External Hazards Document Type: Unique Document ID and Revision No: Date Issued: Review Date: Prepared By: Approved By: Record Reference
External Hazards Document Type: Unique Document ID and Revision No: Date Issued: Review Date: Prepared By: Approved By: Record Reference
ONR GUIDE
External Hazards
NS-TAST-GD-013
TRIM Ref: 2020/227479 Page 1 of 84
Office for Nuclear Regulation
TABLE OF CONTENTS
LIST OF ABBREVIATIONS.......................................................................................................3
1 INTRODUCTION.........................................................................................................5
2 PURPOSE AND SCOPE.............................................................................................6
2.1 Documents Supporting TAG 13...................................................................................7
2.2 Definition and Major Features of External Hazards......................................................9
2.3 Scope of External Hazards Assessment....................................................................10
2.4 Characterising External Hazards...............................................................................12
2.5 Plant Response to External Hazards.........................................................................13
3 RELATIONSHIP TO LICENCE AND OTHER RELEVANT LEGISLATION................15
4 RELATIONSHIP TO SAPS, WENRA REFERENCE LEVELS AND IAEA SAFETY
STANDARDS............................................................................................................. 19
5 ADVICE TO INSPECTORS.......................................................................................23
5.1 Overview of External Hazards Analysis Tasks...........................................................23
5.2 Hazard Identification..................................................................................................23
5.3 Fault Identification (Fault Initiation) and External Hazards Screening........................24
5.4 Hazard Analysis.........................................................................................................25
5.5 Design Basis Analysis for External Hazards..............................................................26
5.6 Probabilistic Safety Analysis for External Hazards.....................................................37
5.7 Severe Accident Analysis for External Hazards.........................................................38
5.8 Special Considerations Relevant to Safety Analysis of External Hazards..................38
5.9 Emergency Preparedness.........................................................................................50
5.10 Post External Hazards Event Operations...................................................................51
6 REFERENCES.......................................................................................................... 52
TABLE 1 – CATEGORIES OF EXTERNAL HAZARDS...........................................................57
TABLE 2 – EXTERNAL HAZARDS RELEVANT TO NUCLEAR SITES IN THE UK*...............58
TABLE 3 – INTERFACES BETWEEN EXTERNAL HAZARDS AND OTHER DISCIPLINES. .60
TABLE 4 – COMPARISON WITH WENRA REFERENCE LEVELS........................................61
TABLE 5 – IAEA SAFETY GUIDES REFERENCED IN TAG 13.............................................68
TABLE 6 – EXAMPLE SCREENING CRITERIA FOR COMBINATIONS OF EXTERNAL
HAZARDS*................................................................................................................ 70
APPENDIX 1 – POST-FUKUSHIMA UPDATES TO THE SAPS AND RELEVANT GOOD
PRACTICE................................................................................................................. 71
APPENDIX 2 – ELECTROMAGNETIC INTERFERENCE AND SPACE WEATHER...............75
APPENDIX 3 – BIOLOGICAL HAZARDS................................................................................80
APPENDIX 4 – INDUSTRIAL HAZARDS................................................................................81
APPENDIX 5 – LANDSCAPE CHANGE..................................................................................83
APPENDIX 6 – EXTERNAL HAZARDS RESULTING FROM NATURALLY AND
ANTHROPOGENICALLY OCCURRING GASES......................................................84
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 2 of 84
Office for Nuclear Regulation
LIST OF ABBREVIATIONS
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 3 of 84
Office for Nuclear Regulation
RP Requesting Party
SAA Severe Accident Analysis
SAMG Severe Accident Management Guideline
SAP Safety Assessment Principle(s)
SEE Single Event Effects
SFR Safety Functional Requirement
SHWP Seismic Hazard Working Party
SLA Site Licence Applicant
SSC Structure, System and Component
SSHAC Senior Seismic Hazard Analysis Committee
STF Stress Test Finding
TAG Technical Assessment Guide(s) (ONR)
UKMO UK Meteorological Office
USNRC US Nuclear Regulatory Commission
WENRA Western European Nuclear Regulators Association
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 4 of 84
Office for Nuclear Regulation
1 INTRODUCTION
1. The Office for Nuclear Regulation (ONR) has established its Safety Assessment
Principles (SAPs) [5], which apply to the assessment by ONR specialist inspectors of
safety cases produced for nuclear facilities by Licensees*. The principles presented in
the SAPs are supported by a suite of guides to further assist ONR inspectors make
regulatory judgements and decisions. This Technical Assessment Guide (TAG) is one
of these guides.
*
The term Licensee is used here generally to refer to all organisations that make safety submissions to
ONR for assessment. This includes; existing Licensees, License Applicants, Potential Licensees and
Requesting Parties to the Generic Design Assessment (GDA) process. Where parts of the TAG refer to
only one type of organisation, this is made explicit in the text. Note that the term Licensee as used here
also includes those responsibilities of a Duty Holder for conventional health and safety as stipulated in
the Health and Safety at Work etc Act 1974.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 5 of 84
Office for Nuclear Regulation
2. The SAPs require an effective process to be applied to identify and characterise all
external hazards (EHs) that could affect the safety of a facility. EHs should be
considered an integral part of demonstrating a facility’s nuclear safety capability. The
safety demonstration in relation to EHs should include analysis of the design basis and
beyond design basis (BDB) conditions† with the aim of defining protection
requirements to move the facility towards and maintain it in a safe state, and identify
opportunities for improvement.
3. EHs on nuclear facilities should be identified and considered in the Licensee’s safety
analysis. This guide explains the approach adopted by ONR in its assessment of
Licensees’ safety submissions where consideration of EHs is relevant to nuclear
safety. It covers the relevance of EHs to Licence Conditions (LCs), to other relevant
legislation, and to ONR’s internal guidance - SAPs and TAGs, and other relevant
standards, in particular guidance published by the International Atomic Energy Agency
(IAEA) and Western European Nuclear Regulators Association (WENRA).
4. This revision of TAG 13 (Rev. 7) is the first that has been able to take full advantage of
the learning arising from the events at Fukushima Dai-ichi on 11th March 2011. There
has been extensive development of standards by international bodies since that time
and comprehensive safety reviews have been performed by UK Licensees. The SAPs
were updated in 2014 to reflect this learning. The lessons most directly relevant to EH
are summarised in Appendix 1.
5. This TAG considers the SAPs in relation to EHs in detail, and forms the principal
interpretation of these principles by ONR. It contains guidance to advise and inform
ONR inspectors in the exercise of their professional regulatory judgement. As for the
SAPs, and to avoid repetition in this guide, the judgement is always subject to the As
Low As Reasonably Practicable (ALARP) requirement for risk assessment (SAPs [5]
paragraph 16). Not all the guidance applies to all assessments or all facilities, and
consideration of proportionality applies throughout. A number of issues concerning
application of this guidance are explained in more detail below:
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 6 of 84
Office for Nuclear Regulation
Use of RGP: The SAPs note in paragraph 11 “that meeting relevant good practice
in engineering and operational safety management is of prime importance”. There
is extensive discussion of RGP applicable to EH in this guide, especially in Section
4 and in the annexes.
Inspectors are referred to TAG 5 [6] Chapter 6 for a detailed discussion of the
importance and application of RGP to nuclear safety. RGP is defined as "… those
standards for controlling risk which have been judged and recognised by HSE§
[Health and Safety Executive] as satisfying the law when applied to a particular
relevant case in an appropriate manner. In nuclear safety applications, where the
potential consequences of accidents can be very serious, the best practice
identified as appropriate to the application would normally be required for new
designs” (TAG 5 [6] paragraph 6.1). For existing facilities paragraph 6.2 states that
RGP “is established by using the standards that would be applied to a new design
as a benchmark and then subjecting any shortfalls to the test of reasonable
practicability.” This latter point is noted above.
Licensees should select RGP most appropriate to their nuclear activities and
justify that their selection does indeed represent RGP (eg consists of widely
recognised relevant codes and standards) and drives out a design of plant /
structure, system and components (SSCs) that ensures that risk is ALARP.
Inspectors should judge the adequacy of this selection by reference to SAPs and
TAGs. This document suite captures those elements of RGP found from
inspectorial experience to be generally applicable to nuclear plant, especially
major radiological hazards plant. Licensees may choose to use alternative
selections of RGP if they lead to an equivalent outcome, in which case inspectors
should challenge the selection, in part, against the expectations of the RGP
provided in this TAG. It is reasonable for Licensees to apply proportionality when
selecting and applying RGP and inspectors should apply the same test when
judging the adequacy of any selection.
6. The SAPs and TAGs are intended for application to nuclear licensed sites and the
facilities on them that affect nuclear safety. With the advent of the new nuclear reactor
build programme in the UK, ONR now engages on non-site-specific assessment of
generic reactor designs through a number of Generic Design Assessment (GDA)
projects. These projects consider generic plant / SSC design features against EHs
defined in a Generic Site Envelope (GSE) only and specifically do not consider aspects
that are site-specific. For these projects, some of the SAPs, especially those in the ST
series relating to siting, and parts of this TAG do not apply. For example, consideration
of coastal flood hazard is not possible until a site has been selected. However,
inspectors’ can assess the extent to which the generic design assumes a siting
approach consistent with the IAEA dry site concept. Inspectors can assess, at the GDA
stage, the adequacy of BDB flood protection and mitigation arrangements, based on
the assumed siting approach. For further details on the expectations for new sites see
Section 5.8.6.
forms of use. The text in this guide makes clear explicitly, or from the context, which form is intended.
§
The wording dates from a time before the legal separation of ONR from HSE. For HSE read ONR.
**
EHs specialist inspectors are supported by a panel of technical experts is seismic (and related
disciplines), meteorology and coastal flooding hazards. The latter two hazard areas are supported by
expertise in climate change.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 7 of 84
Office for Nuclear Regulation
hazards may be significant at particular sites depending on the activities taking place.
The annexes and Expert Panel papers are separate documents referenced from this
document.
Appendices
TAG 13 Main Document EMI & Space Weather
Biological Hazards
Industrial Hazards
Landscape Change
Gas Release Hazards
Expert Panel Paper Expert Panel Paper Expert Panel Paper ONR formal
Seismic Hazards Meteorological Hazards Coastal Flood Hazards advice
Not ONR
advice
Head document: This provides the overarching document for this suite of
references. It is written to the standard TAG format and provides general guidance
applicable to all EHs. Where hazard-specific information is noted, this is
referenced to the appendices or annexes as appropriate. It has been authored by
the ONR EH specialist inspectors. It is supported by a number of attached
appendices covering the minor EHs and four free-standing annexes covering the
major natural hazards and accidental aircraft crash hazard.
Annexes: Refs. [1], [2], [3] & [4]. The annexes provide specific guidance for the
major natural hazards and accidental aircraft crash hazard. They have been
authored by ONR’s EH specialist inspectors. The annexes provide a reasonably
comprehensive discussion of RGP for the hazards they cover. The intent is that
they can be read and understood by ONR’s EHs specialist inspectors and, where
relevant, by other inspectors whose disciplines interface with EHs. They are
written to a standard format that is intended to support the head document.
Expert Panel papers: Refs. [7], [8], [9]. The three natural hazard annexes are each
supported by an Expert Panel paper. These papers provide hazard-specific
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 8 of 84
Office for Nuclear Regulation
8. The description of RGP for natural hazards analysis is generally the preserve of
technical specialists and the Expert Panel papers capture a summary of those
significant examples of which ONR has had regulatory experience. These papers have
been authored by members of the ONR Expert Panel and reviewed by ONR. They do
not represent formal regulatory advice, but provide additional technical background to
the summaries of RGP provided by the annexes.
9. The SAPs define EHs as those natural or man-made hazards to a site and facilities
that originate externally to both the site and its processes, in other words the Licensee
has limited, or no, control over the initiating event, SAP paragraph 228. This last point
is important because it undermines the Licensee’s ability to apply the first element in
the safety hierarchy of hazard control measures, namely, eliminate the hazard.
10. This differentiates external from internal hazards, such as fire arising inside the site
boundary, where, in principle, the operator has substantial control over the chance of
the hazard occurring.
11. A further difference is that EHs in many instances can simultaneously affect the whole
facility, including safety systems, safety-related systems and non-safety-related
systems alike. In addition, the potential for widespread failures and interference with
human intervention can occur. Furthermore, EHs may affect the surrounding off-site
infrastructure through common-cause effects, which may undermine the availability of
back-up supplies and affect emergency arrangements. For multi-facility sites this also
makes the generation of safety cases more complex, and requires appropriate
interface arrangements to deal with the potential secondary and consequential
(domino) effects.
12. Both internal hazards and EHs are differentiated from internal plant fault initiators,
which are defined as a random failure of part of the primary nuclear plant and its
processes, including human error. Whilst the SAPs definition of EHs indicates that EHs
generally originate off the licensed site this is not always the case, for example
subsidence and liquefaction occurring on-site are classed as EHs, as is fault
movement within the site boundary. However, only natural EHs can originate on-site,
man-made or industrial hazards that occur on-site are classed as internal hazards††.
13. A further delineation arises with EHs that are caused by natural processes, such as
weather‡‡ and earthquake, and those of man-made origin such as aircraft crash and
off-site explosion.
14. A final distinction is between man-made EHs that are accidental and those that arise
from malicious intent. The latter are typically criminal acts by third parties with malign
††
This definition implies that the Licensee has been responsible for all current and historical activities on
the site. Situations can arise (and have arisen in the UK) where a site has historically been used by
other organisations for other industrial activities. For example, some licensed sites were once military
sites and have a history of unexploded ordinance within the site boundary. Another example that can
occur is where chemical / radioactive materials have been transported, by groundwater movement say,
from nearby industrial sites and now resides under the licensed site in question. All these would be
classed as EHs.
‡‡
Weather and flood hazards are often referred to with the inclusion of the descriptor “extreme”. This
terminology is not generally used in this guide, except occasionally to provide emphasis.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 9 of 84
Office for Nuclear Regulation
intent, and the characteristics and protection measures associated with such events
are generally subject to national security considerations. For this reason, malicious
EHs are not covered in this TAG, but are assessed by ONR’s Civil Nuclear Security
Division using separate guidance [10].
15. Table 1 summarises the various categories of plant fault initiators, indicating which are
classed as EHs and of these, which are covered in the guide. Table 2 contains a
typical list of EHs that should be covered within Licensee’s safety submissions. The
identification of a comprehensive list of EHs is discussed further in paragraph 61. et
seq.
16. It should be noted that some man-made items, such as dams and human activities
such as gas extraction or water injection into geological structures (hydraulic
fracturing), may initiate additional hazards, or enhance the effects of natural hazards
already defined as credible at a site.
17. Analysis by a Licensee should demonstrate that threats to nuclear safety from EHs are
minimised or tolerated. This may be done by showing that safety-related SSCs and
equipment are designed to meet appropriate performance criteria against the
postulated EH, or by the provision of safety systems which mitigate the effects of fault
sequences, thereby demonstrating that the residual risk is ALARP.
18. A summary description of the high-level tasks the Licensee needs to undertake to
determine the effects of EHs on nuclear plant is given below:
i. Identify the EHs that can credibly affect nuclear safety and thus contribute to
nuclear risk.
ii. Analyse each of these hazards to characterise the nature and severity of the
challenge it makes to nuclear plant / SSCs. This is referred to as the site
challenge.
iii. Define a protection concept to determine the barriers required to satisfy the
relevant nuclear safety principles (eg defence-in-depth (DiD)).
iv. Analyse the response of the plant / SSCs to this challenge through fault analysis to
determine the resulting nuclear safety consequences and risks that could arise.
v. New nuclear sites: For new sites SAP ST.4 anticipates that the suitability of the
site to support safe operation will be assessed from an EHs viewpoint§§.
20. Safety submissions made by the Licensee should cover all the tasks listed above. The
role of EH specialist inspectors is primarily to assess the adequacy of submissions
covering the first two tasks, and in the case of new nuclear sites, task (v). Task (iii) is
covered by a combination of fault analysis and EH inspectors. Task (iv) is undertaken
by specialist inspectors in other disciplines covering SSCs affected by EHs. This
division of work creates a number of interfaces between EH specialist inspectors and
other disciplines within ONR. The most significant interfaces are listed in Table 3,
however EH assessors should be mindful that other interfaces may well exist for
particular projects.
§§
Note that the Government has pre-determined the location of potential new reactor build sites in the
UK [73]. These sites are subjected to detailed site-specific hazard analysis by the SLA and Licensee
subsequently in order to fully demonstrate site suitability.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 10 of 84
Office for Nuclear Regulation
21. For each new reactor construction project, the expectation is that a GSE is defined by
the Requesting Party*** (RP) during the GDA [11], as a series of hazard-specific design
bases. For a given EH the GSE defines a benchmark hazard magnitude which the
nuclear facility will be designed to withstand. It should be noted that not all EHs are
normally represented in a GSE since some, most notably off-site flooding related
hazards, are generally considered as intrinsically site-specific and not amenable to
generalising for the purposes of generic design. For these hazards, protection and
mitigation measures will be bespoke to the site in question and form part of the site-
specific design process. The site-specific EH envelope should be based on screening
of all potential EHs to confirm that all credible hazards and combinations of hazards
have been identified for the site.
22. At the site licensing and subsequent permissioning stages, the site-specific EHs
defined in a manner consistent with the needs of the design process, see Section 5.4
(the site challenge), will be compared against this GSE, a visual example of this
comparison is shown in Figure 2. If the challenge from a proposed site is bounded by
the GSE, then the generic design is likely to meet the regulatory expectations of ONR
from the perspective of those EHs captured by the GSE. If any site-specific EH value
exceeds the GSE design basis value for that hazard, then the inspector should ensure
that the Licensee has provided an appropriately robust justification to demonstrate that
the proposed design remains suitable for that site [11].
23. Using Figure 2 as an example, the Wind Gust site-specific hazard value defined
conservatively at the 10-4/yr 84% confidence level, exceeds the GSE hazard value.
The Licensee in this example would therefore need to provide additional analysis to
demonstrate that the site is suitable, or the SSC design is sufficiently robust. The
Licensee may also be required to provide additional safety justification for hazards
where the site-specific hazard value is close to exceeding the GSE hazard value, as is
the case for Wind Hourly Average and High Air Temperature in Figure 2, to
demonstrate consistency with the expectations of EHA.4. When a design basis is
derived directly from a site-specific hazard analysis, inspectors should assure
themselves that sufficient margin is available over the mean site challenge to meet the
intent of EHA.4.
24. Where an EH has been screened out during the development of the GSE under the
GDA process but is found to be significant in the site-specific context, then the
Licensee will be required to provide additional safety justification and argument to
demonstrate that the design remains suitable for the site.
***
Requesting Party is the generic name given to nuclear reactor system vendors seeking an opportunity
to sell their design to a Site Licence Applicant (SLA). The SLA becomes the site Licensee once a site
licence has been granted.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 11 of 84
Office for Nuclear Regulation
Extreme Sea Temperature Low (˚C) 200% Extreme Wind Gust (m/s)
Extreme Sea Temperature High (˚C) 100% Extreme Wind Hourly Average (m/s)
0%
High Air Temperature 12 hr Average (˚C) High Air Temperature Instantaneous (˚C)
26. Discrete EHs are those that can be defined as one or more discrete events in terms of
frequency of occurrence and severity (SAP paragraph 232). An example of a discrete
hazard defined by multiple events is accidental aircraft crash, where separate
categories of aircraft typically have different crash frequencies at a given location, but
a causal link connecting the statistics of different categories does not exist. The lack of
a causal link is what differentiates discrete from non-discrete hazards.
27. This is a term used in the SAPs for a number of natural hazards: weather, flood and
seismicity (SAP paragraph 233). Here, each hazard is (or in principle can be)
described by a hazard curve of frequency of exceedance versus severity, and a
special feature of the hazard curve is that the events it describes are related by the
physical processes that create them. For example, build-up of strain energy at points in
the earth’s crust can be released causing earthquakes with a range of magnitudes.
The magnitudes and their frequency of occurrence are modelled by the Gutenberg-
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 12 of 84
Office for Nuclear Regulation
28. The hazard curve concept is key to the understanding of the most significant natural
hazards. The “exceedance” in exceedance frequency means that at any given point on
the hazard curve, the frequency of the indicated hazard severity should be interpreted
as the frequency of realising an event of severity greater than the one indicated. This is
important in rationalising the need for beyond design basis analysis (BDBA) for these
hazards (see Section 5.5.3).
29. For some discrete hazards, usually man-made hazards, it may be possible to
characterise a worst-case event, called a Maximum Credible Event (MCE), that can be
used as a surrogate for the hazard as a whole. For example, the release of a toxic gas
from a nearby off-site tank farm will likely be limited by the maximum storage capacity
of the tanks. The MCE concept is useful for quickly estimating worst case scenarios
and is generally applied to hazards whose nuclear safety implications are minor. Quite
often, the Licensee is able to demonstrate in a straightforward way that, even at the
MCE level, the nuclear safety implications are negligible and therefore the hazard can
be screened out from further consideration. The MCE can also be useful in helping to
define a design basis event when probabilistic methods for the hazard in question
carry large uncertainties, and also provides a useful insight for BDBA.
30. In principle, it may also be possible to develop a MCE for a non-discrete hazard, eg if
the hazard curve is asymptotic to some upper value of severity, or if a relevant physical
limit can be defined that limits hazard severity.
31. Where hazards are not amenable to the derivation of a design basis event based on
frequency, a surrogate MCE, supported by scientific evidence, may be defined. The
severity of the surrogate MCE should be chosen and justified to reach an equivalent
level of safety (that is, it should be compatible with the principles of SAP FA.5).
32. The intent of this section is to provide a context within which the analysis of EHs is
undertaken. This analysis is driven primarily by the need to demonstrate safe operation
of nuclear plant. Such plant consists of systems, structures and components (SSCs)
for which safety functional requirements (SFRs) are stated. SFRs define the ability of
SSCs to withstand particular EHs and how the SSC fails in response to EH loading,
and form the basis of claims in safety cases.
33. The extent to which individual EHs are analysed to develop a site challenge should be
proportionate to the significance of the EH to plant risk. Nuclear (and other) plant /
SSC responds to the challenges presented by EHs in a number of ways. This section
gives a general overview of both typical features of SSC / personnel response and the
protection / mitigation measures that Licensees typically implement.
34. Assessment of safety submissions covering the effects of EHs on SSCs is primarily the
responsibility of other discipline areas, especially the engineering disciplines. The
discipline areas likely to be of most interest to EH specialists are:
Civil Engineering
Mechanical Engineering
Electrical Engineering
Human Factors
Control & Instrumentation Engineering
Structural Integrity of metal components
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 13 of 84
Office for Nuclear Regulation
Internal Hazards
Fault Studies & PSA
36. The two most important features of EHs relevant to nuclear safety are the limited ability
to apply the hierarchy of safety principle and the common cause effect that is often
associated with the effects of EHs:
37. Limited ability to apply the Hierarchy of Safety principle: The Licensee has very little or
no control over the hazard’s likelihood of occurrence. The Licensee should however be
able to control the hazard’s potential to initiate faults on the plant. In hierarchy of safety
terms, eliminating the hazard at source is not an option, therefore protection and
mitigation measures should be employed to limit the effects of the EH. Typically, these
are:
39. Common cause effect: The common cause effect of many EHs, especially natural
hazards, such as weather, flooding and seismicity, can affect the entire site at the
same time and often a substantial region off-site as well. Several features of this effect
are worthy of note:
Such hazards have the potential to initiate a large number of SSC / plant faults
simultaneously.
They can adversely affect the off-site infrastructure on which the site depends for
supplies of materials, energy and personnel. They can even affect the severity of
severe accident off-site consequences and the effectiveness of emergency
arrangements. Common cause effects should be considered as part of the design
basis, BDB and within the Licensee’s Severe Accident Management Guidelines
(SAMGs).
40. A further important aspect of EHs is their ability to initiate or induce internal hazards
events as secondary or consequential hazards, eg fire, internal flood and gas release;
for further details consult TAG 14 [12].
41. The potential of EHs to challenge nuclear safety is discussed in the appendices (2-6)
and annexes (1-4) covering each individual hazard category.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 14 of 84
Office for Nuclear Regulation
42. LCs only apply at nuclear licensed sites and to nuclear related activities undertaken by
Licensees on those sites, although third parties working on behalf of the Licensee may
carry out these activities. LCs cover a large number of nuclear safety matters, but
those relevant to EHs are directly concerned with safety case production, the
management of safety case outputs (eg operating rules), maintenance of safety cases
and safety-related plant (including Periodic Safety Reviews), incidents on-site and
emergency arrangements. The Licensee has a duty to develop and maintain site
licence compliance arrangements and these should take full cognisance of the
requirements of EH safety cases. These may include their own nuclear safety
principles; if such principles exist, compliance with them should not lead to a shortfall
against the SAPs or TAG guidance without appropriate justification.
43. This section may also apply to information that is prepared by organisations that are
not Licensees, such as Requesting Parties, to the extent that they will prepare safety
submissions that may, in time, support licensable activities on a nuclear licensed site.
44. The majority of EHs could have an impact on the matters addressed by most of the
nuclear site LCs. However, the following are seen as being most relevant to the
specific threats posed by EHs on nuclear facilities:
c. Licence Condition 10: Training – where the Licensee has provided deployable
defences against EHs – such as flood barriers around doors, suitable training should
be provided to ensure the actions can be carried out in a timely manner. It is important
that the training takes cognisance of the environmental conditions under which any
arrangements need to be implemented, such as during the build-up to a severe storm.
Training in relation to EHs is also relevant to LC 11 – Emergency arrangements.
d. Licence Condition 11: Emergency arrangements – EHs are one class of initiating
events for the instigation of the emergency arrangement procedures. It is important for
Licensees to establish the existence and nature of an EH event, if one occurs, that
could lead to the deployment of emergency arrangements. Licensees should have
access to sufficient sources of information to enable the site to respond to such events
in a timely manner. The following is a non-exhaustive list or information sources:
Weather and flood warnings from services operated by, for example, the UK
Meteorological Office (UKMO) and the Environment Agency (EA).
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 15 of 84
Office for Nuclear Regulation
Seismic hazard information service provided by, for example, the British
Geological Survey (BGS).
Site monitoring equipment providing data on hazards at a site level such as: tide
and river levels, air and sea temperatures, wind speed, site and in-plant seismicity
levels, etc.
Site monitoring equipment is assumed to be under the control of the Licensee and
it may be appropriate to provide annunciations and data readouts directly to the
site / plant control rooms, so that a site response can be initiated quickly.
i. Licence Condition 23: Operating rules – this condition requires that the Licensee
shall, in respect of any operation that may affect safety, produce an adequate safety
case to demonstrate the safety of that operation and to identify the limits and
conditions necessary in the interests of safety. Inspectors should refer to TAG 35 for
further details [13]. Limits and conditions relevant to EHs may include:
Limitations on the state of the plant. The EHs protection mechanisms claimed in
the safety case must be available according to safety case requirements including
examination, inspection, maintenance and testing (EIMT) and when systems are
unavailable due to faults. For EHs that can be forecast, eg weather, a grace time
for establishing a safe plant configuration may be applicable. Inspectors should
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 16 of 84
Office for Nuclear Regulation
assure themselves that a route to a safe operating state without transgressing the
safe operating envelope is available.
Inspection activities prompted by local seismic events greater than the OBE level,
or occurrence of any other type of EH that could challenge the design basis
assumptions in plant safety cases.
Plant conditions for which no safety case justification is available, eg the use of
free-standing scaffolding or a temporary work platform close to safety-related
equipment, where the scaffolding or platform might respond to an EH event
causing interference with the safety function of the equipment.
Plant conditions caused by maintenance activities that undermine the claimed EHs
withstand of safety-related plant and equipment, or undermine the functionality of
EHs monitoring equipment needed to discharge activities claimed in safety cases.
j. Licence Condition 27: Safety mechanisms, devices and circuits – this condition
requires Licensees to ensure that plant is not operated, inspected, maintained or
tested unless suitable and sufficient safety mechanisms, devices and circuits are
connected and in good working order. Generally, there are a large number of EHs
safety claims made on plant and equipment, especially in respect of seismic hazard.
Inspectors should be especially wary of situations where plant is operated when other
plant on which it depends to deliver safety claims is out of service. This can occur, for
example, when “other plant” comprises EHs monitoring equipment, which is either
undergoing maintenance or is in a failed state. The plant being protected should either
be operated in a way that removes the need for the safety claim(s), or substitute
monitoring equipment should be employed that delivers a similar functionality to that
which is out of service.
Explicitly identify relevant EHs safety claims, so that on return to service such
plant and equipment meets the intended EH functional and reliability claims made
on it.
Include other plant and equipment that can cause damage to safety-related items
through secondary action following an EH event.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 17 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 18 of 84
Office for Nuclear Regulation
45. The specific EH SAPs are: EHA.1 to EHA.19, which cover the wide range of EHs and
the tasks needed for their identification and analysis.
46. There are a number of supporting and related SAPs, all of which are relevant to the
analysis of EHs and some of which make explicit reference to EHs. These are:
47. Due to the nature of EHs effects, this list could include virtually all other SAPs.
However, the shortened list above highlights those key SAPs that should be
considered in the first instance. In addition, it is worth noting that the following
paragraphs are also of relevance:
9-18 ALARP
33 Facilities Built to Earlier Standards
35 Ageing
42-43 Multi-facility sites
48. As stated below, benchmarking of the SAPs against the WENRA and IAEA standards
has been undertaken at a high level, the results of which in relation to EHs and
WENRA Reference Levels (RLs) can be seen in Table 4. It has shown that the SAPs
in respect of EHs meet the requirements of both organisations.
WENRA
49. The WENRA RLs most relevant to EHs are published in Refs. [14], [15], [16]. Ref. [14]
provides the head document for Issue T – Natural Hazards – and has subsequently
been supported by a further three documents that post-date publication of the head
document and cover meteorological, flooding (all forms) and seismic hazards
respectively: [17], [18], [19].
50. The guidance in this TAG is consistent with these WENRA RLs. Table 4 presents the
mapping between Reactor Harmonisation Working Group RLs and this TAG. The
guidance in this TAG has also been considered against the WENRA Waste and Spent
Fuel Safety RLs [20] and the Decommissioning Safety RLs [21]. These do not include
specific EHs levels. However they do state that EHs need to be considered as
postulated initiating events (PIEs), and the Decommissioning Safety RLs report
provides an example list of such events. The guidance in this TAG is consistent with
both documents.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 19 of 84
Office for Nuclear Regulation
IAEA
52. The 2006 SAPs were benchmarked against the IAEA Safety Series (requirements and
guidance) documents, especially [22], and their main principles are encompassed
within the SAPs. Specific IAEA guidance relevant to EH is referenced throughout this
TAG and in the hazard specific annexes attached to it, but IAEA Safety Guide NS-R-3
[23] provides a good overview. IAEA guidance referenced in this TAG is summarised
in Table 5.
53. This TAG reflects the IAEA guidance at its time of production. The guidance from IAEA
is recognised as representing RGP under the introduction to the 2014 SAPs [5].
54. In response to the Fukushima Dai-ichi event IAEA undertook a detailed investigation
into the causes and consequences of the accident [24]. As a result of this investigation
new technical standards have recently been published; others are in draft and
expected to become available between publication of this TAG revision and the next
scheduled review date. ONR have contributed to the production and review of these
new standards and regard them as RGP upon publication.
55. Standards already published before this investigation and relevant to external hazards
are summarised in Table 5. They include several relevant to seismic hazard analysis
[25], [26] and [27], and one relevant to meteorological and coastal flood hazard
analysis [28].
General
This publication supports SSR-2/1 [22] and provides detailed guidance on general
design matters with the learning from Fuksushima, and specoifoc guidance on
establishing external hazards design bases and elements of BDBA.
This publication provides guidance on BDBA for existing nuclear power plants and
specifically responds to the expectations of post-Fukushima stress test expectations.
Site Selection
IAEA SSG-35: Site Survey and Site Selection for Nuclear Installations [31].
This publication provides guidance specifically for the selection of new sites for new
nuclear power plants.
IAEA Safety Report 85: Ground Motion Simulation Based on Fault Rupture
Modelling for Seismic Hazard Assessment in Site Evaluation for Nuclear
Installations [32].
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 20 of 84
Office for Nuclear Regulation
This publication describes strong ground motion simulation methods and gives
introductions to simulations using fault rupture modelling.
IAEA Safety Report 89: Diffuse Seismicity in Seismic Hazard Assessment for
Site Evaluation of Nuclear Installations [33].
This publication provides the state-of-the-art practice and detailed technical elements
related to ground motion evaluation by ground motion prediction equations and site
response in the context of seismic hazard assessments as recommended in IAEA
Safety Standards Series No. SSG-9 [27].
IAEA Safety Report 86: Safety Aspects of Nuclear Power Plants in Human
Induced External Events: General Considerations [38].
IAEA Safety Report 87: Safety Aspects of Nuclear Power Plants in Human
Induced External Events: Assessment of Structures [39].
IAEA Safety Report 88: Safety Aspects of Nuclear Power Plants in Human
Induced External Events: Margin Assessment [40].
57. The following standards are in production by IAEA and are expected to be relevant to
this TAG. Inspectors using this TAG should familiarise themselves with the current
status of IAEA guidance relevant to their assessment work:
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 21 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 22 of 84
Office for Nuclear Regulation
5 ADVICE TO INSPECTORS
58. The analysis tasks that the Licensee (or the RP under the GDA process) should
undertake to determine the effects of EHs on nuclear plant have been described at
high level in paragraph 18., and as noted there, EH inspectors should concentrate their
assessment on points i, ii and if necessary, iv. Points i and ii are summarised in more
detail below, where point ii has been sub-divided into the different analysis streams
called for by the SAPs, plus a number of special considerations specific to EH and
emergency preparedness:
Hazard identification
Fault identification (fault initiation) and hazard screening
o Hazard grouping
o Hazard screening on low frequency (discrete hazards)
o Hazard screening on low consequence potential (discrete and non-discrete)
Hazard analysis
Design Basis Analysis (DBA) – specific EHs considerations
o Design bases for screened-in EHs
o Design bases for facilities with low unmitigated consequences
o BDBA for EHs
“Cliff-edge” effects
More severe BDB events
Probabilistic Safety Analysis (PSA) of EHs
Severe Accident Analysis (SAA) of EHs
Special considerations relevant to EHs
o Combinations of EHs (includes consequential hazards / effects)
o Combining EHs loads with normal design loads
o Operating conditions
o Multi-facility sites
o Application of this guide to existing sites and facilities
o Application to new sites
o Single failure criterion
o Reliability, redundancy, diversity and segregation
o Sources of data
o Uncertainty
o Climate change
Emergency preparedness
Post EH event operations
60. DBA, PSA and SAA are collectively known as fault analysis; FA.1 calls for all three of
these analysis streams to be undertaken to demonstrate that facility risks are ALARP.
FA.2 calls for all significant fault initiators to be identified and FA.3 states that fault
sequences should be developed for all initiating faults. EHs initiated faults are fully
embedded in all of these aspects.
61. The fundamental first step in addressing the threats from EHs is to identify those that
are relevant to the facility under consideration. All EHs and credible combinations that
might affect the site should be identified. SAP FA.2 and paragraph 618(c) state that
EHs should be considered as potential fault initiating events. EHA.1 further amplifies
this.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 23 of 84
Office for Nuclear Regulation
62. The Licensee should demonstrate that an effective systematic process has been
applied to identify all types of EHs relevant to a particular site, including reasonably
foreseeable independently occurring hazards, causally-related hazards and
consequential events (SAPs paragraph 234). Furthermore, EHs that threaten
neighbouring installations, which in turn threaten the plant, should be identified.
63. Table 2 contains a typical range of hazards that should be considered in the first
instance and is drawn from an ONR report [42] that summarises ONR and IAEA
guidance, augmented with recent experience from Licensee safety cases identifying
those EHs significant to nuclear safety; IAEA Safety Guide NS-R-3, NS-G-1.5 and
SSG-18 are particularly relevant [23], [43], [28]. A further list of IAEA guidance is
provided by WENRA at Ref. [16]. WENRA also provides further guidance for natural
hazards at Ref. [14] - Appendix 2, which has also been used in the construction of
Table 2 within this TAG†††. Table 2 should not however be seen as exhaustive, as local
site conditions and the plant design may be susceptible to further hazards. The
appendices and annexes to this TAG provide additional detail on specific hazard types.
64. The relevant parts of Table 2 are expanded as appropriate in each of the annexes to
provide a list (not comprehensive) of primary, secondary, correlated and consequential
site hazards associated with each type. This division of hazards into different
categories has been found useful for conveying the interdependencies of various
hazards (especially meteorological and coastal flooding hazards) on each other:
Correlated hazard: An EH that can occur simultaneously with the primary hazard
because both depend on a common physical process, for example, a storm may
give rise to both rain and lightning hazards at the same time.
Consequential hazard / effects: Hazards (internal and external) that are the
derived effects of primary, correlated and secondary hazards and / or their typical
effects, leading to a direct challenge to site safety and / or site operations.
65. The fault identification process should provide sufficient site-specific data to determine
each hazard’s potential for plant / SSC fault initiation and whether the hazard can be
screened out from further fault analysis / hazard analysis (including hazard
combinations and consequential events as noted in paragraph 62.). Fault sequences
should be developed to determine the potential radiological consequence.
66. External hazard grouping: EHs may be grouped together where they have common
features, or initiate similar fault sequences for example. However, inspectors should
confirm that such groupings faithfully reflect the number of hazards and faults collected
†††
A further recent report [48] prepared as part of a research project to extend the PSA methodology to
better accommodate EHs has provided what it claims is a comprehensive list of EHs to be considered
in a Level 1 EHs PSA.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 24 of 84
Office for Nuclear Regulation
5.3.1 Screening
67. Hazards can be screened from further consideration if they are shown by the fault
analysis to make no significant contribution to overall risks from a facility (SAP
EHA.19). A screening process consisting of defined screening criteria should be
applied to each identified hazard. Screening criteria (SAP paragraphs 235, 631 & 649)
can be defined in terms of very low frequency of occurrence (for discrete hazards less
than 10-7/yr)‡‡‡ or in terms of the potential consequences from associated fault
sequences if they are incapable of posing a significant threat to nuclear safety
(discrete and non-discrete hazards). It is important to note that the hazard screening
process can often be a major part of the hazard analysis. Apart from hazards that are
evidently not applicable to a particular site (for example, fluvial flooding if available
national generalised flood mapping indicates the site is not at risk§§§) it is necessary
first to characterise the hazard sufficiently to facilitate a meaningful screening analysis
(eg generate a hazard frequency versus severity curve). Secondly, in order to
determine whether the hazard severity has nuclear safety significance, an
understanding of how the hazard will impact on the plant / SSC and the plant or SSC
response is required. Where generic, rather than site-specific hazard data has been
used (which may pre-date any detailed site-specific hazard characterisation work) the
original assumptions should be justified by reasoned argument.
68. Care should be taken to ensure that combinations (see Section 5.8.1) including
internal faults and operational occurrences are included. Thus, fault sequence
analysis, including combination effects, need to be taken into account in the screening
process.
69. Screened-in hazards are considered as significant fault initiators under FA.2 and
should therefore be subject to DBA and PSA as appropriate. Non-discrete hazards in
particular may also be subject to SAA.
70. Each credible EH should be assessed to establish its frequency and severity (in terms
of magnitude, duration, progression, spatial extent, relationship to other hazards, etc)
at the site. The hazard analysis is used not only for the purpose of defining the design
basis, but also to support BDBA, PSA and SAA. The characterisation of EHs will
depend on the type of analysis that is to be carried out and should be conservative for
the DBA, but best estimate for SAA and PSA. The hazard curves should extend down
to an appropriate frequency generally consistent with the fault screening frequency for
discrete hazards, see paragraph 67., since this represents a frequency at which risk is
considered negligible for a single class of accident, see SAP paragraph 749.
71. It should be noted that for EHs PSA, a range of frequencies and associated hazard
parameters is often required. All relevant characteristics need to be specified and the
rationale for their selection justified. For some EHs the ability to forecast the magnitude
and timing of the event, and the speed at which the event develops may be relevant
and should be considered. Several parameters could be relevant to characterise
severity and / or magnitude. A useful checklist of hazard analysis considerations is
provided in Ref. [16]. Further details are also provided within individual hazard
annexes and appendices in this guide.
‡‡‡
Note that the cut-off frequency may differ depending on the nature of analysis that is to be
undertaken. Where PSA is undertaken for example, the cut-off frequency needs to be low enough to
compare the EH internal plant fault risks.
§§§
https://flood-map-for-planning.service.gov.uk/
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 25 of 84
Office for Nuclear Regulation
72. For significant natural hazards, weather, flooding and earthquake, these often take the
form of complex computational analyses requiring specialist expertise to undertake for
nuclear sites with significant hazard potential. Where appropriate, a MCE may be
defined (see paragraph 30.). In all cases the analysis should use methods,
assumptions or arguments that are justified, take into account all relevant site and
regional data and contain sufficient information to enable a conservative design basis
to be defined.
73. Licensees should provide assurance that uncertainties and their impact have been
given adequate consideration and adequate margins have been included when
defining the design basis events. For sites where the unmitigated consequences
arising from an EH are low (SAP paragraph 241), hazard data from conventional
building codes may be acceptable. For the less significant natural hazards and for
industrial hazards, the complexity of the analysis depends on a number of factors that
are site-specific. Details of the analysis techniques and the degree of expertise
required for the assessment of site-specific analyses in support of nuclear safety cases
are provided as a series of appendices (for less significant hazards) and annexes (for
more significant hazards), as follows:
74. DBA is a robust demonstration of the fault tolerance of the facility, and of the
effectiveness of its safety measures. Its principal aims are to guide the engineering
requirements of the design and to determine limits and conditions to safe operation
(LC 23(1) Operating Rules), so that safety functions can be delivered reliably during all
modes of operation and under reasonably foreseeable faults. In DBA, uncertainties in
the fault progression and consequence analyses are addressed by the use of
appropriate conservatism. The adequacy of the design and the suitability and
sufficiency of the safety measures are assessed against deterministic rules (eg design
codes). These rules are derived from RGP and include the SAPs themselves.
Design basis – The range of conditions and events that should be explicitly taken
into account in the design of the facility, according to established criteria, such that
the facility can withstand them without exceeding authorised limits by the planned
operation of safety systems.
Design basis fault – A fault (sequence) that the plant is designed to take or can be
shown to withstand without unacceptable consequence, by virtue of the facility’s
inherent characteristics or the safety systems.
76. These definitions are discussed further below with respect to EHs.
77. DBA for EHs is predicated on defining a design basis event for each EH screened in to
the fault analysis process (EHA.3). Additional design basis events may be defined to
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 26 of 84
Office for Nuclear Regulation
capture credible combinations of individual events. SAP EHA.4 refers to the design
basis event threshold for external events in terms of a return period (eg 1 in 10,000
years conservatively evaluated for natural EHs). This terminology is in common use in
the nuclear industry****. Note that the annual probability of exceedance of 10-4 is an
annualised value applicable over the lifetime of the facility††††.
78. SAP EHA.4 also defines the EH design basis event exceedance frequency in terms of
SAP FA.5 which defines the threshold frequencies for events to be included within
DBA. As noted in paragraph 60., EHs should be fully embedded into the DBA process.
SAP paragraph 628 identifies hazard initiating fault frequencies below which
application of DBA is unlikely to be proportionate to the radiological hazard. These
have been re-interpreted here as the frequency points at which the EHs design bases
should be established. The exceedance frequency for the EH design basis event
therefore corresponds to the threshold frequencies for events that should be included
within the DBA process. For non-discrete EHs characterised by a hazard curve, DBA is
expected to consider the EH at all exceedance frequencies on the hazard curve down
to the design basis event definition. For discrete EHs, the analysis is expected to
include consideration of hazards that might be grouped within the EH event definition,
in a similar way to plant initiated faults down to a threshold value of 10-5/yr on a best
estimate basis.
79. The EH event design basis exceedance frequencies, and threshold values for DBA are
summarised here: (The basis for these definitions is discussed at paragraph 86.)
Discrete hazards – For internal hazards and man-made EHs the design basis is
defined in one of two ways:
Where a discrete hazard has a frequency of occurrence less than the design basis
threshold of 10-5/yr, but cannot be screened out as insignificant according to SAP
EHA.19 (paragraph 67.), the hazard will still need to be captured by the PSA or other
form of fault analysis, and needs to be considered as a beyond design basis event,
see paragraph 109..
Non-discrete hazards – For natural EHs defined by hazard curves, the design basis is
defined as follows:
80. Note that some Licensees use multiple design bases to describe hazards, with
different levels of protection and mitigation associated with faults analysed at the
****
The term “10,000 year return period” is shorthand for an event with an annual probability of
exceedance of 10-4 or 10-4/yr.
††††
A further common usage is to refer to probabilities as (statistical) frequencies. Use of this
terminology is widespread throughout the nuclear industry and is used also in the SAPs. At the low
probabilistic values of interest here, the numerical difference between probabilities and equivalent
frequencies is insignificant. The term “frequency” is used for convenience in this document and to be
consistent with the expectations of a nuclear audience.
‡‡‡‡
Inspectors should note that the conservative 10-4/yr value should be seen as commensurate with the
10-5/yr value used for discrete hazards (and other non-EH initiating events). The difference recognises
the difficulty in defining natural hazards at exceedance frequencies below 10 -4/yr.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 27 of 84
Office for Nuclear Regulation
different design bases. The demonstration of ALARP is more complex in these cases
and care is needed that the Licensee does not interpret such analyses as justifying an
ALARP position more lax than that intended by the SAPs in the use of DBA.
81. Note that the hazard screening criteria described in Section 5.3.1 are not the same as
the DBA criteria (paragraph 78.). The design basis event might not necessarily pose a
significant nuclear challenge and the subsequent load case may be bounded by other
design load cases. The DBA process should note the SFR to protect against otherwise
bounded design basis events.
The Use of Conservatism in the Definition of Design Bases for Non-Discrete External
Hazards
82. SAP EHA.4 makes a clear expectation that design bases for non-discrete hazards
should be conservatively defined, but provides no advice on how to define either the
level of overall conservatism, or the manner in which conservative assumptions are
applied to the hazard analysis process.
83. Historically, a range of different approaches has been undertaken for the development
of design basis events for UK Licensed sites, especially for sites where there was no
nuclear safety requirement associated with specific hazards (eg seismic) at the time of
construction. These approaches have been developed as a result of the state of
knowledge at the time of their derivation and the level of radiological hazard and / or
risk posed by the site. Inspectors should exercise caution when examining the
derivation of design basis hazards in isolation from the totality of the safety justification
for such facilities. Instead, an appreciation of the manner in which the Licensee has
demonstrated holistically that the risk from EHs events is ALARP is a more
proportionate approach in line with good regulatory practice.
84. The difficulty in deriving a conservative design basis definition is most notable for non-
discrete natural hazards (and has been a matter of considerable debate in respect of
seismic vibration design bases in particular) because the work involved in producing
an adequate safety case is generally greater for these hazards than for others. For
these hazards especially, inspectors should consider the following:
As noted in paragraph 83., the most important aspect is that the Licensee should
demonstrate that the risk arising from EHs is ALARP. The need for a conservative
estimate of design basis hazard severity at the 10-4/yr frequency of exceedance
point on the hazard curve, is considered by ONR to be consistent with such a
demonstration, and is captured by EHA.4 and FA.5 paragraph 628(c).
For a hazard analysis performed in line with modern RGP, a general expectation is
that for a hazard curve whose epistemic uncertainty§§§§ is defined by a normal
probability distribution, a good starting point is to consider the 84th percentile, ie
one standard deviation above the median. More commonly log-normal
distributions are used in which case an equivalent 84th percentile can be
determined, but in this case, the expectation is that this should be above the mean
value. This is generally the case except for highly skewed distributions.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 28 of 84
Office for Nuclear Regulation
o With regard to the shape of the hazard curve (or more specifically whether it
steepens or shallows), if there is significant shallowing between the Annual
Frequencies of Exceedance (AFEs) of 10-4/yr and 10-5/yr, additional
conservatism in the design basis may be necessary, or for the converse
situation it may be acceptable to reduce the level of conservatism*****.
o The level of conservatism selected for a design basis should have regard to
the characteristics of the hazard analysis that underpins it, with particular
regard for the quality and quantity of data used. Where the quality of the
hazard analysis at and around the 10-4/yr level varies with for example,
structural natural frequency in the case of a seismic design basis, or wave
height in the case of a sea level design basis, such uncertainties should be
reflected in the level of conservatism included in the design basis definition.
The use of sensitivity studies (SAP AV.6) can assist in identifying the parameters
or analysis aspects on which a design basis is very dependent. Where these
parameters or issues are also associated with a high degree of uncertainty, this
can indicate where refined data collection, analysis, or even further research is
needed.
For existing plant where it may be difficult for the Licensee to demonstrate that a
hazard design basis is conservative in line with the expectations of EHA.4 and
modern RGP, possibly because the hazard analysis predates a modern
interpretation of RGP, the inspector should confirm that there is conservative
margin in the plant’s capacity to resist the hazard. In such cases, inspectors
should expect Licensee safety cases to make clear that this is where the elements
of conservatism exist and provide a reasoned argument as to why the overall risk
is ALARP.
surrogate of the hazard for design and deterministic analysis purposes. However, selecting a single
point to represent a hazard that is best described by a 2-dimensional curve is problematic. A more
rigorous way of choosing an appropriate design basis value should therefore consider both the severity
of the hazard challenge at this point AND the way the hazard curve varies around it. If the hazard curve
shallows quickly with decreasing values of AFE, then the hazard severity at say 10 -5/yr, may not be
significantly more than at 10-4/yr and invite additional conservatism in the design basis definition.
Conversely, if the curve steepens then the hazard severity at 10 -5/yr may be substantially more and
invite a less conservative design basis value.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 29 of 84
Office for Nuclear Regulation
reduce risks ALARP and that individual hazards do not contribute significantly to
overall plant risk (SAPs [5] paragraph 646). Inspectors should assure themselves that
the level of conservatism selected facilitates this demonstration.
86. The success criteria for DBA are set out in SAP FA.7. The Licensee should define a
protection concept that describes the barriers required to protect against EH design
basis events (with due consideration of BDB events and severe accidents). Further
guidance on the protection concept for natural hazards is provided by WENRA [14].
The intent is that following a design basis event and successful operation of the
protection and mitigation measures, none of the physical barriers to prevent the
escape of a significant quantity of radioactive material should be breached, there
should be no release of radioactivity and no person should receive a significant dose of
radiation, see SAP paragraph 635. SAP paragraph 637 clarifies that a significant
escape of radioactive material is defined by the Basic Safety Objectives quoted in SAP
Target 4.
87. In order to meet this objective, design bases are often used as design withstand
criteria for SSCs, for example sea walls, or the seismic withstand of major safety-
related SSCs. Where a particular design basis is not used directly as a SSC withstand
criterion, DBA should be used to define the necessary additional protection and
mitigation requirements to demonstrate DiD, segregation etc, sufficient to meet the
intent of Target 4.
88. The intent of DBA is that, used in conjunction with good engineering principles as
described in the SAPs (eg EKP.1 to EKP.3), it guides the development of a plant
design that can meet risk targets, or otherwise a design where risk has been reduced
ALARP. The criterion for discrete EHs whose design bases are defined at the mean
10-5/yr frequency††††† is judged to be consistent with this intent.
89. Similarly, the use of good engineering principles applied to protect and mitigate
conservatively defined non-discrete EH initiated faults down to the 10-4/yr exceedance
frequency value is likely to produce a plant that can meet the risk targets, with
balanced risks from different classes of initiating event (EHA.18 paragraph 246(d) and
SAP paragraph 749), and whose risks are reduced ALARP.
90. The following factors are taken into consideration in reaching this conclusion:
The design basis is evaluated on a conservative rather than best estimate basis.
Where the design basis is used as a hazard withstand design criterion there is a
margin available from design codes, for example. In earthquake hazard terms for
some structural forms, the design basis loading condition could be matched to the
so called High Confidence Low Probability of Failure point of a SSC fragility curve.
This would normally result in a sizeable margin to loss of safety function defined
for example as the onset of inelastic behaviour, or structural collapse. A good
understanding of SSC SFRs and modes of failure is needed in this case, and
ONR’s expectation generally is that such failure modes will be gradual and
predictable, see for example SAP paragraph 345.
91. It is important that this assumption is verified by appropriate use of PSA or other
means (SAP FA.14 - use of PSA to inform the design process).
92. The design basis process should prevent EHs considered within the design basis from
initiating accidents that lead to core damage and fission product release for reactor
This is generally interpreted as any fault down to a mean frequency of 10 -5/yr. The SAPs will be
†††††
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 30 of 84
Office for Nuclear Regulation
systems, or significant release for non-reactor systems. Natural hazards, however, are
described by hazard curves covering a wide range of frequencies, part of which
extends well below 10-4/yr, and therefore some consideration must also be given to
events at these very low frequencies. Such events may contribute significantly to
facility risk. For non-discrete hazards therefore, BDBA and PSA are very important and
often help to define the hazard severity at which plant failure occurs.
93. When the hazard analysis is complete and design basis events defined, the Licensee
should define relevant parameters to input to the plant / SSC design process or plant /
SSC withstand substantiation. This subject extends beyond the scope of this TAG, but
is discussed as appropriate within individual hazards appendices and annexes (see
also paragraph 18.).
94. SAP paragraph 240 allows for consideration of a relaxation of the design basis criteria
for non-discrete hazards if the unmitigated potential consequence is low.
95. FA.5 and Target 4 define the frequency / consequence threshold where DBA is likely
to be proportionate to the radiological hazard or consequence potential. It is suggested
that the following guidelines provide the basis for definition of the EH design basis
event providing consistency between plant initiated faults and faults initiated by EHs.
These guidelines are illustrated in Figure 3.
96. For discrete EHs, SAP paragraph 628 (d) is considered applicable. That is, design
basis events should be defined for discrete EHs having an estimated frequency of
occurrence within the DBA region indicated on Figure 3.
97. For non-discrete EHs, the criteria in paragraphs a) to d) below are suggested for the
design basis hazard definition. In this case, DBA is expected to cover the region of the
hazard curve down to the frequency on the hazard curve described in paragraphs a) to
d) and illustrated on Figure 3. The DBA region for non-discrete hazards approximates
to that for plant faults and discrete EHs when the requirements for a conservatively
defined design basis event are taken into account (see paragraph 98.):
a) Facilities that could potentially give rise to unmitigated dose consequences greater
than 100mSv to any person off-site or 500mSv to a worker may have a design
basis event that conservatively has a predicted frequency of being exceeded no
more than 10-4/yr.
b) Facilities that could give rise to doses between 10mSv and 100mSv to any person
off-site or 200mSv to 500mSv to a worker may be designed against a design basis
event, defined on a sliding scale, that conservatively has a predicted frequency of
being exceeded from no more than 10-3/yr to no more than 10-4/yr.
c) Facilities that could give rise to doses between 1mSv and 10mSv to any person
off-site or 20mSv to 200mSv to a worker may be designed against a design basis
event, defined on a sliding scale, that conservatively has a predicted frequency of
being exceeded no more than 10-2/yr to no more than 10-3/yr. For some facilities,
the EH loads arising from application of normal industrial standards may provide
an appropriate design basis and compliance with Building Regulations may be
sufficient.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 31 of 84
Office for Nuclear Regulation
outside the design basis. The Licensee should therefore demonstrate that these
risks are ALARP.
98. The above criteria are overlaid onto Figure 3 (the dotted line). It can be seen that the
design basis event definition and effective DBA threshold for natural hazards appears
to be less onerous than that defined for fault analysis. This is not the case because the
Initiating Event Frequencies (IEFs) for plant / SSC initiated faults are evaluated on a
best estimate basis, whereas exceedance frequencies for non-discrete EHs should be
evaluated on a conservative basis to allow for data uncertainty. For the reasons
discussed above (paragraph 82. et seq), this is considered appropriate.
Initiating
event 10-2
frequency
(/yr)
10-3
10-4
10-5 Target 4
(BSL)
99. Figure 3 indicates the natural EH design basis definition, allowing for conservatism and
uncertainty. As noted in paragraph 78., ONR’s expectation is that the level of
conservatism should generally correspond to approximately one standard deviation
above the median. Since the uncertainty distribution is dependent on the particular
hazard in question and the return period, it is not possible to define precisely the
evaluated design basis region on Figure 3, and the design basis region should be
viewed as indicative. Inspectors should assess the basis upon which Licensees’
consider their selection of non-discrete EH design bases to be conservative to ensure
it meets the intent set out in this section.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 32 of 84
Office for Nuclear Regulation
100. Whilst the approach detailed above is valid, care should be taken when reviewing
Licensee submissions, since for EHs the levels of uncertainty associated with defining
hazard severities can be large (and difficult to quantify). Efforts at extreme precision
should therefore be treated with caution, and the requirements of EHA.7 regarding cliff-
edge effects should also be considered. Alternative approaches based around the
DBA objectives laid out in SAP FA.7 could also be considered provided they can be
justified and the risks shown to be ALARP (see also SAP paragraph 599).
101. Consideration of plant response to EHs beyond the design basis has been an
established principle in the SAPs since 1992 and within some Licensee’s
arrangements before then, but its origins date back to development work by the US
Nuclear Regulatory Commission (USNRC) in the 1980s, see [44]‡‡‡‡‡. The response to
this principle by UK Licensees has primarily concentrated on seismic vibratory hazard
and has generally taken the form of an enhanced design basis approach, either calling
on known conservative assumptions in the design process itself, or extending the
design basis hazard severity by a known (but somewhat arbitrarily defined) factor.
102. BDBA is not restricted to the subject of EHs. However, because some EHs are
characterised as non-discrete (in contrast to plant initiated faults for example), they will
necessarily have a BDB component to consider as the site challenge can be computed
down to very low frequencies (albeit with increasing levels of uncertainty), well below
the design basis frequency. Events in this range are more severe than the design
basis and are all BDB events.
103. The accident at Fukushima in 2011 has generally been interpreted, in terms of plant
response, as a BDB event§§§§§. It raised serious concerns over the operator’s
knowledge of how the plant would respond to such an event and the lack of adequate
protection in place to mitigate the deleterious effects of consequential plant failures.
104. Subsequently, the role of BDBA has attracted significant interest worldwide. Of
particular interest to the UK are recently published standards by IAEA and WENRA,
see Section 4; the WENRA standards are referred to below. Of direct relevance is a
new SAP, EHA.18, and associated text revisions in the 2014 edition of the SAPs [5].
This section provides an explanation of the regulatory expectations that ONR has
developed in response to this recent work.
105. It is generally accepted that two levels of BDB events are relevant to non-discrete
hazards, one of which is primarily concerned with the potential for cliff-edge plant
failures for events marginally above the design basis. The second concerns more
extreme events that could severely challenge plant safety functions across the site.
‡‡‡‡‡
This work derives from the USNRC’s Severe Accident Program set up in the aftermath of the Three
Mile Island accident. A major programme of Independent Plant Examinations was undertaken at all
existing US sites. In tandem a specific programme of Independent Plant Examinations for External
Events was undertaken to cover EH specifically. Ref. [44] provides the learning from that programme.
Subsequently, USNRC has undertaken extensive post-Fukushima development work that effectively
extends the IPEEE work, including re-examination of seismic and flood protection arrangements. At the
time of writing the USNRC is proposing new rulemaking on the mitigation of BDB events.
§§§§§
Although expert opinion now generally agrees that the tsunami that occurred should have been
considered within the design basis and specifically designed against.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 33 of 84
Office for Nuclear Regulation
associated paragraphs 246 (a) & 247. This is a success based analysis, where the
intent is to show that plant failure does not occur (Paragraphs 114. et seq).
To demonstrate that for EH events significantly beyond the design basis, the
Licensee has an understanding of how nuclear safety significant plant / SSCs
responds, what failure modes can occur and how the ability of plant / SSCs and
operators to deliver safety functions is degraded. Principle EHA.18 applies
specifically with paragraphs 246 (b) & (e) and 248 (paragraphs 127. et seq).
107. As noted in paragraph 92., the use of good engineering practice applied to protect and
mitigate conservatively defined non-discrete faults initiated down to the 10-4/yr
exceedance frequency value, is likely to provide a level of risk control that will satisfy
the SAP risk targets. However, because non-discrete EHs are described by hazard
curves covering a wide range of frequencies, parts of which extend well below 10-4/yr
the BDB component may contribute significantly to facility risk. For non-discrete
hazards therefore, BDBA is important and can help to define the hazard severity at
which plant / SSC failure or loss of safety function occurs.
108. Where a design basis is established for a discrete EH and a hazard curve is not
defined, the possibility of an event more severe than the design basis may also need
consideration. This applies if the event initiation frequency is difficult to determine or if
the IEF is less than the design basis criterion. A possible approach to demonstrate
sufficient margin to loss of safety function for the former is to select one or more
hazard-specific loading values that are higher than the design basis event loads and
demonstrate that the safety functions are not endangered by these loads. The severity
of the loading values may be chosen to correspond to a safety margin that is
considered adequate. The use of a MCE for such analyses may also be useful, but
caution should be exercised if the selected MCE is very severe, since this might lead
to the conclusion that for such an event reasonably practicable plant improvements do
not exist. Selecting a more reasonable choice of BDB event may provide opportunities
for reasonably practicable plant improvements.
109. For the latter, where the hazard occurrence frequency is estimated to be below the
design basis criterion but above the EH screening criterion (Section 5.3.1) the fault
analysis guidance given in SAPs paragraph 609-610 is applicable. In this case it is
expected that assessment of the likely accident progression and potential
consequences should take place to allow consideration of reasonably practicable
means of protection or mitigation of the consequences such that the risks are ALARP
(see Section 5.6.2).
Demonstrate sufficient margin to avoid cliff-edge effects just beyond the design
basis (SAP EHA.7).
For non-discrete hazards, identify the hazard level at which safety functions could
be lost, in other words determine the BDB margin.
Provide an input to PSA to establish whether risk targets are met (see SAPs
paragraph 695 et seq).
Ensure that small changes to the design basis fault or event assumptions do not
lead to a disproportionate increase in radiological risk (SAP EHA.7).
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 34 of 84
Office for Nuclear Regulation
111. It has previously been accepted that one satisfactory approach to the demonstration of
absence of a disproportionate increase in consequences is via an EHs PSA. This has
the merit of exploring the response of the plant to a wide range of hazard levels and is
accepted internationally as a reasonable approach for EHs, but inspectors should
exercise caution in their interpretation of the absolute risk values themselves.
112. WENRA [15] has provided guidance on BDBA; they define two levels of Design
Extension Conditions (DEC) that can be broadly mapped to the advice in this guidance
as follows******:
DEC “A” for which prevention of severe fuel damage in the core or in the spent fuel
storage can be achieved. This is broadly equivalent to the expectations expressed
in SAPs EHA.18 (part) and EHA.7 (cliff-edge effects).
DEC “B” with postulated severe fuel damage. This is broadly equivalent to the
expectations regarding SAA expressed in ONR SAPs EHA.18 (part), FA.15
(Scope of SAA) FA.16 (Use of SAA) and FA.26 (Relationship to DBA and PSA).
Cliff-edge analysis
114. The analysis of cliff edge effects should seek to provide confidence that the plant
design and its operation are robust in the face of uncertainties to design basis
definition and the plant design process, and that SFRs if degraded, do so in a
predictable and gradual manner. Events relating to cliff edge effects just beyond the
design basis are broadly consistent with a WENRA DEC “A” event.
115. The objective is to demonstrate that the design remains fit-for-purpose despite these
uncertainties and there is a high degree of confidence that it will be able to deliver
design basis safety functions as intended.
116. A feature of hazard induced faults is that the loss of safety function may be subject to
so called “cliff-edge” effects, where small changes in the hazard severity, facility
response (eg rapid onset of a failure mode or loss of a SFR), or DBA assumptions /
modelling parameters could lead to a disproportionate increase in radiological
consequence. EHA.7 introduces the need to demonstrate that there will not be a
disproportionate increase in radiological consequences from an appropriate range of
events that are more severe than the design basis event.
117. The way in which this principle is satisfied may depend on the nature of the hazard
being addressed. For some non-discrete hazards, a point will be reached where there
is a step change in the effect on the installation. In the case of external flooding, for
example, the site defences may become overtopped by still-water flood height. In such
cases, it needs to be shown that there is a reasonable margin between the design
basis flood level and the height at which this step change would occur.
118. For other hazards, such as earthquake, the forces acting on the facility will continue to
increase progressively with increasing size of event. A demonstration is needed that
there will not be a step change in the response of the installation to the hazard (eg
collapse of a floor or wall) for an appropriate range of events more severe than the
design basis event. The response of a structure to earthquake loads beyond the
design basis can be enhanced considerably by adopting a ductile structural form and
incorporating ductile detailing. This is a preferred method of demonstrating no
See Table 4: Existing Reactor R T6.1, T6.2, T6.3 & New NPP Designs Position 6, Analysis
******
Considerations.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 35 of 84
Office for Nuclear Regulation
119. The accurate identification of critical failure modes and their nature (eg ductile or non-
ductile) is helpful since this can aid the identification of the actual threshold of failure.
120. In respect of safety related equipment, loss of safety function should not, where
practicable, lead to another fault condition, ie equipment should be designed, where
practicable, to fail safe following an EH.
121. Licensees should demonstrate the absence of cliff-edges, associated with both the
hazard severity and plant response. There should be a demonstrable margin between
the design basis and the loss of the design basis safety function that reflects the
known uncertainties in both hazard analysis, plant response analysis. This is
considered to represent good engineering practice.
122. The advice of SAPs ECE.2, ECE.6 and supporting paragraphs, in particular, are
relevant to the analysis of BDB response of civil structures.
123. Special considerations for non-discrete hazards: Where hazards are characterised by
a hazard curve, as noted in paragraph 28., hazard severity can increase significantly
beyond the design basis. To avoid cliff-edges therefore, it is important to establish that
the hazard varies gradually around the design basis frequency, and that the plant
response does not suddenly change in this region, say due to brittle structural failure or
still water overtopping of a flood barrier.
124. For non-discrete hazards the analysis of BDB events cannot generally be divorced
from consideration of the exceedance frequency of the events considered. ONR
considers that if a single BDB event is selected for the BDBA, a reasonable starting
position is to consider the 10-5/yr event (assuming this is more severe than the design
basis), and to examine whether the design basis defined conservatively (alone or in
combination with other design aspects such as response spectral damping ratios),
envelopes the mean 10-5/yr event on the hazard curve. Note that the design basis
hazard value may well be very much greater than the site-specific hazard analysis
value, implying a large in-built margin to the design basis hazard definition. Licensees
may wish to use this directly to support claims of absence of cliff edges.
125. Historically some Licensees have employed a 40% increase on the design basis for
BDBA of seismic vibratory hazard, coupled with removal of some of the inherent
conservatisms in the DBA, as a surrogate to represent no disproportionate increase in
risk. ONR has never considered that a pre-assigned numerical margin provides an
adequate response to the intent of EHA.7, without justification on a case-by-case
basis, and it is unlikely to meet the expectations of the SAPs more generally as a sole
response to the issue of BDBA, except possibly for low radiological hazard facilities.
126. Special considerations for discrete hazards: As noted in paragraph 108., discrete EHs
are free of the complications arising from hazard curves. It may be appropriate to
postulate an event of increased severity such that the design basis can be tested in
light of the uncertainties involved in both the design basis definition and the associated
plant design process, to ensure that safety functions can still be reliably delivered.
127. The analysis for this higher level of BDB event applies inevitably to non-discrete
hazards because the site challenge can be computed in terms of a hazard curve that
extends to very low frequencies, consistent with those considered in SAA. It is also
applicable for discrete EHs having an estimated occurrence frequency below the
design basis criterion, but which cannot be screened out. The IEF itself can be
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 36 of 84
Office for Nuclear Regulation
numerically similar to risk targets defined in the SAPs. At these severe hazard levels, if
conditional plant / SSC failure probability is close to unity (ie loss of safety functions
definitely occurs), such EH events may contribute significantly to overall plant risks.
These events are consistent with WENRA DEC “B” events.
128. It is anticipated that the analysis of nuclear safety plant to EH events in this region will
be captured by an EH PSA, see Section 5.6. A further consideration is the need to
identify plant and SSC damage states arising from very severe EH events for input to
the SAA (Section 5.7) if these differ from those identified for other reasons. In this
regard, particular attention should be given to the potential for widespread common
cause effects and the likely islanding of the site from off-site services and supplies.
This latter effect should also be considered in developing the site’s emergency
arrangements, see Section 5.9.
129. The BDBA should, so far as reasonably practicable, identify the most resilient means
of ensuring that fundamental safety functions are maintained, and estimate the hazard
values at which loss of safety functions occur.
130. EHs PSA supports the DBA by quantifying the frequencies with which radiation doses
to both public and workers from EH faults could occur. This enables direct comparison
with risk targets SAP NT1 etc and provides quantitative support that for the design, risk
has been reduced to ALARP. As discussed in paragraph 91., EHs PSA can be used to
support the selected design basis definitions for non-discrete EHs (10-4 annual
probability of exceedance) as being sufficiently conservative (also see paragraph 98.
and Figure 3). Finally, the EH PSA can contribute to the wider PSA calculations to
show that a balanced design has been achieved such that reasonably practicable
protection is provided across all hazard and fault types (SAP paragraph 749).
132. For major nuclear hazards plant, the expectation is that a Level 1 and 2 PSA will be
undertaken and this is reflected in the UK’s response to the Fukushima event as
Recommendation FR.4, [46]††††††. Note that if a Level 3 PSA is performed, extreme
environmental conditions may affect the transport of fission products and also
expectations regarding countermeasures. These possibilities should also be borne in
mind when interpreting the Level 2 PSA results.
133. For new facilities, it is anticipated that a PSA would include specific consideration of
EHs as initiating events (FA.14). Fragility data tends to be expressed as mean (best
estimate) SFR capability or withstands rather than conservatively as for deterministic
purposes, or the uncertainties are fully quantified as a probability distribution. However,
any withstand data should be developed from the same base information, subject to
relevant scale factors and uncertainties.
134. For existing facilities, the need for EH PSA also exists, however in the UK, Licensees
have adopted a pragmatic approach based on a qualitative appreciation of the EH
risks. The expectation of a quantified analysis of EH risks even for existing major
A major research project is currently underway in response to lessons arising from the Fukushima
††††††
event relevant to PSA, called Advanced Safety Assessment Methodologies: Extended PSA
(ASAMPSA-E). It is funded by a consortium of regulators, utilities and contractor organisations across
Europe, to develop EHs PSA methodology. This project has recently published progress in several
areas. For more details, see http://asampsa.eu/deliverables-library/.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 37 of 84
Office for Nuclear Regulation
135. Development of fragilities against EHs is a potentially complex and time consuming
process, with large levels of uncertainty associated with it. Following completion of the
PSA, it is suggested that the results are interrogated and the relative importance of
plant, structures and equipment extracted. This will give an indication of those areas
where the inspector should focus his attention. Care should be taken in the use of
generic fragility data, especially when applied to bespoke SSCs or items of high
importance to safety.
136. As noted above, non-discrete EHs are characterised by a hazard curve extending well
below the design basis point. The risk potential of the hazard is likely to be adequately
controlled down to the design basis frequency, and the significant risk will likely be
attributable to BDB frequencies. Therefore, PSA is necessary to characterise the risk
from non-discrete EHs, ensuring the risks are ALARP and a balanced plant design is
achieved.
137. Severe accidents are those where a postulated or unforeseen plant fault sequence has
left the nuclear facility in a degraded state (FA.15 & SAPs paragraph 610 and TAG 7
[47]) where significant nuclear safety functions have been severely challenged and the
intent of DBA expressed in FA.7 has not been met.
138. The potential for EH events to lead to severe accidents should be considered by the
Licensee. As noted in paragraph 127., severe accidents are most likely to apply to
non-discrete EHs; TAG 7 classifies severe accidents and the class most likely to apply
is “high consequence event of low frequency beyond the design basis”, see [47]
Section 5.2. The purpose of this (best estimate) analysis is to identify reasonably
practicable provisions that can be implemented for the prevention and / or mitigation of
severe accidents. Where severe accidents are postulated, the analysis should identify
reasonably practicable provisions to mitigate their consequences. In judging the
adequacy of safety cases, inspectors should especially consider the effects of very low
frequency events from non-discrete hazards, eg seismic events in the exceedance
frequency range 10-5/yr – 10-7/yr. If these can credibly lead to severe accident plant
states, they should be considered as part of the SAA. Further detailed analysis of an
event will not be necessary if it is shown that its occurrence can be considered with a
high degree of confidence to be extremely unlikely.
139. A particular aspect of EHs is that in addition to being a potential initiator of an accident
state, the hazard may also affect the consequences in terms of fission product
transportation (eg weather or flood conditions) and also the implementation of the
emergency preparedness arrangements.
140. A further important consideration is that natural EHs are significant common cause
fault initiators, and will also be expected to severely affect off-site areas.
141. Licensees should take into account combinations of EHs that could reasonably be
expected to occur at a given site. Combinations of hazards should be identified and
considered as part of DBA, PSA and SAA.
142. Licensees should follow a systematic process to identify and categorise hazard
combinations and should then screen those hazards on the basis of plant effects and
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 38 of 84
Office for Nuclear Regulation
occurrence frequency.
Identification
143. The identification of combinations of EHs should start with the unscreened list of
individual EHs. The unscreened list should be used because individual hazards that
have been screened out based on plant effect may still have a significant impact in
combination with another hazard.
144. A matrix approach is often used to list and identify hazard combinations. A helpful
cross-correlation matrix has been included in a recent report by a European Union
funded project called ASAMPSA_E, as part of developing a revised EHs PSA
methodology [48].
145. The use of a matrix is beneficial, but care should be taken in its application. Applying a
2-dimensional matrix alone is not sufficient as a 2-dimensional matrix only considers
the combination of two hazards and can cause groups of more than two hazards in
combination to be overlooked. An example of a combination of three or more hazards
that should be considered is the combination of high tide, storm surge and waves.
However, consideration of every possible combination of three of more hazards is
likely to be an onerous task. A reasonable approach would be to apply a 2-dimensional
matrix and then supplement this with expert judgment to ensure that reasonably
foreseeable combinations of more than two hazards are considered. Inspectors should
assure themselves that where expert judgment has been used to identify multiple
hazard combinations, it has been used in a systematic manner as part of the
identification process, to ensure that all credible combinations have been identified, so
far as is reasonably practicable.
146. A possible approach taken by one Licensee to assist in avoiding missing important
combinations was to identify the most significant hazards first, seeking potential
combinations with those of equal and lesser significance. In this way the intent was to
present a cascade of possible combinations with those likely to be most significant
being identified early on.
Categorisation
One or more hazards that affect the plant and occur as the result of a separate
event that also affects the plant. For example, an earthquake that causes a
tsunami.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 39 of 84
Office for Nuclear Regulation
One or more hazards that affect the plant in the same time-frame due to
persistence or similar causal factors. For example, meteorological conditions such
as storms intrinsically involve the combination of several phenomena such as
rainfall, wind, and storm surge.
One or more hazards may exacerbate other hazards. For example freezing
conditions, drought or persistent rain can affect drainage conditions during
subsequent rainfall.
One or more sequential hazards that affect the plant. Hazard combinations can be
important when they occur sequentially, as the following example illustrates.
Consider the case where wind hazard causes damage to building cladding, part of
whose safety function is to provide a weather envelope to keep rainwater from
entering the building. Any rainfall occurring during the period before the cladding is
repaired and the safety function is restored will gain entry to the building and the
potential for internal flooding is heightened.
Screening
152. Combinations can be screened out if they do not pose a significant risk to the plant, or
if the consequences of the combination do not exceed the consequences of one of the
elements of the combination. Combinations of hazards can potentially affect plant and
SSCs in different ways. Some combinations can affect plant by undermining the
diversity of systems – for example, an earthquake that causes loss of off-site power
(LOOP) combined with a tsunami that causes loss of battery power supply, as was the
case for the Fukushima Dai-ichi event. Other combinations of hazards can affect a
single system via the production of an additional load. An example of this would be an
extreme snow load on the roof of a building that must also resist loading from an
extreme wind event. The requirements for segregation, redundancy, separation and
diversity should be considered in light of both of these effects. If the widespread effect
of a combination has the potential to undermine the diversity strategy of the plant, then
this should be taken into account when considering whether or not to screen that
particular combination in to the safety analysis.
153. Many combinations can be screened out based on low frequency. This is likely to be
the case for the majority of coincidental hazards. When considering screening on the
basis of low frequency, both the duration of the hazards and the time to repair SSCs
should be taken into account.
154. An example set of screening criteria, taken from [49], is given in Table 6.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 40 of 84
Office for Nuclear Regulation
156. Inspectors should ensure that Licensees have developed a systematic method of
screening that is consistent with categorisation scheme that identifies individual EHs,
captures the inter-relationship between those EHs and consequential effects that are
significant to nuclear safety for their site. If a matrix approach has been used to identify
potential combinations of hazards, the matrix could then be reviewed against the
categorisation scheme.
Development of Design Bases and other safety analysis inputs for screened in EH
combinations
157. Once combinations have been identified, categorised, and screened, they provide
input for the next stage of safety analysis via the fault schedule, as well as providing
input into the PSA. The goal is to arrive at a plant that meets the risk targets and for
which risks are reduced ALARP. There are very few hard-and-fast rules that form RGP
at this time. Guidance to inspectors is as follows:
Correlated and secondary hazards: These are hazards that have a tendency to
occur in combination. Licensees should analyse these combinations to
establish credible individual hazard severities to be used as combined design
bases for DBA. This could include at worst, assuming the full design basis level
for each individual hazard simultaneously, or deriving a combination effect that
collectively meets the design basis criteria in Section 5.5.1; eg wave and tide
combinations are routinely analysed to develop a composite 10-4/yr design
basis sea level.
Coincidental hazards: These are random combinations and for these inspectors
should ensure that a pragmatic and reasonably conservative approach has
been taken by Licensees. For example, seismic hazard may be combined with
a wind hazard that might reasonably be expected during the life of the site,
typically covered by conventional building codes eg Eurocodes such as [51] at
2x10-2/yr (1/50yr). Combinations with other weather hazards should similarly be
justified on a pragmatic basis. Inspectors should ensure that significant
departure from this guidance is justified to ensure that the resulting safety
analysis demonstrates that risk is ALARP.
158. For all types of hazard combinations, it is the duration of the consequential effects of
each hazard that needs to be considered, rather than the duration of the hazard itself.
For example, a seismic event may last just a few tens of seconds, but the overall effect
on the plant could last several days or weeks. If a severe rainfall event were to occur
before damage from the seismic event had been repaired, the consequences of the
rainfall event could be more significant. This needs to be taken into account in the
safety analysis (see also correlated hazards at paragraph 157. above).
159. It is appropriate to assume best estimate live loadings apply with design basis wind or
seismic hazard loads. Judgment may be required as to whether a "normal" snow load
should apply with a wind loading etc, or whether wind is likely to remove all but the
hardest snow crust. Discretion may be applied to the application of normal wind load
with design basis seismic load. The effects are likely to be additive over at least part of
a structure, so consideration as to an appropriate wind load may be required.
However, inclusion of multiple wind directions considerably increases the number of
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 41 of 84
Office for Nuclear Regulation
seismic load cases, and the combined results make comprehension of the seismic
behaviour more obscure. There may also be a wide range of "normal" (non-EH)
loadings that might apply at any single time, such as crane position or load etc, and in
these the assumed combination should be such that all "normal" cases are shown to
be enveloped. However, the intent of SAP paragraph 631 should be borne in mind, in
particular that the “normal” loads assumed should be the most onerous consistent with
those allowed within Operating Rules established under LC23, but where each load in
the combination is considered on a best estimate basis, or consistent with RGP.
160. Where a wide range of “normal” loads exists or they combine in many ways,
distinguishing the most appropriate combinations from a nuclear safety perspective
can be difficult. In such cases, the use of sensitivity analysis can be helpful to
identifying the likely most onerous “normal” load cases for use in the DBA.
161. A difficulty regarding the use of design codes for EH design basis loads is that loads
due to normal operations will be those that relevant codes would expect as part of the
design process. In the case of the nuclear design basis for EHs, the exceedance
frequency of 10-4/yr may not be considered “normal”. Inspectors should confirm that
Licensees are not using unreasonably low factors of safety, less than unity for
example, on the assumption that the occurrence of a design basis event is an
exceptional event, or an accidental loading.
162. Sometimes a "time at risk" (SAP paragraph 759 et seq including NT2) argument is
proposed to limit the scope of combined load cases. Care should be taken for example
to ensure that short duration, but high risk operations are not automatically accepted
on a time at risk basis, without a thorough investigation into the options for reducing
the risk. T/AST/005 - ONR Guidance on the Demonstration of ALARP [6] provides
further guidance.
163. The inspector should ensure that a reasonable combination of other relevant loads
(including fault loads where appropriate) is assumed to apply simultaneously with the
hazard of interest, see EHA.5. For plant operating loads, temperature, pressure,
availability etc, these should be taken as the extremes of the operating envelope,
which should be reflected in the limits placed in the Operating Rules or Technical
Specifications. Sensitivity studies may also be necessary to ensure that the chosen
values and combinations are conservative.
164. Natural hazards should also be considered potentially coincident with anticipated
operational occurrences, eg equipment outages or minimum manning levels, and
design basis accident conditions. However, as with un-correlated EHs, consideration
should be given to the combined likelihood of non-causally linked occurrences to avoid
undue conservatism.
165. Many EHs such as wind, temperature, flooding and earthquake, have the potential to
challenge all facilities on a single site simultaneously. Furthermore, EHs may threaten
neighbouring installations that in turn threaten the plant under consideration. For
chemical plants and some Ministry of Defence related facilities the total risk targets
from SAP Target 3 are often divided among the facilities on the site in an approximate
way. Licensees may operate in such a way that the hazards presented to one facility
by others, especially if their purpose and processes are completely separate, may be
treated as EHs, yet simultaneously treated as internal hazards or internal plant faults in
the “other” facilities. For example, explosion from gaseous release from one plant may
be treated as an internal hazard in this plant, but an EH in a separate adjacent plant on
the same site.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 42 of 84
Office for Nuclear Regulation
166. Caution should be exercised if the SAP paragraph 241 approach for a less severe
hazard definition (as suggested in Section 5.5.2 above) is adopted for a multi-facility
site. In such cases, a cross-site summary of risk should be undertaken, eg in a high
level site safety case, in addition to the individual facility safety cases, (T/AST/051 -
Guidance on the Purpose, Scope and Content of Nuclear Safety Cases [52]) and
paragraphs 42-43 of the SAPs should also be taken into account.
167. The IAEA offers guidance on the safety analysis applied to multi-unit reactor sites.
Inspectors should consider IAEA SSR 2/1 [22] and especially Requirement 17
paragraph 5.15B reference to common cause effects, and Requirement 33 reference
to DECs, covered here as BDBA.
168. It should be noted that the GDA process is based on the assessment of a single
reactor unit. During the site licensing and subsequent construction permissioning
assessments, due account should be taken of the deployment of multiple units.
169. The overall analysis (DBA, BDBA, PSA and SAA) should consider the use of common
equipment or services and demonstrate that sufficient resources remain available.
170. This TAG and supporting annexes implicitly assume (unless explicitly stated) that the
site consists of plant containing significant nuclear hazard and is of modern design. In
these cases, this guidance, where relevant, should be by inspectors rigorously applied.
As stated in the SAPs paragraphs 31-33, the safety standards used in the design and
construction of older plants may differ from those used in more recently built facilities.
Whilst some hazards may not have been considered fully in the original design of
plants, in the re-evaluation under periodic safety reviews, they should be treated as an
integral part of the safety demonstration.
171. This may mean that for some older facilities it may be difficult to accommodate the
loading associated with a 10-4/yr event. SAP paragraph 33 provides the following
guidance: “For facilities designed and constructed to earlier standards, the issue of
whether suitable and sufficient measures are available to satisfy the ALARP principle
will need to be judged case by case.”
172. In these cases, it is necessary, firstly, to ensure that the risk arising from the hazard is
tolerable, and secondly to determine whether sufficient work is being done by the
Licensee to both ensure and demonstrate that the risk is ALARP. In reaching this
judgment the inspector should take into account the projected future life of the facility,
including the time needed to decommission the facility. In general, the longer the
period for which the plant is needed, the stronger is the case for it to comply with
modern standards. Further guidance on the ALARP principle can be found in
T/AST/005 - ONR Guidance on the Demonstration of ALARP [6].
173. In terms of EHs, inspectors should consider the following factors when judging the
extent to which this guidance applies:
Design basis – Whilst it may not be practicable for older plant to accommodate the
needs of a design basis defined in accordance with EH.4, inspectors should
ensure that the design basis selected provides sufficient challenge to the plant to
ensure that important fault sequences have been identified and mitigated to the
extent needed to ensure risk is ALARP.
Need for PSA and SAA – Many older facilities, even high nuclear hazard facilities,
either do not, or only have simplistic, EHs PSA and SAA analyses. Inspectors
should adopt a pragmatic approach in these cases and keep in mind that such
analyses are there to support the demonstration that risks are ALARP and that
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 43 of 84
Office for Nuclear Regulation
174. It may be difficult to demonstrate that an older facility has an adequate balanced
design in risk terms. Inspectors should consider this aspect on a case-by-case basis,
and seek a response from Licensees that is proportionate.
175. As stated above, this TAG and supporting annexes implicitly assume (unless explicitly
stated) that the site consists of plant containing significant nuclear hazard and is of
modern design. In these cases, this guidance, where relevant, should be rigorously
applied by inspectors. For new sites, ONR expectations are that the full application of
RGP is reasonably practicable.
176. New reactors intended for construction in the UK undergo GDA, which is a pre-
licensing process that provides RPs with the opportunity to demonstrate at an early
stage that the design is capable of meeting the legal requirements of the UK. It also
facilitates a robust ONR assessment of the proposed design. During GDA, the
intended site for the new reactor development may not yet be known, or there may be
several candidate new build sites. Therefore, RPs usually define a “Generic Site” with
characteristics typical of the UK. These characteristics should, as far as possible,
envelop or bound the characteristics of known potential sites in the UK so that reactors
of the proposed type could potentially be built at a number of suitable locations‡‡‡‡‡‡.
Further information on GDA is available in the document “Guidance to Requesting
Parties” [11]. For GDA, the EHs inspector should:
Assess the scope of the GSE and its applicability to the UK context.
Ensure that the RP has applied a robust process to ensure that the design meets
modern standards in accordance with RGP for EHs.
Ensure that the RP has identified potential vulnerabilities of the design to EHs and
examined the possibility of cliff-edge effects.
177. The expectation is that RPs will define a generic design for GDA, including a GSE
complete with a range of EH design basis definitions. However a RP may pursue the
development of a site-specific design, or the subsequent Licensee may modify an
existing generic design to take advantage of, say, a particular site-specific hazard
challenge that is substantially lower than initial generic assumptions, offering
commercial advantages. Under these situations, the inspector should be confident that
site-specific design basis hazard definitions remain consistent with the expectations of
SAP EHA.4.
178. The inspector should also liaise with other specialist inspectors to ensure that
interfaces are taken into account, refer to paragraph 34. and Table 3. This is
particularly important when considering consequential hazards, where appropriate
expertise may lie in other disciplines, such as internal hazards, civil engineering, or
mechanical engineering.
This envelope is referred to in paragraph 21 et seq and Figure 2 as the Generic Site Envelope
‡‡‡‡‡‡
(GSE).
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 44 of 84
Office for Nuclear Regulation
179. Assessment of EHs for New Reactor Licensing and Construction is an iterative
process. One of the major milestones in the process is the assessment to support
licence granting. Other milestones and hold points will be decided as part of the
project.
180. New Reactor Site Licensing: During site licensing, the focus is on-site suitability and
future Licensees’ capability. Before granting a site licence, a Site Licence Applicant
(SLA) needs to demonstrate to ONR’s satisfaction that a particular site is suitable to
support safe nuclear operations. One of the main site suitability aspects that needs to
be demonstrated is that the nuclear facility will have robust defences against a range
of EHs. This is underpinned by SAP ST.4 and paragraph 131, which state:
"The suitability of the site to support safe nuclear operations should be assessed
prior to granting a new site licence. Such attention will normally focus on external
hazards and civil engineering issues. These should consider the potential
vulnerability of the site to external hazards and the extent to which construction of
new facilities can be safely accomplished."
181. The SLA should show that the site-specific EHs challenge is bounded by the GDA
envelope. Hazards having little or no margin between the GDA GSE and the site
challenge will need to be justified. Hazards not included within the GDA assessment
will need to be listed, quantified and their effects on nuclear safety analysed. A
statement on how these will be protected against will need to be made.
182. The SLA should also, as part of its licence application, set out a strategy for producing
adequate site-specific safety submissions.
183. New Reactor Construction: As part of the assessment process leading up to new
reactor construction, the EHs inspector should assess the following aspects of the
Licensee’s safety case. This will consist of the site-specific safety submission, normally
a PCSR, and underpinning technical reports on a sampling basis. The production of
site-specific safety submissions takes place in stages in accordance with
arrangements made against the LCs; see Section 3 for aspects relevant to EHs. The
inspector should be satisfied as to the adequacy of the following aspects of the safety
case:
184. Inspectors should be aware that experience has indicated the time between the GDA
project for a new reactor design and subsequent construction activities can be in the
order of 10 years or more – longer than the normal period between periodic safety
reviews required of operating sites under LC15. The definition of RGP adopted during
the GDA project may have changed in this time, potentially leading to the site-specific
safety case(s) being out-of-date by the time they are approved for use. Inspectors
should ensure Licensees address any such shortfalls in a pragmatic and proportionate
way so that such safety cases remain adequate and fit-for-purpose for the facility at the
point of start of operations.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 45 of 84
Office for Nuclear Regulation
186. The single failure criterion is usually considered in relation to plant initiated faults
where the plant fault leads directly to a requirement for a safety system to operate in
order to restore, or provide a safety function. The safety system, which will probably
contain active components§§§§§§, should be single random failure tolerant. The failure is
random in the sense that the initial plant fault does not affect the safety system
reliability.
187. The single failure criterion is not normally a key issue in the context of EHs
assessment, but its applicability may be somewhat more complex than that for internal
plant faults. There are two basic ways in which protection may be provided against
EHs. Most commonly, protection is provided by virtue of structural or equipment
withstand capability against the EH. In other cases however, equipment may not be
resilient to the hazard and protection may be provided by back-up equipment. The two
cases are discussed below.
188. Where the primary protection against an EH is by virtue of the withstand capability of a
structure not involving active components (often referred to as massive and passive)
the application of the single failure criterion is generally not applicable (eg a sea wall to
protect against coastal flooding). The reliability of a structure or system is likely to be a
function of the hazard severity (often characterised by a fragility function). If the
structure / system does involve active components (although this is not common), the
safety function should still be single failure tolerant. In this case single random failure
(applied as appropriate to the active components) should be assumed to occur over
and above any failures relating the hazard impact. The inspector is advised to liaise
with fault studies specialist inspectors to clarify the application of the single failure
criterion to systems consisting of passive structures with active components.
189. Some barriers (eg flood barriers) will have openings for operational reasons and a high
reliability of these is usually required. However, it is not usually practicable to apply the
single failure criterion to these in the sense that there needs to be two openings in
series (like an air-lock with interlocks).
190. Where massive and passive structures are employed, the concept of single random
failure is not applicable. It is not reasonable to assume a massive or passive structure
may randomly fail in such a way that the safety function is lost. There may be a
possibility of a design shortfall or manufacture / material deficiency, but that is not a
random failure in the sense of the single failure criterion as it is a function of the hazard
impact. Such vulnerabilities should be accounted for in the assessment of the
structural reliability / fragility. Such considerations are not generally the preserve of
EHs specialists, instead reference should be made to the civil engineering discipline.
An active component is one that must be energised to perform its safety function. Electrical and
§§§§§§
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 46 of 84
Office for Nuclear Regulation
191. In some cases the single failure criterion applies to EHs in a similar way to that of
internal plant faults. Here an EH may cause a failure of a duty system and protection
against the hazard is secured through the deployment of a back-up system. For
example, electrical supplies could be vulnerable to flooding, and a back-up diesel
generator system may provide essential power supplies. The diesel generator group
would be expected to be single-failure tolerant*******. The concept of “random” failure is
not so straight forward if the hazard can also affect the reliability of the back-up
system. In principle though, the single failure criterion is still applicable as the back-up
system is likely to have active components that could be vulnerable to random failure.
As discussed above (see paragraph 188. in relation to withstand capability) the
inspector is advised to liaise with fault studies specialist inspectors to check that single
failure fault tolerance and system reliability claims are appropriate.
192. In assessing safety systems claimed to mitigate the effects of EHs, the inspector
should have due regard to SAPs EDR.1, 2 and 3. EHs may particularly give rise to
common mode or common cause failures. Good design against EHs makes use of
redundancy, diversity and segregation to mitigate the effects of common mode and
common cause effects. Inspectors should seek evidence of these features in new
facilities and seek a proportionate approach to the implementation of such features
through modification of existing facilities.
193. For many EHs the available data is sparse and requires specialist interpretation to
facilitate a probabilistic treatment; SAPs EHA.2, AV.3 and AV.7 provide high level
guidance on data collection and use. Although the SAPs intend both deterministic and
probabilistic EH initiated plant safety analyses to be undertaken, the deterministic
approach usually depends on a probabilistic definition of hazard loading, in other
words 10-4 annual frequency of exceedance for most natural EHs, see Section 5.5.1
and especially paragraphs 82. - 85.. Current RGP in respect of available data for
natural hazards is covered in detail in Annexes 1 – 3 and the Expert Panel papers that
support them.
194. For natural hazards, quantitative data is largely dependent on the availability of
instrumentally derived records. For seismic vibratory motion these are available in the
UK from about the 1980s; for meteorological hazards they are available from the
1950s for most areas of the UK; for coastal flooding, benefit can be taken from the long
history of naval activity in UK coastal waters, but even here good scientific quality data
is only available for the last 100 years or so. Short datasets like these can take
advantage of sophisticated statistical methods to estimate hazard parameter values
down to statistical frequencies of 10-4/yr and lower, but only with significant
uncertainty†††††††. In these cases, the way uncertainty is handled becomes an important
and sometimes dominating part in the overall hazard analysis.
This could be achieved by having a system consisting of DGs from diverse suppliers and located in
*******
segregated locations.
†††††††
A parameter dataset of N years’ duration can be used to estimate parameter values over longer
return periods (lower frequencies). This represents an extrapolation of the dataset and typically uses a
statistical technique called extreme value analysis. There is debate over the degree of extrapolation that
is reasonable, ranging from a (dataset duration) / (return period) ratio no less than 10%, to no less than
70%. The ratio typically applying to natural hazards when defining design basis hazard severity values
is of order 1% or less. This manifests itself in an increased uncertainty range associated with a specific
hazard value.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 47 of 84
Office for Nuclear Regulation
195. For seismic hazards, it is considered RGP to investigate instrumental data (dataset
duration of a few decades), historical data from cultural records (a few hundred years
depending on-site location) and geological data (millennia). Instrumental data have the
best quality, but the short duration over which they have been collected makes their
use of limited value. Geological data on the other hand, covers the required timescales
and are scientifically derived, but tend to be mainly qualitative and descriptive. The
most important data source for seismic vibratory hazard is the historical data derived
from cultural records such as newspaper accounts and church records. The quality of
such records is limited, but careful processing can deliver useful quantitative data on
the location, size and timing of historical earthquake events.
196. Meteorological and coastal flood hazard analyses have not typically, to date, made
similar detailed use of cultural records, so in this regard, the techniques developed for
seismic hazard analysis are much more mature than those used for other natural
hazards. There are opportunities for greater use of both historical and geologically
derived data in meteorological and coastal flood hazard analyses and this is an area of
active research at this time.
197. Inspectors should seek to assure themselves that Licensees have taken advantage of
all reasonable sources of data. For major hazards sites, inspectors should confirm that
Licensees have made an attempt to research all available relevant data sources,
consistent with the nuclear hazard potential from the site.
198. SAP EHA.1 calls for an effective process to identify and characterise all EH (and
internal hazards) that could affect the safety of a facility; SAPs AV.1 – AV.4 and AV.6
provide guidance collectively on the adequacy of site / plant models, calculation
methods, data and the uncertainties that surround them. The design basis criterion for
natural EHs (EHA.4) corresponds to a hazard severity having an annual exceedance
probability (or exceedance frequency), conservatively evaluated, of 10-4. Furthermore
SAP EHA.19 (screening) calls for an analysis of less frequent hazards than those
associated with the design basis, which could also affect nuclear safety. The
evaluation of hazard severities corresponding to such extreme probabilities is
particularly problematic for natural hazards due to a lack of suitable data, and also due
to an incomplete understanding of the underlying physical processes. These limitations
mean that there is significant uncertainty involved in hazard analysis.
199. Two types of uncertainty are quite widely used in general scientific literature:
200. Classifying uncertainty in this way may be seen as a convenient way of disentangling a
complex uncertainty problem into elements that can be treated analytically in different
ways.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 48 of 84
Office for Nuclear Regulation
201. Generally, in determining the frequency of natural hazards, an extreme value analysis
with a probability distribution such as the Gumbel, Frechet or Weibull is used. These
techniques rely on extrapolating data from a limited number of years to predict hazards
having return periods typically of 10,000 years or more (exceedance frequencies <10-
4
/yr).
202. For natural hazards especially, EVA is often used to extrapolate limited data to very
low frequencies and the potential exists for such extrapolations to be physically
unrealistic. Inspectors should seek assurance that Licensees have sought to calibrate
any EVA predictions against physically plausible modelling, as far as is reasonably
practicable. More details of these methods can be found in Annex 2 [2] (meteorological
hazards) and the supporting Expert Panel paper [8].
203. Such assessment may be considered to address both aleatory and epistemic
uncertainty. However, some elements of epistemic uncertainty may not be captured in
this process. For example, the meteorological processes driving moderate events in
the dataset may not be entirely the same as those relevant to extreme events, yet a
statistical extrapolation implicitly assumes that they are. Secondly, the statistical
method selected may be one from a range of equally plausible methods, where the
analyst has made a judgment as to which to use, based on criteria (such as
experience) that do not form a visible part of the analysis itself.
204. For meteorological hazards, climate change is also a major source of uncertainty.
Although there is a near-universal consensus among scientists that the climate is
changing due to anthropogenic activities, there is a high level of uncertainty
surrounding the changes that can be expected. This uncertainty is due to natural
variability in the climate, incomplete understanding of climatic processes (eg positive
and negative feedback loops) and the inability to model them perfectly, and uncertainty
surrounding future anthropogenic caused emissions [53]. This applies over the lifetime
of the facility including decommissioning. One solution is to take the “managed
adaptive approach”, ensuring adaptability is built into the design (eg flood defences).
Uncertainty due to climate change may be considered largely epistemic in nature, but
RGP currently does not characterise the nature of the uncertainty as being aleatory or
epistemic.
206. Current RGP in uncertainty analysis for seismic hazard has been developed by the
United States Nuclear Regulatory Commission (USNRC) and is known as the Senior
Seismic Hazard Analysis Committee (SSHAC) approach where the aleatory variability
and epistemic uncertainty are treated separately and then combined to produce the
final analysis. The SSHAC approach [54] was developed because in the 1980s
different seismic hazard analysis teams in the US calculated equally valid, but
substantially different hazard values for the same sites in the central and eastern
US‡‡‡‡‡‡‡. The SSHAC developed an approach to epistemic uncertainty analysis that is
This occurred because of the differing methods used to capture knowledge related uncertainty in
‡‡‡‡‡‡‡
their hazard analyses. One approach to solving this problem would be to insist that each hazard
analysis team had on board sufficient expertise to cover every credible interpretation of data and
methodology. The SSHAC approach recognises that this is not practical and sought to develop an
approach to epistemic uncertainty that, if followed faithfully, would yield similar results, whatever the
composition of the team, so long as it contained a representative set of experts.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 49 of 84
Office for Nuclear Regulation
now considered to be RGP by the worldwide seismic hazard technical community. The
SSHAC explains that the goal of a good epistemic uncertainty analysis is:
“… to represent the center, the body, and the range [of hazard values] that the
larger informed technical community would have if they were to conduct the study”
207. The aleatory variability analysis invokes a series of traditional probability density
functions to describe the random variables that contribute to the hazard severity; the
output is a seismic hazard curve giving hazard severity against frequency of
exceedance. The epistemic uncertainty analysis identifies for these parameters a
range of possible calculation techniques, maximum / minimum values etc, that together
are seen to capture the extent of knowledge that applies to each parameter. These
aspects are typically captured in a logic tree and expressed in the hazard definition as
confidence levels. This gives the analyst the flexibility to take account of, for example,
uncertainty estimates derived from expert elicitation techniques.
208. The inspector should note that whilst SSHAC is seen as RGP, Licensee’s may opt for
an alternative methodology that provides an equivalent level of plant / site safety. The
rigour of the process selected should be shown to be proportionate to the nuclear
hazard present. For more details consult Annex 1 [1] and the supporting Expert Panel
paper [7].
209. Meteorological and coastal flood hazard analyses (as noted above) make
sophisticated use of statistical techniques to estimate uncertainty associated with
hazard parameter values, but generally do not make a distinction between aleatory
and epistemic uncertainties, and do not at this time attempt to incorporate epistemic
uncertainty explicitly into their hazard analyses. However, the incorporation of
epistemic uncertainty in to coastal flood hazard analyses has recently been trialled by
the USNRC [55].
210. The inspector should ensure that the methods adopted for uncertainty analysis are
reasonable, consistent with appropriate RGP, and also that the results are not
sensitive to specific assumptions, or if they are that this is well understood and does
not undermine the overall safety analysis. A specific range of sensitivity studies should
be considered; ERL.1 provides further guidance.
211. It is generally accepted by the informed technical community that climate change is
being largely driven by anthropogenic activities and will affect both current and future
climate and associated weather. This in turn is expected to result in a gradual rise in
sea levels because of the anticipated warming associated with climate change and
associated melting of global ice-sheets, although there is much debate amongst the
informed technical community about how much and when. Consequently, inspectors
should be aware that climate change predictions are associated with substantial
uncertainty, see paragraph 204..
212. Due to the typical operating lifetime of a nuclear site (of the order >100 years);
changes to meteorological and coastal flooding hazards as a result of climate change
could be significant. Further details are provided in Annexes 2 [2] and 3 [3].
213. SAP AM.1 provides an overview of the requirements for emergency preparedness.
The potential effects of EHs should have been considered as part of the hazard
identification and analysis process, as discussed elsewhere in Section 5, and used to
inform the site’s emergency plan and arrangements under LC11. There are often
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 50 of 84
Office for Nuclear Regulation
specific requirements for EHs, which the inspector should be aware of. Typically, these
include:
Availability of access routes onto / off site for essential equipment if local flood /
wind damage excludes normal routes.
Availability of staff and workers that can be called upon in response to bad
weather warnings to complete any necessary hazard mitigation actions, before the
weather deteriorates to a level where worker safety becomes an issue.
214. The claims made against operator actions during and following severe EHs should be
reviewed carefully from a practical standpoint and, wherever possible, limited to a
small number through the use of automatic systems and fail safe devices.
215. An EH event may occur which causes some degree of damage to a facility, but which
does not render the plant outside of its current safety case for that particular hazard.
The plant, however, may have a reduced capability to accommodate the effects of
other hazards until such times as repairs have been undertaken. Licensees should
have in place systems to rapidly assess any damage caused by EHs, assess any
potential undermining of any safety case claims and, if necessary, undertake repairs in
a timescale appropriate to the increase in risk posed. If repairs cannot be made
readily, then mitigation strategies should be developed to reduce the residual risk to
ALARP. At all times, however, the plant / SSCs must be operated within the conditions
of its Operating Rules. This is discussed further in paragraph 44.(i).
216. Examples of such events are earthquake events greater than the OBE, and the
occurrence of weather that may limit the Licensee’s ability to undertake normal
operations external to the plant.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 51 of 84
Office for Nuclear Regulation
6 REFERENCES
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 52 of 84
Office for Nuclear Regulation
[22] IAEA, “SSR-2/1, Rev. 1, Safety of Nuclear Power Plants: Design,” 2016, www-
pub.iaea.org/MTCD/publications/PDF/Pub1715web-46541668.pdf.
[23] IAEA, “NS-R-3, Rev. 1, Site Evaluation for Nuclear Installations,” 2016, www-
pub.iaea.org/MTCD/publications/PDF/Pub1709web-84170892.pdf.
[24] IAEA, “The Fukushima Daiichi Accident, Report by the Director General,” 2016,
www-pub.iaea.org/books/IAEABooks/10962/The-Fukushima-Daiichi-Accident.
[25] IAEA, “Safety Guide No. NS-G-1.6, Seismic Design and Qualification for
Nuclear Power Plants,” 2003,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1158_web.pdf.
[26] IAEA, “Safety Guide No. NS-G-2.13, Evaluation of Seismic Safety for Existing
Nuclear Installations,” 2009,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1379_web.pdf.
[27] IAEA, “Specific Safety Guide No. SSG-9, Seismic Hazards in Site Evaluation for
Nuclear Installations,” 2010,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1448_web.pdf.
[28] IAEA, “Specific Safety Guide No. SSG-18, Meteorological and Hydrological
Hazards in Site Evaluation for Nuclear Installations,” 2011,
www-pub.iaea.org/MTCD/publications/PDF/Pub1506 web.pdf.
[29] IAEA, “TECDOC-1791, Considerations on the Application of the IAEA Safety
Requirements for the Design of Nuclear Power Plants,” 2016, https://www-
pub.iaea.org/MTCD/Publications/PDF/TE-1791_web.pdf.
[30] IAEA, “TECDOC 1834, Assessment of Vulnerabilities of Operating Nuclear
Power Plants to Extreme External Events,” 2017,
https://www-pub.iaea.org/MTCD/Publications/PDF/TE1834_web.pdf.
[31] IAEA, “Specific Safety Guide No. SSG-35, Site Survey and Site Selection for
Nuclear Installations,” 2015,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1690Web-41934783.pdf.
[32] IAEA, “Safety Report Series No. 85: Ground Motion Simulation Based on Fault
Rupture Modelling for Seismic Hazard Assessment in Site Evaluation for
Nuclear Installations,” 2015,
www-pub.iaea.org/books/IAEABooks/10832/Ground-Motion-Simulation-Based-
on-Fault-Rupture-Modelling-for-Seismic-Hazard-Assessment-in-Site-Evaluation-
for-Nuclear-Installations.
[33] IAEA, “Safety Report Series No. 89: Diffuse Seismicity in Seismic Hazard
Assessment for Site Evaluation of Nuclear Installations,” 2016, www-
pub.iaea.org/books/iaeabooks/10916/Diffuse-Seismicity-in-Seismic-Hazard-
Assessment-for-Site-Evaluation-of-Nuclear-Installations.
[34] IAEA, “TECDOC 1767: The Contribution of Palaeoseismology to Seismic
Hazard Assessment in Site Evaluation for Nuclear Installations,” 2015, www-
pub.iaea.org/books/IAEABooks/10887/The-Contribution-of-Palaeoseismology-
to-Seismic-Hazard-Assessment-in-Site-Evaluation-for-Nuclear-Installations.
[35] IAEA, “TECDOC 1796: Seismic Hazard Assessment in Site Evaluation for
Nuclear Installations: Ground Motion Prediction Equations and Site Response,”
2016, www-pub.iaea.org/books/iaeabooks/11067/Seismic-Hazard-Assessment-
in-Site-Evaluation-for-Nuclear-Installations-Ground-Motion-Prediction-
Equations-and-Site-Response.
[36] IAEA, “TECDOC 1795: Volcanic Hazard Assessments for Nuclear Installations:
Methods and Examples in Site Evaluation,” 2016,
www-pub.iaea.org/books/iaeabooks/11063/Volcanic-Hazard-Assessments-for-
Nuclear-Installations-Methods-and-Examples-in-Site-Evaluation.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 53 of 84
Office for Nuclear Regulation
[37] IAEA, “Specific Safety Guide No. SSG-21, Volcanic Hazards for Site Evaluation
for Nuclear Installations,” 2012,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1552_web.pdf.
[38] IAEA, “Safety Report Series No. 86, Safety Aspects of Nuclear Power Plants in
Human Induced External Events: General Considerations,” 2017, www-
pub.iaea.org/MTCD/Publications/PDF/P1721_web.pdf.
[39] IAEA, “Safety Report Series No. 87, Safety Aspects of Nuclear Power Plants in
Human Induced External Events: Assessment of Structures,” 2018, https://www-
pub.iaea.org/MTCD/Publications/PDF/PUB1769_web.pdf.
[40] IAEA, “Safety Report Series No. 88, Safety Aspects of Nuclear Power Plants in
Human Induced External Events: Margin Assessment,” 2017, www-
pub.iaea.org/MTCD/Publications/PDF/P1723_web.pdf.
[41] IAEA, “Safety Guide No. NS-G-3.1, External Human Induced Events in Site
Evaluation for Nuclear Power Plants,” 2002,
www-pub.iaea.org/MTCD/Publications/PDF/Pub1126_scr.pdf.
[42] ONR, “The Identification Selection and Significance of External Hazards to
Nuclear Sites,” 2013, (2013/143209).
[43] IAEA, “NS-G-1.5, External Events Excluding Earthquakes in the Design of
Nuclear Power Plants,” 2003,
www-pub.iaea.org/MTCD/publications/PDF/Pub1159_web.pdf.
[44] USNRC, “Perspectives Gained From the Individual Plant Examination of
External Events (IPEEE) Program - Final Report, NUREG-1742, Vols. 1 & 2,”
April 2002, www.nrc.gov/docs/ML0212/ML021270070.pdf.
[45] ONR, “NS-TAST-GD-030, Rev. 5, Nuclear Safety Technical Assessment Guide:
Probabilistic Safety Analysis,” June 2016,
www.onr.org.uk/operational/tech_asst_guides/ns-tast-gd-030.pdf.
[46] ONR, “Japanese earthquake and tsunami: Implications for the UK nuclear
industry. Final Report. HM Chief Inspector of Nuclear Installations,” September
2011, www.onr.org.uk/fukushima/final-report.pdf.
[47] ONR, “NS-TAST-GD-007, Rev. 3, Nuclear Safety Technical Assessment Guide:
Severe Accident Analysis,” September 2017.
[48] Decker, K. and Brinkman, H., “List of external hazards to be considered in
ASAMPSA_E, EURATOM 7th Framework Prog. ASAPSA_E, Tech. Rpt.
ASAPSA_E/WP21/D21.2/2017-41,” February 2017, http://asampsa.eu/wp-
content/uploads/2014/10/ASAMPSA_E-D21.2_External_Hazard_List.pdf.
[49] Knochenhauer, M. and Louko, P., “Guidance for External Events Analysis, SKI
Report 02,” 27 February 2003.
[50] EPRI (Electric Power Research Institute), “Identification of External Hazards for
Analysis in Probabilistic Risk Assessment: Update of Report 1022997,” 29
October 2015, www.epri.com/#/pages/product/3002005287/.
[51] BSI, “BS EN 1991-1-4: 2005. Eurocode 1: Actions on Structures - Part 1-4:
General Actions – Wind Actions, European Committee for Standardisation,
Brussels,” 2005.
[52] ONR, “NS-TAST-GD-051, Rev. 4, Nuclear Safety Technical Assessment Guide:
Guidance on the Purpose, Scope and Content of Nuclear Safety Cases,” July
2016, www.onr.org.uk/operational/tech_asst_guides/ns-tast-gd-051.pdf.
[53] UK Met. Office, “UK Climate Projections (UKCP09),” 2009,
http://ukclimateprojections.defra.gov.uk/.
[54] USNRC, “Practical Implementation Guidelines for SSHAC Level 3 and 4 Hazard
Studies, NUREG-2117, Rev. 1,” April 2012, www.nrc.gov/reading-rm/doc-
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 54 of 84
Office for Nuclear Regulation
collections/nuregs/staff/sr2117/.
[55] Bensi, M. and Kanney, J., Development of a Framework for Probabilistic Storm
Surge Hazard Assessment for United States Nuclear Power Plants, Paper
submitted to Div. VII, SMiRT23 Conf., Manchester, UK, August 10-14, 2015.
[56] IAEA, “Safety Guide No. NS-G-3.6, Geotechnical Aspects of Site Evaluation and
Foundations for Nuclear Power Plants,” 2004,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1195_web.pdf.
[57] IAEA, “Safety Guide No. NS-G-3.1, External Human Induced Events in Site
Evaluaiton for Nuclear Power Plants,” 2002,
https://www-pub.iaea.org/MTCD/publications/PDF/Pub1126_scr.pdf.
[58] ONR, “Japanese earthquake and tsunami: Implications for the UK Nuclear
Industry – Interim Report,” May 2011, www.onr.org.uk/fukushima/interim-
report.pdf.
[59] ENSREG, “European Council “Stress Tests” for UK nuclear power plants,
National Final Report,” December 2011, www.onr.org.uk/fukushima/european-
council-stress-tests.htm.
[60] HSE, “Safety Assessment Principles for Nuclear Facilities, Rev.1,” 2006,
www.onr.org.uk/saps/saps2006v1.pdf.
[61] IAEA, “Mission report - International Fact Finding Expert Mission of the
Fukushima Dai‐chi NPP Accident Following the Great East Japan Earthquake
and Tsunami,” 24 May 2011,
www-pub.iaea.org/MTCD/meetings/PDFplus/2011/cn200/documentation/cn200_
Final-Fukushima-Mission_Report.pdf.
[62] HSE, “Reducing risks, protecting people: HSE’s decision‐making process,”
2001, www.hse.gov.uk/risk/theory/r2p2.pdf.
[63] ONR, “NS-TAST-GD-015, Rev. 2, Nuclear Safety Technical Assessment Guide:
Electromagnetic Compatibility,” April 2015,
www.onr.org.uk/operational/tech_asst_guides/ns-tast-gd-015.pdf.
[64] Department for Business Innovation and Skills , “Space Weather Preparedness
Strategy, v2.1,” July 2015.
[65] Royal Academy of Engineering, “Extreme space weather: impacts on
engineered systems and infrastructure.,” February 2013,
www.raeng.org.uk/spaceweather.
[66] Executive Office of the President of the United States, “National space weather
strategy,” October 2015.
[67] University of Cambridge, “Solar Storm Emerging Risk Scenario”.
[68] National Research Council, “Severe Space Weather Events: Understanding
Societal and Economic Impacts: A Workshop Report,” Washington, DC: The
National Academies Press, 2008, https://doi.org/10.17226/12507.
[69] Cabinet Office, “National Risk Register of Civil Emergencies,” 2017,
www.gov.uk/government/uploads/system/uploads/attachment_data/file/
644968/UK_National_Risk_Register_2017.pdf.
[70] Oughton, E., Copic, J., Skelton, A., Kesaite, V., Yeo, Z.Y., Ruffle, S.J., Tuveson,
M., Coburn, A.W. and Ralph, D., “Helios Solar Storm Scenario,” Cambridge Risk
Framework series; Centre for Risk Studies, University of Cambridge, 2016.
[71] CL:AIRE, “Assessing risks associated with gases and vapours (INFO-RA2-4),”
17 May 2017,
www.claire.co.uk/information-centre/water-and-land-library-wall/41-water-and-
land-library-wall/212-assessing-risks-associated-with-gases-and-vapours-info-
ra2-4.
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 55 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 56 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 57 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 58 of 84
Office for Nuclear Regulation
+ These EHs refer to malicious activities and are not covered further in this guide, refer to
paragraph 14..
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 59 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 60 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 61 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 62 of 84
Office for Nuclear Regulation
natural hazards.
T3.1 Natural hazards identified as potentially affecting the site can Section 5.2
be screened out on the basis of being incapable of posing a Section 5.3.1
physical threat or being extremely unlikely with a high degree of Section 5.8.1
confidence. Care shall be taken not to exclude hazards which in
combination with other hazards have the potential to pose a threat
to the facility. The screening process shall be based on
conservative assumptions. The arguments in support of the
screening process shall be justified.
T3.2 For all natural hazards that have not been screened out, Section 5.4
hazard assessments shall be performed using deterministic and, as Section 5.5.1
far as practicable, probabilistic methods taking into account the Section 5.5.2
current state of science and technology. This shall take into Section 5.6
account all relevant available data, and produce a relationship Section 5.7
between the hazards severity (eg magnitude and duration) and
exceedance frequency, where practicable. The maximum credible
hazard severity shall be determined where this is practicable.
T3.3 The following shall apply to hazard assessments: Paragraph 44.f
The hazard assessment shall be based on all relevant site Section 5.8.9
and regional data. Particular attention shall be given to Appendices 1 – 4
extending the data available to include events beyond Annexes 1 – 4
recorded and historical data.
Special consideration shall be given to hazards whose
severity changes during the expected lifetime of the plant.
The methods and assumptions used shall be justified.
Uncertainties affecting the results of the hazard
assessments shall be evaluated.
T4.1 Design basis events shall be defined based on the site- Section 5.4
specific hazard assessment. Appendices 2 – 6
Annexes 1 – 4
T4.2 The exceedance frequencies of design basis events shall be Section 5.5.1
low enough to ensure a high degree of protection with respect to Section 5.5.2
natural hazards. A common target value of frequency, not higher
than 10-4/yr, shall be used for each design basis event. Where it is
not possible to calculate these probabilities with an acceptable
degree of certainty, an event shall be chosen and justified to reach
an equivalent level of safety. For the specific case of seismic
loading, as a minimum, a horizontal peak ground acceleration value
of 0.1g (where ‘g’ is the acceleration due to gravity) shall be
applied, even if its exceedance frequency would be below the
common target value.
T4.3 The design basis events shall be compared to relevant Paragraphs – 22.
historical data to verify that historical extreme events are enveloped Section 5.8.9
by the design basis with a sufficient margin.
T4.4 Design basis parameters shall be defined for each design Appendices 2 – 6
basis event taking due consideration of the results of the hazard
assessment.
T4.5 Design basis parameters shall be defined for each design Section 5.4
basis event taking due consideration of the results of the hazard
assessment.
T5.1 Protection shall be provided for design basis events. A Paragraphs 18.(iii.) and 86.
protection concept shall be established to provide a basis for the Table 3
design of suitable protection measures.
T5.2 The protection concept shall be of sufficient reliability that the Paragraph 18., 85.
fundamental safety functions are conservatively ensured for any Section 5.5
direct and credible indirect effects of the design basis event. A Section 5.5.3
protection concept, as meant here, describes the overall strategy Section 5.6
followed to cope with natural hazards. It shall encompass the Section 5.7
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 63 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 64 of 84
Office for Nuclear Regulation
External Hazards
Introduction Section 2.2
Here the EHs of concern are those natural or man-made hazards to
a site and facilities that originate externally to both the site and its
processes, ie the Licensee may have very little or no control over
the initiating event.
In contrast with almost all internal faults or hazards, EHs may
simultaneously affect the whole facility, including back-up safety
systems and non-safety systems alike. In addition, the potential for
widespread failures and hindrances to human intervention may
occur. For multi-facility sites this makes the generation of safety
cases more complex and requires appropriate interface
arrangements to deal with common equipment or services as well
as potential domino effects
Safety Expectation Paragraph 37.
The safety assessment for new reactors should demonstrate that Section 5.4
threats from EHs are either removed or minimised as far as
reasonably practicable.
This may be done by showing that all relevant safety SSCs
required to cope with an EH are designed and adequately qualified
to withstand the conditions related to that EHs.
EHs considered in the general design basis of the plant should not
lead to a core melt accident (Objective O2 ie level 3 DiD).
Accident sequences with core melt resulting from EHs which would
lead to early or large releases should be practically eliminated
(Objective O3 ie level 4 DiD). For that reason, rare and severe EHs,
which may be additional to the general design basis, unless
screened out (see “Screening of EHs” below), need to be taken into
account in the overall safety analysis.
Identification Section 4
See Safety Series Standards NS-R-3, NS-G-3.1, NS-G-3.3, NS-G- Section 5.2
3.6, NS-G-1.5, NS-G-1.6 and relevant events in SSG-3 and SSG- Table 2
18
Screening of External Hazards Section 5.3.1
Screening is used to select the EHs that should be analysed. As a
starting point, the screening process should take the complete list
discussed in the previous section. Each EH on the list should be
considered and selected for analysis if:
(a) It is physically capable of posing a threat to nuclear safety, and
(b) the frequency of occurrence of the EH is higher than pre-set
criteria.
The pre-set frequency criteria may differ depending on the nature of
the analysis that is to be undertaken. Typically for the general
design basis, where the analysis will be done using traditional
conservative methods, assumptions and data, the criterion will be
higher than the frequency criteria used for analyses of rare and
severe EHs or PSA that could employ realistic, best estimate
methods and data. Therefore, the screening process may lead to
separate, but compatible lists of EHs for the range of analyses to
be undertaken and there should be a clear and consistent rationale
for the differences in the lists.
In all cases the pre-set frequency criteria used should be stated
and justified taking into account the way the hazards are going to
be analysed in the safety demonstration.
The degree of confidence of the estimated frequency of occurrence
should be stated and justified taking into account the related
uncertainties according to the state of knowledge.
The screening process should explicitly consider correlated events
and combinations of events
Determination of hazard parameters Section 5.4
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 65 of 84
Office for Nuclear Regulation
All of the candidate EHs that are selected should be characterised Appendices 2 – 6
in terms of their severity and / or magnitude and duration. The Annexes 1 – 4
characterisation of the EH will depend on the type of analysis that is
to be carried out and shall be conservative for the general DBA and
could be realistic / best estimate for rare and severe EHs analysis
and PSA. It should be noted that for EHs PSA, a range of
frequencies and associated hazard parameters is often required. All
relevant characteristics need to be specified and the rationale for
their selection justified. For some EHs:
the ability to forecast the magnitude and timing of the
event, and the speed at which the event develops may be
relevant and should be considered;
several parameters could be relevant to characterise
severity and / or magnitude.
Analysis considerations Section 5.4
The EHs analysis includes the design of SSCs which are relevant Section 5.5.3
to ensuring that the fundamental safety functions are fulfilled, Section 5.8.4
development of probabilistic models where necessary, and the
consideration of rare and severe EHs.
The following should be considered when undertaking this analysis:
Minimising the risk from EHs by initial siting of the facility
Designing plant layout to minimise impact of EHs (this is
particularly important for multi-unit facilities – also where
units are of different generation)
Justification of the lists of identified EHs
Justification of any hazard screening
Combinations of EHs that can occur simultaneously or
successively within a given period of time 26 including
correlated hazards and those combinations which occur
randomly
Consideration of consequential events, such as fire or
flooding following a seismic event
EH induced multiple failure of safety systems and / or their
support systems
Cliff-edge effects – where a small change in a parameter
leads to a disproportionate increase in consequence.
In addition to considering the impact of EHs on the systems
and components, the reliability of the buildings and
structures responding to an EHs should be taken into
account
The PSA for EHs should include consideration of building and
structural reliability as well as system and component fragilities and Section 5.6
should take account of the potential for human response to be
affected by the external event.
Impact of climate change and other potential time related
changes that might affect the site should be considered Section 5.8.11
Consideration should also be given to the impact of EHs on
the ability to support (emergency services) the site Section 5.9
damaged by that external event (relevant to DiD).
The design of the plant should reflect the EHs analyses.
Similarly, the operating and maintenance procedures as Paragraph 44.(k)
well as the training etc should take account of the EHs
analyses.
Care must be taken where the definition of the hazard
levels is imprecise, and claims are made based on the Sections 5.8.9 & 5.8.10
accuracy of calculations which have an accumulation of
assumptions and conservatisms (or lack of)
A clear methodology is important, along with an
understanding of the associated uncertainties, both
epistemic and aleatory. This is particularly important where
the work also supports numerical PSA based approaches
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 66 of 84
Office for Nuclear Regulation
NS-TAST-GD-013
CM9 Ref: 2020/227479 Page 67 of 84
Office for Nuclear Regulation
Safety Report 85 [32] Ground Motion Simulation Based on Fault Rupture Modelling
for Seismic Hazard Assessment in Site Evaluation for Nuclear
Installations
Safety Report 89 [33] Diffuse Seismicity in Seismic Hazard Assessment for Site
Evaluation of Nuclear Installations
TECDOC 1767 [34] The Contribution of Palaeoseismology to Seismic Hazard
Assessment in Site Evaluation for Nuclear Installations
TECDOC 1796 [35] Seismic Hazard Assessment in Site Evaluation for Nuclear
Installations: Ground Motion Prediction Equations and Site
Response
Meteorology & Coastal Flood Hazard Analysis
SSG-18 [28] Meteorological and Hydrological Hazards in Site Evaluation for
Nuclear Installations
Volcanic Hazard Analysis
SSG-21 [37] Volcanic Hazards for Site Evaluation for Nuclear Installations
TECDOC 1795 [36] Volcanic Hazard Assessments for Nuclear Installations:
Methods and Examples in Site Evaluation
Human Factors in External Hazards Analysis
NS-G-3.1 [57] External Human Induced Events in Site Evaluaiton for Nuclear
Power Plants
Safety Report 86 [38] Safety Aspects of Nuclear Power Plants in Human Induced
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 68 of 84
Office for Nuclear Regulation
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 69 of 84
Office for Nuclear Regulation
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 70 of 84
Office for Nuclear Regulation
1. Following the earthquake and tsunami which severely damaged the Fukushima Dai-
ichi and Dai-ini nuclear power plants in Japan in March 2011, ONR’s HM Chief
Inspector produced a set of reports for the UK Government on the events at
Fukushima [58] & [46]. The reports made a number of Final Recommendations (FRs)
and Interim Recommendations (IRs) to ensure appropriate lessons were learnt and
implemented from the Fukushima event by nuclear operators. Nuclear operators
across Europe were also tasked with responding to the Stress Test Findings (STFs)
generated from a separate EU review of the Fukushima event [59].
2. The FRs, IRs and STFs most directly relevant to EHs are below, but others, eg
relevant to emergency arrangements, are also relevant:
Recommendation IR‐11: The UK nuclear industry should ensure that safety cases for
new sites for multiple reactors adequately demonstrate the capability for dealing with
multiple serious concurrent events induced by extreme off‐site hazards.
Recommendation IR 13: The UK nuclear industry should review the plant and site
layouts of existing plants and any proposed new designs to ensure that safety systems
and their essential supplies and controls have adequate robustness against severe
flooding and other extreme external events.
Stress Test Finding STF-2: The nuclear industry should establish a research
programme to review the Seismic Hazard Working Party (SHWP) methodology against
the latest approaches. This should include a gap analysis comparing the SHWP
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 71 of 84
Office for Nuclear Regulation
methodology with more recent approaches such as those developed by the Senior
Seismic Hazard Analysis Committee (SSHAC).
Stress Test Finding STF-3: Licensees should undertake a further review of the totality
of the required actions from operators when they are claimed in mitigation within
external hazards safety cases. This should also extend into beyond design basis
events as appropriate.
Stress Test Finding STF-4: Licensees should undertake a further systematic review
of the potential for seismically‐induced fire which may disrupt the availability of safety‐
significant structures, systems and components (SSC) in the seismic safety case and
access to plant areas.
Stress Test Finding STF-5: Licensees should further review the margins for all safety
significant structures, systems and components (SSC), including cooling ponds, in a
structured systematic and comprehensive manner to understand the beyond design
basis sequence of failure and any cliff-edges that apply for all external hazards.
Stress Test Finding STF-7: Licensees should undertake a more structured and
systematic study of the potential for floodwater entry to buildings containing safety-
significant structures, systems and components (SSC) from extreme rainfall and / or
overtopping of sea defences.
3. ONR’s expectation is that the recommendations and findings that arose from the post-
Fukushima lessons learnt should be incorporated into safety cases for EHs, as
appropriate, as part of normal business. The expectations set out in the post-
Fukushima Recommendations and Findings are now considered RGP in the UK, and
all licensees, potential licensees and requesting parties should ensure they are met in
accordance with their lifecycle positions.
4. ONR’s SAPs were updated in 2014 to incorporate these expectations. The SAPs were
reviewed post-Fukushima after ONR’s Chief Nuclear Inspector’s report on the
Implications of the Fukushima events on the GB nuclear industry was published. That
report concluded that there were no significant gaps in the SAPs but recommended a
review to ensure lessons learnt were incorporated. The review resulted in a number of
changes to the SAPs which were reissued in 2014.
BDB events: New principle EHA.18 added and links added to EHA.7 and to
PSA and SAA.
Extreme weather: EHA.11 updated to clearly include BDB weather hazards and
the requirement to have forewarning systems in place (but see below on the
hierarchy of safety measures).
Discrete & non-discrete external hazards: SAPs paragraph 235 added to bring
out the difference between EHs defined as discrete frequency / severity events
and those defined by hazard curves. This facilitates a better understanding of
the implications of non-discrete hazards on BDBA.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 72 of 84
Office for Nuclear Regulation
Uncertainty analysis: Improved clarity on the links from the EH section of the
SAPs to the principles covering uncertainty analysis, SAPs paragraph 238.
7. SAP EHA.7- Cliff-edge effects has also been updated and SAP EHA.18 – BDB events
has been added as part of the post-Fukushima updates. The main point behind these
two SAPs is to clarify the expectation that explicit margins assessments should be
performed to examine the potential effects of BDB flooding as set out in STFs 5 and 7
for external flooding for example. ONR expects that the analysis of external flooding
should identify the margins beyond the design basis to the point(s) where safety
functions would no longer be achieved, as a function of increasing hazard severity.
This analysis should confirm the absence of ‘cliff-edge’ effects just beyond the design
basis and should provide an input into PSA and SAA.
8. SAP EHA.12 is the most relevant Principle relating to external flooding, and it has been
enhanced significantly since the 2006 version [60] of the SAPs. Previously, the SAP
said simply that “nuclear facilities should withstand flooding conditions that meet the
design basis event criteria.” It now states that “facilities should be shown to withstand
flooding conditions up to and including the design basis event. Severe accidents
involving flooding should also be analysed.” The changes reflect the increased
importance on the analysis of extreme flooding events post-Fukushima, including the
consideration of BDB flooding.
9. The explanatory paragraphs following the SAP itself have also been greatly expanded.
These paragraphs now refer explicitly to the “dry site” concept and say that “facilities
should be protected against a design basis flood by adopting a layout based on
maintaining the ‘dry site concept’. In the dry site concept, all vulnerable structures,
systems and components should be located above the level of the design basis flood,
together with an appropriate margin…” In the next paragraph, the SAPs then go on to
say that, “where it is not practicable to adopt the dry site concept, the design should
include permanent external barriers such as levees, sea walls and bulkheads…” and
that “the design parameters for these barriers may need to be more onerous than
those derived from the design basis flooding event.”
10. This update stems from the lessons described in the report from the IAEA’s fact-finding
mission to Japan that took place post-Fukushima. The IAEA conducted this fact-finding
mission by agreement with the government of Japan, and ONR’s Chief Inspector was
asked by IAEA to lead this mission, which was undertaken in 2011. The resulting
mission report [61] states that “plant layout should be based on maintaining a ‘dry site
concept’, where practicable” which, it goes on to state in Finding Number A1-02 of the
report, is “preferred in many Member States to the alternative solution of permanent
external barriers such as levees, sea walls and bulkheads.” The IAEA Director
General’s report [24] on Fukushima, in Technical Volume II, considered the “dry site
concept” further. It states that “the dry site concept is considered a key measure
against site flooding hazards that may affect safety.” The report explains that “in many
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 73 of 84
Office for Nuclear Regulation
11. Uncertainty in flood hazard analysis: A high degree of uncertainty is present in the
analysis of external flooding. The following factors should be taken into account to
ensure that the uncertainty is mitigated and risks reduced ALARP:
12. When faced with significant uncertainty, the precautionary principle (Referred to as the
“precautionary approach” in the SAPs.) means it is necessary to err on the side of
safety and to ensure that safety measures are adequate [62].
13. Generally speaking, the precautionary principle is invoked for two key reasons – either
due to the potential for serious harm as an outcome, or due to levels of uncertainty so
high that the outcomes are highly divergent. For external flooding, uncertainty is high
so a wide range of scenarios should be examined and potential mitigations and
resilience enhancements identified. These should then subjected to ALARP
considerations in accordance with guidance in TAG 5 [6]. The concept of reducing
risks ALARP takes into account gross disproportionality, and clearly what is reasonably
practicable for a site at greater risk of flooding is different from one where an external
flood is not credible. Inspectors should ensure that ALARP considerations have been
applied in accordance with the risk that could arise from external flooding in
accordance with a site’s vulnerability to flooding and lifecycle position.
14. Hierarchy of Safety Measures: In order of preference, safety measures should be:
15. Safety measures should be ranked in order of importance by making use of the
hierarchy of safety concept. Passive measures (such as waterproofing around doors
and cable penetrations into buildings) or automatically initiated preventative
engineered measures (such as activation of fail-safe cooling systems), if adequately
conceived and executed, should provide robust reassurance that unacceptable
consequences will not be realised in case an extreme flood event occurs.
Administrative measures, such as responding to weather forecasts, should be treated
with a degree of caution, since potential for human error exists both in the forecasts
themselves, and any operator actions on-site being taken in response. Manually
initiated engineering measures to prevent EH-induced failures are typically less reliable
than passive or automatically initiated measures.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 74 of 84
Office for Nuclear Regulation
Electromagnetic Interference
14. The potential for EMI to instrumentation and control equipment should be considered.
Guidance on the assessment of EMI is set out in T/AST/015 on electromagnetic
compatibility [63], which also includes references and sources of further information.
Depending on whether the hazard can be adequately controlled, the Licensee may
need to provide screening to protect equipment from EMI or install instrumentation and
control equipment of a proven electromagnetic compatibility.
2. Sources of EMI local to the site should be identified and characterised. External
sources of EMI may vary in power with time and may be manually controlled and
directional. These variations should be considered when characterising the EMI EH.
Space Weather
3. Space weather is a term which describes variations in the Sun, solar wind,
magnetosphere, ionosphere and thermosphere, which can influence the performance
and reliability of space based and ground based technological systems.
4. The Sun is a source of EMI and other radiation at the Earth’s surface. This radiation
has a multitude of effects on the earth, not least in determining the earth’s weather
systems. This appendix is however only concerned with electromagnetic and radiation
effects on engineered systems. The Sun has an approximately 11 year magnetic
activity cycle during which its magnetic field grows and diminishes in strength and
reverses in polarity. This cycle is observed through changes in the sun spot activity on
the Sun’s surface.
5. In addition to the continually varying interplanetary magnetic and particle flux, which is
referred to as the solar wind, a related phenomenon, termed solar storm, has the
additional potential to affect engineered systems.
6. Space weather (or more specifically solar storms) has been identified as a threat to
infrastructure nationally. It is monitored as part of the UK natural hazards partnership,
with the UKMO being the lead agency. Space weather is also considered in the USA,
with NASA being the lead agency. The threat to UK and USA infrastructure from space
weather has been studied in order to advise policy [64], [65], [66], [67]. Nuclear
facilities are not specifically highlighted, but the vulnerability of electric grid and other
infrastructure is highlighted.
7. This appendix is focused on the hazard potential associated with solar storms. Note
however that this is generally referred to as space weather within the wider scientific
community.
Solar Storms
8. Solar storms are a particular aspect of space weather associated with the sudden
brightening of solar active regions known as sunspots and may be characterised in
terms of three phenomena; solar flares, solar energetic particles and coronal mass
ejections.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 75 of 84
Office for Nuclear Regulation
9. A solar flare is loosely defined as a sudden release of energy from the sun in the form
of X-rays, extreme UV and gamma-rays which take about 8 minutes to reach Earth
(speed of light) and persist in a timeframe of minutes to hours. A solar flare may also
be the precursor for the ejection of solar energetic particles (SEP) and subsequent
coronal mass ejections (CME).
10. SEPs are highly energetic solar particles (protons and ions) travelling at relativistic
speeds which may take the order of 15 minutes to 24 hrs to reach earth and persist for
several days. A particle cascade can be created by solar particles at high energies
interacting with the upper atmosphere. The particle cascade can be composed of
neutrons, protons, muons, pi-mesons, gamma rays and electrons. These particles are
typically observed at high elevation in satellite and aviation systems but also have the
potential to create ground-level particle fluxes of neutrons and muons. These events
are referred to as ground level events (GLE).
11. A CME is an eruption of electrical plasma and magnetic fields from the solar corona as
a plasma ‘bubble’ which may take typically 1 to 4 days to reach earth and persist for
typically 1-2 days. CMEs interact with the Earth’s geomagnetic field, with the impact
accentuated when the magnetic field of the CME is oppositely aligned to the direction
of the geomagnetic field. In such a configuration CME energy and plasma is efficiently
directed into the Earth’s environment, including the radiation belts, ionosphere,
atmosphere and ground.
13. Given the physical dimensions of CMEs and the geomagnetic field (both many Earth
diameters wide), the impact of space weather is generally global in extent, though it is
stronger towards both poles where the geomagnetic field is more readily magnetically
connected to the solar wind. However regional (few hundred km to continental scale)
impacts do occur, depending on the local time, with impacts stronger on the night side
of the Earth.
14. Ground level infrastructure affected by GIC includes electrical power transmission
systems, pipelines and railways. These systems are affected by the GIC due to their
large span.
15. Space weather is known to affect man-made satellites and the aviation industry. The
electronics within man-made satellites can be disrupted by the particle flux, giving the
potential for reducing the reliability of signals and data. This includes man-made
satellites providing Global Navigation Satellite Systems (GNSS)§§§§§§§ . Where ground
level infrastructure also relies on GNSS (position and/or timing), satellite
communications, mobile or HF communications, or contain electronic hardware
sensitive to ionising radiation then there are additional space weather risks [65], [68].
15. GLE are relevant to Control and Instrumentation (C&I) systems, with certain materials
being particularly susceptible to particle fluxes creating false signals.
§§§§§§§
Often referred to as Global Positioning System (GPS), although this is one of a series of systems.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 76 of 84
Office for Nuclear Regulation
Forecasting
16. The correlation between sunspot activity and the occurrence rate of solar storms is not
well established, with the correlation becoming weaker for more severe solar storms.
Sunspots are a manifestation of the magnetic cycle of the Sun, a dynamo process, for
which no agreed physical model currently exists capable of explaining the periodicities.
However, comparable ‘star spot’ records suggest the Sun is not atypical. Indeed Sun-
like stars are observed for which spots are rare or cover a substantial fraction of the
surface, suggesting that a wide range of activities are possible, if not yet observed, in
solar sunspot data.
17. Warning and detection systems are in place for space weather. Space based
instruments in orbit between Earth and the Sun can detect CME and provide a 15 to 60
minute warning, depending on the speed of the CME. Terrestrial monitoring systems
are also in place in the form of the INTERMAGNET network. These provide monitoring
for geomagnetic storms and GIC.
18. Due to the near relativistic speed of SEP, there is little scope for the development of
warning systems against GLE. As noted above, there may be only a few minutes delay
between the observation of a significant solar flare and the first arrival of SEP at Earth.
Characterisation
19. The UK National Risk Register [69] classes severe space weather as a low probability
(1 in 20 years or less********) but potentially high impact event. There are continuous
ground-level geomagnetic records, dating back some 170 years, to substantiate the
impact of space weather, as well as evidence from space-based measurements of
solar activity for the last 50 years. The sunspot record itself dates back 400 years and
provides some broader indication of past solar behaviour. Work is ongoing to try to
establish a longer record of solar activity from isotopic analysis of polar ice cores; there
is not wide consensus on the validity of the methodology.
20. As part of the UK preparedness for space weather events, a single hypothetical event
was modelled and the consequences for UK infrastructure and industry estimated [70].
21. The “Carrington Event” of 1859, which has become a benchmark for extreme space
weather events has been extensively studied. Of particular note are: the fast travel
time of the CME (17.6 hours to Earth from first observation of a related solar flare at
the Sun by Carrington); observation of the Aurora Borealis at low latitudes and mis-
operation and fires in telegraph systems. The latter impact is particularly relevant as a
benchmark for the potential effects of a Carrington-like event today on grounded
infrastructures. Telegraph systems of the time used batteries, and operators found that
the system could work without the batteries, ‘powered by the aurora’, as GIC flowed to
and from the ground into the network due to the enhanced surface electric field driven
by the storm. The Carrington Event has been used to estimate the frequency of
extreme events, but as a single event the results are very dependent upon
methodology and do not have a consensus in the scientific community.
22. The characterisation of GLEs is difficult as they have only been detectable since the
mid-20th century, e.g. no GLE data is available for the Carrington Event. Frequency
and severity are therefore difficult to determine.
23. Since the publication of a report by the Royal Academy of Engineering [65], which
estimated that a solar storm having magnitude similar to the Carrington event is
thought to have a return period of around 100 years, the nuclear industry, supported
The difference in expectation of hazard return frequency between the UK national risk register and
********
the SAPs should be noted when qualifying language such as “low probability” is used instead of
numerical values.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 77 of 84
Office for Nuclear Regulation
CINIF (Control & Instrumentation Nuclear Industry Forum) has undertaken research to
characterise the potential hazard posed by severe space weather. Work carried out by
the National Physical Laboratory estimated neutron fluxes at ground level
corresponding to return periods of 100, 1000, and 10,000 years. The work is however
supported by little actual data, so there is insufficient information for these fluxes to be
used to design engineered protection. However, the flux magnitudes at return periods
of 1000 years - 10,000 years are such that the hazard posed by SEP cannot be
ignored.
24. Unsung the flux estimates established by NPL, the nuclear industry undertook further
work through CINIF to consider the effects of neutron irradiation on the electronic
components used within ground-level control and instrumentation (C&I) electronics in
the nuclear industry. Radiation effects in general were reviewed but the major focus
was on single event effects (SEE) whereby individual particles of ionising radiation can
trigger soft, firm or hard failures in modern microelectronics. In the absence of
mitigating factors such as shielding and de-rating, certain microelectronic technologies
will suffer significant effects in the case of extreme GLEs. Older C&I equipment
incorporating similar component families is also a concern since SEE vulnerability
dates back thirty years or more. On the other hand certain other technologies such as
the simpler forms of flash memory appear considerably more robust based on current
evidence and would thus suffer minimal impact.
25. Due to the uncertainties associated with space weather and the immaturity of an
engineered response it is difficult to protect SSCs against space weather. Lessons can
be learnt from systems which are subject to harsher space weather environments,
including aircraft and satellite systems. Satellites are currently designed to withstand or
detect and react to space weather. The particle and magnetic fluxes experienced by
satellites is clearly much larger than that for ground based systems, it is therefore not
expected that ground-based systems should necessarily replicate the engineering
solutions such as multiple detectors used in these systems, but this example does
illustrate that engineered protection against space weather has matured in other
industries.
26. Research is ongoing to consider suitable mitigation strategies such as the use of less
vulnerable components, operating high voltage devices below rated values, shielding,
error detection/correction and radiation alert monitoring to reduce the likelihood of
inappropriate reaction to system anomalies.
Hazard combinations
27. Space weather EH analysis should consider the combined and consequential hazards
and faults and the multiple ground-level phenomena from a space weather event.
28. For example, a significant GIC is generally considered to be a frequent event, and is
likely to result in Loss of Offsite Power (LOOP). Whilst LOOP (without a solar storm) is
covered in nuclear safety cases as a frequent event, the combined effect of LOOP and
GIC and GLE should be considered. Depending on the severity of the solar storm,
offsite power may be unavailable for some time due to the potential for damage to
transformers within the off-site power supply network, and there is likely to be
disruption to communications and transport networks. Furthermore, damage to
microelectronic C&I systems may be expected for severe solar storms.
ONR expectations
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 78 of 84
Office for Nuclear Regulation
the SAPs for EHs to be identified and the vulnerability of SSCs to be assessed.
Inspectors should expect licensees to have considered the implications of the latest
research as outlined above and to have developed an appropriate protection strategy.
The strategy should identify whether there are any vulnerable components, what the
impact is on nuclear safety and any practicable mitigation or protection measures. The
strategy should take into account the level of uncertainty associated with the hazard
characterisation and its effect on components in order to ensure a proportionate and
balanced response to space weather hazard. The strategy should be updated as more
information becomes available.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 79 of 84
Office for Nuclear Regulation
1. Biological hazards cover a wide range of potential issues. There is no specific SAP
that refers specifically to biological hazards, however they should be considered as
part of the general need to cover all credible hazards (EHA.1).
Marine
o Jellyfish
o Seaweed
o Fish
Land
o Infestation from mice, rats, rabbits etc
o Biological debris such as fallen leaves
Air
o Swarms of insects / birds
3. Marine hazards can create a blockage or flow restriction on the intakes for sea or river
cooling water systems. This has led in the past to reactor trips and must therefore be
considered as a fault. In some cases, severe damage to drum screens has ensued,
and material has passed into the seaward side of coolers within the plant itself. This
has led in a number of cases to reactor trips. Where there is a high reliance on cooling
systems that have secondary cooling from river or sea, the sensitivity of the plant to
interruptions of supply should be well understood.
4. There are some techniques such as sonar and bubble curtains that can limit / deter the
influx of marine creatures. However, against organisms that can be dispersed and
spread (such as seaweed through wave action for example) it is preferable to rely on
more physical means to prevent ingress.
5. Infestation of mice etc is primarily prevented through the use of high quality doors and
sealing arrangements to buildings and service trenches etc, and by management
arrangements to deter animals from entering buildings.
6. Insect swarms can pose a threat to intakes, to heating, ventilation and air conditioning
or back-up diesel plant by restricting air flow and limiting their operability. It is therefore
useful to ensure that this hazard is considered as part of the design, and measures are
in place to allow a bypass or back-up system to provide support.
7. Fallen leaves and similar debris can block drains and gullies, especially in autumn or
after severe storms. Protection is normally provided by routine inspection/maintenance
activities to ensure drainage systems remain operational.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 80 of 84
Office for Nuclear Regulation
1. These hazards arise either due to the conveyance of hazardous materials on adjacent
transport routes (eg pipeline, rail, road and sea) or adjacent permanent facilities (eg
quarries, tank farms etc). Typical hazards that can arise from industrial plants may be
from; stored gas, fuel, explosives, pressure vessels or turbine disintegration. Useful
data and references are available on some of these aspects in a variety of Licensee
specific documents, in particular, the reactor Licensees have developed a
comprehensive methodology for assessing missile damage. EHs analyses should
consider all potential sources of external missiles and explosion.
Explosion / missiles
2. Inspectors should ensure that, where appropriate, the following have been considered:
o Refineries
o Liquid petroleum gas pipelines
o Wind Turbines
o Explosive-handling facilities
o Dockyards
3. Inspectors should ensure that, where appropriate, the following have been considered:
Toxic, corrosive and cryogenic materials and gases have the potential to disable
both personnel and safety-related plant. Therefore, the safety case should provide
a demonstration that the range of materials that if released could either disable,
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 81 of 84
Office for Nuclear Regulation
4. Adjacent or nearby nuclear sites have the potential under accident conditions to
release nuclear and other types of radioactive materials that could affect the site being
assessed. This is in addition to the conventional industrial hazards that might arise,
such as missiles from turbine disintegration and hazardous gas release (eg carbon
dioxide). Also, EHs affecting the site being assessed have the potential to affect
nearby nuclear sites through the common cause effect.
5. It is likely that any hazard arising from an adjacent nuclear site would prompt the
implementation of emergency arrangements on that site and, if severe enough, invoke
the off-site emergency plan. In both cases, the response of the site being assessed will
likely be governed by its own emergency arrangements and its contribution to the local
authority off-site plan. EHs inspectors should assure themselves that provision has
been made in the site’s emergency arrangements to accommodate the effects of EHs
on nearby nuclear sites.
Other considerations
6. A number of situations can arise that may provide the potential either directly or
indirectly, to create hazards. For example:
Tenants may exist on a licensed site, whose operations are not under the direct
control of the Licensee. In such cases the tenancy arrangements with the
Licensee should positively identify the potential hazards arising from the
tenants activities.
Third party activities may take place near the licensed site that could affect the
effectiveness of eg sea defences, or the potential for transport accidents.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 82 of 84
Office for Nuclear Regulation
1. Landscape change is not a particular EH itself. However, the processes that drive it
are clearly related to EHs. The processes themselves may well be gradual in nature,
(although significant change could arise from a single EH event such as a severe
storm winds or strong wave action impacting on the local coastline). However, over
time they may undermine the protection against the more extreme design basis and
BDB events.
3. Other effects such as glacial rebound are of minimal practical interest for the 100-year
timeframe generally under consideration.
4. The more detailed effects that result from the above are listed below:
5. The gradual nature of these processes mean that in most case, a monitoring regime
(by inspection) is appropriate to ensure that significant changes are identified in a
timely manner, so that management actions can be implemented to prevent or mitigate
the effects of landscape change hazards. Inspectors should confirm that the monitoring
system is appropriate, such that after a storm surge event, there is a requirement to
inspect those areas of sea defence that may have been damaged, and to have
arrangements in place to ensure that repairs can be undertaken in a suitable
timeframe. Clearly, this should be linked to any weather warning arrangements that
may be in place.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 83 of 84
Office for Nuclear Regulation
1. Naturally and anthropogenically occurring ground gases that could present a threat to
nuclear and conventional safety can be generated by the natural lithology of a nuclear
installation site, putrescible constituents of made ground and the degradation of
organic materials and contaminants in soils and / or groundwater. Ground gases of
concern typically comprise carbon dioxide (an asphyxiant) and methane (explosive),
though in some cases other gases such as hydrogen sulphide or carbon monoxide
(poisons) or radon (radioactive) could be present.
2. The risk of naturally occurring gases should be determined at the siting stage of a
nuclear facility including new sites and new facilities on an existing site. The suitability
of a site is covered by SAP ST.4 which requires that the suitability of the site to support
safe nuclear operations should be assessed prior to granting a new site licence. The
risk should be identified and evaluated according to the significance for the safe
operation of the nuclear installation and any important natural phenomena that could
lead to potential hazards should be investigated.
4. The following are common natural and anthropogenic sources of gas and their typical
products:
5. In order to prevent the collection of gases that could pose a threat to the health and
safety of personnel, limit access to areas that could affect nuclear safety or prevent
operators from carrying out safety related tasks, civil engineering design SAP ECE.11
states that “The design should take account of the possible presence of naturally
occurring explosive, asphyxiant or toxic gases or vapours in underground structures
such as tunnels, trenches and basements”. Plant areas such as cooling water intake
tunnels, drum screens and forebays may allow the collection of organic material (eg
seaweed and jellyfish) that could decompose with the risk of gas generation and gas
may be dissolved in water.
NS-TAST-GD-013 Revision 7
TRIM Ref: 2018/315641 Page 84 of 84