LCC Procedure Commissioning: Product Documentation GIS (PGHV DEPARTMENT) On Site Test / SAT

This document outlines the commissioning procedure for a Local Control Cubicle (LCC) panel. It details the steps to check the earthing system and electrical connections before energizing the supply voltage to the LCC panel. It then describes performing visual inspections of devices and terminals, resistance measurements to check for short circuits and earth faults, and voltage measurements to check the auxiliary voltage supply. Finally, it covers energizing the local control cubicle and additional checks of the auxiliary voltage supply and ensuring each circuit is potential free.

Uploaded by

Hendra Laksmana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

LCC Procedure Commissioning: Product Documentation GIS (PGHV DEPARTMENT) On Site Test / SAT

This document outlines the commissioning procedure for a Local Control Cubicle (LCC) panel. It details the steps to check the earthing system and electrical connections before energizing the supply voltage to the LCC panel. It then describes performing visual inspections of devices and terminals, resistance measurements to check for short circuits and earth faults, and voltage measurements to check the auxiliary voltage supply. Finally, it covers energizing the local control cubicle and additional checks of the auxiliary voltage supply and ensuring each circuit is potential free.

Uploaded by

Hendra Laksmana
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Product Documentation GIS (PGHV DEPARTMENT)

abb On Site Test / SAT JAKARTA, INDONESIA

LCC PROCEDURE
COMMISSIONING

Doc. Kind Doc Title Doc No. Lang. Rev.

abb PT. ABB SAKTI INDUSTRI Procedure LCC Procedure 01 Eng A

Page 1 of 3
Product Documentation GIS (PGHV DEPARTMENT)
abb On Site Test / SAT JAKARTA, INDONESIA

A. Before Energize supply ac/dc voltage (Preliminaries) on LCC Panel;


1. Check earthing of GIS bays and Local Control Cubicle.
2. All electrical connections within the earthing system shall be properly installed.
3. Earthing system shall not be interrupted at any point.
4. Earthing system shall be inspected before commissioning.

B. Visual Inspections;
• of devices for damages.
• of all terminal for correct design and proper connection.

C. Resistant Measurement;
• Check resistance between +(L) and –(N) of all control/alarm circuits to detect any short-circuits.
• Check resistance between + and PE, as well as – and PE, of all control/alarm circuits to detect
any earth-faults.

Doc. Kind Doc Title Doc No. Lang. Rev.

abb PT. ABB SAKTI INDUSTRI Procedure LCC Procedure 01 Eng A

Page 2 of 3
Product Documentation GIS (PGHV DEPARTMENT)
abb On Site Test / SAT JAKARTA, INDONESIA

D. Voltage Measurement;
• Check auxiliary voltage supply at terminals for:
› Voltage ac/dc, ( pahse - ground; + and ground; - and ground; + and - )
› Polarity supply dc.

E. Energization of Local Control Cubicle;


• Energization of all control/alarm circuits.
› Check auxiliary voltage supply at MCBs for:
- Voltage ac/dc, ( pahse - ground; + and ground; - and ground; + and - )
› Check for separated circuits. Switch off each MCB one by one.
› Symmetrical earthing of battery system: (if available)
- Check voltage between + and PE, as well as – and PE, + and - ;
› Each circuit has to be potential free!

Doc. Kind Doc Title Doc No. Lang. Rev.

abb PT. ABB SAKTI INDUSTRI Procedure LCC Procedure 01 Eng A

Page 3 of 3