of energy storage. What storage plants either operating or under construction,
continues to present a challenge to those seeking to representing a combined generating capacity of over
understand the varying costs for different energy 127,000 MW. Of these total installations, 36 units
storage technologies is the recognized inconsistency consist of adjustable speed machines, 17 of which
between how each energy storage technology (PSH, are currently in operation (totaling 3,569 MW) and
batteries, compressed air, flywheels, etc.), present their 19 of which are under construction (totaling 4,558
costs. Clearly, it is in the interest of long-life assets (i.e. MW). Adjustable-speed pump-turbines have been
PSH) to use levelized cost of energy (LCOE) using used since the early 1990s in Japan and the late 1990s
a 25-plus year asset life cycle because the physical in Europe. In these areas, adjustable speed pumped
assets (major cost components) can depreciate over a storage can reduce significant quantities of oil burned
longer time period, showing a lower LCOE compared in combustion turbines in off-peak hours by shifting
to shorter-life assets (i.e. batteries, flywheels). Battery the responsibility for regulation to pumped storage
technologies in particular would need equipment plants. Another advantage is the increase in overall
replacement over the same period because their unit efficiency as the turbine can be operated at its
physical assets are not expected to last the full life cycle. optimum efficiency level under all head conditions,
A recent energy storage policy guide concluded that resulting in increased energy generated on the order
energy storage costs can be expressed by using two of 3% annually. The current U.S. fleet of operating
metrics: rated power and discharge duration. By only (single-speed) pumped storage plants does not provide
utilizing these two metrics, the true representation of regulation in the pump mode because the pumping
10CAISO Final Flexible Capacity Needs Assessment for 2021, May 2020
11CAISO 2019 annual report on market issues and performance, June 2020
Figure 7. Contrast of PSH and Lithium-ion batteries with respect to size, storage duration and grid support services.
In recent years, Europe has been seeing steady growth of It is possible to retrofit an existing fixed speed pumped
pumped storage whereas China has been experiencing storage unit with variable speed, but often the costs
exponential growth. In the past 10 years, China has associated with this change and the space required are
commissioned 14 GW of PSH, all fixed speed except not economically viable.
for one 600 MW (0.6 GW) variable speed plant under When considering all the details that affect efficiency, a
construction. China typically locates their PSH near global cycle efficiency generally between 75% and 80%
large cities and are able to manage the grid with this wire to wire is obtained. This efficiency varies whether
configuration. It should also be noted that China views the units are operated all together, at maximum load, or
PSH as a generation asset and they have plans for similar if a few of them are operated at best efficiency.
2 Vconsideration
ertically integrated states should require
of long duration energy storage
5 Sstorage
tates policy makers should allow all energy
technologies, including PSH, to participate
resources in integrated resource planning in renewable portfolio standard programs (or clean
processes, including requiring equal consideration energy standards) on a technology neutral-basis.
with traditional resources. In addition, state energy storage targets should
incorporate longer term goals to ensure the most
3 Oneutral
cost effective long-duration storage technology,
rganized markets should design technology-
pumped storage, can compete with other
products and services for future system
technologies.
needs. A decarbonized grid will require many
essential reliability services that currently are
under-compensated or not compensated at all
(examples include fast ramping, primary frequency 6 for
Request FERC to establish a common methodology
value of energy storage and capacity products
response, inertia, and load following). Grid that can be utilized across the spectrum of
operators and FERC should implement longer term technologies available to provide these services.
market designs to ensure capital is attracted to
critical grid services in advance of the demand.
equest FERC to streamline the licensing process
7 Reven further for low-impact pumped storage
hydropower, such as off-channel, modular or
closed-loop projects.
RECOMMENDATIONS 27
PSH