Highway Engineering
Highway Engineering
LEVELLING
BS IS FS HPC R. L ADJ. R. CHAINAGE REMARKS
LEVEL
4.500 74.500 70.000 TBM= 70.0
4.130 70.370 70.344 0+000
3.489 71.011 70.986 0+020
2.958 71.542 71.516 0+040
2.089 72.411 72.385 0+060
0.750 73.750 73.724 0+080
4.585 0.785 78.300 73.715 73.664
3.039 75.261 75.210 0+100
2.049 76.253 76.202 0+120
3.845 1.070 81.075 77.230 77.153
2.590 78.485 78.408 0+140
1.870 79.205 79.128 0+160
1.490 79.585 79.508 0+180
1.509 79.566 79.489 0+200
1.657 79.418 79.341 0+220
1.980 79.095 79.018 0+240
2.085 78.990 78.913 0+260
1.889 79.186 79.109 0+280
1.360 79.715 79.638 0+300
0.829 80.246 80.169 0+320
0.440 80.635 80.558 0+340
0.229 80.846 80.769 0+360
0.220 80.855 80.778 0+380
0.450 80.625 80.548 0+400
0.455 80.620 80.543 0+420
0.400 80.675 80.598 0+440
0.669 80.406 80.329 0+460
0.320 0.700 80.695 80.375 80.273
0.890 79.805 79.703 0+480
1.779 78.916 78.814 0+500
2.249 78.446 78.345 0+520
2.490 78.205 78.103 0+540
2.840 77.855 77.753 0+560
3.560 77.135 77.033 0+580
1.370 3.590 78.475 77.105 76.977
2.685 75.790 75.662 0+600
2.700 75.775 75.647 0+620
BS IS FS HPC R. L ADJ. R. CHAINAGE REMARKS
LEVEL
0.340 78.135 78.007
2.710 0.310 80.875 78.165 78.011
0.340 80.535 80.381
1.089 0.365 81.599 80.510 80.331
2.208 79.391 79.212
2.510 79.089 78.910
0.165 2.590 79.174 75.009 74.804
4.059 75.115 74.910
0.055 4.169 75.060 70.005 69.775
4.500 70.560 70.330
4.830 70.230 70.000 TBM= 70.0
HPC= BS + RL
Arithmetic checks
∑ BS -∑ FS =Last RL -First RL
18.639-18 .409 = 70.230-70.00
0.23 – 0.23
Misclosure = 0.23
For adjustment;
misclosure
e= where n = number of BS
n
0.23
e=
9
e = 0.0256
Adjusted R.L = R.L – e
B (78.5) m B(78.5)m
+p
-q
A (75.7) m A(72.3)m
TANGENT ELEVATION
PVC + P×X
i. 81.56 + (0.0396×0.00) = 81.56
ii. 81.56 + (1.36×0.0396) = 81.61
iii. 81.56 + (0.0396×21.36) = 82.13
iv. 81.56 + (0.0396×41.36) = 83.20
v. 81.56 + (0.0396×52.72) = 83.65
VERTICAL OFFSET
q−p 2
Y= ×x
2L
−0.0263−0.0396
i. ×(0)2 = 0
2(52.72)
−0.0263−0.0396
ii. ×(1.36)2 = -0.0012
2(52.72)
−0.0263−0.0396
iii. ×(21.36)2 = -0.285
2(52.72)
−0.0263−0.0396
iv. ×(41.36)2 = -1.069
2(52.72)
−0.0263−0.0396
v. ×(52.72)2 = -1.737
2(52.72)
CURVE ELEVATION
T.E + Offset
i. 81.56+0.00 =81.56
ii. 81.61 – 0.0012 = 81.61
iii. 82.41 – 0.285 = 82.13
iv. 83.20 – 1.069 = 82.13
v. 83.65 – 1.737 = 81.91
OBSERVATIONS
The moisture content in the soil sample dried up and was placed in the oven for
24hours under 115o C temperature.
Mass of the soil sample reduced from 1784.9g to 1483.2g. Thus, the difference of
301.7g in weight.
The dried sample was passed through various sieves and the mass recorded are as fellows;
Sieve size (mm) Mass of passing % Mass of retained (g)
10 1288.5 199.7
4.75 1090.6 192.9
2.36 984.4 106.2
1.18 917.3 67.1
0.60 851.5 65.8
0.425 780.6 70.9
0.30 576.1 204.5
0.150 95.4 480.7
0.75 13.9 81.5
For % Retained;
Mass retained
Percentage retained = ×100 %
total mass retained
Total mass retained = 1469.3g
199.7
% Retained in 10mm sieve = ×100 %
1469.3
= 13.591%
192.9
% Retained in 4.75mm sieve = ×100 %
1469.3
= 13.129%
106.2
% Retained in 2.36mm sieve = ×100 %
1469.3
= 7.228%
67.1
% Retained in 1.18mm sieve = ×100 %
1469.3
= 4.567%
65.8
% Retained in 0.60mm sieve = ×100 %
1469.3
= 4.478%
70.9
% Retained in 0.425mm sieve = ×100 %
1469.3
= 4.825%
204.5
% Retained in 0.30mm sieve = ×100 %
1469.3
= 13.918%
480.7
% Retained in 0.150mm sieve = ×100 %
1469.3
= 32.716%
81.5
% Retained in 0.075mm sieve = ×100 %
1469.3
= 5.547%
For % Passing
Percentage Passing = 100 – percentage retained
% Passing 10mm = 100 – 13.591 =86.409 %
% Passing 4.75mm = 86.409 – 13.129= 73.280%
% Passing 2.36mm = 73.280 – 7.228 = 66.052%
% Passing 1.18mm = 66.052 – 4.567 = 61.485%
% Passing 0.60mm = 61.485 – 4.478 = 57.007%
% Passing 0.425mm = 57.007 – 4.825 = 52.182%
% Passing 0.30mm = 52.182 – 13.918 = 38.264%
% Passing 0.150mm = 38.264 – 32.716 = 5.548%
% Passing 0.075mm = 5.548 – 5.47 = 0.001%
Sieve size (mm) Mass of retained (g) % Retained (%) % Passing (%)
10 199.7 13.591 86.409
4.75 LANE DAY 1
192.9 DAY 2
13.129 TOTAL 73.280
2.36 Lane 1 106.2431 4547.228 885 66.052
1.18 Lane 2 67.1314 3754.567 689 61.485
0.60 65.8 4.478 57.007
0.425 70.9 4.825 ∑ ¿1574
52.182
0.30 204.5 13.918 38.264
0.150 480.7 32.716 5.548
0.75 81.5 5.547 0.001
TRAFFIC COUNTS
For pickups;
79+64
Average number of pickups = =71.5=72 pickups
2
24hours volume =72×H.E. F
= 72×1.4 = 108
108× D . E . F
ADT =
7
108× 6.9
=
7
= 106.5
AADT = ADT×M.E. F
= 106.5×0.5
= 53.25
From the growth rate of Ghana in the year 2019 is 6.5% (worldbank.org)
n
(1+r ) −1
Fg =
r
R= 6.5% and n = 10
10
(1+0.065) −1
Fg =
0.065
Fg = 13.49
FORMATION LEVEL
1m = 1000mm
X = 275mm
275 mm× 1 m
X=
1000 mm
X = 0.275m
Finished Level = Pavement thickness + Formation level
= 2614.985m3
Total volume of fill = Fill (A) + fill (B) +fill (C)
= 265.848m3+ 1885.23m3+ 35.287m3
= 2186.365m3