This document summarizes hazards identified and risk assessments for the job of picking and making up Bottom Hole Assembly (BHA) components using rig tongs and an iron roughneck, as well as picking up and laying out BHA components with cranes. Key hazards identified include dropped objects down the hole, lifting equipment parting, and personnel being trapped in pinch points. Existing control measures include ensuring the hole and pipe are covered and tools are secured correctly. Additional control measures proposed include being aware of pinch points and controlled operation of handling equipment.

Uploaded by

Avinash Mathew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views2 pages

BHA - Handling 004

This document summarizes hazards identified and risk assessments for the job of picking and making up Bottom Hole Assembly (BHA) components using rig tongs and an iron roughneck, as well as picking up and laying out BHA components with cranes. Key hazards identified include dropped objects down the hole, lifting equipment parting, and personnel being trapped in pinch points. Existing control measures include ensuring the hole and pipe are covered and tools are secured correctly. Additional control measures proposed include being aware of pinch points and controlled operation of handling equipment.

Uploaded by

Avinash Mathew
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Hazard Identification and Risk Assessment Worksheet

Job Picking and Making up / Laying and Braking out BHA’s Job No 0077 Location Ben Rinnes Worksheet 1 of

Task Description Making up BHA’s using rig tongs , iron roughneck. Picking up and laying out with the cranes. Date
Residual
Hazard Hazard Effect Existing Control Measures L S RISK Additional Control Measures By Risk ALARP

Changing Dropped objects Ensure the hole and the pipe is Be aware of pinch points. Controlled operation of
out BHA down the hole. covered. Ensure tools are secured
handling Lifting correctly. Use the correct
equipment equipment techniques for slinging elevators.
parting. Pinch
points personnel
trapped

Assessment Leader: Position Attendee Position

Attendee Position Attendee Position


Attendee Position Attendee Position
Hazard Identification and Risk Assessment Worksheet
Job Picking and Making up / Laying and Braking out BHA’s Job No 0077 Location Ben Rinnes Worksheet 2 of

Task Description Making up BHA’s using rig tongs , iron roughneck. Picking up and laying out with the cranes. Date
Residual
Hazard Hazard Effect Existing Control Measures L S RISK Additional Control Measures By Risk ALARP

Assessment Leader: Position Attendee Position

Attendee Position Attendee Position


Attendee Position Attendee Position