Project Cost Reduction and Value Engineering PDF
Project Cost Reduction and Value Engineering PDF
and
Value Engineering
Project Updating
and
Resource Allocation
1-2 1
Overview
Understand how the process of estimating and pricing, from concept
through detailed estimating to change orders.
Understand how cost reporting can improve the overall success of a
project.
Know and apply important project cost management principles.
Know and apply basic management ideas, principles, and skills that
will enable you to immediately manage the crew on your construction
project more effectively.
Proactively manage project costs.
Proactively manage various risks/potential delays that could impact
your project.
1-3
2
Session List
1-4
3
Learning Objectives
Identify how contractors obtain work and the process that leads up to
the physical construction process.
Recognize the role of the contractor’s staff and the designers in the
pre-construction phases of the project.
Indicate how a project is obtained and how that process relates to the
construction of the project.
1-54
A New Project
1-65
The Construction Process
1-76
The Pre-Design Phase
1-87
The Design Phase
Schematic design
Floor plans, elevations, site plans.
Design development
Progression of design; includes structural, electrical, and
mechanical, modeling of components, including clash
detection.
Construction documents
Completion of details, production of drawings, and
specifications.
1-98
The Bid
1-10
9
Examine Documents
1-11
10
Estimating Process
1-12
11
Estimating Process
SPECIFIC ISSUES FOR CONSIDERATION:
Bidding time
Surety bond requirements
Consistent with company business plans
Personnel required
Cost of bidding
Other projects being bid
Equipment
Supervision
Support staff
Finances
Adequacy of company resources
1-13
12
Estimating Process
SPECIFIC ISSUES FOR CONSIDERATION (continued):
Competition
Experience with parties to the contact
Design considerations in the contract
Conditions in the contract
Quality of documents
Labor supply
Licensing
Community Relations
Availability of suppliers and subcontractors
Time
Availability of funds
Special requirements
1-14
13
The Rest of the Process
1-15
14
Project Delivery Methods
1-16
15
Construction Contract Types
1-17
16
The Project
1-18
17
Session 1 Review
Pre-Construction Phases
Pre-design
Design
Bid/award
The Estimating Process
Project Delivery and Contract Types
The Project
1-19
18
Apply What You Have Learned
1-20
19
Looking Forward to Session 2
Learn about the estimate that was required for your firm to win
the job you are currently on.
Bring an engineer’s scale and an architect’s scale to the next
session.
1-21
20
What is Value Engineering?
Value engineering is a systematic method to improve the “value” of a product or
service that the project produces. It is an integral component of project quality.
Value is defined as containing two components, function and cost:
Value = Function / Cost
Function: a measure of the the performance capabilities of the product, service, or
project. A function might be to “achieve traffic flow across the river.” In practice
value engineers look at many different functions that the bridge serves, like
accommodating floods, passengers, bicycles, endangered turtles, emergency
vehicles, the sun on the horizon, and anything else that serves in a functionary
capacity.
Cost: The resources required to achieve the function. This can include materials,
tools, price, time, or anything that is required to achieve the functional
specifications.
Clearly, project value is increased when the function is increased, the cost is
decreased, or both. Alternatively, the function and cost could both be increased or
decreased, as long as the cost becomes proportionately less to the function, the
value will increase. 21
Value Engineering
Value Engineering (VE) is not a design/peer review or a
cost-cutting exercise. VE is a creative, organized effort, which
analyzes the requirements of a project for the purpose of
achieving the essential functions at the lowest total costs
(capital, staffing, energy, maintenance) over the life of the project.
Through a group investigation, using experienced,
multi-disciplinary teams, value and economy are improved
through the study of alternate design concepts, materials, and
methods without compromising the functional and value
objectives of the client.
A "second look" at the design produced by the architect and The VE Job Plan follows five key steps:
engineers gives the assurance that all reasonable alternatives 1. Information Phase
have been explored. 2. Speculation (Creative) Phase
Cost estimates and scope statements are checked thoroughly 3. Evaluation (Analysis) Phase
assuring that nothing has been omitted or underestimated. 4. Development Phase (Value Management
Proposals)
Assures that the best value will be obtained over the life of the
5. Presentation Phase (Report/Oral
building
Presentation)
22
Session 2
23
Learning Objectives
2-2
24
The Conceptual Estimate
2-3
25
A Simple Conceptual Estimate
Item Type Area SF Cost Total Cost
$7,239,500
Figure 2.1
2-4
26
Conceptual Estimate Summary Sheet
for the Project
Item Description Area Unit Unit Price Cost
Site Development Entire Site 3,525,000 SF $ .20 $ 705,000
Bridges 2 Each 7,200 SF $ 100.00 $720,000
Site Utilities Entire Site 3,525,000 SF $ .20 $705,000
Truck Access Paving 624,483 SF $ 2.72 $1,698,594
Parking Lots +90,000 SF 141,750 SF $ 2.09 $ 296,258
Landscaping 75,474 SY $ .81 $ 61,134
Gatehouse 1 200 SF $ 150.00 $ 30,000
Gatehouse 2 200 SF $ 150.00 $ 30,000
Building A Receiving Building 35,000 SF $ 33.51 $1,172,850
Building B Warehouse 250,000 SF $ 33.51 $8,377,500
Building C Warehouse 250,000 SF $ 33.51 $8,377,500
Building D Warehouse 250,000 SF $ 33.51 $8,377,500
Office Building 25,000 SF $ 103.43 $2,585,750
Total Cost $ 33,137,086
20% Contingency $6,627,417
Total Budget $ 39,764,503
2-5
27
Creating the Project Budget
28
2-6
Phase I Budget
Figure 2.3
2-7
29
Phase II Budget
2-8
30
Phase III Budget
2-9
31
The Detailed Estimate
2-10
32
The Detailed Estimate
The Detailed Estimate Includes:
1. A break down of the work by categories of similar items or as required by
the bid form.
2. Quantification of similar elements of work for each category for costing.
3. Determination of a construction plan.
4. Determination of a construction schedule.
5. An estimate of cost of labor, material, equipment, subcontractors and
service providers for each element of each item of work.
6. The direct and indirect cost of the work which includes all the cost
elements.
7. Solicitation and receipt of quotes for materials, services by others and work
to be subcontracted.
8. A summary of all elements of costs (labor, material, equipment,
subcontractors and service providers) to determine the total estimated cost
of work.
9. Analysis of risk the project should bear.
10. Determination of a markup to be added to the cost of work to produce a
2-11
33
selling or bid price.
Commonly Used Conversion Factors
Figure 2.4
34
2-12
Relationship of Estimating, Accounting,
and Productivity
Figure 2.5
35
2-13
Concrete Quantity Take-Off
36
2-14
Concrete Quantity Take-Off
Project Concrete Recap Labo Materia
Sheet r l
Man- Unit
Cost Ite Quantity Uni Unit/h hours Cost/h Total Cos Total Total
code m t r r Labor t Mat. Cost
03 03 Grade
03 03 Beams
Form Beam 30,00 SFC 1 300 $ 45.0 $ 135,00 $ 0.3 $ 10,50 $ 145,50
03.01
03 03 Sides
Reinforcing 0 23. A
Ton 0.0370 0 63 0
$ 50.0 $ 0 31,60 5
$ 500.0 $ 0
11,850 $ 0 43,45
03.02
03 03 Steel
Place 761 C 5 3 2
20 0
$ 42.0 $ 0 8,55 $ 0 52.0 $ 31,77 0
$ 40,32
03.03
03 03 Concrete
Chamfer 1
250 Y
L 20 41 0
$ 45.0 $ 4 56 $ 0 0.1 $ 2 25 $ 6 81
03.04
03 03 Strips
Float 0
250 F
S 0
30 38 0
$ 42.0 $ 3
35 $ 0- $ 0- $ 3
35
03.05
03 03 Top
Embed 0
125 F
E 0 3 41 0
$ 50.0 $ 0
20,83 $ 17.0 $ 21,25 0
$ 42,08
03.06 sTotal Grade Beams 0 a 7
427 0 $ 3
196,90 0 $ 0
75,62 3
$ 272,52
03 03 Slab-on-Grad 3 0 2 2
04
03 03 e
Fine 25000 S 40 62 $ 42.0 $ 26,25 $ - $ - $ 26,25
04.01
03 03 Grade
Slab 0 336 F
C 0 5 5
67 $042.0 $ 0
28,23 $ 10.5 $ 35,29 $ 0
63,52
04.02
03 03 Gravel
Vapor Barrier 1
28250 Y
S 100 2
28 $042.0 $ 2
11,865 $ 0 0.0 $ 1 5,65 $ 3
17,51
04.03
03 03 Reinforcing 0 183. F
Ton 00.0 3
367 $050.0 $ 183,70 2
$ 500.0 0
$ 91,85 $ 5
275,55
04.04
03 03 Steel
Edge 7250 L 5 2 4 12 $045.0 $ 0 5,62 $ 0 1.0 $ 0 2,50 $ 0 8,12
04.05
03 03 Form
Screed 0
500 F
L 0
4 5
12 $045.0 $ 5
5,62 $ 0
0.3 $ 0
1,50 $ 5
7,12
04.06
03 03 sExpansion 0
900 F
L 0
4 5
22 $045.0 $ 5
10,12 $ 0
0.3 $ 0
2,88 $ 5
13,00
04.07
03 03 Joint
Place 0
486 F
C 0 2 243 5 0
$ 42.0 $ 5
102,08 2
$ 52.0 0
$ 252,77 $ 5
354,85
04.08
03 03 Concrete
Finis 1
250,00 Y
S 12 1
208 0
$ 42.0 $ 1 87,50 $ 0 - $2 - $ 3 87,50
04.09
03 03 h
Cur 0
250,00 F
S 0
100 3 25 0
$ 42.0 $ 0
10,50 $ 0.0 $ 15,00 $ 0
25,50
04.10
03 03 e
Box-Out 0 10 F
S 0 6. 01 0
$ 45.0 $ 0 74 $ 6
2.5 $ 0 27 $ 0 1,01
04.11 Columns
Total Slab-on-Grade 8 F 5 10507 0 $ 472,258 0 $ 407,710 $ 8
879,96
9 1 3 4
37
2-15
Selecting Subcontract Bids
38
2-16
Combination Bid Analysis
Figure 2.6
2-17
39
Subcontractor Selection
Section Description Bidder Price
31 64 00 Piles/Caissons Northwest Caisson $1,220,990
32 12 16 Asphalt Paving Statewide Paving $1,730,000
32 90 00 Landscaping Mulchers, $ 42,000
LGL Sprinkler $ 35,000
03 45 00 P/C Deck Panels PC Precast $ 85,000
05 10 00 Structural Steel Steel Struct, Inc. $ 175,000
05 20 00 Metal Joists Steel Struct, Inc.
05 30 00 Metal Deck Steel Struct, Inc.
06 40 00 Arch. Woodwork Chris’s Cabinets $ 7,200
07 20 00 Insulation Quick Insulation $ 35,000
07 50 00 Membrane Roofing Local Roofing $ 89,916
07 60 00 Flashing Local Roofing
08 31 00 Overhead Doors Door & Window Co. $ 18,000
08 80 00 Glazing/Windows Door & Window Co.
09 25 00 Gypsum Drywall Universal Finishes $ 7,300
09 65 00 Floor Covering Universal Finishes
09 90 00 Painting Universal Finishes
23 00 00 Mechanical Charlie’s Plumbing $ 249,000
26 00 00 Electrical Ellen’s Electrical $ 309,000
Total Subcontracts $4,003,406
40
2-18
Session 2 Review
41
2-19
Session 2 Review
(Continued)
2-20
42
Apply What You Have Learned
43
2-21
Looking Forward to
Session 3
Become familiar with the type of cost control system your firm uses.
Evaluate the cost reporting and control system on your project
44
2-22
Session 3
45
Learning Objectives
3-2
46
From Estimate to Construction
3-3
47
Cost Control
3-4
48
Typical Mistakes in Estimates
3-5
49
Responsibility for Cost Control
Estimator
Responsible for the quality of estimate.
Project manager
Responsible for the overall project and primary manager
of the project costs.
Superintendent
Responsible for crew productivity and for reporting the
actual amount of work performed by the crews under his
or her direction.
Roles:
Project Manager
Estimator
Superintendent
Discuss, maintaining your roles, in groups.
What resolution did your group reach?
Worksheet 3-1
3-7
51
Potential Financial Risks
Material
Relatively small risk.
Labor
Largest potential risk.
Equipment
Tied to productivity estimates for labor.
Subcontracts
Could substantially affect total project costs, especially general
conditions and labor productivity.
Jobsite Overhead (General Condition) Costs
Extended project schedule will increase these costs.
3-8
52
Identifying Cost Risks from
the Construction Documents
3-9
53
Identifying Cost “Trouble Spots”
on the Project
Worksheet 3-2
3-10
54
Session 3 Review
3-11
55
Session 3 Review
(Continued)
3-12
56
Apply What You Have Learned
3-13
57
Looking Forward to Session 4
3-14
58
Session 4
59
Learning Objectives
4-2
60
The Importance of Cost Control
4-3
61
The Contractor’s Accounting System
Figure 4.1
4-4
62
Generating Cost Data
Labor Hours
Labor is coded to specific activities.
Cost codes may be organized using MasterFormat 2004
numbers, or developed from a Work Breakdown Structure.
Example:
A labor cost will come from time cards. Cards will be coded to
specific cost items.
03 30 02 is cast-in-place concrete.
4-5
63
Daily Time Sheet for Cast-in-Place
Concrete Work
Figure 4.2
4-6
64
Reporting Process
for Labor Hours
Figure 4.5
4-7
65
Reporting Process for Material Purchases
Figure 4.5
4-8
66
Reporting Process for
Company-Owned Equipment
Figure 4.6
4-9
67
Analysis of Cost Data
4-10
68
Analysis of Cost Data
Worksheet 4-1
4-11
69
Analysis of Cost Data
(Continued)
Tim and Tom want to take a day off and go holiday. To accomplish
this they must:
Complete all work in nine days or less instead of ten.
Cover their wages for the last day $832 + $250 in estimated
expenses.
Use the cost data from Week 1 to forecast their final costs and
determine whether they can go holiday.
4-12
70
Tim and Tom’s
Week 1 Cost Analysis
Hours 16 16 16 16 16 80
4-13
71
Information from Cost Data
4-14
72
Typical Analysis Information
from Cost Data
Quantity of work remaining
Current percentage of work completed
Current cost variance
Forecasted unit cost
Projected cost of remaining work
Projected variance
Percent variance
4-15
73
Analysis of Tim and Tom’s Cost Data
Week 1 (Continued)
Projected cost remaining
Quantity remaining x Forecasted unit cost
4,727 x $0.70 = $3,308.90
Projected variance
Estimated cost – (Current cost + Projected cost remaining)
$8,320 – ($4,160 + $3,308.90) = $851.10
Percent variance
Projected variance/Estimated cost
$851.10/$8,320 = 10.2%
4-16
74
Should Tim and Tom Go Fishing?
4-17
75
Tim and Tom’s
Week 2 Cost Analysis
Hours 16 16 16 11 59 139
4-18
76
Analysis of Cost Data
4-19
77
Converting Estimate Items
to Cost Control Items
Cost control items need to be easily identifiable and unique.
The work activity must be unique for reporting and historical cost
data.
A cost control item shouldn’t be too small (in cost, quantity, or
time).
A cost control item should align with the firm’s historical cost
control database whenever possible.
4-20
78
Converting Estimate Items
to Cost Control, Gatehouses
Item Unit Labor Per Labor Quantity Unit Price Material Total Cost
hours Hour Cost Cost
Footings 5.4 12 $30.36 $364.32 132 SFCA $0.40 $375.47 $739.79
4-21
79
Converting Project Estimate Items
to Cost Control, Bridge 1
Item Unit Man-ho Per Hour Labor Quantity Unit Material Total Cost
urs Cost Price Cost
Abutment 40 crew $150.34/ $6,013.60 2107 SFCA .50 $1,053.50 $7,067.
Forms hours crew hour
Abutment 5.3 Ton $4,240.00 5.3 Ton $600 $3,180.00 $7,420.
Rebar
Pour 136 CY 8 crew $169.02/ $1,352.16 136 CY $60 $8,160.00 $9,513.
Abutment hours crew hour
Total $24,000.
4-22
80
Session 4 Review
4-23
81
Session 4 Review
(Continued)
4-24
82
Apply What You Have Learned
4-25
83
Looking Forward to Session 5
4-26
84
Session 5
85
Learning Objectives
5-2
86
Cost Management Plan
5-3
87
Cost Management Plan
(Continued)
5-4
88
Identifying Cost Activities
and Cost Control Numbers
Description of the activity, from start to finish.
Quantity of the activity.
Crew for the activity.
Hours necessary to complete the activity:
Composite crew cost per hour
Average hourly cost per hour
Cost of each craft per hour
5-5
89
The Responsibility for Daily
Coding and Reporting Cost Data
5-6
90
Method for Organizing
Material Purchases
Identify:
The specific materials used in the work
activity.
The material costs for the work activity.
The vendor and purchase order.
The order and delivery dates.
5-7
91
Sample Bill of Materials
Figure 5.1
5-8
92
Crew Assignment Information
Cost code number.
Description of activity.
Quantity of work involved.
Crew composition.
Time allowed for the activity.
Cost of labor for the activity.
Material required for the activity.
5-9
93
Crew Assignment Information
(Continued)
5-10
94
Bill of Materials for Grade Beam
Bill of Materials
Cost Code: 03 03 02 11
Item Quantity Unit Price Total
BB Form-Ply 10,800 MSF $929 $10,033.00
2x4 21.222 MBF $407 $8,637.35
Ties 27 C $75 $2,025.00
Rebar 8.72 Tons $540 $4,708.80
Concrete 220 CY $56.45 $12,419.00
5-11
95
Bill of Materials for Bridge 1
Bill of Materials
Cost Code: 03 03 02 11
Item Quantity Unit Price Total
3/4” Form-Ply 2.11 MSF $929 $1,960.19
4x4 12.4 MBF $858 $10,639.20
Ties 1,050 Ea $4.62 $4,851.00
Rebar 5.3 Tons $540 $2,862.00
Concrete 136 CY $60.93 $8,286.48
Note: 2 abutments (2 x above)
5-12
96
Crew Assignment for Grade Beam
Work
STP Construction Co.
Work Assignment • Sure Fresh Project • STP Project 01-10
Cost Code: 03 03 02 11
Project Area: Building A Grade Beam
Work Description: Form grade beam at Building A Drawing of Details and Work Area:
Document Reference: Foundation plan, sheet 3; Sections, sheet 6
Quantity of Work: 10.800 SFCA formwork
Crew and Rates: 3 carpenters at $52.00 + 1 laborer at $48.00/Hour
Crew Rate: $204/Hour $1,632/Day
Daily Production: 50 LF/day
Time Allowed: 18 days
Labor Cost: $29,376.00
Material: 10,800 MSF B-B OES; 21.22 MBF 2x4 studs/walers;
2,700 snap ties; 5,400 wedges
Material Location: To be delivered to Building A
Equipment/Equipment Cost: Forklift at $100/day
Tools: 4 skill saws; cut-off saw; 2 drills; form oil sprayer
5-13
97
Crew Assignment for Bridge 1
STP Construction Co.
Work Assignment • Project • STP Project 01-10
Cost Code: 03 03 02 11
Project Area: Bridge 1
Work Description: Form abutment, Bridge 1 Drawing of Details and Work Area:
Document Reference: Sheet 8
Quantity of Work: 4,220 SFCA formwork
Crew and Rates: 3 carpenters at $52.00 + 1 laborer at $48.00 +
1 equipment operator at $56.00
Crew Rate: $260/Hour $2,080/Day
Daily Production: 422 SFCA/day
Time Allowed: 10 days
Labor Cost: 20,800.00
Material: 2.11 MSF 3/4” B-B OES; 12.4 MBF 4x4; 1,050
rods/catheads (rental) at each abutment
Material Location: To be delivered close to each abutment
Equipment/Equipment Cost: 30-ton crane
Tools: 4 skill saws; cut-off saw; 2 drills; form oil sprayer
5-14
98
Day-by-Day Projection of Budgeted
Costs
29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec
Budgeted
Daily Labor $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544
Cost
Accumulated
$1,544 $3,088 $4,632 $6,176 $7,720 $9,264 $10,808 $12,352 $13,896 $15,440
Labor Cost
Estimated
200 200 200 200 200 200 200 200 200 200
Daily Quantity
Estimated
Accumulated 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000
Quantity
Budgeted
Cost/LF $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Today
Budgeted
Cost/LF $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Accumulated
Figure 5.3
5-15
99
4-Day Comparison of Actual Costs with Budgeted Costs
29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec
Budgeted
Daily Labor $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544 $1,544
Cost
Actual Daily
Labor Cost $1,544 $1,544 $1,544 $2,448
Budgeted
Accumulated $1,544 $3,088 $4,632 $6,176 $7,720 $9,264 $10,808 $12,352 $13,896 $15,440
Labor Cost
Actual
Accumulated $1,544 $3,088 $4,632 $7,080
Labor Cost
Estimated
Daily Quantity 200 200 200 200 200 200 200 200 200 200
Actual Daily
Quantity 160 200 155 230
Estimated
Accumulated 200 400 600 800 1,000 1,200 1,400 1,600 1,800 2,000
Quantity
Actual
Accumulated 160 360 515 745
Quantity
Budgeted
Cost/LF Today $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Actual Cost/LF
Today $9.65 $7.72 $9.96 $10.64
Budgeted
Cost/LF
Accumulated $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72 $7.72
Actual Cost/
LF
Accumulated $9.65 $8.58 $8.99 $9.50
Figure 5.4
5-16
100
4-Day Comparison of Labor Cost
Variances
29-Nov 30-Nov 1-Dec 2-Dec
Quantity to
1,840 1,640 1,485 1,255
Complete
Projected Cost at
Accumulated $19,300.00 $17,160.00 $17,980.00 $10,000
Rate
Variance from
$(3,860.00) $(1,720.00) $(2,540.00) $(3,560.00)
Budget
Figure 5.5
5-17
101
Comparison of Actual Costs with
Budgeted Costs, Lowered Productivity
Figure 5.6
5-18
102
Resource allocation
103
Updating a Project
A network designed during planning may not adhere to the schedule
when put to work, because situations are sometimes keep on changing
and during actual execution they are different than that assumed at the
stage of planning.
Following are few reasons for not following the designed schedule
exactly:
(i) Error in estimation during planning. Planner’s under or over
estimation is mainly responsible for not adhering to the schedule.
(ii) Unforeseen circumstances, like delay in availability of resources as
planned, break down in plant and machinery.
(iii) National calamity etc.
Updating helps in evaluating the present status of the project and assess
the probability of completing the project in due time. Updating enables
to take corrective actions in time and take managerial decisions in
problem areas. The updating must regularly be done.
104
Method for Obtaining
Supervisor Feedback
A superintendent will need to know why a problem
happened to solve it.
Supervisors need encouragement to supply
information.
You need to have a system that will offer reliable
information.
If not verbal, then develop a written report for
supervisors.
5-19
105
Determining the Impact
of Subcontractor Actions
Your planning should include:
Dates subcontractors must be on the project.
List of subcontractor activities.
Creating awareness among supervisors regarding
subcontractor involvement.
A reporting method for problems.
A predetermined channel of communication.
5-20
106
Session 5 Review
5-21
107
Session 5 Review
(Continued)
5-22
108
Apply What You Have Learned
5-23
109
Looking Forward to Session 6
Discuss the control of labor costs.
Familiarize yourself with the ways that
your firm encourages crew productivity,
efficiency and cost savings.
Discuss the change order process.
5-24
110
Session 6
111
Learning Objectives
6-2
112
Implementing Cost Control
6-3
113
Implementing Cost Control
(Continued)
6-4
114
Cost Control Summary
Figure 6.1
6-5
115
Accounting for the “Learning
Curve”
Production on the activity starts out slow and then picks up
pace.
Allocate production to take this into account.
Expect higher productivity later in project.
6-6
116
Review Questions for
Supervisors
Were the instructions/layout adequate?
Were the details adequate?
Was there amount of work as expected?
Were the shop drawings accurate/adequate?
Was there enough material?
Was the material in good condition?
Was the material in a convenient location?
6-7
117
Review Questions for Supervisors
(Continued)
6-8
118
Review Questions for Supervisors
(Continued)
6-9
119
Management Responsibilities
6-10
120
Compensation from Owner
Must have agreement.
Areas where it might occur:
Errors and omissions in construction documents.
Discovery of unknown or latent conditions.
Direction to complete additional work.
Requirement to complete additional work to
accommodate a specified product.
6-11
121
A Role Play in Problem Analysis
6-12
122
Cost Control for
Change Orders
To develop a cost control account for a change
order:
Develop a detailed description of the work.
Develop an estimate for each work area.
Determine a method for isolating and verifying each
cost.
Record the change order costs.
Compare the change order estimate with actual costs.
6-13
123
Change Order Estimate for
Electrical Work
in Project Gatehouses
Section Item Labor Material Subcontract Total
32 90 00 Fencing $ 600.00 $ 600.00
06 41 00 Cabinets $ 408.00 $1,000.00 $1,408.00
26 00 00 Electrical $9,500.00
26 30 00 Underground Conduit $3,000.00
26 05 23 Wiring $2,500.00
27 51 00 Itercom $2,000.00
25 13 16 Control Panels $2,000.00
Total Cost $11,508.00
15% Profit and Overhead $ 1,726.20
Change Proposal Estimate $13,234.20
Figure 6.12
6-14
124
Organizing Change Order Cost
Information
Worksheet 6-2
6-15
125
Dock Seals Work Assignment
STP Construction Co.
Work Assignment • Project
SCC Project 01-10 Date: ___________________________
Cost Code: 11 16 01, 11 16 03 Project Area: Building A
Work Description 11 16 01: (Change Order 2): Install dock seals at the 5 overhead doors, Building A. 11 16 03:
Install dock bumpers at the 5 overhead doors, Building A. Note: Separate cost for dock seal
from door bumper. Dock seals are Change Order 2.
Document Reference Sheets 3, 5, and 6. Section 11 16 00, loading dock equipment. Shop drawings and submittals
from Ted’s Loading Dock Supply Company.
Quantity of Work 11 16 01: 5 Dock Seals
11 16 03: 5 Dock Bumpers
Crew and Rates 1 Carpenter @ $52.00/hour
1 Laborer @ $48.00/hour
Crew Rate $100.00/Hour $800/Day
Daily Production 1 dock seal; or dock bumper and a portion of the dock seal
Time Allowed 11 16 01: Dock Seal: 8 hours
11 16 03: Dock Bumper: 2 hours
Labor Cost (11 16 01) Dock Seal: $800.00 x 5 = $4,000.00
(11 16 03) Dock Bumper: $200.00 x 5 = $1,000.00
Material Door Seals, Dock Bumpers (Ted’s Loading Dock Supply)
Miscellaneous screws and anchor bolts
Material Location In Building A
Equipment/ Rolling Scaffold, No charge
Equipment Cost
Tools Drill # 106, Rolling Dolly
Form 6.1
6-16
126
Dock Seals Change Order
Worksheet 6-2
6-17
127
Subcontractor Back
Charges
You might want to back charge subcontractors for:
Work in their contract that was accomplished by your
crew or by use of your equipment.
Work in their contract that was accomplished by
another subcontractor.
The cost of causing delays for other crews (this might be
difficult).
Rework charges.
6-18
128
Subcontractor Back
Charges
(Continued)
Practices to observe:
Be sure the contractor-subcontractor agreement has a
clause allowing back charges.
Get agreement from the subcontractor’s supervisor on
charges.
Keep track of exact charges.
Present a detailed record of the back charge.
6-19
129
Session 6 Review
6-20
130
Apply What You Have Learned
Examine the challenges and cost overruns on your
job:
Is there a pattern to the causes?
Look carefully at your scope of work and potential
change orders.
Is there a comparison made between estimated and actual
costs?
Was there work performed outside of your scope of work?
Were change orders requested for this additional work?
What will you do differently on the next project?
Where did you make money on this project?
Where did you lose money on this project?
Why did you make money on this job?
6-21
131
Looking Forward to Session 7
6-22
132
Session 7
133
Learning Objectives
7-2
134
7-3
135
Categories of Factors That
Negatively Impact
Productivity (negative impact factors)
Worker ability to do work.
Work sequencing (continuity of the work process).
Environmental factors.
Disruption of the work process.
Added support activities.
Human element.
7-4
136
Loss of Labor Productivity
(Impact) Due to Changes and
External Events
Examples of construction changes include the
following:
Schedule changed and work shifted into colder temperatures.
Contractor required to work overtime due to owner or designer delays.
Contractor required to add workers to project to accelerate schedule.
Contractor required to do work in an unexpectedly crowded or tight
working area.
Contractor required to store materials farther from project than
planned, due to unavailability of lay-down areas.
Contractor required to start-stop, start-stop work process because
design documents or design decisions are unavailable.
7-5
137
Loss of Labor Productivity
Construction labor productivity is a complex process and
the productivity or units of output produced per
person-hour of effort or input is very sensitive to many
input factors:
• The amount and quality of labor, equipment, materials, weather,
and expected working conditions.
• The quality and completeness of the drawings and specifications.
• The expected actions of the project owner.
The contractor’s labor productivity estimate is predicated
upon a reasonable estimate of each of these factors. This is
illustrated in the next slide.
7-6
138
Unexpected Events That
Negatively Impact Site Labor
Productivity
(outside of the Construction Supervisor’s control)
7-7
139
Unexpected Events That
Result in Work Performed
Under Adverse Conditions
Overtime
Learning curve
Temperature, wind, humidity
Start-stop-start-stop
Double handling of material
Morale problems
7-8
140
Impact of Overtime on
Productivity
Overtime needed to accelerate the work
process.
Construction is hard, physically-demanding
work. When required to work overtime, the
onsite craft worker is likely to become fatigued
and do less than the normal hourly output.
Studies conducted by the Business Roundtable,
the National Electrical Contractors Association
(NECA) and various contractor associations and
contractor groups illustrate the loss of
productivity, as shown in the next slide.
7-9
141
Impact of Overtime on
Productivity
7-10
142
Impact of Crew Size on
Productivity
Ideal Crew Size
There normally is an ideal crew size and mix for every work task.
The construction firm and supervisor should collect data from past
performances of work tasks to estimate productivity lost when crew size is
changed.
Dilution of Supervision
Supervision is a critical component of worker productivity.
Studies have indicated a 15% to 20% possible decrease in worker
productivity if needed supervision is absent.
When workers or crews are added to the supervisor’s workload, the
supervisor’s inability to be in three places at one time will result in lower
worker productivity.
7-11
143
Impact of “Learning” on
Productivity
7-12
144
Impact of Work Space on
Productivity
Stacking – Available Work Space
To make up time crew sizes may be increased.
To make up time crews may be brought in before previous
work finished.
Extra workers or crews in a space reduces productivity.
7-13
145
Impact of Work Space on
Productivity
7-14
146
Impact of “Learning” on
Productivity
Learning Curve of Workers
7-15
147
Impact of Environmental Factors
on Productivity
Adverse temperature (hot and/or cold).
Humidity.
Wind.
Precipitation.
Noise.
Poor lighting.
Significant variation from the expected would require the supervisor
to attempt to quantify the impact on worker productivity and adjust
accordingly.
7-16
148
Impact of Temperature
on Productivity
7-17
149
Session 7 Review
Look back over Session 7 and review these key points to be sure you
understand them.
There are six different categories of factors that negatively impact labor
productivity.
There is a loss of productivity when a worker is subjected to conditions
that were not expected.
There has been a considerable amount of research conducted on
measuring lost productivity as a function of various impact factors.
Change orders can negatively impact overall project productivity.
7-18
150
Apply what you have Learned
Learn how your firm uses data on the learning curve for new work
processes.
Determine how your firm gathers and uses data on work process
disruption.
Determine how your firm gathers and uses data on environmental
effects.
Determine how your firm gathers and uses data on human element
productivity impacts.
Learn what data your firm uses when workers or crews must be added
to the work space.
7-19
151
Session 8
152
Learning Objectives
8-2
153
Ten-Step Equipment Productivity
Improvement Program
1. View equipment as money, not 6. Be attentive to scheduling work
just as equipment or metal. tasks around equipment
2. Plan the logistics of equipment. availability.
3. When determining the best 7. Be attentive to proper equipment
method to do a work task, maintenance.
evaluate the benefits of using 8. Always be attentive to working safe
equipment versus labor. with equipment.
4. Be attentive to the work capacity 9. Be attentive to equipment as
of a machine. having an ownership and an
5. Be attentive to the percentage of operating cost component.
time equipment is working 10. Be prepared to model or consider
versus being idle. the interrelationship of two or
more pieces of equipment working
together.
8-3
154
Determining the Hourly Cost
of Owning Equipment
Hourly Cost=
Depreciation + Interest + Maintenance + Repair + Operating + Insurance + PT +Repl. + Prod Loss
Hours of Use
8-4
155
Modeling the Queuing
or Waiting Line Problem
Secondary work task
Queue
= Arrival units
= Service unit
8-5
156
Session 8 Review
View equipment as money, not just as machinery or metal.
Plan the logistics of equipment.
Adequately staff equipment with needed labor support.
Be attentive to the work capacity of a machine.
Be attentive to the percentage of time equipment is working versus
being idle or in a “support” state.
Be attentive to scheduling work tasks around equipment availability.
Be attentive to proper equipment maintenance.
Always be attentive to working safely with equipment.
Remember that equipment has an ownership cost component and an
operating cost component.
Be prepared to model or consider the interrelationship of two or more
pieces of equipment working together.
8-6
157
Apply what you have Learned
While on your projects, focus on a few pieces you
are using at the project and a few workers.
Using random samples of their work states, calculate
the amount of time each worker and each machine
is in a non-productive work state.
If you don’t know the equipment’s hourly cost
(ownership and operating), attempt to determine the
hourly cost of each piece of equipment by use of a
cost estimating book or the US Army Corps of
Engineers publication. 8-7
158
Session 9
159
Learning Objectives
Describe the costs and cost effects associated with project partners.
Explain how to examine scope statements and specifications to
determine project partners’ responsibilities and the scope of work on
the jobsite.
Describe how to use the construction schedule to track subcontractor
progress.
Explain methods of providing information to project partners.
Describe control of changes and cost-plus subcontractor activities.
Explain back charging to receive compensation from subcontractors.
Explain the importance of documentation in working with project
partners.
9-2
160
The Cost Impact of Project Partners
9-3
161
The Cost Impact of Project
Partners
Exclusions, non-covered work.
Additional work required by subcontractor.
Subcontractor default or bankruptcy.
9-4
162
Working with Project Partners
During the Bid Period
9-5
163
Working with Project Partners
During the Buyout Period
9-6
164
Working with Project
Partners
During the Buyout Period
(Continued)
9-7
165
Working with Subcontractors
Before They Start Work
Meetings
Notify project partners of all applicable meetings.
Set expectations for who attends.
Provide meeting minutes.
Update on progress and changes.
Advise on schedule progress.
Conduct an onsite orientation meeting.
9-8
166
Subcontractor Orientation
9-9
167
Subcontractor
Orientation
Topics for Orientation:
Jobsite access.
Storage of material.
Schedule for work.
Weather protection, if necessary.
Coordination with other work.
Safety.
Jobsite security.
Cleanup.
Communication channels.
Worksheet 9-1
9-10
168
Subcontractor
Orientation
Subcontracts to examine:
Structural steel, joist, and deck erection.
Roofing, roof insulation, and flashing.
Building electrical.
Building HVAC.
Building plumbing.
Overhead doors.
Windows/storefront.
Painting.
9-11
169
Working with Subcontractors
While They Are on the Job
As the subcontractor starts of work, the
superintendent and subcontractor’s supervisor should
discuss:
Quality of work expected.
Coordination with other work.
Your expectations for cleanup (in the contract?).
Hours of work.
Special security requirements.
Safety policies and your safety program.
Access and equipment usage.
9-12
170
Documenting Subcontractors
During the Project
9-13
171
Analyzing a
Subcontractor
Change
Proposal
Figure 9.5
9-14
172
Working with Subcontractors
Before They Leave the Jobsite
Review with the subcontractor:
Their work.
Acceptance of finishes by other subs.
Any additional cleaning of work and waste
disposal.
Any protection of work in place.
9-15
173
Working with Subcontractors
Before They Leave the Jobsite
(Continued)
9-16
174
Project Partner Management
The building envelope must be complete by
October 7 to allow the 30 working days
guaranteed for the Tenant Improvements
contract.
Read subcontractor action descriptions.
Discuss, in groups, what could have been done
to avoid the problems.
Worksheet 9-5
9-17
175
Project Partner
Management
9-18
176
Session 9 Review
9-19
177
Session 9 Review
(Continued)
9-20
178
Apply What You Have Learned
9-21
179
Looking Forward to Session 10
9-22
180
Session 10
Post-Project Evaluations
181
Learning Objectives
10-2
182
Evaluating the Project
10-3
183
Evaluating the Project (Continued)
10-4
184
Measures of Project Success
Fee recovery.
Meeting schedule.
Quality.
Safety.
Customer satisfaction.
10-5
185
Evaluation Analysis
Evaluation of cost reports should determine:
Project fee recovery.
Line item performance compared with the estimate.
Data update for historical cost data.
The identification of successful methods for
future cost reduction.
The identification of work processes to be improved.
The identification of areas that shouldn’t be
self-performed.
The evaluation of processes/techniques for
current activities.
10-6
186
Actions Following
Evaluation
Update/change historical cost data.
Company adoption of processes, techniques or
equipment for specific activities.
Determination of alternatives to those activities
failing to meet budget/expectations.
Seek or avoid projects with comparable attributes.
Make personnel decisions.
10-7
187
Possible Conclusions
from Evaluation
Effectiveness of management team.
Future training needs for jobsite personnel.
Future use of subcontractors.
Future use of suppliers and/or products.
Future pursuit of the type of work and geographical
area.
Willingness to work with designer on future projects.
Willingness to work with owner on future projects.
10-8
188
Evaluation Communication
The lessons learned from project
evaluations should be shared with:
Project supervisors.
Project team.
Other project teams.
Upper management.
10-9
189
Session 10 Review
10-10
190
Course Review
10-11
191
Thank you
10-12
192