A. Formwork
1. Fabrication:
Erect formwork in accordance with reviewed shop drawings.
7200 X DEPTH
3. Removal of Forms
Forms and shoring in the formwork used to support the weight of concrete in
beams, slabs and other structural members shall remain in place until the concrete
has reached a minimum of 70% of the specified 28 day strength. Unless specified
otherwise, the following minimum periods shall apply to the removal of formwork.
Removal of Form work from Cold Normal
Weather Weather (above
(Below 600 F 600 F or 160 C)
or 160 C)
Sides of beams, slabs, walls and 72 hours 48 hours
Columns (unloaded)
Slab soffit forms (props left under) 14 days 7 days
Beams soffit forms (props left 14 days 7 days
under)
Props to slab 18 days 11 days
Props to Beams 21 days 14 days
4. Re-shoring:
While re-shoring is under way, no live load shall be permitted on the new
construction.
5. Stripping of Formwork:
1 General
The Engineer shall be notified in writing before the removal of any formwork.
Architectural and Structural Specification 03 30 00 Cast In Place Concrete Page 1 of 2