Extension of Time Claim (Detailed Analysis)
Extension of Time Claim (Detailed Analysis)
Development
Contents
1 PROJECT PARTICULARITIES.......................................................................................................2
1.1 Introduction About the Project......................................................................................................2
1.2 The Parties.....................................................................................................................................2
1.3 Basic Contract Information...........................................................................................................3
2 Background On The Claim Cases............................................................................................4
3 Delay in The Provision Of Work Orders For Lift Top Elevation...................................4
4 Delay In The Provision Quartz Paint Color Specification ……………………...….……
5
5 Shortage of 10cm HCB……………………………………………………….……..
……..6
6 Conclusion............................................................................................................................7
Annex:
Appendix A
Appendix B
Appendix C
1 PROJECT PARTICULARITIES
1.1 Introduction About The Project
On the May 29th 2015 Afro-Tsion construction entered into a contract agreement with City
Government of Addis Ababa Saving Houses Development Enterprise for the construction of
40/60 Saving House Building Project. Work on the project commenced on June 5th, 2015
G.C.. The original date for completion of the project is June 4th 2017 with a contract period
of 730 Calendar Days.
3.1.1 According to the contract G.C.C. Clause 15.2 and G.C.C. Clause 15.4, the Engineer
shall issue any change or work order required for the execution of the project in
writing. Accordingly the decision on the level of the top lift elevation requires
issuance of instruction from the Engineer.
3.1.2 The work order has been requested on 08/01/2011, 03/02/2011and 04/03/2011[See
Appendix A], but no response has been given up to now. This has caused
retardation in the project progress as described below.
o Had the Work Order Been Issued on 29/01/2019, the construction of the lift top,
shear wall, fire escape requires (Concrete):
Crew composition=2 mason,14 Daily laborer
Output of 1crew for masonry work=3.75m2/day
Total concrete to be constructed=76.77 m3
Total number of days required for concrete work =20.47
=21days
o Had the Work Order Been Issued on 29/01/2019, the construction of the lift top,
shear wall, fire escape (Rebar):
Crew composition=3 barbender,6Daily laborer
Output of 1crew for masonry work=450 kg/day
Total Rebar to be done=12626.61 kg
Total number of days required for rebar work=28.05
=28days
o Had the Work Order Been Issued on 29/01/2019, the construction of the lift top,
shear wall, fire escape (Formwork):
Crew composition=2 carpenter,4Daily laborer
4.1.1 According to the contract GCC clause 15.2 and G.C.C. Clause 15.4, the Engineer
shall issue any change or work order required for the execution of the project.
4.1.2 The work order has been requested on 08/01/2011, 03/02/2011 and 04/03/2011 [See
Appendix B], but the response has not been issued up to now. This has caused
retardation in the project progress as described below.
4.2.1 Due to the delay in issuance of instruction to start executing quartz paint contract
bill item, the Contractor was forced to stop production and purchase of material
and this in turn caused delay in time.
o As per the original contract, 19,608.47 m2 Quartz work require the
construction of the lift top, shear wall, fire escape Formwork:
Crew composition=12 painter, 24daily laborer
Output of 1crew for quartz paint=144 m2/day
Total paint to be done=19608.47 m2
Total number of days required for paint =136.11 days
=137days
4.2.1 The Approval of the material, purchase and Production require additional 30
calendar days.
4.2.2 In conclusion, the project completion date needs to be extended for (137+30) = 167
calendar days due to the delay in the issuance of quartz color specification.
5 Shortage of 10 Cm HCB
5.1 The Cause of the Claim
5.1.1 According to the contract S.C.C. Clause 1.2 and Annex A of the Contract, the HCB
supply is not the responsibility of the contractor. Accordingly delays in the supply
of HCB are justifiable causes for a time extension claim.
3.1.2 The issue of shortage of 10cm HCB and delay in supply thereof have been
repeatedly flagged by the contractor with letters written on 27/12/2010,
08/01/2011,09/01/2011 and 03/02/2011[Appendix C] .
6 Conclusion
In conclusion the claim submitted herein contains the Contractor’s request for an extension of
Time for Completion up until September 1, 2019(i.e., A total sum of 534 Calendar Days
Requested Extension of Time under Section 3,4 & Section 5of this document)
APPENDIX A
APPENDIX B
APPENDIX C
APPENDIX D