This document contains solutions to two problems from a tutorial sheet. The first problem calculates the number of truck loads needed to haul 1 million cubic cubic yards (CCY) of material. It is determined that 1,470,588.2 loose cubic yards (LCY) would be needed, which could be hauled in 245,098 truck loads with a capacity of 6 LCY per truck. The second problem calculates the volume of excavation required for a basement. It is found that the first part requires 4,519.2 bank cubic feet (BCF) of excavation and the second part requires 8,716.5 BCF, for a total excavation volume of 13,235.7 BCF.

Uploaded by

gerlyn montilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views

Tutorial 2 - 0

This document contains solutions to two problems from a tutorial sheet. The first problem calculates the number of truck loads needed to haul 1 million cubic cubic yards (CCY) of material. It is determined that 1,470,588.2 loose cubic yards (LCY) would be needed, which could be hauled in 245,098 truck loads with a capacity of 6 LCY per truck. The second problem calculates the volume of excavation required for a basement. It is found that the first part requires 4,519.2 bank cubic feet (BCF) of excavation and the second part requires 8,716.5 BCF, for a total excavation volume of 13,235.7 BCF.

Uploaded by

gerlyn montilla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Chapter # 2 Part # 2

1 ) How many truck loads of truck hauling an average volume of 6 LCY would be required to
haul 1 million CCY of problem #4 in tutorial sheet #1?

Solution:

Load factor = 80.6% ≈ 0.8

Shrinkage factor = 84.9% ≈ .85


𝐶𝑜𝑚𝑝𝑎𝑐𝑡𝑒𝑑 𝑣𝑜𝑙𝑢𝑚𝑒 1,000,000 𝐶𝐶𝑌
Bank volume =
𝑆𝑕𝑟𝑖𝑛𝑘𝑎𝑔𝑒 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.85
= 1,176,470.6 BCY

𝐵𝑎𝑛𝑘 𝑣𝑜𝑙𝑢𝑚𝑒 1,176,470.6 𝐵𝐶𝑌


Loose volume =
𝐿𝑜𝑎𝑑 𝑓𝑎𝑐𝑡𝑜𝑟
= 0.8
= 1,470,588.2 LCY

𝐿𝑜𝑜𝑠𝑒 𝑣𝑜𝑙𝑢𝑚𝑒 1,470,588.2 𝐿𝐶𝑌


Number of trucks =
𝑇𝑟𝑢𝑐𝑘 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦
= 6 𝐿𝐶𝑌/𝑡𝑟𝑢𝑐𝑘
= 245,098 Truck

■■■■

2) Calculate the volume of excavation in bank measure required for the basement shown.

6.6 ft
8.2 ft

28 ft

6.9 ft 6 ft
45 ft

7.4 ft 6.8 ft

26 ft 24 ft

Eng. Ibrahim Al Mohanna, Civil Engineering, 2 A 92 CE417 Tutorial # 2


Solution:

First Part

Second Part

6.6 + 6 + 6.9 + 8.2 +


2
6.6
Average depth of first part = = 6.725 ft
4

Area of the first part = 24 ×28 = 672 ft2

Volume of excavation of the first part = area × depth = 672 × 6.725 = 4519.2 BCf

7.4+ 6.8 + 8.2 + 8.2 +


2
6.6
Average depth of second part = = 7.45 ft
4

Area of the second part = 45 ×26 = 1170 ft2

Volume of excavation of the second part = area × depth = 1170 × 7.45 = 8716.5 BCf

Total volume of excavation = 4519.2 + 8716.5 = 13235.7 BCf

■■■■

Eng. Ibrahim Al Mohanna, Civil Engineering, 2 A 92 CE417 Tutorial # 2