Geo Asia 04 Schaefer
Geo Asia 04 Schaefer
P. Schaefer
Institute of Hydraulic and Water Resources Engineering, Technische Universität München, Germany
[email protected]
Th. Strobl
Institute of Hydraulic and Water Resources Engineering, Technische Universität München, Germany
[email protected]
ABSTRACT: In Europe numerous concrete-faced open water canals are being used for hydropower produc-
tion, of which some are as old as 80 years. As a result of ageing the concrete facing looses its water-tightness.
A modern approach for the rehabilitation of such canals is the installation of a geomembrane-based facing
onto the existing concrete. For aid in the design of a rehabilitation measure, loads onto geomembranes have
been studied in a canal in the Laboratory of Hydraulic and Water Resources Engineering of the Technische
Universität München, Germany. In this paper results of the tests in the canal in the Laboratory will be pre-
sented together with suggestions for the design of geomembrane-based sealing systems and case-studies of
previous rehabilitation measures with geomembranes in open water canals.
1 INTRODUCTION
473
Figure 1. Rehabilitation of canals with concrete and asphaltic concrete and geomembrane
Figure 2. Pair of cars found during draw-down of the Innkanal, Germany, 2003
474
For a conservative design of the fixation of geomembranes the loading condition ’damage of a membrane
perpendicular to the direction of flow, from one fixation profile to the next’ (Figure 3) must be taken into ac-
count.
geomembrane fixation l0
profile
lp
α
existing
concrete
damaged pdyn N
membrane anchor
Figure 3. Example of damage of geomembrane in bottom area between two fixation profiles
and deformation of membrane due to hydrodynamic pressure
In this case the hydrodynamic water pressure, which develops below the membrane, can be calculated with
v2 1
p dyn = ρ ⋅ g ⋅ = ρ ⋅ v2 (1)
2g 2
where ρ = density and v = mean velocity of the water. According to the geometry the normal force N is:
N = p dyn ⋅ r (2)
2.3 Fixation
With the above calculation the possible loads, which must be transferred by the fixation system can be deter-
mined. The load which can be transferred by the mechanical or preferably chemical anchors is defined by the
manufacturer. The amount of load which can be carried by the aged concrete however must be determined in-
dividually for each subgrade and situation.
475
For the purpose of studying these loads a canal in the Laboratory of Hydraulic and Water Resources Engi-
neering with a 4 m wide bottom and a maximum discharge of 4 m³/s was used. It was lined with three differ-
ent geomembrane systems (HDPE, PVC-geocomposite and FPP) and the loading condition of “a membrane
damaged perpendicular to the direction of flow, from one fixation line to the next” was simulated by preparing
a cut in the bottom, which was opened during operation of the canal. The basic question, whether the mem-
brane behaves in the presumed way, was answered positively; the membrane lifted and allowed water to flow
underneath (Figure 4), only minor dynamic effects were observed
12
~ 11 kN/m
load [kN/m]
10
0
08:00 08:05 08:10 08:15 08:20
time
476
Tests were carried out up to a point beyond serviceability (Figure 6, right). The aim was to determine the
portion of the load being carried by friction between the membrane and the concrete and the steel profile, and
the part carried by the contact between the membrane and the anchor directly. For this reason each test was
carried out once with a membrane with slits in it (friction only, Figure 7, left), once with untightened screws
(anchors only, Figure 7, center) and once with regular fixation (Figure 7, right).
Figure 7. Membrane after test: friction only, anchor only, anchor + friction
Figure 8 shows the diagrams with two fixation types. The results are very similar, except that a closer spac-
ing of the anchors (Figure 8, left) improves the part of the load carried by the “anchor only”. Apparently the
load carried by a proper fixation cannot be defined as the superposition of “anchors only” and “friction only”.
250 standard fixation 250
friction only
friction only (anchor + friction)
200 200
anchor only
pull-out [mm]
pull-out [mm]
standard fixation
(anchor + friction) 150 150
anchor only
100 100
50 50
0 0
0 -5 -10 -15 -20 -25 -30 0 -5 -10 -15 -20 -25 -30
load [kN/m] load [kN/m]
Figure 8. Pull-out test with HDPE, anchor Ø = 8 mm, d = 20 mm (left); Ø = 12 mm, d = 25 mm (right)
This shows that for a reliable transmission of the strains to the concrete the contact of the anchors with the
membrane and the friction are both important. As sufficient concentration of anchors must be warranted as
well as sufficient clamping torque, which should be controlled also some time after installation.
477
4 IMPACT OF DIFFERENT GEOMEMBRANE PROPERTIES
The design of a lining with geomembranes tries to achieve several aims. From the hydraulic point of view,
in case of a damage of the membrane and its deformation due to the hydrodynamic water pressure underneath,
the reduction of the cross section of the canal must be limited to avoid backwater or even a change of flow. To
attain this goal either a stiff membrane must be chosen, or the distance between the lines of fixation must be
reduced. On the other hand, up to half of the expenses for such a rehabilitation measure can be accounted for
the fixation alone. So with regard to cost effectiveness the amount of required anchors should be kept to a
minimum. This can be reached by using a soft membrane, which according to equations (2) and (3) produces
reduced strains to the fixation. The following gives two examples for two different geomembrane materials
with otherwise same boundary conditions. The reduction of the cross-section of the canal and the developing
strains in the fixation are compared.
1
v = 1.5 m/s A = 56 m² 1
4m
∆A
F F
10 m
In this example the stronger HDPE membrane allows a satisfactory 8% reduction of the area of flow, how-
ever requires a supporting force of 20.9 kN/m (Table 1). The softer PVC membrane would require roughly
only half the supporting force, however would lead to more than twice the reduction of the area of flow, thus
possibly requiring an additional line of fixation in the middle of the bottom. This shows that the design must
be made individually according to the geometry, the hydraulic situation and the state of the concrete.
5 REFERENCE PROJECTS
478
5.2 Isarkanal, Germany
The rehabilitation of the Alzkanal near Trostberg, Germany in 2001 included a 700 m section with a rec-
tangular cross-section. This section of the canal lies in a town with narrow space. The membrane was the only
economical alternative to a removal of the old structure and the building of a new one. A soft membrane made
of 2.5 mm flexible polypropylene (FPP) was chosen to be the only feasible alternative (Figure 12, left).
In a further 5.5 km trapezoidal cross-section the right embankment surmounts the ground level and the loss
of water tightness threatened the slope stability. The rehabilitation measure included the placement of a layer
of asphaltic concretre onto the bottom and the lining of the right slope with an HDPE geomembrane.
The rehabilitation measure was carried out successfully within 4 months. The reduction of the roughness of
the surface resulted in a considerable increase in hydropower production. The above mentioned lining of areas
of the canal resulted in a decreased roughness of the canal, which led to an increase of water level at the
powerhouse intake of about 20 cm. With a mean flow of 60 m³/s this means an additional power production of
600,000 kWh per year (Figure 12).
Both sections of the Alzkanal are monitored by fibre-optical temperature measurement which verifies the
water-tightness (Strobl et. al., 2002).
REFERENCES
Strobl, Th.; Schmautz, M.; Perzlmaier, S.; Schäfer, P.: “Geomembranebased facings of existing open canals -
application, monitoring and comparison with conventional sealing systems”, Proceedings of the Seventh In-
ternational Conference on Geosynthetics 7 ICG, Nice, Vol. 2, S. 723-728 (2002)
Koerner, R.M., Designing with Geosynthetics, Fourth Edition, Prentice-Hall, New Jersey, (1998).
479