Scope of Work 2. References 3. Work Methodology: Quality Assurance/Control
Scope of Work 2. References 3. Work Methodology: Quality Assurance/Control
1. SCOPE OF WORK
2. REFERENCES
3. WORK METHODOLOGY
03-30-21
3.1 METHODOLOGY FOR PIPE SLEEVES INSTALLATION
3.2 METHODOLOGY FOR SLAB ON GRADE INSTALLATION
3.3 BALL TEST AND FLOW TEST METHODOLOGY
3.4 METHODOLOGY FOR VERTICAL AND HORIZONTAL PIPES AND SUPPORT INSTALLATION
3.5 VERTICAL AND HORIZONTAL BRACKET SUPPORT
3.6 METHODOLOGY FOR WATERLINE INSTALLATION
3.7 HYDROSTATIC TEST METHODOLOGY
3.8 METHODOLOGY FOR SEWERLINE VENTLINE AND KITCHEN WASTE INSTALLATION
3.9 GRAVITY TEST METHODOLOGY
3.10 METHODOLOGY FOR AIRCON DRAIN INSTALLATION
3.11 FLOW TEST METHODOLOGY
3.12 METHODOLOGY FOR STORM DRAINAGE INSTALLATION
3.13 GRAVITY TEST METHODOLOGY
3.14 SECOND FIX INSTALLATION
3.15 THIRD FIX INSTALLATION
3.16 METHODOLOGY FOR DISINFECTION WATERLINE SYSTEM
4 MAJOR PLANT AND EQUIPMENT
5. QUALITY ASSURANCE/CONTROL
c NOTED
c NOTED WITH COMMENT/S
c FOR RESUBMISSION
Checking done by EDD is to provide additional
comment/s and/or recommendation/s only. Design
consultant shall still be responsible for the submittal final
approval.
21 Apr 22
MJVillanueva DATE:_____________
CHECKED BY:___________________
The Sanitary / Plumbing System for Park McKinley West shall cover the supply and Installation
materials based strictly on Bid Documents, Plans, Technical Specification, General Conditions and
other documents.
2 REFERENCES
3 WORK METHODOLOGY
1. Excavate from finish floor line below grade as per approved plan or actual site condition
based on existing Drainage Line.
2. Place saddle to maintain the 1% slope of the embedded pipes at every 1.50 meters clear
distance.
3. Prepare Gravel beddings for embedded pipe to resist the vibration during compaction.
4. Layout PVC, Perforated Pipe or RC Pipe along the line and grade on the top of sand
beddings. Fit the pipe on the shape of the saddle provided. Maintain 1% slope on pipe.
5. For Perforated Pipe, maximum seepage action shall be ensured by wrapping the pipes
With sufficient and approved filter cloth surrounded by ¾” gravel.
6. The exposed pipes, fittings and joints couplings should be visually inspected and
examined.
1. All embedded piping system shall conduct testing before backfilling proceed.
2. Provide opening in every stub out provided with a height of 1m, to be filled with water.
Prepare Ping-Pong ball and a drum full of water for the Flow Test to be conducted.
3. Pour water in the stub out provided to test the system this is to ensure that piping is
free for foreign matters inside, and outfall has to be cleared of obstruction.
4. Drop the Ball signed by the Inspector in every Stub out provided and filled it with water
simultaneously to push the Ping-Pong Ball going to the outlet of the main line. If the ball
does not come out, the slope of the main line does not meet the required 1% slope to
discharge the water from the system.
5. Repair and Re-test if there are any defects or leak.
6. The QA/QC and Inspector must witness the on-going testing.
7. After pipe has been tested, inspected and approved by the engineer, back filling must
proceed. Placed un-suitable back filling materials.
Installation of Vertical for Soil Stack used HDPE and Horizontal Pipes used PVC. Down Spout,
Vent stack, Vent line for sanitary line used PVC Pipe. G.I and PPR Pipe are used for Water
line Riser and supply.
1. During Installation of pipes support and hangers are needed to hold the pipe while
installing. This is to avoid movement of the pipes to be installed. Hangers are used to the
pipe installed horizontally with maximum of 1.5 space while bracket and braces to the
pipe installed vertically. The space for adjustable wrought iron and malleable iron pipe is
3.0m apart. While hub less, bell and spigot soil pipe hanger spaced not over 1.3m apart
and located near the hub. For vertical pipe bracket spaced not more than 9m apart.
2. The arrangement, position and connection of all pipes, drains, and valve must be checked
before tapping.
a. Fo r tapping PVC cement solvent are used to connect pipes. Provide stub out for
clean out, sanitary line, vent line etc.. While upon installation of waterline welding
machine or Fusion machine are used to unite the pipes. Plug out the end of the
pipe.
b. In using Cast Iron Pipe, Stainless Coupling with gasket is used as a joint connection
Of the pipe. It should be properly tightened to avoid leak at the joints.
c. F o r FCU drain pipe, Rubber insulation with blue tape is applied to absorb the
moisture content.
d. All stacks shall be anchored on walls and columns using the required support or
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 3
<PARK MCKINLEY WEST>
Braces. Plumbness of all exposed downspouts shall be observed and check.
e. For horizontal pipe make sure that the minimum of 1% slope are maintain, this is
to ensure easy circulation of the system.
1. Installation of waterline roughing-ins starts after the line & grade, zocalo and masonry wall
has been layout at toilet & bath.
2. Established the elevation and exact location of cold water stub-outs thru marking of paint at
Wall.
After the marking has been established, proceed with the cutting and then chipping of wall with
appropriate permit. Width and depth depending on the sizes of pipe to be installed and for
waterline not to expose on wall.
4. Install all water line roughing-ins based on approved plans, shop drawings and
Specifications.
5. Provided with the approved support on water lines above ceiling.
6. Consider the distance of hanger support base on the manufacturer’s specification.
7. Provide pipe sleeve on pipeline passing thru wall.
8. Conduct inspection & punch listing.
9. Close-out of punch list.
10. Initial hydrostatic pressure testing is conducted after roughing-ins is finished to determine
leaks on pipes and fitting connections. If ever there’s a leak determined, repair immediately
and re-test until such portion has satisfactory passed the test.
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 4
<PARK MCKINLEY WEST>
11. Prepare the area for final inspection and testing with corresponding inspection and testing
Documents. (See testing procedure)
12. After the inspection and testing has satisfactory passed and approved by the Construction
Management and Third Party, proceed with the restoration of wall.
13. Ensure to have plug at every stub-out to prevent damage and clogging of waterlines.
1. Ensure that all block-outs at Meter Room are acceptably finished before installation.
2. Prepare approved bracket that will hold & support the vertical pipeline.
3. Install water riser & down feed base on approved drawing & specification. Provide pipe
sleeve on every floor.
4. Tighten all bolts & nuts to support & hold the pipeline in place. Paint all welded joints with
primer paint to prevent from rusting.
5. Conduct inspection & punch listing.
6. Close-out of punch list.
7. Conduct initial testing to determine leaks at welded joints and connections. If ever there’s a
leak determined, repair immediately and re-test until such portion has satisfactory passed
the test.
8. Prepare the pipeline for final inspection and testing. Final inspection & testing for cold water
riser & down feed is conducted at every ten (10) floors. (see testing procedure)
9. After the final inspection & testing passed and approved by general contractor , proceed
with the final painting of all pipeline with approved colors base on specification.
10. Ensure to have proper plug or protection at every open end of the pipeline to
prevent foreign objects from falling inside that might cause clogging.
3.7 H Y D R O S T A T I C TEST
TOILETS
INSTALLATION A. ROUGHING-INS
1. Line and grade must first be established on the area as reference for installation of vent line
roughing-ins on wall.
2. After the layout of vent line roughing-ins, zocalo and masonry wall may proceed with the layout.
3. Established working point for tile layout as reference for the exact location of sewer and kitchen
stub-outs, floor drain and clean-out base on approved tile layout.
4. Determine the slope, elevation and exact location of the pipeline. Take into consideration all
pipe crossing and utilities in establishing the elevation to avoid interference in the piping
installation.
5. Establish the elevation and exact location of the pipeline. Install hangers and sway braces to
support and hold the pipeline in place following the required spacing for the support and
hangers. Use approved masonry anchors, inserts, hangers and braces.
6. Install the pipe and tighten all hangers, bolts and nuts to secure the pipeline in place. Hangers
and braces should not be spaced at more than three (1.5) meters apart.
7. Provide pipe sleeve on pipeline passing thru wall.
8. Removed PVC sleeves and install floor drain body. Restore the floor slab including overhead
restoration of slab.
9. Conduct inspection and punch listing with general contractor’s representative.
10. Close-out of punch list.
11. Conduct initial gravity leak test to determine leak on pipe connection. If ever there are leak
found repair immediately and re-test until such portion has satisfactory passed the test.
12. Prepare the area for final inspection and testing provided with the necessary inspection &
Testing documents. (See testing procedure)
13. After the inspection and testing has satisfactory passed and approved by general contractor, water
proofing and tile setter may proceed with their trade.
14. Ensure that all drains have plug to prevent clogging on pipeline.
1. Ensure that all pipe chases are acceptably finished before installation.
2. Determine exact location of pipeline to be installed according to approved plans & specification.
Consider all other pipes & utilities that may cause conflict prior to the installation.
3. Install sway braces, brackets & floor anchors to support and hold the pipeline in place.
4. Install the pipeline and tighten all brackets, bolts & nuts to secure the pipeline in place.
5. Ensure to fit all connections. Vertical pipeline shall be plumb & straight.
6. Conduct inspection & punch listing with MC and BV representative.
7. Close-out of punch list.
8. Conduct initial testing to determine leaks on pipes & its connection. If there’s leak determined,
Repair and retest with the same procedure until such portion is satisfactory passed the test.
9. Prepare for final inspection and testing (See testing procedure).
10. After the final inspection & testing passed and approved by MC and BV, provide tagging
And retouch all damage paint.
11. Ensure that all open end of the pipe have plug or cover to prevent foreign objects from falling
inside pipeline that might cause clogging.
3.9 G R A V I T Y TEST
KITCHEN WASTE
INSTALLATION A. ROUGHING-INS
1. Determine the slope, elevation and exact location of the pipeline. Take into consideration all
pipe crossing and utilities in establishing the elevation to avoid interference in the piping
installation.
2. Establish the elevation and exact location of the pipeline. Install hangers and sway braces to
support and hold the pipeline in place following the required spacing for the support and
hangers. Use approved masonry anchors, inserts, hangers and braces.
3. Install the pipe and tighten all hangers, bolts and nuts to secure the pipeline in place. Hangers
and braces should not be spaced at more than three (1.5) meters apart.
4. Provide pipe sleeve on pipeline passing thru wall.
5. Conduct inspection and punch listing with MC and BV representative.
6. Close-out of punch list.
7. Conduct initial flow test to determine leak on pipe connection. If ever there are leak found
repair immediately and re-test until such portion has satisfactory passed the test.
8. Prepare the area for final inspection and testing provided with the necessary inspection &
Testing documents. (See testing procedure)
9. Ensure that all stub-outs have plug to prevent clogging on pipeline
1. Provide opening in every stub out to be filled with water. Prepare drum full of Water for the
Flow Test to be conducted.
2. Pour water in the stub out provided to test the system this is to ensure that piping is free for
foreign matters inside, and outfall has to be cleared of obstruction.
3. Fill the stub-out with water simultaneously going to the outlet of the main line. If the water
Does not come out, the slope of the main line does not meet the required 1% slope to discharge
the water from the system.
4. Repair and Re-test if there are any defects or leak.
5. The QA/QC and Inspector must witness the on-going testing.
6. After pipe has been tested, inspected and approved by the engineer, ensure that all stub-outs
have plug to prevent clogging on pipeline.
1. Determine the slope, elevation and exact location of the pipeline. Take into consideration all
pipe crossing and utilities in establishing the elevation to avoid interference in the piping installation.
2. Establish the elevation and exact location of the pipeline. Install hangers and sway braces to
support and hold the pipeline in place following the required spacing for the support and hangers.
Use approved masonry anchors, inserts, hangers and braces.
3. Install the pipe and tighten all hangers, bolts and nuts to secure the pipeline in place.
4. Provide pipe sleeve on pipeline passing thru wall.
5. Removed PVC sleeves and install roof drains, deck drains, canopy drains & trench drains.
Restore the floor slab including overhead restoration of slab.
6. Conduct inspection and punch listing with MC and BV representative.
7. Close-out of punch list.
8. Conduct initial gravity leak test to determine leak on pipe connection. If ever there are leak
found repair immediately and re-test until such portion has satisfactory passed the test.
9. Prepare the area for final inspection and testing provided with the necessary inspection &
Testing documents. (See testing procedure)
10. After the inspection and testing has satisfactory passed and approved by MC and BV, water
proofing and tile setter may proceed with their trade.
11. Ensure that all drains have plug to prevent clogging on pipeline.
B. DOWNSPOUTS
1. Ensure that all pipe chases are acceptably finished before installation.
2. Determine exact location of pipeline to be installed according to approved plans & specification.
Consider all other pipes & utilities that may cause conflict prior to the installation.
3. Install sway braces, brackets & floor anchors to support and hold the pipeline in place.
4. Install the pipeline and tighten all brackets, bolts & nuts to secure the pipeline in place.
5. Ensure to fit all connections. Vertical pipeline shall be plumb & straight.
6. Conduct inspection & punch listing with general contractor’s representative (Construction
Management).
7. Close-out of punch list.
8. Conduct initial testing to determine leaks on pipes & its connection. If there’s leak determined,
Repair and retest with the same procedure until such portion is satisfactory passed the test.
9. Prepare for final inspection and testing (See testing procedure).
10. After the final inspection & testing passed and approved by general contractor, provide tagging
and retouch all damage paint.
11. Ensure that all open end of the pipe have plug or cover to prevent foreign objects from falling
Inside pipeline that might cause clogging.
3.13 G R A V I T Y TEST
METHODOLOGY A. COLLECTOR
PIPES
B. DOWNSPOUT
1. Ensure that all toilets are acceptably finished (painting works & tile installation). Request for
hand-over of the area.
2. Prepare the area for installation of plumbing fixtures. (Install floor flange for water closet, wall
Supports for lavatory & sand bedding for bath tub)
3. Install all plumbing fixtures with the approved model on designated toilets. Apply sealant on
water closet, lavatory & bath tub.
4. Conduct a joint inspection and punch listing
5. Close-out of punch list.
6. Conduct initial flushing of plumbing fixture.
7. Testing and commissioning of plumbing fixtures.
C PROCEDURE
1. Toilet bowl / water closet
Put ½ roll of tissue paper on the bowl. Flush the water closet and check the
draining time.
Draining time: min. of 3 sec.
max. of 10 sec.
2. Lavatory
Fill the bowl with water. Open the pop-up or plug and drain water and check
Draining time: min. of 20 sec.
max. of 45 sec.
3. Urinal
Put rubber plug into the drain to hold the water and fill up with water. Unplug to
release water and check the draining time. Draining time: min. of 3 sec. max. of 8 sec.
Objective to disinfect the entire water system with a dosage of75ppm (paths per million).
WARNING
1. Use safety goggles when handling chlorine.
2. Deal with chlorine in an open space to avoid suffocation.
3. Water used in the disinfection process should not be used for drinking but excellent for
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 11
<PARK MCKINLEY WEST>
cleaning purposes like bathrooms and kitchen utensils.
MATERIAL TO BE USE
1. Close all isolation valve and drain Valve of domestic water tank.
2. Fill the domestic tank with water up to its full capacity.
3. On separate container, dissolve a solution of calcium Hypochlorite (Chlorine) into water
with exact dosage.
4. Mix the solution to the water in the domestic tank.
5. Let the tank soak with chlorine at least 24 hours.
6. After 24 hours pump up the solution of water and chlorine to elevated tank and let the
elevated tank soak for at least 24 hours. Suspend the distribution of water by closing the
isolation valve of distribution system.
7. Open the isolation valve to distribution system to flush the chlorinated water to piping
system.
8. Open the isolation valve at every floor/unit to flush chlorinated water to the system,
wait until the elevated tank is empty.
9. Get water sample of piping system , domestic tank and elevated tank for potability test
10. Refill the water tank and return for operation.
DOSAGE
1. Chipping gun
2. Grinder
3. Rotary Hammer
4. Speed Cutter
5. Welding Machine
6. Fusion Machine
7. Heat Gun
8. Scaffolding
9. Chain Vice
10. Threading Machine
11. Manual/ Pressurized Test Pump
12. Press Drill
QUALITY ASSURANCE/CONTROL
➢ QA/QC program addresses specific quality assurance and quality control testing
requirements for each and various components of systems based on the intended designed
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 12
<PARK MCKINLEY WEST>
of construction. During construction, required documents will provided as supporting
documents prior to project hand- over and related construction certification report. The team
will solely participate in the quality assurance function and perform multiple
responsibilities with regards to QA/QC.
7.1 TESTS
a. Ball test
b. Flow Test
c. Hydrostatic test
d. Gravity test
e. Testing and Commissioning
f. Disinfection for Domestic and Elevated tank
1. Tape Measure
2. Pressure Gauge
3. Water Meter
4. Stop Watch
7.3 INSPECTIONS
1. Materials Inspection
2. Line Check Inspection
3. Visual Inspection
1. Subcontractor
2. General contractor (DDTKI) QA/QC
3. Third Party
B. DOWNSPOUTS
1. Ensure that all pipe chases are acceptably finished before installation.
2. Determine exact location of pipeline to be installed according to approved plans & specification.
Consider all other pipes & utilities that may cause conflict prior to the installation.
3. Install sway braces, brackets & floor anchors to support and hold the pipeline in place.
4. Install the pipeline and tighten all brackets, bolts & nuts to secure the pipeline in place.
5. Ensure to fit all connections. Vertical pipeline shall be plumb & straight.
6. Conduct inspection & punch listing with general contractor’s representative (Construction
Management).
7. Close-out of punch list.
8. Conduct initial testing to determine leaks on pipes & its connection. If there’s leak determined,
Repair and retest with the same procedure until such portion is satisfactory passed the test.
9. Prepare for final inspection and testing (See testing procedure).
10. After the final inspection & testing passed and approved by general contractor, provide tagging
and retouch all damage paint.
11. Ensure that all open end of the pipe have plug or cover to prevent foreign objects from falling
Inside pipeline that might cause clogging.
3.13 G R A V I T Y TEST
METHODOLOGY A. COLLECTOR
PIPES
B. DOWNSPOUT
1. Ensure that all toilets are acceptably finished (painting works & tile installation). Request for
hand-over of the area.
2. Prepare the area for installation of plumbing fixtures. (Install floor flange for water closet, wall
supports for lavatory & sand bedding for bath tub)
3. Install all plumbing fixtures with the approved model on designated toilets. Apply sealant on
water closet, lavatory & bath tub.
4. Conduct a joint inspection and punch listing
5. Close-out of punch list.
6. Conduct initial flushing of plumbing fixture.
7. Testing and commissioning of plumbing fixtures.
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 15
<PARK MCKINLEY WEST>
3.15 T H I R D FIX INSTALLATION
C PROCEDURE
1. Toilet bowl / water closet
Put ½ roll of tissue paper on the bowl. Flush the water closet and check the
draining time.
Draining time: min. of 3 sec.
max. of 10 sec.
2. Lavatory
Fill the bowl with water. Open the pop-up or plug and drain water and check
Draining time: min. of 20 sec.
max. of 45 sec.
3. Urinal
Put rubber plug into the drain to hold the water and fill up with water. Unplug to
release water and check the draining time. Draining time: min. of 3 sec. max. of 8 sec.
Objective to disinfect the entire water system with a dosage of75ppm (paths per million).
MATERIAL TO BE USE
1. Close all isolation valve and drain Valve of domestic water tank.
2. Fill the domestic tank with water up to its full capacity.
3. On separate container, dissolve a solution of calcium Hypochlorite (Chlorine) into water
with exact dosage.
4. Mix the solution to the water in the domestic tank.
5. Let the tank soak with chlorine at least 24 hours.
6. After 24 hours pump up the solution of water and chlorine to elevated tank and let the
elevated tank soak for at least 24 hours. Suspend the distribution of water by closing the
isolation valve of distribution system.
7. Open the isolation valve to distribution system to flush the chlorinated water to piping
System.
8. Open the isolation valve at every floor/unit to flush chlorinated water to the system,
wait until the elevated tank is empty.
9. Get water sample of piping system, domestic tank and elevated tank for potability test
10. Refill the water tank and return for operation.
DOSAGE
1. Chipping gun
2. Grinder
3. Rotary Hammer
4. Speed Cutter
5. Welding Machine
6. Fusion Machine
7. Heat Gun
8. Scaffolding
9. Chain Vice
10. Threading Machine
11. Manual/ Pressurized Test Pump
12. Press Drill
ROUGHING INS Procedure – Plumbing, Sanitary & Drainage System Page 17
<PARK MCKINLEY WEST>
5. QUALITY ASSURANCE/CONTROL
➢ QA/QC program addresses specific quality assurance and quality control testing
requirements for each and various components of systems based on the intended designed
of construction. During construction, required documents will provided as supporting
documents prior to project hand- over and related construction certification report. The team
will solely participate in the quality assurance function and perform multiple
Responsibilities with regards to QA/QC.
5.1 TESTS
a. Ball test
b. Flow Test
c. Hydrostatic test
d. Gravity test
e. Testing and Commissioning
f. Disinfection for Domestic and Elevated tank
1. Tape Measure
2. Pressure Gauge
3. Water Meter
4. Stop Watch
5.3 INSPECTIONS
1. Materials Inspection
2. Line Check Inspection
3. Visual Inspection
1. Subcontractor QA/QC
2. General contractor (DDTKI) QA/QC
3. Third Part