Construction Leak Test Procedure
Construction Leak Test Procedure
INSTRUMENT
TUBING PRESSURE & LEAK
TEST
PROCEDURE
CONSTRUCTION INSTRUMENT REVISION NO. : 0
PROCEDURE NO.
PAGE 1 OF 11
TUBING PRESSURE & LEAK TEST
PROCEDURE
TABLE OF CONTENTS
1.0 PURPOSE 2
2.0 SCOPE 2
3.0 REFERENCE 2
5.0 PROCEDURE 4
8.0 APPENDICES 6
1.0 PURPOSE
CONSTRUCTION INSTRUMENT REVISION NO. : 0
PROCEDURE NO.
PAGE 2 OF 11
TUBING PRESSURE & LEAK TEST
PROCEDURE
This procedure serves as a guideline for the implementation of standard requirements for construction
instrument tubing pressure & leak test. The purpose of pressure & leak test is to confirm the tubing and
fittings joints have been properly tightened and the working pressure of the tubing system flow smoothly.
2.0 SCOPE
This procedure applies to construction instrument tubing pressure & leak test to the following:
- Transport line Instrument air/gas supply line tubing
- Process Impulse and pneumatic signal line tubing
- Fusible plug loop line tubing
- Sample line and N2 line tubing
- Hydraulic line tubing
3.0 REFERENCES
Generally all fabrication, installation and inspection works shall be carried out in accordance with PTS as
main reference, IFC Drawings, manufacturer’s recommendations, applicable codes and standards as
stated below.
No Description
No Description Details
16 QC Quality Control
5.0 PROCEDURE
5.1 General
5.1.1 This procedure covers the method and document/record control for the pressure & leak test of
instrument tubing installation.
5.2.2 Personnel stated in (i) is the team leader and shall be responsible for the preparation of
procedures if any, scheduling and overall execution of the job. Personnel stated in (ii) shall be
totally involved in the tubing pressure & leak test of the tubing.
5.2.3 Prior to commencement of pressure & leak test activity, the following should be made available by
Supervisor:
5.2.4 Prior to pressure & leak test activity, all related individually instruments shall be checked to
ensure installation complies with PTS.
5.2.5 All leak test tests shall be witnessed by CONTRACTOR QC and CLIENT representative and the
data will be recorded.
6.1.1 Check and verify that all the connection was tightened and installed properly.
6.1.2 Process impulse (IMP), sample line (SPL), hydraulic line (HYD) and transport line Instrument
air/gas supply line shall be pressure tested 1.5 times the maximum operating pressure (refer Note
1 and 2).
6.1.3 Pnuematic signal line (SIG) shall be leak tested at pressure of 2 barg.
CONSTRUCTION INSTRUMENT REVISION NO. : 0
PROCEDURE NO.
PAGE 5 OF 11
TUBING PRESSURE & LEAK TEST
PROCEDURE
6.1.4 All joints and connection shall be applied with soap solution to facilitate the leak detection of the
line.
6.1.5 The pressure shall be maintained for 60 minutes and pressure drop must not exceeding 0.069 bar
or 1 psi per hour. Minimum scale division of test gauge or manometer used shall be 1 psi.
6.1.6 All joints and connections that were found defective shall be repaired immediately and retested
again.
6.1.7 Reference test gauge must have an accuracy of not less than +/- 5% of the full scale. Complete
with the calibration certificate.
6.1.9 After all the instrument has been checked/tested, all color coded marked will be in place for
identification; Red – Fail, Green – Pass.
6.1.10 All tested lines are to be witness by CONTRACTOR QC and CLIENT representative.
6.1.11 Result will be recorded to the applicable check sheet and signed by CONTRACTOR QC and
CLIENT representative.
Notes :
1) Pressure test for pipe rating 150# below can be with pneumatic test at 1.5 times.
2) For 150# above, the test shall be using water (hydrotest) only because of safety concern using
high pressure pneumatic. Hydrotest performed shall be in accordance with CLIENT approved
hydrotest procedure.
CONSTRUCTION INSTRUMENT REVISION NO. : 0
PROCEDURE NO.
PAGE 6 OF 11
TUBING PRESSURE & LEAK TEST
PROCEDURE
VENT VALVE AT
PRESSURE GAUGE HIGHEST POINT
END PLUG
CLOSE
VALVE
PUMP
TUBING TO
CLOSE BE
VALVE PRESSURE /
LEAK
TESTED
DRAIN VALVE
FIGURE 1 – SCHEMATIC DIAGRAM FOR INSTRUMENT TUBING PRESSURE & LEAK TEST
8.1.2 If hydrotest is required, hydrotest report shall be attached together with the ITR-I05A.
9.0 APPENDICES
9.1 Appendix 1
9.2 Appendix 2
Prepare procedure,
JHA and any
needed document
Check tubing
Pnuematic line type e.g
signal line (SIG) IMP, HYD, SPL
& supply line
Test
Repair with 2
barg
Check Pressure rate
pressure 150# and above
need to be
Report tested.
and
recorded
Hydrotest
(Refer to CSP -
22)
Pressure
Repair test rate
150# and
below Report
and
recorded
Report
and
recorded
9.3 Appendix 3