Module 05 Blast and Drill - Presentation Part 1 2
Module 05 Blast and Drill - Presentation Part 1 2
Drilling Charging/loading
Alignment Blasting
Rockbolting Ventilation
Scaling Mucking/hauling
Sequence of tunnelling
Time one round 415 Approx 7 hours per round, pull appr 1.4 -1.45 m
Weekly 2 shifts x 8 hrs/day 12 shifts x 1.4 17 m/week
progress: 12 shifts per week m/shift
* Drill time was 3-4 min for 1.5 m length. Drilling time varies a lot, depending on rock mass
Module 05 Drill and Blast Tunnels 3
Cycle times of a full round – some examples
Activity Time Specifics Tunnel 6.5 x 6.5 m D shape
(min) Mechanized operation
Drilling 60 100 holes per round, 2 boom drillrig, 3 m long holes
Charge/Load 30 Approx 3.5 kg/m3, hard rock
Blasting 10
Ventilation 30 Single fan
Scaling 30 Semi manual
Mucking 60 Mechanical
Rockbolting 60 boomer
Shotcreting 60 Wet shotcrete w steelfibres
Misc rigging etc 60
Time one round 400 Approx 7 hours per round, pull appr 2.7 – 2.8 m
Weekly 2 shifts x 7 hrs/day 12 shifts x 2.7 32 m/week
progress: 12 shifts per week m/shift
Smooth blasting
is often used in
underground
caverns.
Specially to the
roof of the
cavern.