Coworking Port: Master Thesis Maja Magdalena Koszulinska Architecture & Design Aalborg University May 2015
Coworking Port: Master Thesis Maja Magdalena Koszulinska Architecture & Design Aalborg University May 2015
Master Thesis
Maja Magdalena Koszulinska
Architecture & Design
Aalborg University
May 2015
89
CoWorking Port
Aalborg University
Architecture & Design
Semester: MSc 04
Project period: February - May 2015
Pages: 87
Architectural supervisor:
Claus Bonderup, Professor
Department of Architecture, Design & Media
Technology, Aalborg University
Technical supervisor:
Lars Damkilde, Professor
Department of Civil Engineering in Esbjerg
Aalborg University
1
2
ABSTRACT
3
4
CONTENT
Abstract 3 Presentation 31
Concept 32
Introduction 7 Concept of the transition 38
Method 10 Masterplan 39
Tectonic 11 Axonometry diagram 40
Plan 42
Programme 13 Elevations 50
Coworking 14 Interior 54
Programme 15 Sections 58
Structure 60
Analysis 17 Detail 61
Portugal 18 Conclusion 62
Porto 20
Climate in Porto 22 Process 65
Site in a context 23 Location on the site 66
Site 24 Tests of the shape 67
Views from the site 26 Elevation / windows 68
Inspiration 28 Dayilight 69
Vision 29 Materials 71
Construction 72
Interior 74
References 76
Appendix 78
5
6
INTRODUCTION
7
8
INTRODUCTION
9
METHOD
Good architecture must simultaneously fulfill Additionally, it implies iterativeness. It means Additionally, the project was also prepared for
various criterias. Aesthetics of a designed that at every stage the current results must a competition with a deadline in the middle
building is only a piece of a puzzle which be evaluated and before they are satisfying of April 2015. This required reaching the
involves such aspects as functionality, the designer may need to return to a previous presentation phase of the integrated design
sustainability, or technical requirements and phases. Different methods are used to assess process very early, what allowed to perceive
limitations. The process of designing a building the project during the process, such as creating problems which would later be significantly
is complicated and involves knowledge physical models, sketching, 3D modelling, CAD harder to solve.
and specialists from different branches that drawing, lightning or construction simulation
cowork with each other on different stages. and analysis with software like Velux Daylight
Furthermore, it is not possible to assess all Visualizer or Robot Structural Analysis.
requirements at early stages of a project, what
may lead to unsatisfactory results or delays. Due to the diverse and demanding location of the
site during the designing phase various building
In this project the Integrated Design Process shapes were considered. Many directions
was applied to improve the workflow and thus proved to be unsatisfactory on different levels
assure that the final results will meet all the criteria of the analysis because they did not solve all the
for a good architecture. The integrated design aspects such as blending in the surrounding or
process consists of five phases – problem, construction limitations. This required repeating
analysis, sketching, synthesis and presentation. various phases until reaching satisfying results.
10
TECTONIC
Nowadays, the capabilities in architecture are Resistance” says, that architecture has to have “The bulldozing of an irregular topography
almost unlimited. Whatever the architect will an authentic connection to a place. into a flat site is clearly a technocratic gesture
design, it can be built, anywhere. The fact that which aspires to a condition of absolute
limitations almost do not exist, allows to let the “The fundamental strategy of Critical placelessness, whereas the terracing of
imagination run wild. This leads to having the Regionalism is to mediate the impact of the same site to receive the stepped form of
same architecture all around the world – It is the universal civilisation with elements derived a building is an engagement in the act of
same in terms of presented values, where the ‘indirectly’ from the peculiarities of a particular ‘cultivating’ the site.”
focus is put on creating an architecture which place.”
will suit the designer and the client, but not Designers cannot adjust the site to their ideas,
necessarily the environment. Critical Regionalism is about making it should be the opposite. The topography,
architecture which coexists with the climate or light should be a designing factor
The globalisation in architecture creates a surrounding. The good design needs to be a which will help to generate/shape/create
surrounding that does not any more have its part of the whole, not separate element. Critical something unique.
identity. As a result, the architecture feels out Regionalism does not mean that architecture
of place or the place loses its uniqueness cannot be modern – it should be. But with Steven Holl said: “Architecture surrounds you,
completely. respect to the place and nature. in the same way as music surrounds you”.
Thus, it should not be without a soul, but rather
Kenneth Frampton in his “Towards a Critical full of values and harmony.
Regionalism: Six Points for an Architecture of
11
12
PROGRAMME
13
Place of work before coworking
At home
COWORKING In a traditional office
No fixed location
In a small shared office
In a coffe shop
Coworking space is a fairly fresh idea for a place In a library
to work for people from different branches. In In a business center
the era of the Internet and “global village” many Other
people, especially among freelancers such as
software developers and graphic designers, Business network 80%
started working remotely from their homes.
SERVICES
Printing area 20 m2
Stationery 15 m2
Zen space 80 m2
Kitchen 60 m2
Dining area 120 m2
Bar 80 m2
Technical room 25 m2
Meeting area 160 m2
Conference room 200 m2
Group activities area 160 m2
Proffesional support office 30 m2
Restroom
GREEN SPACES
PARKING 50 places
17
PORTUGAL
PORTO
Fig. 3.10. Cascades of tarraces Fig. 3.11. Famous port wine cellars
21
Average high (°C) Avarage low (°C)
30 Average high (°C) Avarage low (°C)
30 Average high (°C) Avarage low (°C)
30
22.5
22.5
January
February
March
April
May
June
July
August
September
October
November
December
0
as a mediterranean climate.
January
February
March
AprilApril
May May
JuneJune
July July
August
September
October
November
December
0
January
February
March
August
September
October
November
December
Porto has warm, dry summers and mild, rainy
winters. However, even during winter the long
periods with sun and mild temperatures are Fig. 3.12. Average temperatures in Porto (Wikipedia, 2015)
Mean monthly sunshine hours
common. 320.0 Mean monthly sunshine hours
During the summer the average temperature is 320.0
Mean monthly sunshine hours
between 16°C and 27°C. The occasional heat 320.0
240.0
waves are possible and then temperature can 240.0
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
AprilApril
May May
JuneJune
July July
August
September
October
November
December
0.0
January
February
March
August
September
October
November
December
Fig. 3.13. Mean monthly sunshine hours in Porto (Wikipedia, 2015)
13:36
12:07
12:07
12:07
10:38
10:38
10:38
9:10
9:10
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
April April
May May
JuneJune
July July
August
September
October
November
December
9:10
January
February
March
August
September
October
November
December
Fig. 3.14. Average daylight hours in Porto (ClimaTemps, 2015)
22
SITE IN A CONTEXT Site of the project is placed close to the old city The site is an unused area, which is very
center of Porto, which is listed by UNESCO. The visible from the bridges and the opposite side
specific character of the buildings creates the of the river. The empty space disturbs the
atmosphere one of a kind. Location between characteristic city panorama.
two bridges, on a high slope of the riverside
make the area even more attractive.
Site
o
Lu
is
The site can be described as an area which is
full of potential, with a great view to the bridge 4 2
Ponte Luis I, the hallmark of the city. One part
of the site is located on a steep, southern slope 1
and ends just on the riverbank. In the middle
of the site there is a road which goes partially
ias
above the ground. The only current function of Sou
sa D
.
o Gen
the area is a car park which is located under R. d
the road. The northern part of the site is much
less steep, partially completely flat.
s
inha
F onta
das
seio
Pas
Eiffel
G ustavo
Av. de
3 4
The good building is not one that hurts the landscape, but one which makes
the landscape more beautiful than it was before the building was built.
— Frank Lloyd Wright
29
30
PRESENTATION
31
CONCEPT The site inspires through being an empty gap in
the urban panorama. The shape of the building
should blend in the character of the surrounding
buildings and continue the rhythm of the city.
38
MASTERPLAN
Outdoor gym
Restaurant
Terraces with
panorama view
The level 0 was set where is the car parking Technical rooms 64.5m2
and the most flat part of the site. The building Service room 5.4m2
has in total seven floors and on most of them Bathroom 26m2
the coworking areas are intertwined with Locker rooms 66m2
other functions. Shared kitchen 90m2
The special character has the Zen space, Dining area 115m2
which is 8m high and 4.5m wide. It has a big Lounge areas 274.5m2
vertical window, which is the only source of Group rooms 283m2
light. The idea for the place was to create a Coworking space 1024m2
room with calm and inspiring atmosphere. Printing/stationery 40m2
Gym 321m2
The other function is a restaurant with a view Conference rooms 251m2
to the bridge Ponte Luis I from the inside as Restaurant 145m2
well as from the spacious terrace. Zen space 60m2
From the northern side, on the square, a Professional support office 30m2
cafe and gym were designed – functions Entrance halls 75m2
which will gather people and help to revive Lobby 50m2
the place. Bar 104m2
Archives 34.4m2
Administration 17.4m2
Office 37.2m2
Meeting area 164m2
Cloak room 14m2
Coffee bar 18m2
Magasin 7.5m2
Restaurant kitchen 36m2
Meeting room 43m2
Terraces 158m2
42
B
C C
A A
C C
A A
B Maja Koszulinska
Scale: 1:100 Date: 27.05.2015
C C
A A
Maja Koszulinska
Scale: 1:100 Date: 27.05.2015
C C
A A
B Maja Koszulinska
Scale: 1:100 Date: 27.05.2015
A A
Maja Koszulinska
Scale: 1:100 Date: 27.05.2015
A A
Maja Koszulinska
Scale: 1:100 Date: 27.05.2015
+ 10.5
+ 6.5
+ 4.0
+ 2.5
+
- 0.5 - 0.0
- 4.0
- 8.0
- 12.0
+
- 0.0
- 4.0
- 8.0
- 12.0
- 16.0
+ 10.5
+ 6.5
+ 2.5
- 0.5
60
DETAIL Reinforced in-situ concrete 70mm
Separation layer 10mm
Isoboard 80mm
Waterproofing membrane
Lightweight concrete with slope 100mm
Plasterboard 125mm Bubbledeck slab 280mm
Vapour control layer
Insulation 80mm
Air gap 40mm
In-situ concrete 280mm
Roof detail
Wooden flooring
Underlay
Lightweight concrete 30mm Wooden flooring
Insulation 50mm Underlay
Reinforced concrete bubbledeck 280mm Lightweight concrete 30mm
Installation space with suspending structure Insulation 50mm
Suspended ceiling Reinforced concrete bubbledeck 280mm
Installation space with suspending structure
Suspended ceiling
Plasterboard 125mm
Vapour control layer
Insulation 80mm
Air gap 40mm
In-situ concrete 280mm
Scale: 1:10
The main focus through the designing process “A building should appear to grow easily from
was to create a building which will respect the its site and be shaped to harmonize with its
neighbourhood. The main guides were found surroundings (…)” —Frank Lloyd Wright
by extracting the most characteristic shape – a
slim cuboid. The building was formed to have a perceptible
To make the building more integrated into connection with the neighbourhood, but
the surrounding, its volume was divided into representing the architecture of these days.
sections and placed wall by wall on different The similarity is through the overall principle of
levels and depth. shape, to respectively fill the gap in the urban
fabric.
The topography of the site formed the final The designed proposal belongs to the
shape of the building. One part is on a steep panorama repeating the same rhythm of the
slope, more like a terraced building, while the city.
other is placed on a flat area and, together
with the existing buildings, it creates a public
square.
62
Fig. 4.30. Visualisation from the riverside
63
64
PROCESS
65
LOCATION ON THE SITE
69
The materials for the building were chosen by
the criteria of modern look, but at the same
time suiting the old surrounding. The materials
used in the design were corten steel, concrete
(in-situ) and coloured concrete. These three
materials were applied alternately in order to
achieve the look of separate sections.
Reinforced concrete was chosen as the material In the structure the prefabricated version of the
for the structural system of the building. The slab is used, which works as a one-way slab.
constructing elements are bearing walls and The slab is supported by beams hidden in the
columns. thickness of the slab and by bearing walls.
For the slab the BubbleDeck system was
chosen. It is a new technology, around 20 years
on the market, but becomes more popular
thanks to its advantages.
The difference between BubbleDeck and
classic slab is that Bubbledeck has plastic balls
which are replacing the concrete in the middle
of a classic slab, which does not contribute to
its structural performance. As a result the slab
is lighter and can work in wider spans.
The wider spans were the main reason why this
solution is used. The building is designed as
an open plan, so the number of columns were
limited to minimum.
Moreover, the Bubbledeck slab is much more
sustainable than classical. According to
producer, 35% less concrete is used in the slab
compared to the traditional floor system. It has
the impact on the whole structure, as the total
weight of the construction is lighter.
Furthermore the balls for the slab are made
from recycled plastic and all materials used
can be reused upon demolition.
Fig. 5.9. Construction scheme.
72
The prefabricated BubbleDeck slab needs Furthermore the beam in the axis ‘M’ was
to be supported by bearing walls or beams. calculated, to get the reactions in the point of
However beams are in the thickness of the slab, connection with the column.
which means that slab creates a flat ceiling and For the calculations the prefabricated beam
thickness of the slab is the final thickness. from concrete C25 was used.
Robot Structural Analysis was used to calculate
To calculate the accurate thickness of the slab, the reactions on the beam. Two separate Fig. 5.10. Double span beam
the bending-strenght design for a rectangular calculations were made, for a beam under the
cross section was performed - according to roof and under the slab.
producer recommendations. As a result the maximum force on the beam
The calculations where based on the part of a from roof is 681kN, while 970kN for the beam
slab between axis ‘L’ and ‘M’, where the span under the slab.
is the biggest.
To calculate the maximum bending moment the The next step was to calculate the dimensions
model of bearing walls and columns were build of the column. The columns of 400mm x 400mm
in Robot. Calculations of the roof loads were are dimensioned to take forces of 2508kN. The
made manual and implemented in Robot. The applied force for the column on the first floor,
maximum bending moment for the slab is 122,6 extracted from Robot, is 1651kN, so the column
kNm. will hold. Unfortunately, the column of the same
After calculations, taking into account the dimensions was not able to hold the forces in
span of the slab, the thickness of 280mm was the ground floor. Hence, the dimensions were
chosen. changed into 450mm x 450mm. As a result, the
applied force is 2653kN while the column can
hold 3318kN.
All of the calculations were made according to Fig. 5.11. Placement of the beam – in axis M
Eurocodes and can be found in Appendix.
73
Fig. 5.12. Interior visualisation - competition version
74
75
REFERENCES
ILLUSTRATIONS
Loads
Layers:
Chosen slab
78
where:
µsds — relative bending moment in the ball zone
msd — max bending moment [M N m]
DBD — ball diameter [m]
dB — static height of the BubbleDeck [m]
fck — characteristic strength according to DIN 1045-1 [M N/m2 ]
DBD = 0.225m
dB = 0.25m
Beam
All calculations are done for the beam in the ”M” axis.
79
25kN/m3 — concrete beam load C25
w = 0.4m — width of the beam
h = 0.28m — height of the beam
To calculate reactions on the beam, the Robot Structural Analysis was used.
Fz = 969.99kN ≃ 970kN — the value of the reaction in the point of connection of the slab with a column (from RSA). Slab load.
Fz 2 = 681kN — the value of the reaction in the point of connection of the slab with a column (from RSA). Roof load.
80
Column
h = 4m
w = 0.4m
l = 0.4m
Esk 2 · 105 M P a
Esd = =
γs 1.2
The concrete design compressive strength:
fck 35M P a
γc = 1.4 fcd = = = 25M P a
γc 1.4
The steel design compressive strength:
fyk 550M P a
γs = 1.2 fyd = fyd = = 458.3M P a
γs 1.2
81
Ultimate limit state
Slenderness ratio – λ:
l b · h3
λ= ! I= b·h=A
I 12
A
√ √
l· 12 4000mm · 12
λ= = = 34.6
h 400mm
The reinforcement ratio – ρ:
Asc 8 · 253 ∗ π4
ρ= = = 0.024 = 2.4% {0.2% ≤ 2.4% ≤ 4.0%}
Ac 400 · 400
Beginning modulus of elasticity – E0,crd :
" #
1000 · fcd f or fcd ≤ 25M P a
E0,crd =
0.75 · E0d f or fcd > 25M P a
Critical tension – σ:
• concrete
fcd 25M P a
σcrd = fcd ·λ2
= = 11.52M P a
1+ π 2 ·E0,crd
1 + 28900M Pa
24674M P a
82
Column load capacity Ultimate limit state
w = 450mm
h = 450mm • concrete
l = 4000mm fcd 25M P a
σcrd = fcd ·λ2
= = 12.75M P a
1+ π 2 ·E0,crd
1 + 23716M Pa
24674M P a
Concrete 32 — fck = 35M P a
The relationship between reinforcement and the concrete modulus of elasticity – λ:
Steel ⊘25 — fyk = 550M P a
Ecm
Ec,ef f =
Modulus of elasticity — Esk = 2 · 105 M P a (for steel) 1+ϕ
Ecm = 34000M P a (concrete class)
Esk 2 · 105 M P a
Esd = = ϕ = 1.5
γs 1.2
34000M P a
The concrete design compressive strength: Ec,ef f = = 136000M P a
1 + 1.5
fck 35M P a Esk
γc = 1.4 fcd = = = 25M P a λ= = 14.7
γc 1.4 Ec,ef f
• steel
The steel design compressive strength:
σs = λ · σcrd = 14.7 · 12.75M P a = 187.4M P a
fyk 550M P a
γs = 1.2 fyd = fyd = = 458.3M P a σs < fyd ⇒ 169.34M P a < 458.3M P a
γs 1.2
83
Column load capacity
The force extracted from Robot on the most exposed and critical column (on the ground floor) is 2621kN .
84
Additional informations about BubbleDeck.
Report from AEC Consulting Engineers Ltd. / Professor M.P. Nielsen - The Technical University of Denmark – Enclosure H2.
Only differences in materials concerning the slabs are considered. Advantages in the building design and building process are not taken into
account.
For the same amount of steel and concrete, BubbleDeck has 40 % larger span and is furthermore 15 % cheaper.
For the same span, BubbleDeck reduces the amount of concrete with 33 %, and reduces the price with 30 %.”
“Parts of the floor construction are pre-fabricated. There are three alternatives:
- Reinforcement Modules in which the bubbles are
trapped between the upper and lower reinforcement
mesh;
- Filigree Elements as above, but also with a pre-
fabricated concrete biscuit cast onto the bottom
reinforcement mesh (permanent formwork);
- Pre-cast Finished Planks in which the reinforcement
modules have been cast into concrete to full finished depth.”
Reference: BubbleDeck. (2013) BubbleDeck Voided Flat Slab Solutions. [Online] Available from:
http://www.bubbledeck-uk.com/pdf/2-BDTechManualv1a.pdf. [Accessed: 11.05.2015]
The beams can be hidden in the deck by spreading the reinforcement to make a space for a beam. Then the concrete is poured to
connect parts together.
85
86
Screenshot from Robot Structural Analysis. Double span beam, reactions.
Screenshot from Robot Structural Analysis. Model of the slab with bearing walls and columns.
Screenshot from Robot Structural Analysis. Beam with the additional load of the roof.
87
88