0% found this document useful (0 votes)
95 views

RAP - Concrete Slab Con 1 Laydown Area

This document is a cost estimate for a concrete slab construction project. It provides estimates for manpower costs, equipment rental costs, transportation costs, material and consumable costs, and taxes/insurance. The total estimated cost is 8.535 billion IDR, including over 971 million IDR for manpower, 311 million IDR for equipment rental, 319 million IDR for transportation, 5.071 billion IDR for materials, and 437 million IDR for taxes, insurance and other expenses. The estimated profit from the project is 1.425 billion IDR.

Uploaded by

tegal parang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views

RAP - Concrete Slab Con 1 Laydown Area

This document is a cost estimate for a concrete slab construction project. It provides estimates for manpower costs, equipment rental costs, transportation costs, material and consumable costs, and taxes/insurance. The total estimated cost is 8.535 billion IDR, including over 971 million IDR for manpower, 311 million IDR for equipment rental, 319 million IDR for transportation, 5.071 billion IDR for materials, and 437 million IDR for taxes, insurance and other expenses. The estimated profit from the project is 1.425 billion IDR.

Uploaded by

tegal parang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project : CONCRETE SLAB CON 1 LAYDOWN AREA

Rencana Anggaran Pelaksanaan


No. Job Description Qty Unit Perkiraan Unit Price Total Price Ket
Hari (IDR) (IDR)
Kerja
A Manpower
1 Project Manager 1 Org/Bln 78 475.000,00 37.050.000,00 Include OT
2 Supervisor 1 Org/Bln 78 450.000,00 35.100.000,00 Include OT
3 Safety Officer 1 Org/Bln 78 375.000,00 29.250.000,00 Include OT
4 Admin & Logistic 2 Org/Bln 78 325.000,00 50.700.000,00 Include OT
5 Surveyor 1 Org/Bln 78 350.000,00 27.300.000,00 Include OT
6 Surveyor Assistant 1 Org/Bln 78 245.000,00 19.110.000,00 Include OT
7 Mason 8 Org/Bln 78 325.000,00 202.800.000,00 Include OT
8 Carpenter 6 Org/Bln 78 325.000,00 152.100.000,00 Include OT
9 Rebarman 2 Org/Bln 78 325.000,00 50.700.000,00 Include OT
10 Driver 3 Org/Bln 78 275.000,00 64.350.000,00 Include OT
11 Helper 12 Org/Bln 78 245.000,00 229.320.000,00 Include OT
12 Makan 38 Bgks/Hari 78 25.000,00 74.100.000,00
Subtotal 971.880.000,00
B Peralatan ( Nilai Penyusutan)
1 Drum Roller HDDR 1860D 1 Unit 1 74.500.000,00 74.500.000,00
2 Plate Compactor 2 Unit 1 13.000.000,00 26.000.000,00
3 Concrete Trowel 2 Unit 1 18.200.000,00 36.400.000,00
4 Concrete Vibrator 2 Unit 1 12.500.000,00 25.000.000,00
5 Auto level Top-con 1 Unit 1 4.500.000,00 4.500.000,00
6 Jack Hammer 2 Unit 1 10.500.000,00 21.000.000,00
7 Gerobak Sorong 6 Unit 1 850.000,00 5.100.000,00
8 Circle Saw 2 Unit 1 1.650.000,00 3.300.000,00
9 Genset 5 Kva 1 Unit 3 4.000.000,00 12.000.000,00
10 Gunting Wiremesh 2 Unit 1 645.000,00 1.290.000,00
11 Grinding Machine 2 Unit 1 1.145.000,00 2.290.000,00
12 Mason Tools 1 Set 1 24.650.000,00 24.650.000,00
13 Carpenter Tools 1 Set 1 18.650.000,00 18.650.000,00
14 Safety Set 1 Set 38 1.177.050,00 44.727.900,00
15 Fuel/Solar 1500 Ltr 1 7.650,00 11.475.000,00
Subtotal 310.882.900,00
C Tansportasi
1 Kijang Innova 1 Unit/bln 3 11.000.000,00 33.000.000,00
2 Bus Transportasi 1 Unit/bln 3 30.000.000,00 90.000.000,00
3 Light Truck Isuzu Traga 1 Unit/bln 3 7.500.000,00 22.500.000,00
4 Fuel (Asumsi 50 ltr perhari utk 3 Kendaraan) 1800 Ltr/bln 3 7.500,00 40.500.000,00
5 Delivery Material Surabaya - Maluk 132.971,64 Kg 1 850,00 113.025.894,00
6 Biaya mob bus ke site 1,00 ls 1 7.500.000,00 7.500.000,00
7 Delivery Material Mataram, KSB - Site 1 ls 1 12.500.000,00 12.500.000,00
Subtotal 319.025.894,00
D Materials/Consumable
1 Concrete K350 1.460,44 M³ 1 2.202.183,39 3.216.156.710,09
2 Wiremesh M10 150-150 (2,1m X 5,4m) 1.361,00 Lbr 1 1.110.000,00 1.510.710.000,00
3 Wiremesh M8 150-150 (2,1m X 5,4m) 140,00 Lbr 1 705.000,00 98.700.000,00
Decking layer
4 Wiremesh M6 150-150 (2,1m X 52m) 4 Rool 1 3.775.000,00 15.100.000,00
kedua
5 Playwood 18 mm 100,00 Lbr 1 295.000,00 29.500.000,00
6 Kasau 5/7 12,00 M³ 1 4.650.000,00 55.800.000,00
7 Kasau 4/6 12,00 M³ 1 4.650.000,00 55.800.000,00
8 Plastic sheet for concrete base @ 1,2 X 50 m 126,00 roll 1 139.890,00 17.626.140,00
9 Galv. Grating 1 Sheet 1 6.500.000,00 6.500.000,00
10 Paku Campuran 100,00 Kg 1 25.000,00 2.500.000,00
11 Kawat Beton 250 kg 1 25.000,00 6.250.000,00
12 Semen Tiga Roda 150 Zak 1 95.000,00 14.250.000,00
13 Papan untuk bouwplank 40 sheet 1 225.000,00 9.000.000,00
14 Benang Nylon 10,00 Roll 1 26.500,00 265.000,00
15 Sarung Tangan Kombinasi 648 Pcs 1 27.750,00 17.982.000,00
16 Masker CIG 801 F 50 Box 1 205.350,00 10.267.500,00
17 Ear Plug 38 Pcs 1 34.500,00 1.311.000,00
18 Pasir 12 M³ 1 271.428,57 3.257.142,86 Beton Decking

Subtotal 5.070.975.492,95
E PPh 25, Insurance, etc
1 PPh 25 / tax withheld by PTAMNT 1 Ls 2,40% 8.535.273.040,00 204.846.552,96
2 Insurance BPJS TK & Kes 1 Crew/Bln 3,0 24.700.000,00 74.100.000,00
3 Overhead/Biaya tak terduga 1 Ls 1,50% 8.535.273.040,00 128.029.095,60
4 Biaya MCU Karyawan 38 Ls 1,00 800.000,00 30.400.000,00
Subtotal 437.375.648,56
Total Rincian Anggaran Pelaksanaan 7.110.139.935,51
Total Nilai Penawaran IDR 8.535.273.040,00
Gross Profit 1.425.133.104,49
Presentance Profit & Modal 16,70%

You might also like