1 S4HANA Best Practice - Highlights From Implementation Project
1 S4HANA Best Practice - Highlights From Implementation Project
SAP Best Description Client creation process BP activation process Resulting Example of Reference for
Practices Client after BP resulting S/4HANA 1909
activation activation configuration FPS0 Best
strategy (1809) Practices US
1) Best Standard process Following BP activation note, Standard activation process Client with only 55 Sales Order https://blogs.sap.com/201
Practices that follow the Configure the Table according to the BP activation Best Practices types 9/09/27/new-installation-
of-s4hana-1909fps0-part-
Client procedure in the BP /FTI/T_NOCLN000 with the note configuration 3-best-practices-content-
activation note new Client ID (without the activation/
Client 000
configuration)
2) Merged Copy of all client Skip the step “Configure the Additional errors will occur Client with client 202 Sales Order https://launchpad.support.
Client 000 reference Table /FTI/T_NOCLN000” during the activation, due to 000 + Best types sap.com/#/notes/2839315
settings/ conflicts with already existing Practices • 55 Best Note 2839315 -
configurations Without this step, all client client 000 configurations configurations Practices Implementation of SAP
000 reference settings/ Sales Order S/4HANA SAP Best
configurations will be copied For Best Practices 1909 US types Practices 1909 (on
to the new Client and DE there is the note • 115 Client premise) - Activation in a
merged client
2839315 with the additional 000
errors and how to overcome Standard
them Sales order
types
In the Greenfield landscape deployment, the Partner will have to activate the SAP Best Practices with Merged Client approach (*),
implement the country localization notes and optionally import change requests with the Partner Package configurations and
developments. The Partner needs to remember to check if a Scope Item requires additional license (see Administration Guide to
Implementation of S4H 1909 with Best Practices).
If the Partner decides for the deployment of enterprise management layer for S4HC EX in all tiers (DEV, QAS, PRD), tests of the note
2838358 tool need to be performed before any estimation of effort and time to fulfill the gaps of missing Client 000 configuration. We
recommend the execution of tests before the decision of the S4HC EX deployment option.
It’s important to inform the Customer, that since the enterprise management layer for S4HC EX/ Model Company Single country is a
subset of scope items from S4H 1909, we will not lose any S4H capability. As an example, the S4H 1909 US has 257 Scope Items and
the EML for S4HC EX US 166 Scope Items. For Multi country, the Customer will lose the activation of all 42 countries and additional
Model Company Finance configurations (e.g. Parallel accounting for multinational organizations).
* For Partners: If you need guidance on how to activated the SAP Best Practices in a greenfield landscape, contact your PXM and
ask for support from the Partner Solution Center LAC
• If we choose the Alternative 1 Best Practices Client, without the complete copy of Client 000 tables, the configurations that are not in
the scope of Best Practices will be empty.
• The note 2838358 provide a report that is a tool to copy configurations from Client 000 to the Best Practices Client. The report was
designed as a tool to fill smaller gaps of configuration in the Best Practices Client. Therefore, the use of the tool should not be part of
a standard delivery approach.
• By design the report of note 2838358 doesn’t copy some types of configuration, for example condition technique configurations,
configurations that contain address (e.g. Sales Organization). All these configurations that are not copied are reported in the program
execution log, so the Partners / Customers will be able to be aware of potential missing configuration and manually copy them later.
• In the note 2838358 there is a disclaimer that explains that the use of the tool provided in is at the risk of the Partner or Customer.
Therefore, the Partner should test the report of note 2838358 and not assume that it will fill all the Client 000 configurations gaps.
These tests should be done before the decision of the S4HC EX deployment option (with or without Model Company/ enterprise
management layer for S4HC EX, that uses the Best Practices Client approach).
• Since the enterprise management layer for S/4HC EX Multi-Country edition will be included in the deployed scope for every EX
customer by default. If the Partner don’t ask for a greenfield system landscape, a landscape “re-deployment” is required (additional
cost).
See SAP Note attached file as example, “2 How to – Tests of Copy configuration from Client 000 – Note 2838358.pdf”