Section - 9 Hydraulic Design of Energy Dissipaters
Section - 9 Hydraulic Design of Energy Dissipaters
TABLE OF CONTENTS
9.5 Design Procedure for (Type A) Riprap Basin Energy Dissipater 9-4
FIGURES
Figure 9.1 : Conceptual Model of Energy Dissipater (Design Source HEC 14) 9-3
Figure 9.2 : Riprap Basin Depth of Scour(Source: Drainage Design Manual, ERA, 2001) 9-8
Figure 9.3 : Type 'A' Riprap Energy Dissipater (Source: RTA NSW, 1993) 9-9
Figure 9.4 : Distribution of Centerline Velocity for Flow from Submerged Outlets 9-11
Figure 9.5 : Riprap Size versus Exit Velocity 9-12
Figure 9.6 : Flow Chart for Design Procedure of Energy Dissipaters 9-17
Figure 9.7 : Flow Chart for Design Procedure of Riprap Basin 9-18
Figure 9.8 : Common Types of Energy Dissipaters (Source: RTA NSW 1993) 9-19
TABLES
Table 9.1: Factor for Determining the Hydraulic Radius of Uniform Flows in Circular Sections 9-13
The failure of many highway culverts can be attributed to unchecked erosion. Erosive forces prevailing in the
natural drainage network are often increased by the construction of roads. Interception and concentration of
overland flow and constriction of natural waterways inevitably result in increased erosion potential. To protect
the roads and adjacent areas, it is sometimes necessary to employ an energy dissipating device.
These devices cover a wide range in complexity and cost and the particular type selected will depend on the
assessment of the scour and erosion hazard. The purpose of this section is to discuss the points to be
considered in selecting and designing an energy dissipater which will meet the requirements indicated by an
erosion hazard assessment.
Energy dissipaters should be treated as part of the overall drainage system. Requirements to dissipate
energy may be increased, reduced or possibly eliminated by the change in culvert design; and downstream
conditions such as depth and velocity of flow and the channel stability. The designer should keep in mind
that the primary objective is to protect the highway structure and adjacent area from excessive damage due
to erosion. One way to accomplish this objective is to return flow to the downstream channel in a condition
that approximates the natural flow regime.
If hydraulic investigations indicate the need for an energy dissipater, the first step should be the
consideration of the possible ways to modify the outlet velocity and erosion potential. This can include
modifications in size of number of the culvert barrels. If modifications are not cost effective or hydraulically
unacceptable the design of an energy dissipater should be undertaken (HDS4 2001). The data, which are
available to the designer at previous design steps include:
design discharge;
flow depth and velocity;
culvert slope;
culvert operating characteristics; and
dimensions of the culvert and its components.
Along with the specific features of the energy dissipaters, the designers should consider the interrelationship
of the various parts as the energy dissipaters can change the culvert performance and channel protection
requirements. Figure 9.1 presents the conceptual model of energy dissipater design to elaborate the
relationship of various variables within this mini-system.
Internal dissipaters have limited application. Stilling basins are expensive and should be considered only in
extreme circumstances. This chapter, therefore, focuses on Riprap type dissipaters which are appropriate for
Addis Ababa city road drainage.
IN P U T D A T A
C u lver t D esign F l o w T r a n s it i o n
S tan dar d D esign
C h a n n e l C h a r a c t er i s ti c s W i n g w a ll s , e tc ..
S tan d ar d O u tlet D esign s N a tura l S cou r N o P r o te c t i o n
C o m p u ta t i on s R eq u ir ed
A llow a ble S co u r
E s t im a t e s
V elocity
L o c a t i o n D a ta M o d i fi c a t i o n
in C u l v e r t
F l o w T r a n s iti o n D e s ig n
E N E R G Y D IS S IP A T E R D E S IG N
N a t u r a l H y d r a u li c J u m p
F o r c e d H y d r a u li c J u m p
Im p a ct
I n cr e a s e d R e s i s t a n c e
D r o p S r tr u c tu r e s
R ip r ap
S t i ll in g W e l l s
OUTPUT DATA
D e t a i le d D e s i g n
E ffi c i e n c y
C ost
F l o w C o n d i ti o n s a t
E x it o f D i s s i p a t er
D i ff e r e n t D e s i g n S E L E C T IO N C R T IT E R IA F in a l D e s i g n
R eq u e sted
E ffi c i e n c y
C ost
F its N atura l C h an n el
G eom eter y V elocit y
W i th in P e r m i s s i b l e
S cou r R an ge
When a culvert outlet discharges on to a level bed, the plunging jet of water will scour a hole near the head
wall, and create a mound just downstream with the debris. The turbulence created by this modified
streambed, and the friction of the water against the ground, results in significant energy dissipation. The
Type-A rip rap basin is designed to imitate this natural streambed shape.
Riprap stilling basins are commonly used at culvert outfalls. The results of testing and research indicated that
the size of the scour hole at the outlet of a culvert was related to the size of the riprap, discharge, brink depth
and tailwater depth (RTA NSW, 1993). The mound of rock material that often forms on the bed downstream
of the scour hole contributes to dissipation of energy and reduces the size of scour hole. The general design
guidelines for riprap stilling basins include preshaping the scour hole and lining it with riprap. This dissipater
works most efficiently for culverts with low tail water depth (TW Y < 0.75) . It operates effectively for culverts
o
with high tail water. However, rip rap protection may be required for channel protection down stream of the
basin.
The main design features include dimensions of the basin and the size of the rock to be used. The following
design assumes the use of loose rock as riprap. Rock mattresses can be used even more effectively.
A curtain wall should be provided at the end of the riprap in erodible soils. The end of the basin can also be
turned down wards to create a curtain wall as a protection against undermining. The depth of the curtain wall
depends upon the type of soil.
Normally the calculation used to determine the culvert size will provide the information required for the
design of the dissipater. In this case the designer can proceed directly to step 3. If this information has not
been calculated, then step 1,2 and 3 should be used.
Ao = Wo y o (9-1)
Where:
Ao = Flow area at culvert outlet (m2)
Wo = Width of culvert (m)
y o = Depth of flow at culvert outlet (m)
Ao
Ro = (9-2)
Po
Where:
Ro = Hydraulic radius (m)
Ao = Flow area at culvert outlet (m2)
Po = wetted perimeter (m)
Ro = KD (9-3)
Where:
Ro = Hydraulic radius (m)
K = Factor obtained from Table 9.1
D = Pipe culvert diameter (m)
The out let flow velocity can be calculated using Manning's formula for culverts with sufficient length to act as
an open channel.
The flows in to the dissipater from circular, elliptical or oval culverts are converted to an equivalent
rectangular cross section with a depth of flow of half the width.
The Froude Number is calculated for flow conditions at the end of the culvert.
Vo
Fr = (9-6)
gy e
Where,
Fr = Froude number
Vo =Culvert outlet velocity (m/sec)
g = gravity (9.807m/s2)
y e =equivalent depth of water at culvert outlet (m)
Where possible, the invert elevation at the end of the culvert should be such that TW
yo ≤ 0.75 at the design
discharge. This results in the most efficient operation of the basin. If the tail water is deeper than indicated
the above condition, the dissipation occurs in a manner similar to that of a jet concentrating in a large body of
water. In such a condition, the velocity is reduced over a longer distance, and rip rap protection of the
channel down stream of the basin may be necessary.
For best results, the ratio of rock size to equivalent depth should be in the range:
where:
d 50 = median rock size (m)
y e = equivalent depth of flow at culvert outlet
hs
Obtain ye from Figure 9.2 and calculate the basin depth:
H s = ( hs ye )Ye (9-8)
Where,
H s = depth of basin
Ye = equivalent depth of flow at culvert outlet
hs
Calculate the value d 50 . This ratio should be greater than 2 and less than 4 for efficient basin operation. If
this criterion is not met, a different rock size should be chosen and the subsequent steps repeated.
Once hs is determined, all other dimensions could be found from Figure 9.3 In the exit region of the basin,
the walls and apron of the basin should be warped or transitioned so that the cross section of the basin at
the exit conforms to the cross section of the natural channel Abrupt transition of the surfaces in the direction
of flow should be avoided to minimize separation zones and resultant eddies.
If a maximum exit velocity is specified, the width of the outlet will have to be increased by extending the
length of the energy basin.
As a first step, determine the average flow depth in the natural channel under design flow conditions. To
satisfy the exit velocity criterion, the width of the end of the dissipater multiplied by the flow depth in the
natural channel, should approximately equal the design discharge divided by the specified exit velocity i.e.:
We d n = Q V s (9-9)
And hence:
Min. We = Q ( d n Vs ) (9-10)
Where:
We = energy dissipater end width (m)
Dn = average normal flow depth in channel (m)
Q = design discharge (m3/sec)
V s = specified exit velocity (m/sec)
If the width, We, is not already provided, extend the basin at the specified 3 to 1 flare until this with is
achieved. The outfall of the basin should be shaped so that it matches the cross section of the natural
stream. This transition should be as gentle as possible to avoid turbulence.
This design assumes low tail water depths (TW ≤ 0.75 y o ) . If tailwater depths are higher than this, the
distance required to slow the flow is increased. At site where this is likely to occur, the riprap basin should be
designed as above, with additional rip rap protection being provided for the necessary distance downstream
from the culvert outlet. To design this additional riprap protection, use Figure 9.4 to determine the central line
velocity profile. Once this is done, provide rip rap of appropriate size Figure 9.5 If the velocity is not
acceptable in the unprotected stream it may be desirable to use the same size rock as in the dissipater.
The above mentioned design procedures are summarized in the flow charts given in Figure 9.6 and Figure
9.7
Figure 9.4: Distribution of Centerline Velocity for Flow from Submerged Outlets
Source: Drainage Design Manual, ERA, 2001
Table 9.1: Factor for Determining the Hydraulic Radius of Uniform Flows in Circular Sections
Source: RTA NSW, 1993
Yo K Yo K Yo K Yo K
D Factor D Factor D Factor D Factor
0.01 0.0066 0.26 0.1516 0.51 0.2531 0.76 0.3024
0.02 0.0132 0.27 0.1566 0.52 0.2562 0.77 0.3031
0.03 0.0197 0.28 0.1614 0.53 0.2592 0.78 0.3036
0.04 0.0262 0.29 0.1662 0.54 0.2621 0.79 0.3039
0.05 0.0326 0.30 0.1709 0.55 0.2649 0.80 0.3042
Solution:
The procedures of Step 1 are taken care of in the given parameters and hence the computation starts from
Step 2
Step 6: Computation of basin depth to rock size ratio (Sizing the basin)
Step 7: Determine VS
a. d n = critical depth at basin exit = 1.01 m (Assuming a rectangular cross section with
width We = 7.32 m)
Solution:
TW = 1.28/1.22 = 1.05 > 0.75 (high tail water condition)
yo
Design riprap basin (Design Example 1) use steps 1-7
d 50 =0.55m, hs =1.95m
Ld =19.5m, LB =29.25m
b. Estimate centerline velocity at a series of downstream cross sections using Figure 9.4.
(VL )ave
L * L Vave V L VL d 50 **
D
10 19.5 0.59 4.50 0.43
15*** 29.25 0.37 2.82 0.18
20 37.01 0.30 2.32 0.12
21 41.15 0.28 2.32 0.12
*
use Wo = D in Figure 9.4
* from Figure 9.5
*** is on a logarithmic scale so interpolations must be logarithmically.
Riprap should be at least the size shown. As a practical consideration, the channel can be lined with the
same size rock used for the basin. Protection must extend at least 41.15 meters downstream from the culvert
brink.
Compile Hydrology
Is the Scourhole
Size Acceptable ?
No
Fr < 3
No
No
Is dissipater OK Yes
Hydraulically ?
End
d 50
Select ye
d 50
With 0.25< ye <0.45
hs
Obtain ye
(Figure 9.1)
No
24< hs <?
d 50
Yes
Length of dissipater pool
L p =max(10 hs , 3 Wo )
Length of Basin
Ld = max(15hs ,4Wo )
0.5
D = ⎡⎢ o o ⎤⎥
4y W
⎣ π⎦
No
VS =
Q d
TW ≤ 0.75
(WB B) do
Yes
Redesign rip rap
Yes
END
9.7 REFERENCES
Austroads-Australia (1994),“Waterway Design- A Guide to the Hydraulic Design of Bridges, Culverts and
Floodways”, AUSTROADS National Office, Sydney.
Ethiopian Road Authority (ERA - 2001), “Drainage Design Manual”, Federal Democratic Republic of Ethiopia.
HEC 14 (1983) - Federal Highway Administration, ”Hydraulic Design of Energy Dissipators for Culverts and
Channels”, US Department of Transportation.
Road and Traffic Authority- RTA NSW (1993), “Road Design Guide”, Australia