MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 1 of 10
Contents
1.0 Introduction...................................................................................................................................2
2.0 Scope of works Covered............................................................................................................3
3.0 Reference Documents................................................................................................................3
4.0 Definitions and Abbreviations..................................................................................................3
5.0 Personnel Required and Designated Responsibilities.......................................................3
6.0 Subcontractors Utilized..............................................................................................................4
7.0 Products Required.......................................................................................................................5
8.0 Tools and Equipment’s required..............................................................................................5
9.0 Procedure......................................................................................................................................5
9.1 Receiving materials:...................................................................................................................5
9.2 Handling / Storage and Transportation of materials at Site:.............................................5
9.3 Pre-Installation:............................................................................................................................6
9.4 Testing............................................................................................................................................9
10.0 Quality Control and Quality Assurance:................................................................................9
11.0 Hazard Identification, Risk Assessment & Determining Controls (HIRADC):...............9
12.0 Appendices:..................................................................................................................................9
Appendix 1 - Inspection and Testing Plan..............................................................................................9
Appendix 2 - Checklist..............................................................................................................................9
Appendix 3 - Risk Assessment................................................................................................................9
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 2 of 10
1.0 Introduction
This method statement covers the method of installation and testing of below ground
Sewage drainage using UPVC pipes.
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 3 of 10
5.0 Personnel Required and Designated Responsibilities
Project Manager (PM) - Organize & manage all resources and field activities to achieve
an efficient and effective completion of the contract, within the agreed time and cost,
whilst paying due regard to safety and meeting Quality requirements.
Ensure the construction activity as per approved construction & work methods.
Site Engineer (Civil) - Prepare construction method statements, work methods and obtain
approval for the same for civil works.
Site Engineer (Utilities & Pipeline) - Co-ordination with the construction team for safe
excavation procedure to existing utilities and liaison with relevant authorities when
required.
Land Surveyor - To establish control points as per survey plan.
Construction Superintendent - Front line supervision of the workman.
QA/QC Engineer - Set up and monitor QA/QC activities at site.
HSE Officer - Implementation of the project HSE plan.
Flagmen/Banksman – To indicate the operator to hold and proceed with the work.
Electrician - To prepare required power connection and illumination.
Foreman- To direct work for the workman.
Operators-To operate excavators, Dozer, Etc.
Drivers -To drive the vehicles required for excavation operation
Helper - To help the skilled workman.
Riggers- To align pipe
Welders-For welding
The detail responsibilities of above mentioned personnel’s are mentioned in the approved
Project Quality Plan.
The Criteria for fixing the subcontractor will be mainly as per the requirement of Project. The
Sub Contractors will be analysed according to their previous work experience of the similar
nature, their Company profile, their ability to execute the work as per the project specification
and up to the satisfaction of the Client. More weightage will be given to the Subcontractors
who are registered with the SME.
Before the deployment of every Subcontractor, we shall submit their relevant document to
the Client for their approval. We shall also insist the Subcontractor to get themselves
registered with Salalah Free Zone Company S.A.O.C. Once the subcontractor is approved
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 4 of 10
by the Client, the necessary HSE induction will be given to them to understand them the
requirement of the Client as well as ours.
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 5 of 10
When loading pipes on to vehicles, care shall be taken not to allow them to come in to contact
with any sharp corners such as loose nail heads as pipes may be damaged by being rubbed
against these during transit.
9.3 Pre-Installation:
9.3.1 Trench Preparation and Bedding
Centerline marking and excavation dimensions shall be done as per the Approved
drawing including clearance from the face of any structure and within necessary working
space.
Adequate signage shall be placed near the excavation.
Trench inspection shall be carried out as Per approved Excavation MST&ITP
The trench bottom shall be carefully examined for the presence of hard objects, rocky
projections or large tree roots and shall be trimmed to an even finish.
Depth of bedding shall be as per approved drawing.
It shall be ensured that the Bedding material is free from large stones and granular
material crushed stone(Aggregate)
Initial filling material shall be crushed stone(Aggregate)
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 6 of 10
Jointing Procedure:
Thoroughly clean the inner of the socket with fine cotton cloth particularly in the groove
provided for rubber O-ring and ensure it is free from any foreign particles.
1. Cleaning
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 7 of 10
2. Application of Lubricant
Immediately after lubrication, the spigot with marking of the socket depth shall be
brought into contact with the socket.
The spigot pipe and parent shall be accurately aligned so that the axes of the pipes are
precisely in line.
Ensure that socket end is opposite to the flow direction.
The spigot shall be hand fed into the socket until resistance from inner sealing section
is felt.
3. Joining Pipes
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 8 of 10
The joint shall be completed by applying leverage with a crow bar at the following
Socket end. A stout timber shall be inserted between the crow bar and the pipe socket
to prevent damage to the latter.
4. Applying Leverage
9.4 Testing
a) Pre- Testing
Inspection shall be carried out as per the sequence referred in Inspection Test plan for
installation and testing of sewage network system – UPVC Pipe & Fittings during construction
& before backfilling.
b) Air Testing
Air testing shall be done as per clause no 8.2.3.9 of OMAN standard specification volume no
3.
As soon as practicable after a length of pipe has been completed, it shall be subjected to an
air test to BS EN 1610
Length of pipe shall be plugged and sealed and air pumped into the pipe by approved
method.
We shall allow 5 minutes for stabilization of air temperature and adjust pressure to 100 mm,
the section will not be considered satisfactory if the air air pressure fails from 100 mm to 75
mm head of water in 5 minutes or less
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 9 of 10
Failure to pass the air test is not conclusive and if no leakage can be traced by externally
application of soapy water to all sealing areas.
12.0 Appendices:
Appendix 1 - Inspection and Testing Plan
Appendix 2 - Checklist
Appendix 3 - Risk Assessment
MST/SFZ/MEP 04, Rev 1 METHOD STATEMENT FOR UNDERGROUND DRAINAGE & SEWAGE SYSTEM– UPVC PIPES
Page 10 of 10