Specification For Inspection, Flushing and Testing of Piping System (HydroTesting)
Specification For Inspection, Flushing and Testing of Piping System (HydroTesting)
CAIRN-TSG-L-SP-0012
REVISION RECORD
Revision Philosophy
All revisions for review will be issued at A1, with subsequent A2, A3, etc as required.
All revisions approved for issue or implementation will be issued at B1, with subsequent B2, B3, etc as
required.
All revisions approved for issue or design and construction will be issued at C1, with subsequent C2, C3,
etc as required.
Narrative sections revised from previous pprove issues are to be noted in the table below and/or
highlighted using the appropriate revision status thus: | A2
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas
and by the use of a triangle containing the revision status.
Revision History
CONTENTS
1.0 SCOPE 4
2.0 REFERENCES 4
3.0 INSPECTION 4
4.0 FLUSHING 4
1.0 SCOPE
This specification covers the general requirement for inspection, flushing and testing of piping systems.
However, testing of steam lines falling under IBR shall also be governed by Indian Boiler Regulations.
Flushing and testing of all piping systems shall be witnessed by the Engineer-In-Charge.
2.0 REFERENCES
ASME B31.3 Process Piping
IBR: Indian Boiler Regulations
3.0 INSPECTION
During various stages and after completion of fabrication and erection, the piping system shall be inspected
by the Engineer-In-Charge to ensure that:
- Proper piping material has been used.
- Piping has been erected as per drawings and instructions of Engineer-In-Charge.
- All supports have been installed correctly.
- Test preparations mentioned in this specification have been carried out.
4.0 FLUSHING
Flushing of all lines shall be done before pressure testing.
Flushing shall be done by 'fresh potable water' or by 'dry compressed air wherever water flushing is not
desirable to clean the pipe of all dirt, debris or loose foreign material.
Required pressure for water flushing shall meet the fire hydrant pressure or utility water pressure. For air
flushing, the line/system shall be pressurized by compressed air at the required pressure which shall be 50
psi maximum. The pressure shall then be released by quick opening of a valve, already in line or installed
temporarily for this purpose. This procedure shall be repeated as many times as required till the inside of the
pipe is fully cleaned. In line instruments like control valves, orifice plates, rotameters, safety valves and other
Instruments like thermowells which may interfere with flushing shall not be included in Flushing circuit
The screens/meshes shall be removed from all permanent strainers before flushing. Screens/meshes shall be
reinstalled after flushing but before testing.
During flushing temporary strainers shall be retained. These shall he removed, cleaned and reinstalled after
flushing, but, before resting.
In case any equipment such as vessel, exchanger etc. form part of a piping circuit during flushing, this shall
be done with the approval of Engineer-In-Charge. However, equipment’s thus included in the circuit shall be
completely drained and dried with compressed air after flushing is completed.
During flushing discharged water/air shall be drained to the place directed by the Engineer-In-Charge. If
necessary, proper temporary drainage shall be provided by the contractor. Care shall be taken during flushing
so as not to damage/spoil work of other agencies. Precautions shall also be taken to prevent entry of
water/foreign matter into equipment’s, electric motors, instruments, electrical installations etc. in the vicinity of
lines being flushed.
The contractor shall carry out all the activities required before, during and after the flushing operation, arising
because of flushing requirements, such as but not limited to the following:
Dropping of valves, specials, distance pieces, inline instruments and any other piping part before flushing.
The flanges to be disengaged for this purpose shall be envisaged by the contractor and approved by the
Engineer-In-Charge. These flanges shall be provided with temporary gaskets at the time of flushing.
After flushing is completed and approved, the valve distance pieces, piping specials etc. shall be reinstalled
by the contractor with permanent gaskets. However, flanges at equipment nozzles and other places where
isolation is required during testing, only temporary gaskets shall be provided.
Records in triplicate shall be prepared and submitted by the contractor for each piping system for the flushing
done in the proforma provided/approved by the Engineer-in-Charge.
With the exclusion of instrumentation, piping systems fabricated or assembled in the field shall be tested
irrespective of whether or not they have been pressure tested prior to site welding or fabrication.
To facilitate the testing of piping systems, vessels and other equipment’s may be included in the system with
the prior approval of Engineer-In-Charge if the test pressure specified is equal to or less than that for the
vessels and other equipment’s. Pumps, compressors and other rotary equipment’s shall not be subjected to
field test pressure. Lines which are directly open to atmosphere such as vents, drains, safety valves
discharge need not be tested, but all joints shall be visually inspected. Wherever necessary, such lines shall
be tested by continuous flow of fluid to eliminate the possibility of blockage. However, such lines if provided
with block valve shall be pressure tested up to the last block valve.
Seats of all valves shall not be subjected to a pressure in excess of the maximum cold working pressure of
the valve. Test pressure applied to valves shall not be greater than the manufacturer's recommendation nor
less than that required by the applicable code. Where allowable seat pressure is less than test pressure, test
shall be made through an open valve.
Instruments in the system to be tested shall be excluded from the test by isolation or removals, unless
approved otherwise by the Engineer-In-Charge.
Restrictions which interfere with filling, venting, draining such as orifice plates etc. shall not be installed unless
testing is complete.
Control valves shall not be included in the test system. Where bypasses are provided test shall be performed
through the bypass and/or necessary spool shall be used in place of the control valve.
Pressure gauges which are part of the finished system, but cannot withstand test pressure shall not be
installed until the system has been tested. Where piping systems to be tested are directly connected at the
battery limits to piping for which the responsibility rests with other agencies, the piping to be tested shall be
isolated from such piping by physical disconnection such as valve or blinds.
x pH : 6.5 to 10.5
x Total dissolved Solids : less than 30 Kg/m³
x H2S : Max. 0.001 Kg/m³
x Suspended Solids : 0.005 Kg/m³
x Appearance/Turbidity : Clear with no visible sediment
Air shall be used for testing only if water would cause corrosion of the system or overloading of
supports etc. in special cases as directed by Engineer-in-Charge.
Defects, if any, noticed during testing shall be rectified immediately and retesting of the system (line shall be
done by the contractor at his cost.
A complete and accurate record shall be endorsed and kept by the company and certifying authority as
necessary for each spool and system tested. It shall include: