Powercube1000 Installation and Commissioning
Powercube1000 Installation and Commissioning
www.huawei.com
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
1. Installation Preparations
1.1 Tools
Cables of different types must keep a minimum distance of 30 mm from each other. Cables must not be tangled or
twisted.
Cables that are bound together should be close to each other, neat, and free from damage.
Cable ties are bound neatly in the same direction. Cable ties at the same horizontal line must be in a straight line.
The extra part of each indoor cable tie must be cut off. A slack of 5 mm is reserved for each outdoor cable tie. All cut
surfaces have no sharp edges.
After cables are installed, labels or nameplates must be attached to both ends, joints, or turns of the cables.
Cables should be routed away from heat sources, or heat-insulation materials should be added between cables and
heat sources.
Sufficient slack (about 0.1 m recommended) should be provided in cables at turns or the position close to a device,
facilitating cable and device maintenance.
Trap the cable part outside the feeder window according to requirements for the minimum bending radius.
When routing a cable into the room, ensure that a person is assisting you in the room.
Outdoor cables must be routed through a pipe to protect them from being damaged.
AC power cables, transmission cables, and cables buried in the ground must be protected.
If cables at the cabinet bottom need to be routed through a pipe along the ground, the pipe should be routed into
the cabinet base for about 30 mm to 50 mm, but not into the cabinet. The pipe end should be sealed with
waterproof tape or silicon gel, and the pipe should be secured to the cable hole at the cabinet bottom using sheet
metal.
If cables at the cabinet bottom need to be routed through a pipe along a metal cable trough, the pipe should not
be routed into the cabinet base. The cable trough should be sealed and routed through the cable hole at the
cabinet bottom.
Arrange the cables in order in the routing direction, and install cable clips.
The positions for laying out power cables should be in accordance with the design drawing.
If the cable length is insufficient, use another power cable with a sufficient length. No joint or weld is allowed on a
power cable.
Power cables must be routed by only qualified and trained personnel after all preparations are made.
Ground cables in a base station should be connected to the same ground bar.
Ground cables must not be routed in from the overhead. They must be routed underground or indoors.
Both ends of the external conductor of a coaxial cable and the shield layer of a shielded cable should have good
electrical contact with the metal shell of the device they connect to.
Ground cables and signal cables should be bound separately with a proper distance in between to avoid
interference.
All conductive metal components in the shell should properly connect to protection ground terminals.
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
2. Installing ICC
2.1 Installing the ICC330/ESC720
Prerequisites:
• The installation environment is clean and dry.
• The concrete floor on which a cabinet is to be
installed is level.
Step 1 Turn over the packing box, the marking-off
template is shown.
Step 2 Drill holes in the four dots on the position of
mounting holes on the marking-off template.
Step 3 Mark cabinet mounting holes based on the
marking-off template.
Note:
• Install the cabinet according to the actual situation.
• For safety, the lifting ropes for carrying a cabinet should be able to bear a
weight that is more than three times the maximum weight of the cabinet.
• To prevent scraping the cabinet coating, do not use metal lifting ropes
such as steel ropes.
• To avoid friction between the lifting ropes and the cabinet during hoisting,
place protective materials (such as paper and foamed plastics) where the
ropes will contact the cabinet.
the cabinet.
washers.
Ensure that the ground cables are installed securely. If devices are not
properly grounded, damage to devices or personal injury may occur.
If a DG is deployed, connect the DG and ICC cabinet to the same site
ground bar.
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
3. Installing Components
3.1 Component Installation Positions 3.11 Installing an ATS
Step 3 Gently insert the communications expansion module into its slot along the guide rails.
Step 2 Insert the SIM card into the SIM card slot in the communications expansion modules.
Step 2 Remove the filler panel in the NIM02D installation position from the
Step 4 Push the NIM02D in position and secure it with holes aligned.
Step 6 Push the UIM02C into the slot until its front panel is flush with the front panel of the monitoring unit, and tighten the screws.
Step 7 Connect the communications cable delivered with the NIM02D from the FE port on the SMU to the FE CASCADE port on the NIM02D.
Refer to the phase layout when installing PSUs to ensure the balance of phases.
The SSU and BCU can also be installed in the space for modules.
Step 3 Connect the ATS ground cable to the nearest ground bolt or
ground bar.
Step 3 Secure the ACDU equipotential cable to the nearest ground bolt or
ground bar
1. Connect one end of the cable to the SPD terminal on the ACDU.
2. Connect the other end to the DIN6 port on the UIM02C.
interior of the cabinet top. sensor and the other end to the SMOKE port on the user
Step 2 Secure the smoke sensor base to the top of the cabinet by interface module (UIM).
Step 3 Connect the signal cable for the temperature and humidity
Step 7 Connect the other end of the temperature and humidity sensor signal cable to the TEM-HUM port on the UIM02C.
wall.
the bracket, adjust the camera angle, and tighten the screws.
camera cables, and route it to the cable hole at the rear of the camera. ground bar.
Step 4 Connect the camera power cable and install it at the 12 V port on the CIM02C.
Installing power cables (ESC330, using the ESM-48100A1 as an example) Installing power cables (ESC720, using the ESM-48100A1 as an example)
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
4. Installing Cables
4.1 Installing Dry Contact Signal Cables 4.11 Installing Cables for the DCDB48160-2
4.2 Installing the Communications Cables 4.12 Installing DC Input Power Cables
4.13 Installing DC Output Power Cables for the DCDU
4.3 Installing CAN Communications Cables
4.14 Installing PV Module DC Input Power Cables
4.4 Installing DG Cables
4.15 Installing AC Input Power Cables
4.5 Installing a DG Battery Charging Cable (BCU-1203A)
4.6 Installing Cables Between the Battery Cabinet and the ICC Cabinet
Step 3 Check that the signal cable properly connects to the dry contact. Put aside the screwdriver.
on the SMU.
Installing a communications cable (without an SPM01A) Installing a communications cable (without an SPM01A)
SPM01A.
Installing a communications cable (with an SPM01A) Installing a communications cable (with an SPM01A)
Step 1 Insert a SIM card into the SIM card slot in the NIM01C3.
Note:
The SIM card inserted into the 4G communications expansion module (NIM01C3) should support GSM, WCDMA, and FDD standards or GSM, TD-SCDMA,
and TDD standards, and PS (data service) functions enabled.
Note:
Before installing the antenna, remove the plastic shell from the antenna installation
base to ensure magnetic adherence.
Notices:
For single-DG scenarios, connect the DG startup/shutdown and resetting signal cables to the DG1_CTL and RST1 ports
respectively on the GIM01C. Otherwise, power supply to the site may be disconnected.
For dual-DG scenarios, connect the DG 1 startup/shutdown and resetting signal cables to the DG1_CTL and RST1 ports on
the GIM01C, and connect DG 2 startup/shutdown and resetting signal cables to the DG2_CTL and RST2 ports on the
GIM01C.
For dual-DG scenarios, connect the communications cables for DGs 1 and 2 to the male connector of the interconnection
terminal, and connect the other end from the female connector to the COM port on the GIM01C.
(1) DG 1 (2) DG 2
RST1, and COM ports on the GIM01C. PVC corrugated pipe and secure the pipe to a cable hole on the cabinet.
DG_COM DG1_CTL M
DG startup/shut down
signal cable
DG_NC DG1_CTL NC
RST1_NO RST1_NO
DG resetting signal
cable
RST_COM RST1_M
RS+ COM_R+
DG communications
cable
RS- COM_R-
Step 3 Install the air conditioner power cable for the battery cabinet.
1. Locate the air conditioner power cable bound in the ESC720. One end of
the cable is connected before delivery.
2. Connect the other end to the power transfer box for the temperature
control device.
Nine PV modules are used as an example to illustrate the antitheft alarm cable installation.
and connect the other end to the BLVD circuit breaker and RTN+
Step 4 (Optional) In the single-phase scenario, install the short-circuit distribution box to the input terminal on the AC monitoring module.
copper bars available in the fitting bag to the AC input and output Step 6 Connect the AC output power cables from the output
terminals L1, L2, and L3. terminal on the AC monitoring module to the AC input circuit
Step 4 Cover a PVC corrugated pipe over the cable parts outside the
cabinet and secure the PVC corrugated pipe to the cable hole.
Step 2 Secure the positive and negative DC input power cables to the DC input terminals.
Step 2 Secure the negative DC output power cable to the corresponding DC output circuit breaker based on the actual load power.
Step 3 Secure the positive DC output power cable to the corresponding screw on the RTN+ busbar.
Installing DC output power cables (DCDU-400AN5) Installing DC output power cables (DCDU-400AS4)
Step 1 Install DC power cables between SJBs and the PVDU-60A1 Step 2 Install power cables between the SSU and the
1. Prepare a suitable length cable based on site requirements. Install a cord end PVDU, as shown in the following figure.
terminal or an OT terminal on each end of the cable. 1. Connect the blue output power cables from the
2. Secure the negative DC input power cable to the bolt on the PVDU. PVDU to the PV– port.
3. Secure the positive DC input power cable to the circuit breaker on the PVDU. 2. Connect the black output power cables from the
4. Secure the other end to the output terminals on the SJB. PVDU to the PV+ port.
Step 1 Connect DC input power cables between the SJB and the PVDU-200A1.
1. Prepare a suitable length cable based on site requirements. Install a cord end terminal or an OT terminal on each end of the cable.
2. Secure one end of the positive DC input power cable to the screw on the PVDU.
3. Secure one end of the negative DC input power cable to the circuit breaker on the PVDU.
4. Secure the other end of the DC input power cables to the output terminals in the SJB.
Installing cables between the PVDU and the DCDU-400AN5 Installing cables between the PVDU and the DCDU-400AS4
1. Connect the blue output power cable from the PVDU to the PV– port on the SSU.
2. Connect the black output power cable from the PVDU to the PV+ port on the SSU.
Step 4 Cover a PVC corrugated pipe over the cable parts outside the cabinet and secure the PVC corrugated pipe to the cable hole.
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
1. Installation Preparations
2. Installing ICC
3. Installing Components
4. Installing Cables
6. Commissioning
6. Commissioning
6.1 Grid Hybrid Power Supply Solution (Lithium Battery)
Step 1 Measure the input voltage on the AC input circuit breaker. The value should range from 85 V AC to 300 V AC.
Step 2 Switch on the AC input circuit breaker and measure the output voltage of the AC input circuit breaker. The value should range
Step 3 Check that the run indicators on the rectifiers are steady on.
Step 4 Measure the voltage between the –48 V busbar and the RTN+ busbar. The value should range from –42 V DC to –58 V DC.
Step 1 Check whether the RUN indicator on each lithium battery is steady on.
2. If the RUN indicator blinks fast, the ESM fails to communicate with the host.
3. If the RUN indicator is off, check and correct the ESM cable connections. Use a multimeter to measure the voltage at the + and –
output ports of the ESM. Ensure that the voltage is positive and in the range of 43.2 V DC to 56.4 V DC. Replace the ESM if the cable
connections are correct, the battery port voltage is in the range of 43.2 V DC to 56.4 V DC, but the indicator is still off.
Step 2 After Setup Wizard Init is displayed on the LCD, set the following parameters.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 100
6.1 Grid Hybrid Power Supply Solution (Lithium Battery)
Step 13 Set communications parameters-NetEco parameters.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 101
6.1 Grid Hybrid Power Supply Solution (Lithium Battery)
Step 13 Set communications parameters-Set wireless communications parameters.
SIMn User
-
Password
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 102
6.1 Grid Hybrid Power Supply Solution (Lithium Battery)
Step 13 Set communications parameters-Set BBU in-band networking parameters.
Switch on all load circuit breakers one by one. During the process, measure the busbar voltage using a clamp meter after
switching on each circuit breaker. Then continue to switch on another circuit breaker after ensuring that the busbar voltage is
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 103
6.2 Grid + Backup DG Hybrid Power Supply Solution (Lithium Battery)
1. Set the ATS working scenario.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 104
6.2 Grid + Backup DG Hybrid Power Supply Solution (Lithium Battery)
3. Set parameters for the reused DG.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 105
6.2 Grid + Backup DG Hybrid Power Supply Solution (Lithium Battery)
4. Connecting the DG Supply
Checking before power-on
Item Expected Result
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 106
6.2 Grid + Backup DG Hybrid Power Supply Solution (Lithium Battery)
4. Connecting the DG Supply
Step 1 Check that all DG switches and circuit breakers are OFF.
Step 4 Check that the AC output voltage of the DG ranges from 207 V AC to 253 V AC by using a clamp meter.
Step 5 If the DG works properly, switch the DG AC output circuit breaker to ON.
Step 7 Check that the Run indicators on rectifiers are steady on.
Step 8 Check that the voltage between the –48 V busbar and the RTN(+) busbar ranges from –43.2 V DC to –56.4 V DC.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 107
6.2 Grid + Backup DG Hybrid Power Supply Solution (Lithium Battery)
5. Starting a DG Self-Check
Step 1 Set the DG to work in automatic mode.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 108
6.3 Setting IP Camera Parameters
Step 1 Ensure that the PC IP address is in the same network segment as the camera IP address.
If the IP camera has a default IP address of 192.168.0.120, a subnet mask of 255.255.255.0, and
a default gateway of 192.168.0.1, set the IP address to 192.168.0.11, subnet mask to
255.255.255.0, and default gateway to 192.168.0.1 on the PC.
Step 3 Enter https://192.168.0.120 in the PC browser and press Enter to log in to the IP camera.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 109
6.3 Setting IP Camera Parameters
Step 4 Enter the preset user name admin and the preset password HuaWei123 on the login
Step 5 Choose Settings > Network Configuration > Network Parameters, set the following parameters, and click Save.
1. Way to obtain IP: Use the following IP address.
2. IP address, subnet mask, and gateway IP address: obtain the information from the customer.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 110
6.3 Setting IP Camera Parameters
Step 6 Choose Settings > Snapshot Manager > Snapshot
f. Port: 22
h. Password: Changeme
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 111
6.3 Setting IP Camera Parameters
Step 7 Choose Settings > Basic Configuration > Time Configuration, set the following parameters, and click Save.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 112
6.4 Previewing the Real-Time Site Situation
Step 1 Connect a PC to the IP camera and log in to the IP camera.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 113
6.4 Previewing the Real-Time Site Situation
Step 4 After installation is complete, refresh the page and click One push.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 114
6.5 Configuring the IP Camera on the WebUI
Step 1 On the monitoring WebUI of the power system, choose System Settings > IP Camera and set the following parameters:
a. Current User Name, Old Password: Set them to the IP camera user name and password.
IP Camera Number
a. IP Camera Number: 1
Camera IP
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 115
6.6 Viewing Real-time Photos and Alarm Photos on the WebUI
Viewing Real-time Photos
The SMU obtains a real-time photo from the IP camera every 40s (configurable). To view the real-time photos, choose Monitoring >
Camera Group on the WebUI.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 116
6.6 Viewing Real-time Photos and Alarm Photos on the WebUI
To modify parameter settings, choose Monitoring > Camera Group > Camera n > Running Parameter on the WebUI.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 117
6.6 Viewing Real-time Photos and Alarm Photos on the WebUI
To modify parameter settings, choose Monitoring > Camera Group > Camera n > Running Parameter on the WebUI.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 118
6.6 Viewing Real-time Photos and Alarm Photos on the WebUI
Viewing and Exporting Alarm Photos
Choose Query > Camera and view photos saved by the SMU when a door status or infrared sensor alarm is generated onsite.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 119
6.7 Opening an Electronic Door Lock
1. Prerequisites
The following are the prerequisites for opening an electronic lock on the WebUI:
The following are the prerequisites for opening an electronic lock using an access card:
c. You have the access card that matches the electronic door lock.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 120
6.7 Opening an Electronic Door Lock
2. Setting Parameters
Parameter Description Default Value Value Range
Access Card Set this mode to Yes. The access card information
No Yes, No
Authenticated can be recorded onsite.
Start Date Validity start time for the access card. Current time YYYY-MM-DD HH:MM:SS
2069-12-31
Expire Date Validity end time for the access card. YYYY-MM-DD HH:MM:SS
23:59:59
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 121
6.7 Opening an Electronic Door Lock
3. Opening a lock on the WebUI
1. Opening all door locks Choose Monitoring > E-Lock Group > Running Control, set Open All locks to Yes, and click Submit.
2. Opening a single door lock Choose Monitoring > E-Lock Group > Electronic Lock n > Running Control, set Open lock to
Yes, and click Submit.
Step 2 Place the access card near the electronic door lock.
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 122
6.8 Flipping the Commissioning Switch to AUTO
Step 1 Flip the commissioning switch to AUTO.
DCDU-400AS4
DCDU-400AN5
Copyright © Huawei Technologies Co., Ltd. All rights reserved. Page 123
Thank You
www.huawei.com