Assignments
Assignments
NO STUDENT QUESTION
NAME
1 Maçka Police Station employs 30 police officers. Each officer works for 5
days per week. The crime rate fluctuates with the day of week, so the
number of the police officers required each day depends on which day of
the week it is: Monday, 18; Tuesday, 24; Wednesday, 25; Thursday, 16;
Friday, 21; Saturday, 28; Sunday, 18. The Police Station wants to schedule
police officers to minimize the number whose days off are not consecutive.
Formulate an LP that will accomplish this goal.
2 The Airline Company builds commercial airplanes and the last stage in the
production process is to produce the jet engines and then to install them in
the completed airplane frame. The company has been working under some
contracts to deliver airplanes in the near future, and the production of the
jet
engines for these planes must now be scheduled for the next 4 months. To
meet the contracted dates for delivery, the company must supply engines
for installation in the quantities indicated in the second column of the Table.
The facilities that will be available for producing the engines vary according
to
works scheduled during this period. The resulting monthly differences in the
maximum number that can be produced and the cost (in millions of dollars)
of producing each one is given in the third and fourth columns of Table.
Because of the variations in production costs, it may well be worthwhile to
produce some of the engines a month or more before they are scheduled
for installation. The drawback is that such engines must be stored until the
scheduled installation (the airplane frames will not be ready early) at storage
cost of $100,000 per month for each engine.
4 A freight plane has three large compartments to carry cargo. Weight and
volume limitations of these compartments are:
There are four cargos waiting to be loaded in this plane. Properties of these
cargos are shown on the table below:
Because this primal problem has more functional constraints than variables,
suppose that the simplex method has been applied directly to its dual
problem. If we let s1 and s2 denote the slack variables for this dual problem,
the resulting final simplex tableau is
For each of the following independent changes in the original primal model,
you now are to conduct sensitivity analysis by directly investigating the
effect on the dual problem and then inferring the complementary effect on
the primal problem.
a) Find the allowable range in the objective function coefficient of y1 to
remain the current basis optimal.
b) If the objective function coefficient of y1 is changed to 3, what
would be the new optimal W?
c) Find the allowable range in the right-hand side of the first constraint
to remain the current basis optimal.
d) d) If the right-hand side of the first constraint is changed to 5, what
would be the new optimal W?
7 Three electric power plants with capacities of 25, 40, and 30 million kWh
supply electricity to three cities. The maximum demands at the three cities
are estimated at 30, 35, and 25 million kWh. The price per million kWh at
the three cities is given in Table, below. During the month of August, there is
a 20% increase in demand at each of the three cities, which can be met by
purchasing electricity from another network at a premium rate of $1000 per
million kWh. The network is not linked to city 3, however. The utility
company wishes to determine the most economical plan for the distribution
and purchase of additional energy.