0% found this document useful (0 votes)
194 views6 pages

Detailed Abstract of Estimated Cost For Bank Loan

This document provides a bill of quantities for the construction of a proposed residential building. It includes 3 sentences summarizing the key information: The bill of quantities details material costs for various construction items over a total area of approximately 1281 square meters, with a subtotal estimated cost of 924,409.65. Major expenses include earthwork, concrete work, reinforcement, brickwork, woodwork, doors and windows. The document provides unit rates and quantities for 25 line items to estimate the total cost of the construction project.

Uploaded by

ramakrishna6469
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
194 views6 pages

Detailed Abstract of Estimated Cost For Bank Loan

This document provides a bill of quantities for the construction of a proposed residential building. It includes 3 sentences summarizing the key information: The bill of quantities details material costs for various construction items over a total area of approximately 1281 square meters, with a subtotal estimated cost of 924,409.65. Major expenses include earthwork, concrete work, reinforcement, brickwork, woodwork, doors and windows. The document provides unit rates and quantities for 25 line items to estimate the total cost of the construction project.

Uploaded by

ramakrishna6469
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Detailed abstract of Estimated Cost (B.O.

Q) for construction of proposed Residential Building

Bill of Quantity

S.No. Description of Items Unit Quantity Rate Amount

Earth work in excavation by mechanical


means (hydraulic excavator)/manual means
over areas (exceeding 30cmin depth, 1.5m in
1 width as well as 10sqm on plan) including cum 172.58 150 25,887.00
disposal of excavated earth, lead upto 50m
and lift upto 1.5m, disposed earth to be
leveled and neatly dressed.

Filling available excavated earth (excluding


rock) in trenches, plinth, sides of foundations
etc. in layers not exceeding 20cm in depth:
2 cum 172.58 35 6,040.30
consolidating each deposited layer by
ramming and watering, lead up to 50 m and
lift upto 1.5 m

Supply & laying and compacting of 150mm


thick over burnt brick aggregate 90mm to
45mm including spreading in uniform
3 thickness, applying and brooming requisite cum 21.19 1400 29,664.77
type screening / binding material to up
interstices coarse aggregate watering and
compacting to required density.

Diluting and injecting chemical emulsion for


POST-CONSTRUCTIONAL anti-termite
4        
treatment (excluding the cost of chemical
emulsion) :

Treatment of soil under existing floors using


chemical emulsion @ one litre per hole, 300
mm apart including drilling 12 mm diameter
         
holes and plugging with cement mortar 1 :2
(1 cement : 2 Coarse sand) to match the
existing floor.

With Chlorpyriphos/Lindane E.C. 20% with


  sqm 128.41 240 30,817.58
1% concentration.

Sub-Total 92409.65

Providing and laying in position cement


5 concrete 1:4:8 of specified grade including cum 14.46 3460.00 50,035.92
the cost of centring and shuttering.

Centring and shuttering including strutting,


6        
propping etc. and removal of form for :

Foundations, footings, bases of columns, etc.


6.1 sqm 40.26 170 6,844.20
for mass concrete.

Suspended floors, roofs, landings, balconies


6.2 sqm 171.99 265 45,577.35
and access platform.

6.3 Lintels, beams, plinth beams, girders, sqm 229.96 250 57,490.00
bressumers and cantilevers.

Columns, Pillars, Piers, Abutments, Posts and


6.4 sqm 165.08 270 44,572.41
Struts.

Stairs, (excluding landings) except spiral-


6.5 sqm 11.84 290 3,433.60
staircases.

Providing and laying in position specified


grade of reinforced cement concrete
7 excluding the cost of centering, shuttering,        
finishing and reinforcement- All work upto
plinth level:

1:1:2 (1cement : 1 coarse sand : 2 graded


7.1 cum 29.58 5040 149,083.20
stone aggregate 20 mm nominal size)

Reinforced cement concrete work in beams,


suspended floors. Roofs having slope upto
15°, landings, balconies, shelves, chhajjas,
lintels, bands, alain window sills, staircases
8 and spiral stair cases upto floor five level cum 64.46 4800 309,408.00
excluding the cost of centring shuttering
finishing and reinforcement with 1:1:5:3 (1
cement: 1.5 coarse sand : 3 graded stone
aggregate 20mm nominal size)

9 Mild steel and Medium Tensile steel bars qtls 119.27 5640 672,682.80

Sub-Total 1339127.48

Brick work with F.P.S. bricks of class


10 designation 150 in foundation and plinth in cum 9.57 3920 37,514.40
Cem. Mortar 1:6

Brick work with F.P.S. bricks of class


11 designation 150 in superstructure above cum 70.15 3785 265,517.75
plinth level in 9” th. Walls in Cem.Mortar 1:6

Brick work with F.P.S. bricks of class


designation 150 in superstructure above
12 sqm 105.86 430 45,519.80
plinth level in 4.5” th. Walls in Cem. Mortar
1:4

Extra for providing and placing in position 2


12.1 Nos. 6mm dia. M.S.bars at every third course sqm 105.86 60 6,351.60
of half brick masonry (with F.P.S. bricks).

Sub-Total 354,903.55

Providing sal wood work in frames of doors,


13 windows, clerestory windows and other cum 1.55 70000 108,500.00
frames, wrought framed and fixed in position.

Providing and fixing ISI marked flush door


shutter conforming to IS:2202 (Part - 1) non-
decorative type, core of block board
14 construction with frame of 1st class hard        
wood and well matched commercial 3 ply
veneering with vertical grains or cross bands
and face veneers on both faces of shutters:
35 mm thick including ISI marked Stainless
  sqm 30.83 2600 80,158.00
Steel butt hinges with necessary

Extra for Providing and fixing flush doors with


15        
decorative veneering

  On one side sqm 30.83 320 9,865.60

Extra for providing lipping with 2nd class teak


wood battens 25 mm minimum depth on all
16 sqm 30.83 250 7,707.50
edges of shutters (over all area of door
shutter to be measured)

Providing and fixing glazed shutters for doors,


windows and clerestory windows using 5 mm
17 thick float glass panes including black        
enamelled ISI marked MS butt hinges with
necessary screws.

Kiln seasoned and chemically treated Hollock


         
wood

  30 mm thick sqm 37.92 1500 56,880.00

Providing 40x5mm flat iron hold fast 40cm


long including fixing to frame with 10mm dia
bolts, nuts and wooden plugs and embedding
18 No 139.00 90 12,510.00
in cement concrete block 30x10x15cm 1:3:6
mix (1cement : 3 coarse sand : 6 graded
stone aggregate 20mm nominal size)

M.S work in grills, frames, guard bar, ladders,


19 kg 879.55 90 79,159.50
railings, brackets, gates & similar works.

Providing and fixing stainless steel railing in


20 Rm 7.90 1500 11,850.00
stair case etc complete in all respect.

Sub-Total 366,630.60

Providing and fixing 18mm thick gang saw cut


mirror polished (premoulded and prepolished)
machine cut for kitchen platforms, vanity
counters ,window sills , facias and similar
locations of required size of approved shade,
colour and texture laid over 20mm thick base
21        
cement mortar 1:4 (1 cement : 4 coarse
sand) with joints treated with white cement,
mixed with matching pigment, epoxy touch
ups, including rubbing, curing moulding and
polishing to edge to give high gloss finish etc.
complete at all levels.

  Granite work.        

  Area of slab over 0.50sqm sqm 9.45 2600 24,570.00

Extra for providing edge moulding to 18mm


thick marble stone counters, Vanities etc.
22 including machine polishing to edge to give        
high gloss finish etc. complete as per design
approved by Engineer-in-Charge.
  Granite work. Rm 19.35 180 3,483.00

Extra for providing opening of required size &


shape for wash basins/ kitchen sink in kitchen
platform, vanity counters and similar location
23 in marble/Granite/stone work including each 3 250 750.00
necessary holes for pillar taps etc. including
rubbing and polishing of cut edges etc.
complete.

Mirror polishing on marble work/Granite


24 work/stone work where ever required to give sqm 9.45 150 1,417.50
high gloss finish complete.

Marble Stone (Raj Nagar Plain) slab with


18mm thick marble flooring over 20mm thick
base laid over and jointed with white cement
25 sqm 109.55 1250 136,937.50
slurry including rubbing and polishing
complete with base of 1:4 (1 cement: 4
Coarse sand)

Kota slab flooring over 20mm average thick


base laid over and jointed with grey cement
slurry mixed with pigment to match the shade
26        
of the slab including rubbing and polishing
complete with base of cement mortar 1:4
(1cement : 4 coarse sand):

  25mm thick sqm 30.67 950 29,140.07

Kota stone slab 25mm thick in risers of steps,


skirting and dado laid on 12mm average thick
cement mortar 1:3 (1 cement : 3 coarse sand
27 sqm 6.01 940 5,651.28
) and jointed with grey cement slurry mixed
with pigment to match the shade of the slabs,
including rubbing and polishing complete.

Providing and laying Antiskid Ceramic glazed


floor tiles 300 x 300mm of 1st quality
conforming to IS: 13755 of NITCO, ORIENT,
28 SOMANY, KAJARIA laid on 20mm thick cem. sqm 55.51 827 45,906.77
Mortar 1:4 including pointing the joints with
white cement and matching pigment etc.,
complete.

Providing and laying Ceramic glazed wall tiles


300 x 300mm of 1st quality conforming to IS:
13755 of NITCO, ORIENT, SOMANY, KAJARIA
29 sqm 85.07 850 72,309.50
laid on 20mm thick cem. Mortar 1:4 including
pointing the joints with white cement and
matching pigment etc., complete.

Sub-Total 320165.62

12mm thick cement plaster of mix 1:5 (1


30 sqm 821.72 140 115,040.80
cement: 5 Coarse sand) on walls.

6mm thick cement plaster of mix 1:4 (1


31 sqm 171.99 160 27,518.40
cement: 4 Coarse sand) on ceiling.
OBD on ceiling in 3 coats to give an even
32 sqm 171.99 130 22,358.70
shade complete works.

Painting on walls in 3 coats to give an even


33 shade complete works including base coats sqm 410.86 180 73,954.80
and wall putty etc.

Finishing walls with textured exterior paint of


34        
required shade:

New work ( two or more coats applied


@3.28ltr/10sqm) over and including base
  sqm 287.61 209 60,110.49
coat of water proofing cement paint applied
@ 2.20kg/10 sqm.

Finishing walls with Premium Acrylic Smooth


35 exterior paint with Silicone additives of        
required shadeof required shade

New work (Two or more coat applied @ 1.43


ltr/10 sqm over and including base coat of
  sqm 123.26 143 17,626.18
water proofing cement paint applied @ 2.20
kg/10 sqm)

Painting/ Polishing over doors/ windows/


36 ventilators including priming coat/ rubbing sqm 75.84 114 8,645.76
etc. complete job.

Sub-Total 325255.13

Providing gola 75x75 mm in cement concrete


1:2:4 (1 cement: 2 coarse sand : 4 stone
37 aggregate 10mm and down gauge) including        
finishing with cement mortar 1:3 (1 cement:
3 fine sand) as per standard design :

  In 75x75mm deep chase Rm 54.37 84 4,567.08

Making khurras 45x45 cm with average


minimum thickness of 5 cm cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate of 20 mm nominal size) over
38 P.V.C. sheet 1mx 1mx 400 micron, finished each 4.00 270 1,080.00
with 12mm cement plaster 1:3 (1 cement : 3
coarse sand) and a coat of neat cement
rounding the edge and making and finishing
the outlet complete.

Providing and laying integral cement based


water proofing treatment including
39 preparation of surface as required for        
treatment of roofs, balconies, terraces etc
consisting of following operations:

  Applying a slurry coat of neat cement using        


2.75 kg/sqm. of cement admixed with water
proofing compound conforming to IS. 2645
and approved by Engineer-in-charge over the
RCC slab including adjoining walls upto
300mm height including cleaning the surface
before treatment.

Laying brick bats with mortar using broken


bricks/brick bats 25 mm to 115mm size with
50% of cement mortar 1:5 (1 cement : 5
coarse sand) admixed with water proofing
compound conforming to IS : 2645 and
approved by Engineer-in-charge over 20 mm
  thick layer of cement mortar of mix 1:5 (1        
cement :5 coarse sand )admixed with water
proofing compound conforming to IS : 2645
and approved by Engineer-in-charge to
required slope and treating similarly the
adjoining walls upto 300 mm height including
rounding of junctions of walls and slabs

The whole terrace so finished shall be flooded


with water for a minimum period of two
weeks for curing and for final test. All above
         
operations to be done in order and as
directed and specified by the Engineer-in-
Charge :

With average thickness of 120mm and


  sqm 84.61 670 56,688.70
minimum thickness at khurra as 65 mm.

Sub-Total 62335.78

40 Extrenal Development sqm 32.75 1600 52,400.00

41 Boundary Wall Rm 43.8 3250 142,350.00

42 Entrance gate No 1 30000 30,000.00

Sub-Total 224,750.00

43 Total Cost of Civil Works       3,085,577.81

Add. For water supply, sewerage,


44 drainage and sanitation @ 12.5% of       385697.23
civil works

Add. For electrification @ 12% of civil


45       385697.23
works

Add. For contingencies @ 3% of civil


46       385697.23
works for miscellaneous works

47 GRAND TOTAL       4242669.5

  GRAND TOTAL ( In lacs)       42.43

Note:
Above quantities and rates maybe vary +/- 5% to 10% as per site condition.
-