Integrity Management of Brownfield Projects PDF
Integrity Management of Brownfield Projects PDF
Presenters
1 Asset Integrity
Integrity Management of Brownfield Projects: Challenges and Rewards
Agenda
• Introductions
• About Oceaneering
• Integrity Build : Definition and Objectives
• Brownfield RBA Overview
• Challenges of RBA Programmes
• Operational Elements and Influencing Factors
• Industry Best Practice - Process, Plant, People, Performance
• Conclusion and Discussion
2 Asset Integrity
About Oceaneering
Oceaneering provides services to deep water, space, Oil & Gas, and
Motion entertainment environments to execute with new, leading-edge
connections to solve tomorrow’s challenges, today.
Founded in 1964 as an ROV/ Diving specialist
Oceaneering Acquisition of OIS in 2004 ( Asset Integrity )
Branches in 5 continents
Has more than 8000 employees
3
Worldwide Locations
4
Inspection, Maintenance,
and Repair (IMR) Asset Integrity
Decommissioning
Installation Services
Diving Services
Subsea Connections
BOP Intervention
ROV Services
Intervention Tooling
Pipeline Repair
Subsea Control
Valves
Dredging
Flow Assurance
5
Integrity Management of Brownfield Projects: Challenges and Rewards
Asset Integrity
6
Integrity Management of Brownfield Projects: Challenges and Rewards
Share Best Practice for Operators/EPC/Vendors for a more efficient Integrity New
Build (INB) programmes (Brownfield)
Lessons learnt/Best Practice in INB can benefit the existing operating facilities (e.g.
Generic RBA / FM programmes)
The Use of Technology (Recent Software RBA, CAD, IDB -Inspection Data Base)
improves Governance & Standardization
7 Asset Integrity
Equipment Life Cycle Flowchart
Scope Definition
I N T E G R I T Y
Design - suitable materials
ETP 32-10
- inspection requirements
B U I L D
Asset Records
Site Construction
ETP 32-20
Procedures
Handover / Acceptance
Auditing
Commissioning
O P E R A T I O N
Operation
Competent
Resources
ETP 32-30 & ETP 32-40
Operation
In-Service Inspection
Training
Decommissioning
Retirement
8 Asset Integrity
Integrity Build
9
Governance & Compliance Integrity Build
Project Deliverables
Operator/Partners/Region
Integrity Management Systems
Process details
Commissioning
IMS & Philosophy,
Plans ( WSE)
Implementation Risk Based Assessment
strategy Project
Close out
Vibration Inspection
and
Local Processes &
Programme Handover
Integrity Systems
PSV
Project
Baseline Inspection Vibration Lessons
Programme Learnt
Engineering Design Fabric Maintenance
Review & Revamp PSV Testing
Project Dead Leg
Programme
Stakeholder Life Cycle
Engagement Approach
Front End IMS
Corrosion
Strategies
Management
PHASE (A) PREPARE PHASE (B) DEVELOP PHASE (C & D) APPROVE DELIVER
10 Sept 2016
A Typical RBA process (Greenfield vs. Brownfield)
Planning Implementation
11
Brownfield RBA Process Highlights
Critical path data maturity & Quality for Brownfield revamp project
12 Asset Integrity
RBA Process for a typical Brownfield Facility
High level Criticality review as per
-Location (Offshore/Onshore)
-Unit/System criticality (Safety, Environmental, Business)
-Process/Utility
-Fluid corrosivity (Wet, Dry, Sour, ...)
-Material Selection (CS, CRA, Clad, Non-metal, ...)
-Threat complexity and barrier effectiveness
-Inspection requirements / complexity
-History of failure / Significant anomalies in the same or similar facilities
13 Asset Integrity
Challenges in conducting a Brownfield RBA
-Methodology (Quantitative/Qualitative)
-Stakeholders engagement
-Different scenarios
-Various modes of failure
-Availability of backup data
-On time assessment
• Process safety • Pin hole leak • New / old • Brainstorming • Adequate time
engineer • Medium size studies sessions before RBA
• Environmental • HAZOP, • Software assessment
• Large size
engineer • FRA, • Manual
• Full rupture
• Mechanical • ENVIID calculation
engineer • Use of other
• Operation and QRA done
Maintenance
14 Asset Integrity
Challenges in conducting a Brownfield RBA
-Data availability
-Data validation
-Anomaly reports
-Tagging
-Monitoring records
15 Asset Integrity
Challenges in conducting a Brownfield RBA
16 Asset Integrity
Challenges in conducting a Brownfield RBA
Corrosion by chemicals (including well workover fluids) Crevice corrosion (including flange faces)
Erosion, erosion-corrosion and solids-free flow-induced damage Marine corrosion (including external MIC and Splash Zone)
Oxygen corrosion
Chloride stress corrosion cracking (SCC) Chloride stress corrosion cracking (SCC)
17 Asset Integrity
Challenges in conducting a Brownfield RBA
-Deadleg identification
-Deadleg risk assessment
-Operational / Physical deadlegs
-Mitigation
Deadleg Operational /
Threat assessment Mitigation in place
identification Physical deadlegs
• Isometrics • Failure histories • Change in the • Draining
available? captured? process • Flushing
• Line walk carried • Sampling from captured?
• Chemical
out? deposits / • Isolated, treatment
• Deadleg tagging stagnant fluids mothballed,
decommissioned • Preservation
(old and new philosophy
tags) items
• ... • ...
18 Asset Integrity
Challenges in conducting a Brownfield RBA
19 Asset Integrity
Challenge of developing and implementing an asset integrity
program during Brownfield development projects
QA issues
during
Schedule and Risk for delay in implementation
milestones often emerging vital Task conflict- Cost variance – clear and
take primacy integrity related Planning throughout the common
over integrity interventions Challenges project acceptance
management
criteria for
processes,
existing
anomalies
20 Asset Integrity
Operational Elements and Influencing Factors
OPS
ELEMENTS
I N F L U E N C E
21 Asset Integrity
Best Practice-Process
22 Asset Integrity
Best Practice-Plant
• Historical data
• Punch List items – and handover process
• As build P & ID and construction drawings
DOCUMENTATION
• In-situ verification of existing equipment ( 3D laser mapping)
STANDARISATION ENGAGEMENT COMPETENCY
23 Asset Integrity
Best Practice-People
24 Asset Integrity
Best Practice-Performance
25 Asset Integrity
Integrity Management of Brownfield Projects: Challenges and Rewards
26 Asset Integrity
Thank You for Your Attention!
Or contact:
Monzar Najami ([email protected])
Hooman Takhtechian ([email protected])
27 Asset Integrity