Reducing Help Desk Turnaround Time Project Example - MFT 2005 03 PDF
Reducing Help Desk Turnaround Time Project Example - MFT 2005 03 PDF
M A G A Z I N E
T H E F I N A L T O L L G AT E
An Individual Copy
This copyrighted reprint from iSixSigma Magazine is for individual use only.
It may not be republished, electronically or physically reproduced, changed,
posted to a website or otherwise distributed without written permission.
For reprint permissions, please contact iSixSigma Magazine
at [email protected] or 847-919-0922 x4.
This report and others can be ordered
at http://www.iSixSigma.com/pubs
$
995 EACH
2
T H E F I N A L T O L L G AT E
The Final Tollgate features a Six Sigma project as it would presentation. It is assumed that the project leader has been
be presented to a panel of company executives at the final making regular presentations at each tollgate and that the
project review. The objectives of such a presentation are to executives in the audience have a basic understanding of
1) communicate significant results of the project, 2) share Six Sigma. The content for this project was assembled for
highlights of how results were achieved and 3) gain agree- illustration purposes. It is based on fabricated data from a
ment to close the project. The slides are the Black Belt’s fictional company. Any similarities to an actual project are
visual presentation and the accompanying text is the verbal coincidental.
Do you have an exemplary Six Sigma project to share? Would you like to see it here? Submit it to us at isixsigma.com/submit
DEFINE D M A I C
As you know, strong competition and low profit The team’s operational definition of TAT is the
margins are the nature of our business. We cannot elapsed time from when support from the help
afford to ignore or respond slowly to any desk is requested by an employee until the work
opportunity to reduce costs. With this motivation is completed by the IT technician and logged by
in mind, the team was asked to tackle this the help desk coordinator.
problem immediately and complete the project
within four months. By following the DMAIC In the course of completing the SIPOC and
process, we were able to accomplish the aggres- identifying suppliers, we realized that the site
MEASURE D M A I C
29.3
28.1
2.96
-7.1
-9.6
-8.3
-5.8
-4.6
-3.3
-2.1
-0.8
0.45
1.7
4.22
9.24
10.5
11.8
13
14.3
15.5
16.8
18
19.3
20.5
21.8
23.1
24.3
25.6
26.8
5.47
6.73
7.99
16
12
4
2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
July Aug Sept Oct Nov Dec Jan Feb Mar April May
Measurement error (after) = 9.5%
Month
ANALYZE D M A I C
Improve D M A I C
TAT, Days
spare parts 10
Results
• Within five months, TAT reduced to 3.2 hours and variation to 0.82 hours
• Reduction of defects yields $586,000 in annualized savings
• Implementation of solutions cuts risk in half: RPN reduced from 1282 to 619
chases, because ordering spare parts and of the Black Belt team. The accounting manager
waiting for material request approvals was was added to the team to help set up blanket
very time consuming. A tighter inventory purchase orders.
control for spare parts was established as
well. IT technicians also were allowed to A pilot test was conducted, in which corrective
keep an inventory of commonly used actions were put in place in a limited part of the
parts in their area. business to determine the impact on TAT. After
one month, a two-sample hypothesis test of the
3. The client-server was upgraded with print- mean and of variation was conducted on the
ing fixes, resulting in an improved print TAT data – both before and after the pilot. This
service that alleviated the problem of print- evaluation showed that implementation of the
ers losing connection to the network and corrective actions had a statistically significant
not distributing printers to the desktop. effect on the mean TAT (t = 7.7, p < 0.001) and
TAT standard deviation (F = 58.7, p < 0.001).
4. Several standard operating procedures
(SOPs) were developed: Based on the good results in the pilot, the cor-
a. Basic trouble shooting SOP to rective actions were institutionalized throughout
determine the root cause of the the organization, and the progress was followed
problem more rapidly for five additional months.
b. SOPs for installing hardware and
software After five months, the average TAT was reduced
c. SOP for inputting information onto from 10.2 hours before implementation to 3.2
the work request ticket hours after implementation of the corrective
actions (t = 22.1, p < 0.001). The standard devi-
Addressing the root causes affected the make-up ation was reduced from 2.1 hours to 0.82 hours
Control D M A I C
4 CEN = 3.2333
2 LCL = 3.107
0 LCL = 0.9989
July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct
(F = 489, p < 0.001). The defect rate decreased coordinator has been trained to monitor the
from 88 percent to 1.4 percent, resulting in an control chart and therefore follow the OCAP
annual savings of $586,000. The FMEA was when an assignable cause is observed.
revisited, and implementation of the corrective
actions resulted in a significant decrease in the The procedures that were developed in the
overall risk. Improve phase were institutionalized throughout
the site by training all members who touch the
Control (Slide 5) process and ensuring that the procedures are
The effect of implementing the corrective aligned with the site’s quality manual. The work-
actions was observed almost immediately and is station managers will conduct an audit of the
illustrated using an Individuals and Moving procedures and the control charts in another
Range (I-MR) chart. The work request process three months to ensure that the new procedures
from this point forward will be monitored daily are being used and the TAT level is being main-
using the I-MR chart. tained. u
Initially, only one out-of-control symptom will Your input is welcome. Please send comments to
be used for detection of assignable causes: one [email protected].
data point outside the control limits. As the IT
members become more sophisticated in the use
of the I-MR chart, a second out-of-control symp-
tom will be added: four of five data points Wayne Stansbury is a certified Master Black Belt.
greater than one sigma from the center line. He has taught Champion, Black Belt and Green
Belt courses across the United States, Mexico and
An out-of-control action plan (OCAP) has been Japan. Mr. Stansbury is currently a senior project
developed for the I-MR chart. The help desk manager at Harcourt Assessment.