Abstract Cost For Intake Well & Pontoon

The document provides cost estimates for two projects: 1) Intake cum jack well totaling Rs. 123,318,692.57 which includes costs for resurveying, coffer dams, excavation dewatering, wells, HDD, pipes, valves, bridges and equipment. 2) A floating pontoon totaling Rs. 67,200,000 which includes costs for the pontoon, walkway, pump house, contingencies, contractor profit, inspection and installation. The final costs will be determined by approved designs and drawings.

Uploaded by

Praveen Rander
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views1 page

Abstract Cost For Intake Well & Pontoon

The document provides cost estimates for two projects: 1) Intake cum jack well totaling Rs. 123,318,692.57 which includes costs for resurveying, coffer dams, excavation dewatering, wells, HDD, pipes, valves, bridges and equipment. 2) A floating pontoon totaling Rs. 67,200,000 which includes costs for the pontoon, walkway, pump house, contingencies, contractor profit, inspection and installation. The final costs will be determined by approved designs and drawings.

Uploaded by

Praveen Rander
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Abstract of Cost for Intake Cum Jack Well

Total
Sr. No. Description
Amount (Rs.)
1 Resurveyed of Proposed Side 557,500.00
Coffer Dam for Intake Well, 2 Nos of Inspections well & Jack well
2 35,000,000.00
100 m long & 20 m Ht.
3 Dewatering Work during Excavation 16,000,000.00
Cost of Intake well 1 Nos, Inspection well 2 Nos, & Jack well 10 m
4 30,765,957.99
Dia. & 40 m Ht
5 HDD in Hard Rock for Rosepiece I & II (2 Nos.) 6,593,009.00
5 Rosepiece I - 85m MS Pipe @ 900mm Dia. 1,472,836.00
6 Rosepiece II - 15m DI K9 @ 900mm Dia. 799,367.00
7 Rosepiece III - 5m DI K9 @ 900mm Dia. 338,216.00
8 Sluice Gate Valve @ 900mm Dia. - 3 Nos. 3,200,000.00
9 Approach Bridge of 150 m Length 22,500,000.00
10 Mechanical Euipments EOT crane & others 2,500,000.00
Net Cost 119,726,885.99
Contingencies Charges (3% of Project Cost) 3,591,806.58
Grand Cost 123,318,692.57

Abstract of Cost for Floating Pontoon


Total
Sr. No. Description
Amount (Rs.)
1 Floating Pontoon Along with Walkway 45,000,000.00
2 Pump House & Shore foundation 7,500,000.00
Net Cost 52,500,000.00
3 Contingencies Charges (3% of Project Cost) 1,575,000.00
4 Contractor Profit and overhead (15% of Project Cost) 7,875,000.00
5 IRS Inspection and Launching Charges (5% of Project cost) 2,625,000.00
6 Installation, Commissioning and Testing (5% of Project Cost) 2,625,000.00
Grand Cost 67,200,000.00
Note : Final cost would be as per Approved Design & Drawing