Material Costing
Material Costing
2. Calculate Maximum stock level, Minimum stock level and Reorder level from the following data
Reordering quantity 1200 units; Reordering period 4 to 6 weeks
Maximum consumption 300 units per week; Minimum consumption 200 units per week; Normal consumption
250 units per week.
3. P ltd furnished the following regarding the details of its manufacturing operation during 2004-
Average monthly market demand 4600 units
Ordering cost Rs. 52 per order; Inventory carrying cost 20% per annum
Cost of materials Rs. 630 per unit; Normal usage 245 units per week
Minimum usage 70 units per week; Maximum usage 380 units per week
Lead time to supply: 4 6 weeks. Compute Maximum Level and Minimum Level of stock.
5. Annual consumption of a material of a company is 100000 units at Rs. 2..40 per unit. Each order costs Rs. 90 and
carrying cost is 15% of the annual average value. Company operates 250 days per year. The procurement time is 10
days and safety stock is 1000 units.
Calculate Maximum stock level
6.
7.
8.
9.
11. From the following info., find out the Economic order quantity and the number of orders placed in the year
12. The annual demand for an item is 3200 units. The unit cost is Rs. 6 and the inventory carrying cost is 25% pa.
if the cost of an order is Rs. 150, determine
i. EOQ, ii. Number of order per year, iii. Time between two consecutive orders.
13. The Ganges Pump Company uses about 75000 valves per year and the usage is fairly constant at 6250 per
month. The valves cost Rs. 1.50 per unit when bought in quantities and the carrying cost is estimated to be
20% of average inventory investment on the annual basis. The cost to place an order and process the
delivery is Rs. 18. It takes 45 days to receive delivery from the date of an order and a safety stock of 3250
valves is desires.
You are required to determine
i. The most economical order quantity and the frequency of orders,
ii. The order point (reorder level)
iii. The most economical order quantity if the valves cost Rs. 4.50 each instead of Rs. 1.50 each.
14. A factory buys and uses a component for production at Rs. 10 per unit. Annual requirement is 2000 units.
Carrying cost is 10% pa of inventory and ordering coat is Rs. 40 per order. The purchase manager proposes
that as the ordering cost is very high it is profitable to place a single order for the entire annual requirement.
He also says that if we order 2000 units at one time we can get 2% discount from the supplier. Evaluate the
proposal and make your recommendation.
15. A company buys 8000 units of an item for its annual requirements. Each unit costs Rs. 10. The ordering cost
per order is Rs. 30 and the carrying cost is 7.5% of the average inventory per year.
a. Determine the EOQ and the total inventory cost.
b. Should the company accept an offer of 2% discount in price on 4 bigger orders of quarterly
requirements of the material?
16.
order, while the carrying cost is 10% per year per unit of average inventory. For orders for less than 4000
units, there is no discount on the purchase price of Re. 1 per unit but a discount of 5% is available if order
18.
19.
21.
22.
for the year 2001
Cost of the Materials per unit --- Rs. 50
Weekly consumption --- 300 units
Ordering cost per order --- Rs. 650
Stock holding cost --- 2% pm (on cost)
Compute a. EOQ, b. Optimum number of orders per year and c. Time lag between two consecutive orders. [Sanjiv
14/2.30]
24. P ltd. Furnishes the following regarding the details of its manufacturing operation during 2004 -
Average monthly market demand --- 4600 units
Ordering cost --- Rs. 52 per order
26. A company manufactures a product from a raw material, which is purchased at Rs. 60 per kg. The company incurs
a handling cost of Rs. 360 plus freight of Rs. 390 per order. The incremental carrying cost of inventory of raw material
is Re. 0.50 per kg per month. In addition the cost of working capital finance on the investment in inventory of raw
material is Rs. 9 per kg per annum. The annual production is 100000 units and 2.5 units are obtained from one kg of
raw material.
Required
i. Calculate the EOQ of raw materials
ii. Advice, how frequently should orders for procurement be placed?
iii. If the company proposes to rationalise placement of orders on quarterly basis, what % of discount in
the price of raw materials should be negotiated? [Rathnam 12/444]
27. Modern Manufacturing Company Kolkata purchased a material of 20 tonnes from a mining company. The
following data is available for the lot of material purchased
a. Invoice price of material @ Rs. 2000 per tonne
b. Trade discount @ 20% on Invoice Price
c. Excise duty @ 10% on Invoice Price
d. Sales Tax/ GST @ 10%
e. Freight and insurance @ 2%
f. Other charges for delivery @ Rs. 100 per tonne
g. Cost of containers @ Rs. 20 per box of 1 quintal
h. Cost of loading and unloading @ 1 % of total cost
Compute the materials purchased cost and cost per tonne to Modern Manufacturing Company. [ Sanjiv 1]
21