PPDS S4 Features

This document provides an overview of Production Planning and Detailed Scheduling (PP/DS) for SAP S/4HANA. It discusses the key features and benefits of PP/DS, how to activate it, improvements in S/4HANA, implementation considerations, and changes to material master data. PP/DS supports advanced planning capabilities and industry-specific features for automotive, process, and other industries. Activating it requires a separate license beyond the standard S/4HANA license.

Uploaded by

Srini Donapati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
898 views21 pages

PPDS S4 Features

This document provides an overview of Production Planning and Detailed Scheduling (PP/DS) for SAP S/4HANA. It discusses the key features and benefits of PP/DS, how to activate it, improvements in S/4HANA, implementation considerations, and changes to material master data. PP/DS supports advanced planning capabilities and industry-specific features for automotive, process, and other industries. Activating it requires a separate license beyond the standard S/4HANA license.

Uploaded by

Srini Donapati
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 21

PP/DS for SAP S/4HANA (Advanced

Planning)
Jomerce PJ SAP
SAP S/4HANA

Why PP/DS
PP/DS supports various features, that is considered
as very advanced features

 Sub-daily planning possibilities.


 Advanced planning and scheduling features like
Finite/ Detailed scheduling, setup matrix,
sequence constraints, Min/Max distances,
alternative modes, propagation of schedule
changes across all BOM levels, multilevel
material flow visibility using pegging.
 Simulative (what-if) planning capabilities
 Industry planning features and advanced
algorithms to support Automotive, mill, process
industries etc including
o Conti-IO, full pegging, Block Planning,
Campaign Planning, Shelf-Life
o Heuristics for compact planning, load
leveling, closing gaps, … and heuristic
framework
o Various optimizers

To be able to use Production Planning and Detailed


Scheduling for SAP S/4HANA, you must activate
Advanced Planning and Scheduling in the back-end
system. In

Customizing, choose Advanced Planning ->


Basic Settings -> Activate Advanced
Planning and Scheduling.

Fig 1: Customizing: Activate advanced planning

The features activated by the Advanced Planning and


Scheduling switch are not part of the standard SAP
S/4HANA Enterprise license. A dedicated license,
Manufacturing for Planning and Scheduling is required
if this switch is set to Active.

What’s new
PP/DS for S/4HANA has made several improvements
Standalone SCM-APO-PP/DS to simplify CIF in one
system, eventhough its not completely eliminated.
Improvements are made in following topics

 Harmonized master data


o One Material Master (Material master as a
CDS view), One Resource Maintenance
o Create, Update for Source of Supply
without Queues
 Simplified transactional data Integration (The
settings are controlled in customizing by
selecting Advanced Planning > Basic Settings >
Settings for Data Transfer)
 MRP Live Run with SAP ERP and “Advanced
Planning” Materials
 Unified Order Conversion Reports
 Period-Based consumption adopted for PP/DS
 Visually Harmonized screens for PP/DS (HINT:
For the list search with “/sapapo/ “in Fiori apps
reference library)
 Fiori apps Monitor Capacity Utilization and
Production Scheduling Board

For 1709 On -Premise:


 Location simplification
 Support for combined orders (mainly for Mill
industries)
 Fiori app for Capacity and shift maintenance

Fig 2: Integrated material master maintenance


Fig 3: One Workcenter maintiainance
Fig 4: Settings for data transfer.

Implementation considerations
The concept for PP/DS for S/4HANA starts with
classifying if a material is relevant for advanced
planning or not.
It is recommended that all downstream materials
should be Advanced Planning-relevant if planned
together with MRP Live. This means the data
modelling should be such that once a material at one
BOM level is PP/DS-relevant (Advanced Planning-
relevant), then the materials above that BOM level
should also PP/DS-relevant (Advanced Planning-
relevant). This is to ensure that depended demands
are also in liveCache or PP/DS.

In addition to this you also needs to maintain


advanced planning flag for work centers.

Once this is done, you can transfer PDS with


transaction CURTOADV_CREATE (in the SAP Easy
Access Menu, select Logistics > Master Data > PDS
for Advanced Planning) to enable PDS transfer to
PP/DS

Most of the Order and batches are always enabled to


be integrated once a material is classified as
Advanced Planning. The settings are controlled in
customizing by selecting Advanced Planning > Basic
Settings > Settings for Data Transfer. In case some
order types need not be needed to be integrated(eg:
Production order only), uncheck unnecessary items

In most of the common cases of Sales Scheduling


Agreement, if delivery schedules are managed in SAP
S/4HANA, and not in PP/DS, you need to unflag
check box SD Sched. Agmt.

Note: All objects that needs to be in PP/DS is not


simplified to be integrated without integration model,
that includes

 Plant(1610 only)
 Source of supply for external
procurement(purchase info record, contracts,
scheduling agreements)
 Classes and characteristics in case of using
CDP(characteristics depended planning) using
integration model for organisational area
 Setup groups
 Maintenance and network orders(material
Independed)
more.. (HINT: To see what all objects needs
integration model in Txn CFM1, and in Logical
System male the entry of same logical
system(own logical system) and press ENTER)

It is recommended to read the initial sections of


note 2382787 where it is mentioned in detail on
how to integrate the objects to PP/DS for
S/4HANA.

As in Standalone SCM-APO-PP/DS, in case you are


using CDP configuration, you need to set this client
depended settings.

Note : “Standalone SCM-APO” and PP/DS for SAP


S/4HANA can be used together, but the data
modelling should ensure that there is no data
dependency.

Only active model is supported in PP/DS for


S/4HANA.

PPM is not supported in PP/DS for S/4HANA. So it will


be needed to migrate from PPM to PDS. It could be
also achieved in the source system before migration.
This can effect standard support for

 Parameter efficiency
 Extended order generation (EOG)
 Multiple output planning (MOP)

Since only PDS is possible in PP/DS for S/4HANA,


the support for the above functionalities can only be
supported with help of BADI implementation

In S/4HANA, production versions are mandatory for


in-house production sources.

Material master changes


While migrating to from Standalone
SCM-APO-PP/DS, the main change you notice would
be that the material master is not maintainable in
PP/DS for active planning versions. This will have an
impact on your migration and modelling of PP/DS.

Its important to note that the mapping is done with a


redirect CDS view and is also have no option to
change standard mapping, event though the product
master can be extensible with new fields.

I recommend to verify the standard mapping and see


if this is matching with you modelling blue print before
implementation. The mapping is available at SAP
Note 2393581
Its important to note that there are some fields that are
defaulted in PP/DS for S/4HANA due to simplification
reasons. Few major ones are below

TABLE : MATLOC:

 
PP/DS Horizon
Alternative : use
in Calendar
CONVH value from Model
Days
 
Used by standard
heuristic
 
Requirements SAP_PP_014.
Ascertainment Ascertaining
CTHOR
Horizon in Pl.Ind.Requirement
Workdays s. You can
  maintain this in
Heuristics settings.
  Strategy for Always considered
Container
CONRESS
Resource-
TRAT
based Pegging
 

Below items defaults values are used. Automatic


Propagation is not desirable. In case needed, could be
managed with BADI’s.

 
Quantity Propagation By
CONF_PROPAG
Confirmations
ATION

 
 

CONF_COMPON Component Adjustment by


ENTS Confirmation

 
 

CONF_DURATIO /SAPAPO/
N DM_CONF_DURATION

Table : MATRQ:
Defaulted to Max
value. Alerts are
  Maximum
the way forward.
Allowed
Not used in
PEG_PAST_M Lateness for a
netting
AX Receipt
calculation. Only
Element
used in dynamic
  pegging.
  Maximum Defaulted to Max
Allowed value. Alerts are
Earliness for a the way forward.
Receipt
Not used in
PEG_FUTURE Elementequire netting
ments
_MAX calculation. Only
Ascertainment
used in dynamic
Horizon in
  Workdays
pegging
Always False.
Alternative : In
case custom
solution needs to
be achieved, it
 
could be solved
Deactivate by an extension
PEG_NO_DY
Dynamic with the heuristic
N
Pegging framework of
PP/DS. you need
  to have to copy
the standard lot
heuristics and in
the copy turn off
dynamic pegging.

TABLE: MATLOTSZ

Use Always
 
from product
Target
master. User
/SAPAPO/ Stock Level
Option
TARGET_METHOD Method
available in
Heuristics.
 

In addition it is to be noted that PP/DS product


master(Transaction /SAPAPO/MAT1) is read-only for
active planning versions, but can be used for
maintaining simulation depended parameters for
inactive planning versions

Modelling customer and vendor product-


locations
There is no standard way to have product at customer
and vendor locations. This will impact you if non
supported processes like VMI is used.

Alternatives:

An alternative to evaluate would be to model customer


and vendor locations as storage location MRP area, if
modelling is made in a way that only one plant is
supplying to customer or vendor locations. With this it
would be still possible to have visibility on the
customer or vendor locations. It should be noted that
in this case MRP areas should be used as a stock
transfer to production plant and not as a production
location.

It should be noted that the modelling should fit to


storage location modelling support in S/4HANA and
standard PP/DS. Locations corresponding to Storage
location MRP areas (location type 1007) and
subcontracting MRP areas (location type 1050) are
planned before planning the corresponding plant
locations MRP live. Also MRP live will not support
planning with stock transfer between MRP areas

Local Product/Work center Creations


PP/DS specific product locations and work centers are
not possible to be created. This means that all
products and work centers that needs to be needs to
be enabled to with “Advanced Planning” flag to be
used in PP/DS for SAP S/4HANA.

Most of the resource master data do not need any


maintenance from PP/DS resource
master(/SAPAPO/RES01). But PP/DS specific
features like block maintenance needs to be
performed from PP/DS resource master

To create a Handling Resource for Storage Location


and subcontracting MRP areas, the report
/SAPAPO/COPY_RESOURCE_HU can be used

Forecast Management
Since PP/DS is the only APO solution embedded with
S/4AHANA, it it required to have forecast
management and creation in S/4HANA and integrate
that with PP/DS. You will have to adopt you business
process to achieve this.

Note that characteristics based forecasts while


planning with characteristics for CDP and CBF is not
supported.

Forecast Consumption
Consumption period is calculated in calendar days in
PP/DS for SAP S/4HANA and in working days in SAP
S/4HANA. Also it should be noted that since the
consumption BAdI’s are not available, its not possible
to also have a working day calendar set to enable
consumption in working days.

Weekly, Monthly and user-defined consumption from


standalone SCM-APO-PP/DS is not supported for
PP/DS for S/4HANA.

In addition Forecast Consumption for sales orders for


characteristics-based
forecasts while planning with characteristics for CDP
and CBF are no longer supported.

Alternatives:
A new consumption type “5 – Period-Based
Consumption“ is also supported which will support
Forecast periods into account for consumption. For
more details refer SAP Note 2567437 – Forecast
consumption with mode 5 (Period-Based
Consumption) for Advanced Planning materials

It is recommended to read section “Forecast


Consumption” of SAP note 2382787 for details.

Subcontracting
Subcontracting is modeled with subcontracting MRP
areas for components in PP/DS for SAP S/4HANA,
inline with S/4HANA modelling. Subcontracting is only
supported with rough cut planning. So a finite planning
of subcontractor is not possible

Also it needs to be noted that subcontracting location


type 1050 is now mandatory.
the modelling of subcontracting is changed from
standalone PP/DS and is not modeled with
subcontracting MRP areas for components. It is
recommended to check section “Modeling
considerations” in SAP note 2518497 for details.

Alternatives:
In case it is needed to have finite scheduling model for
subcontracting some work around like below could be
evaluated.

A solution could be designed with a dedicated storage


location for each Subcontractor, a routing with 2
operations, one with external key just for PR creation
and one with fake internal key for resource capacity
management and order scheduling.

BAdi’s and User Exits


PP/DS for SAP S/4HANA has made BAdi’s,
Enh.Spots and user exits removed, especially true for
areas in

 Master data (not just material master)


 Many CIF APO inbound that changes just data
 Txn data that is having scope outside that of
only PPDS.

Only process related BAdi’s, Enh.Spots and user exits


and fully PP/DS specific txn data BAdi’s, Enh.Spots
and user exits are available.

The main idea is that there is no possibility of


changing mapping that makes data different in ECC
and in PP/DS, as now its one system.

It is recommended to review your custom code


implementation, before going for a migration.

Safety Stock as a Live-Cache element


In stand alone APO-PP/DS , we had following options.

 Virtual Safety Stock Elements that is used to


cover unexpectedly high requirements. This also
helps to allow planner to see that in case of a
delayed receipt, how much is covered
immediately by safety stock and how much is
delayed. Focused in planning.
 The option Real Safety Stock Requirements that
is needed to resolve delays or problems in
production

Real Safety Stock Requirements are not supported in


PP/DS for S/4HANA.

Alternatives:

What is supported in PP/DS for S/4HANA is custom


heuristics and heuristics framework. You could simply
copy the existing heuristics from somewhere and
remove the check of safety stock from /sapapo/mvm
in the heuristics(also make customizing of safety stock
in /SAPAPO/MVM initial, if needed) and use this
heuristics to create real safety stock.
MRP
PP/DS for S/4HANA in standard supports only
planning and scheduling with advanced planning. It is
recommended to use MRP live, in case you do not
have restrictions mentioned in “MRP Live” section of
SAP note 2382787 as classic MRP is in compatibility
list.

In general customer use-cases comes with derivations


and below are the cases used.

Case : PP/DS with split planning( Not with MRP


live)

Use (MRP classic(MD01) + PP/DS planning Run).


Needs a setup similar to MRP type X0 with MRP
Procedure “X Without MRP, with BOM explosion” for
material with advanced planning

In case using MRP Live(to plan only for PP materials),


you need to implement BAdI
MRP_DISPATCHER_BADI and need to skip the
Advanced Planning materials.

Case : Planning PP/DS materials only in PP and


schedule in PP/DS.

Use (MRP classic(MD01) + PPDS planning Run).


Needs a setup similar to MRP type X0 with MRP
Procedure “X Without MRP, with BOM explosion”. Use
P/PDS planing run only for scheduling heuristics.

In case using MRP Live, you need to implement BAdI


MRP_DISPATCHER_BADI and need to route the
Advanced Planning materials to plan in PP(probably
with classic ABAP if you need replication, similar to
MRP_FORCE_CLASSIC). You need to also use a
Planning procedure like ‘PD’ , Planning in Planning
run or that suits your business need.

Case: No planning for PP/DS material

The best option is to have a custom product heuristics


that not do anything. Optionally for MRP live you need
to implement BAdI MRP_DISPATCHER_BADI and
need to skip the Advanced Planning materials.
Another option would be to use MRP type similar to
“ND – No Planning” as MRP live will not plan these
materials.

Case: Skip planning MRP areas and only Plant


locations

Use BAdI “/SAPAPO/RRP_HEUR_DO” and on the


BEFORE method, customer has to filter out the peg
areas that has location type “1007

Heuristics and Planning Procedure


Due to the simplification reasons the following
heuristics are not supported.

 
PP/DS Deployment Multiple
SAP_DEPL_MUL Products

 
 
PP/DS Deployment Single
SAP_DEPL_SNG
Product
 
 
Planning Shortage Quantities
SAP_PP_CTP
for CTP
 

SNP –> PP/DS Conversion


SAP_SNP_MULT
for Many Prods

Individual Conversion SNP –>


SAP_SNP_SNGL
PP/DS

Stage-Numbering Algorithm
SAP_SNP_LLC
for SNP

Product Planning (Plan Comp


SAP_MRP_002
Immediately)

MRP-Based Det. Scheduling:


SAP_PP_MRPDS
Order Network

SAP_PP_20 Stage-Numbering Algorithm

Propagation of descriptive
SAP_PP_023
char. Values

SAP_PP_018 Create Safety Stock in SAP


liveCache

Planning of Shortage
SAP_PP_003
Quantities

In addition standard planning procedures, 3-Cover


Dependent Requirements Immediately, 5-Multilevel
ATP Check and 7-Length-Based Planning Procedure
are not supported. This is mainly due to non
supported CTP and gATP usecases.

However multilevel automatic planning can be used


without CTP process using custom specified planning
procedures and heuristics.

Integration with advanced- ATP


gATP is not available/integrated with PP/DS for SAP
S/4HANA. The basic principle followed is that PP/DS
for S/4HANA is integrated to advanced-ATP for
planned and production/process orders for component
check. In this case, integration with advanced ATP will
not check with orders in liveCache, but with PP orders
instead.

Also for a consistent result, it requires the orders in


liveCache to have the same components as that of the
PP orders. This restriction coudl efffect business
processes like CDP, interchangeability etc where PP
orders do not have visibility of PPDS.

In addition, ATP Check for Planned Orders for RPM


Products is supported for component check during
order conversion for PP/DS for S/4HANA.
Orders other than planned and production/process
orders can rely on the fact that the advanced-ATP
executes an ATP check during conversion anyway,
given appropriate customizing settings in S/4HANA
For details its recommended to check the “Availability
to Promise Integration” section in SAP note 2382787

Migration Options
There is no standard migration tools available yet for
To migrate PP/DS for SAP S/4HANA. But there are
few options to help.

Material master could be integrated with


MASSD/MM17 transactions by setting “Advanced
Planning” indicator.
For integrating orders, re-transfer report
/SAPAPO/PPDS_DELTA_ORD_TRANS could be
used.

There is also a PP/DS migration solution currently


delivered through SAP consultants. Please
communicate with your SAP contacts for details on
this.

Fiori Apps
Following Fiori apps are delivered with PP/DS for SAP
S/4 HANA.

Production Scheduling Board


https://fioriappslibrary.hana.ondemand.com/sap/fix/ext
ernalViewer/#/detail/Apps(‘F2176’)

Monitor Capacity Utilisation :


https://fioriappslibrary.hana.ondemand.com/sap/fix/ext
ernalViewer/#/detail/Apps(‘F1523’)/S6OP

Monitor Capacity Utilisation – Object page (1709


onwards)
https://fioriappslibrary.hana.ondemand.com/sap/fix/ext
ernalViewer/#/detail/Apps(‘F2900’)/S9OP

Shift management
From S/4HANA OP1709 onwards there is a Fiori App
to manage shifts (Monitor Capacity Utilization – Object
Page) for PP/DS for S/4HANA. This powerful app
helps you to change the shifts and operations in
simulation mode and then see capacity
situation/utilization depending on different parameters
like order type, materials to adapt the changes

The Capacity Variants and Definitions for Resources


with External Capacity are disabled in SAP GUI by
default, is enabled for editing Monitor Capacity
Utilization Fiori app. This is to prevent data corruption.
In case you are not using Monitor Capacity Utilization
Fiori app, for shift maintenance, you can enable this.
Refer note 2598760 for details.

Combined Orders
From S/4HANA OP1709 onwards order combination
for production/process orders are supported. The
details can be found in PP/DS Help Landing Page:

To navigate go to S/4 HANA 1709 Landing


Page( https://help.sap.com/s4hana_op_1709) and
then navigate to Enterprise Business Applications ->
Manufacturing -> Production Planning and Detailed
Scheduling (PP/DS)-> extended orders -> combined
order scheduling

Integration with stand-alone APO or IBP


Standalone SCM-APO or IBP and PP/DS for SAP
S/4HANA can be used together, but the data
modelling should ensure that there is no data
dependency.Integration of orders generated out of
Standalone SCM-APO or IBP to PP/DS for SAP
S/4HANA or vice versa is not supported.

From a process point of view both “Standalone SCM-


APO” or IBP and PP/DS for SAP S/4HANA schedules
the orders(eg: planned orders), if enabled could create
a recursion.