Week 7 PROJECT PLANNING and SCHEDULING PDF
Week 7 PROJECT PLANNING and SCHEDULING PDF
5-P rule
Proper Planning Prevents Poor Performance
Focus of Planning
Determining the future objectives and appropriate
means to achieve it
Answers the basic questions:
What must be done ?
How it should be done ?
Who should do it ?
When it must be done ?
How much it will cost?
The Basic Project Planning Cycle
Construction Planning
1. Project Organization
1.1 Types of Organization Structure
1.2 Project Roles and Responsibility
1.3 Leadership and Motivation in Construction Management
2. Project Planning and Scheduling
2.1 Introduction
2.2 Concept tools of planning
2.2.1 Bar Chart
2.2.2 Critical Path Method
2.2.2.1 Activity of Arrow (AOA) Method
2.2.2.2 Activity on Node (AON) Method
2.2.3 Line of Balance
3. Introduction to Computer Software
3.1 Microsoft Project
3.2 Primavera Project Planner
WBS EXAMPLE
WBS EXAMPLE
WBS EXAMPLE
WBS EXAMPLE
Project Scheduling
It is a process for setting various operations of a
construction projects in sequential order
Project Scheduling addresses issues in time
planning/management
It is graphical representation of work package
Process for setting activities in sequential order by fixing
start & completion date in such manner that whole project
should be done in orderly and systematic way
It helps to understand project objectives & eliminate any
uncertainties
It provides a basis for monitoring and controlling the work
Advantages of Planning and Scheduling
Alternative methods of construction can be examined at the
planning stage so that a most economical method can be
identified and chosen.
Time schedule
Resource schedule
• Material schedule.
• Labour schedule.
• Equipment schedule.
Project Scheduling Techniques
By charts
Gantt chart or bar chart.
Linked bar chart/ Modified Bar Chart
By net work Techniques.
A-O-A (Activity on arrow)
C.P.M (Critical path method)
P.E.R.T (Programme evaluation Review Techniques)
A-O-N (Activity on mode)
P.D.M (Precedence Diagramming method)
L.B.S (Line of balance system).
Scheduling with Bar Charts
Gantt Chart or Bar Chart
Bar Chart was developed by Henry Gantt in 1917
It is a graphical representation of work activities
Acts as planning-scheduling model and reporting-control model
The length of bar represents duration of activity
Advantages Gantt Chart or Bar Chart
Ability to clearly and quickly present the states of project.
To convey often to upper management, the over all status
of a project.
No extensive training is required to learn hw to extract in
formation from them.
The period required for execution of each activity or
operation can be observed.
Up date progress of each activity.
Resource aggregation.
Lagging of activities can be noticed to manage work.
Bar Chart for Concrete Gravity-Arch Dam
P2 P4 P6
H1 S1 H2 S2 H3
P1 P3 P5
Bar Chart
• Example 1
A project consist of six activities that should be done in a period of
time. Try to create a bar chart to ease the project planning and
scheduling.
• STEP 1: Identify start date & finish date for all activities
Activity
• A: 1 week, starting from 1 Oct 2005 (1/10/10 - 8/10/10)
• B: 2 week, starting from 5 Oct 2005 (5/10/10 - 19/10/10)
• C: 3 week, starting from 15 Oct 2005 (15/10/10 - 5/11/10)
• D: 2 week, starting from 25 Oct 2005 (25/10/10 - 8/11/10)
• E: 2 week, starting from 29 Oct 2005 (29/10/10 - 12/11/10)
• F: 1 week, starting from 5 Nov 2005 (5/11/10 - 12/11/10)
Bar Chart
2 B 2
3 C 3
4 D 2
5 E 2
6 F 1
Bar Chart
A:(1/10/10 - 8/10/10)
2 B 2
3 C 3
`
4 D 2
5 E 2
6 F 1
Modified Bar Chart
Example 2
Data of a project consist of five activities with their duration and also amount of
human resource needed for this project. Create a modified bar chart according
to the data below.
1 G 1 01 October 2010 5 H, I
2 H 2 08 October 2010 8 J
3 I 3 10 October 2010 15 K
4 J 2 22 October 2010 4 K
5 K 1 05 November 2010 3 -
Modified Bar Chart
Step 1: Identify start & finish date for all
activities
No activity duration starting human resources Successor
1 G 1 01 October 2010 5 H, I
2 H 2 08 October 2010 8 J
3 I 3 10 October 2010 15 K
4 J 2 22 October 2010 4 K
5 K 1 05 November 2010 3 -
G:(1/10/10 - 8/10/10)
H:(8/10/10 - 22/10/10)
I:(10/10/10 - 31/10/10)
J:(22/10/10 - 5/11/10)
K:(5/11/10 - 12/11/10)
Modified Bar Chart
(week) (people) 1 2 3 4 5 6
3 I 3 15
4 J 2 4
5 K 1 3
Modified Bar Chart
Step 3: Insert activity bars
Modified Bar Chart for Example 2
(week) (people) 1 2 3 4 5 6
2 H 2 8
3 I 3 15
4 J 2 4
5 K 1 3
Modified Bar Chart
(week) (people) 1 2 3 4 5 6
2 H 2 8
3 I 3 15
4 J 2 4
5 K 1 3
Modified Bar Chart
Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2
(week) (people) 1 2 3 4 5 6
3 I 3 15
4 J 2 4
5 K 1 3
Modified Bar Chart
Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2
(week) (people) 1 2 3 4 5 6
5 K 1 3
Modified Bar Chart
Step 5: Calculate human resources for each week
Modified Bar Chart for Example 2
(week) (people) 1 2 3 4 5 6
5 K 1 3
Modified Bar Chart
Step 5: Calculate human resources for each week
(week) (people) 1 2 3 4 5 6
(week) (people) 1 2 3 4 5 6
(week) (people) 1 2 3 4 5 6
10
0
Duration (week)
Progress Curves
1 2 3 4 5 6 7 8 9 10
1 Mobilization 100
2 Foundation Excavation
3 Diversion Stage
Original Schedule
4 Foundation Grouting
5 Dam Concrete
8 Prestress
9 Radial Gates
10 Spillway Bridge
Actual progress
11 Curtain Grout
Example 3
As a bar chart is created in Example 1, try to draw a
progress curve or S-Curve of the project with additional
data as follow :
(week) (RM)
1 A 1 1600
2 B 2 2000
3 C 3 6000
4 D 2 4800
5 E 2 3600
6 F 1 2000
Total 20000
Progress Curves
1 A 1 1600 8
2 B 2 2000 10
3 C 3 6000 30
4 D 2 4800 24
5 E 2 3600 18
6 F 1 2000 10
Total 20000 100
Progress Curves
Step 4: Divide those progress ratio equally for
each activity according to its duration
3 C 3 30
4 D 2 24
50
5 E 2 18
6 F 1 10
6 F 1 10 10
6 F 1 10 10
6 F 1 10 10