Time and Programm Group CCL
Time and Programm Group CCL
Time & Program: its Regulation & Management under the MDB-FIDIC
(2010) & the PPA (2011) Conditions of Construction Contracts & the Applicable
Laws: with special emphasis to Delay & Disruption Claims Management
Name ID No
Assignment Page 1
Construction and contract Law
Acknowledgements
First all we would like to thank the almighty GOD for everything that he did for us and our next
deepest appreciation goes to our instructor Mr. Zewudu Tefera (Engineering Contracts Lawyer)
for his valuable and endless share of academic knowledge and advice to perform our project
study well.
Finally, we would like to thank all those who give data and information for us for successful
completion of this project thesis.
ABSTRACT
Construction projects play an important role in the economic development of every country.
These essential sectors in Ethiopia phases usually delay risks which consequently, have negative
impacts in terms of quality, budget, and scope of construction projects. Effective time and work
program management in Construction contract highly solves delay followed by disruption claim
which have its own the legal remedies as clearly described in conditions of contract.
The main objective of the study is to find out the role of stakeholder in time management, to
identify the effect of time on the project and consequence on failure on time in relation to both
national PPA (2011) and international FIDIC MDB (2010) condition of contracts.
Assignment Page 2
Construction and contract Law
Assignment Page 3
Construction and contract Law
Assignment Page 4
Construction and contract Law
9.1 Conclusion……………………………………………………...…………………………42
9.2 Recommendation…………………………………………………….……………………43
REFERENCES…………………………..………………………………………………………44
Assignment Page 5
Construction and contract Law
CHAPTER ONE
INTRODUCTION
Construction industry plays important role in providing the required infrastructure to improve
the quality of life. Sustainable development of construction industry is so crucial. Construction
projects require on-schedule completion; however, unexpected conditions or planning errors
may lead to failures, which can dent the successful realization of the objectives of time, cost,
scope and quality. The distinctive nature of construction projects in developing countries, such
as Ethiopia most of the time leads to delay; consequently, it negatively impacts the quality,
budget, and safety of construction projects. Construction projects undergo large deviations in
terms of schedule delays, project scope, cost overruns, and quality issues, thus resulting to
unsuccessful project accomplishment. Time overrun as delay and some of them describe that
the time overrun is an effect from the construction delay, no matter what it was described, time
overrun become the most general problem in construction industry [10].
Time overrun occur when the actual progress of a construction project is slower than the
planned schedule. Delay or time overrun will affect all parties involved in the project. It will
affect the profits which would be obtained if the project can be completed on the schedule. But
due to the time overrun, contractors had to spend more money on labor, plant and may lose the
opportunity to get the next project.
Hence, effective time management is very important and crucial to achieve successful
completion of construction projects. On large projects, the employer may appoint a consultant
to prepare a detailed program for the project including an outline for construction if a
contractor has not been appointed. Once the contractor is appointed, they will take
responsibility for programming the construction works, but the consultant may continue to
develop an overall quality check for the client.
Assignment Page 6
Construction and contract Law
The objective of this study is to identify and understand the value of time, consequence of failure
on time, in construction contract with respect to both National (PPA 2011) and International
(MDB-FIDIC 2010) standards.
The scope of the study is limited to identifying time related issues in construction project as
per both National (PPA 2011) and International (MDB-FIDIC 2010) standard conditions of
contract in Ethiopia’s construction industry.
The methodology of we used in this study are information gathering from web sites , journals,
different books and literature review on the concepts of time, program, its regulation &
management in the construction projects and also case study was conducted. After we have
collected all necessary document and information we have analyzed, compared and contrasted
Assignment Page 7
Construction and contract Law
CHAPTER ONE
LITERATURE REVIEW
2. Background
Work Program is an essential management tools, enabling forward planning to ensure project are
delivered on time, within budget and required quality. A program of work as a formal approved
document used to guide both project execution and project control. It is a road map of
construction document that shows the series of work items, their relationship, and the time
allocated for their execution. [2].
Assignment Page 8
Construction and contract Law
A program of works will often identify dates and durations allocated to tasks, a critical path (the
sequence of critical tasks upon which the overall duration of the program is dependent), Tasks
which can only be carried out after other tasks have been completed and tasks which can be
carried out simultaneously. For a program of works to be effective, it must be used as a tool to
help plan activities, monitor progress and identify where additional resources may be required.
As per FIDIC MDB (2010) Clause 8.3 regarding work program, the Contractor shall submit a
detailed time program to the Engineer within 28 days after receiving the notice. The Contractor
shall also submit a revised program whenever the previous program is inconsistent with
actual progress or with the Contractor’s obligations, and as per PPA (2011) Clause 41
Completing the work program given as part of the Bid, the Contractor shall within the time stated
in the SCC provide the Engineer with a program of implementation of the tasks, broken down by
activity and by month. An update of the program shall be a program showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing of the remaining
work, including any changes to the sequence of the activities.
Assignment Page 9
Construction and contract Law
Project Designer/managers use different methods of project scheduling with effective work
program in order to estimate the time required for projects before starting. The period of
working on a project can be divided into three parts, which are before, during, and after
completion of construction. The first part, before planning, includes planning and estimation of
the project duration, cost, materials, number of workers, and sequence of activities.
Project work program in scheduling is vital because once everything is planned, everyone,
including engineers, workers, contractors, and the owner of the project will get an idea about
when they have to start and finish constructing, how much the project costs, what materials,
machines, equipment are needed, how many workers and engineers are required, what type of
skills from the workers and engineers are sought, and so on (planning) [5].
So during the construction period, most of the issues and operations would be clear and
understandable prior to happening. Another advantage of project planning is that in case of
needing a type of material, equipment, or any machine, which might be unavailable in the
country, we can order them earlier, so it will be ready to use when needed for a particular
activity of the project [7].
Otherwise, it may delay the project for months or more. In the case of the unavailability of
any type of machine or materials during the construction process, everyone has to wait and
delay their job, including workers and engineers. So before starting any project, the project
manager, engineers, and supervisors have to make sure of the material deliveries on time.
The Work program is not usually included as a contract document and is therefore not
considered binding on the parties. In this case the Work program will be used as an indicative
tool for the parties, suppliers and consultants for administering the progress of the works.
Where the contract lists the program as a contract document, the program will be binding on
the parties. Any departure from it will constitute a breach of contract entitling the aggrieved
party to compensation if they can prove they have incurred additional costs or delay
Employers primarily concerned with completing stages of the works by precise dates may be
tempted to include the program in the list of contract documents. The advantage for the
Assignment Page 10
Construction and contract Law
employer is that it will afford him greater control over the manner and order in which the
contractor will carry out the works. It will allow him to specify the works that are a priority
and oblige the contractor to priorities the same matter. The advantage for the contractor is that
he will be aware of what is expected of him from the outset. The same applies to third parties,
such as suppliers and consultants, who are often ignorant or left in limbo as to the timing of
their own contributions to the works. Where this approach is adopted, the contract should
clearly set out which part or parts of the program are binding. It could be that only the
key milestone dates are binding. Conversely, it could be that all dates, the order of the
works and the methods employed by the contractor are obligatory.
Time is measurable period during which an action, process or condition exists or continues. Time
is all things (time is money, times are life, time is gold etc) we can relate with project
management. Time management in project management is about allocating resource to
completing tasks on time while staying within the approved budget.
Project time management refer to a component of aver all project management in which a
timeline is analyzed and developed for the completion of a project
Construction contract define time ‘‘the number of days or dates related to construction phases
that as stated in construction documents applies to achievement of substantial completion of the
work’
Time in construction contract can be classified as
Commencement time
Completion time
Sectional completion time
Extension time
Progress time
Commencement date: The date on which the contractor must begin work on the job site is
specified in the contract. (PPA 2011Sub-Clause 8.1 & FIDIC MDB 2010 clause 1.1.3.2)
Assignment Page 11
Construction and contract Law
A contractor must start work based on a commencement date. The date of a contract's
commencement is frequently the source of argument in the construction industry, and it is
advised that a commencement date be agreed upon as soon as feasible by all parties involved.
Completion Date: the time for completing the work calculated from commencement date. (PPA
2011clause 8.2 & FIDIC MDB 2010 clause 1.1.3.3)
Most contracts specify a deadline by which the contract's work must be completed. This is not
the day by which all contract duties must be fulfilled, but rather the date by which substantial
practical completion must be certified. That is the date by which the work will be finished and
the client will be able to take possession of the property.
Sectional Completion Time: If the intention of the parties is that the contract work should be
completed and handed over in phases, it is essential that the contract documents make proper
provision for this, each with its own time for completion and own related contractual issues
(such as insurance, retention, defect liabilities and so on). (FIDIC MDB 2010 clause 10.2) and
PPA 2011 provision for partial acceptance: Clause 86 Partial Acceptance
Assignment Page 12
Construction and contract Law
Liquidated Damages Clause is generally recognized and applied in the common law system.
This clause is applicable at law when the terms of the contract are breached. Liquidated
damages are not penalties, they are predetermined damages set at the time that a contract is
entered into, based on a calculation of the actual loss of the party’s is likely to incur. They are
generally set as a fixed percentage of from the total sum. It may be complicated where the works
are phased, where may be partial possession and so on. In the case of sectional completion, it is
important that separate completion dates and liquidated damages are set out in the contract for
each section [8].
Liquidated damages can be beneficial for the client, as they remove their obligation to prove
actual losses in the event of delay occurring. They can also be beneficial to the contractor as
they limit their liability to a known amount in the event of delay. PPA(2011) clause 27 describe
liquidated damage, if the Contractor fails to carry out any or all of the Works within the period
specified in the Contract, the Public Body may without prejudice to all its other remedies under
the Contract, deduct from the Contract Price, as liquidated damages
Assignment Page 13
Construction and contract Law
Assignment Page 14
Construction and contract Law
Hence, effective time management is very important and crucial to achieve successful
completion of construction projects. On large projects, the client may appoint a consultant to
prepare a detailed program for the project including an outline for construction if a contractor
has not been appointed. Once the contractor is appointed, they will take responsibility for
programming the construction works, but the consultant may continue to develop an overall
quality check for the client [11].
During the planning stage, all work activities should be properly understood, and planned in
detail to optimize the allocation of resources and reduce the potential for ‘unknowns’.
Estimates can then be made of how long each activity will take. This is critical to the setting of
milestones and deadlines, for allocation of resources, and for determining the pricing of
contracts and cash flow requirements.
There are various time management techniques and software packages used for project
planning and scheduling worldwide. Each of the techniques has different functions and process
in providing a list of dates on which certain items are to be completed. Two main technique
used in time management in construction project is conventional time management method &
software package time management method.
Conventional time management method: the most common method for effective project
time management technique. There are several techniques or methods commonly used for
managing time in construction projects are; [5].
Critical path method
Gantt bar Chart method
Milestone date programming techniques
program evaluation and review technique
Line of balance method
Precedence network diagram
Simulation method
Assignment Page 15
Construction and contract Law
Delays in construction come at a costly price and achieving timely delivery of projects is
beneficial to the project and construction team. Along with cost and quality, project schedule is
often regarded as a significant aspect of the construction management life cycle, as well as one
of the drivers for project success. Despite its importance, most construction projects both in
developed and developing nations face project delays, which results a severe problem [14]
Assignment Page 16
Construction and contract Law
However, there remains a cost in demobilizing and remobilizing the labor working on the activity
and this will be the disruption cost. Over this single activity the disruption is easy to identify,
however, where multiple activities are affected, the disruption costs become more difficult to
establish and measure. Where several events which affect the progress of the works are disrupted
the impact of any one event may not be discernible from the impact of another event. Disruption
is not a cause of action at law in its own right and the contractor must explain the legal basis of
entitlement. Most standard forms of contract do not address recovery for disruption but may give
entitlement to claim some of the events that could lead to it in the form of loss and expense or
damages. When it comes to explaining the cause of reimbursable disruption, contractors often
rely upon multiple and intermingled events to explain loss of productivity and entitlement. Once
those items that can be dealt with in isolation have been quantified, it may be acceptable to deal
with the remaining disruption globally. However, the bar for acceptance of a global claim is very
high and therefore carries significant risks.
Assignment Page 17
Construction and contract Law
CHAPTER THREE
Assignment Page 18
Construction and contract Law
Excusable & non-excusable Delay: a delay where the contractor is entitled for extension of
time or compensation or both, under the terms & conditions of contract is excusable delay. In
this case, contractor does not have any control on the activity getting delayed. The causes may
be; force measure clause, natural disaster, political/social unrest, terrorist attacks, delay from
client (approvals, decisions, etc.), etc all these delay are compensable delay.
However, a delay where the contractor is fully responsible for the activities getting delayed
and resulted in extending project duration (responsible for critical delays) are non excusable
delay. In this case, the contractor has to bear the risk of cost consequences including the
liability to pay damages for itself but possibly for the other parties as well. The causes may be
delayed mobilization, delayed Procurement, delayed submission of important documents
planning & scheduling, critical events that were not highlighted to client on right time, etc.
Assignment Page 19
Construction and contract Law
Concurrent Delays: a situation where more than one delay event occurs at the same time
affecting multiple activities simultaneously/independently affecting the completion is
a concurrent delay. However, not all those events enable the contractor to be entitled for
extension of time & cost claim. Importantly, it is the causes of delay rather the delay
themselves, that must overlap.
3.1.4 Consequences of Delaying Construction Projects
Delaying construction projects is a common problem in Ethiopia which results increase in the
project cost. Construction Projects are essential requirements and needed to be done to meet the
population demand and necessities. So when a project is delayed, a huge amount of money is
going to be spent and wasted, however, that amount could be invested for other projects or used
for buying new equipment. There are many Data showing that the delay in construction projects
causes
Time overrun and
Cost overrun.
Assignment Page 20
Construction and contract Law
A) Planned vs. As-built method: this approach is probably the oldest and most straightforward
one. It compares activities from Contractor’s planned Baseline Schedule with the actual
Completion Dates of the delayed activities on the “As-Built” Schedule. The activity or
activities need to be clearly falling on the Baseline Critical Path
B) Impacted As-planned method: In this approach delayed event(s) by the client are
incorporated in the planned Baseline Schedule and then the re-run is done to determine the
resultant impact of the delayed event(s) to particular Milestones and overall project. In this
method, the contractor inserts the owner caused delays only.
C) Collapsed as-built (known as “but for” method): The beginning point of this approach is to
develop “As Built” schedule that reflects the actual dates and actual sequence of schedule
activities. In this method, the owner caused delay event(s) shall be removed from the As-
Built schedule to show what the completion date for particular milestones and/or overall
project completion would have been if the owner delay events had not occurred i.e.
recalculate the schedule to determine new completion date in the absence of owner caused
delays
D) Windows/slide method: Windows analysis (also known as contemporary method) is based
on the analysis of the effect of delayed events on the entire length of the project by looking
at the events which have impact within the Schedule at the reporting time period when the
events occurred.
Assignment Page 21
Construction and contract Law
CHAPTER FOUR
4.1. Disruption
A distinction should be made between prolongation claims (involving costs and losses incurred
as a result of delays to the activity in question or the works as a whole which have led to critical
delay to the contract completion date) and disruption claims (which involve those additional
costs and losses incurred during extended or disrupted periods of activities usually without any
effect on the completion date for the works [18].
Disruption can be caused by a variety of events, some of which are excusable, some are neutral,
and some are non-excusable. Common examples include, but are in no way limited to; change
orders, variations, instructions, late information, late approvals, adverse inclement weather, out
of sequence working, excessive overtime working, interface works with others, piecemeal
access, stacking of trades, abortive works, acceleration, mitigation, new and additional imposed
obligations, etc. These factors can occur, operate and compete at the same time, making it
practically impossible to separate out each of them to determine how much disruption was
caused by each factor. This makes it difficult to establish definitive causal linkages and may lead
to claims being more global in nature, i.e. all of these factors listed above affected the actual
performance of the labor, reducing their productivity, extending and prolonging the work
activities and, where critical, caused delay to the date for completion of the project. Therefore, it
is common that loss of productivity cases cannot be proven purely by reference to records,
schedules and other documentation, which will likely increase the reliance on witnesses of fact
and the opinion of expert witnesses [1].
Assignment Page 22
Construction and contract Law
Contractor’s disruption claim arises when an owner changes the method and/or
sequence of construction from that upon which the contractor based its bid. When the
planned method of completing the project is disrupted, contractors incur increased labor costs
because it takes them more time to complete the task than originally contemplated. When this
occurs, contractors either allege a breach of an express contract provision that requires
cooperation between the owner and the contractor, or a breach of the implied duties of the owner
to cooperate with the contractor or to refrain from hindering the contractor.
To counter a contractor’s disruption claim, owners often argue that they had the right in the
contract to change the schedule and, therefore, the sequence of construction because of the terms
of the contract. Owners often urge that these express terms trump the implied duty to cooperate,
thereby undermine the legal basis for a contractor’s disruption claim.
Disruption damages are the result of the timing or sequence of the flow of work (e.g., lost
productivity) and not necessarily an extension beyond the originally anticipated project
completion. Loss of productivity claims are difficult, but vitally important, and almost always
require expert testimony. Productivity is a measurement of rate of output per unit of time or
effort, usually measured in labor hours or equipment hours. A loss of productivity, also
sometimes known as “disruption” or “loss of efficiency,” can have significant negative effects on
a contractor’s bottom line. There can be many causes of disruption on a project such as differing
site conditions, design deficiencies, or lack of access to the work. Quantifying that loss of
productivity is the difficult part. Knowledgeable construction counsel and knowledgeable experts
can guide you through this difficult process.
Importance of records
Whatever method is used to measure disruption, the most important requirement is to have
contemporaneous records that support the disruption calculations to the required level of proof.
The better the records, the greater chance of a successful outcome, Unlike prolongation,
disruption claims are quite often considered as an afterthought at the end of the project, using the
existing day to day records in the best manner possible. Unfortunately, at this stage the
opportunity to put systems in place to measure disruption and collect sufficient contemporaneous
Assignment Page 23
Construction and contract Law
records may have been lost. As mentioned, some types of project (linear/repetitive work) are
more suited to identifying and measuring disruption. With these projects, especially those of
larger value, it may well be cost effective for contractors to employ resources (project
planning/quantity surveyors) solely for the purposes of putting systems in place to ensure
appropriate contemporaneous records are kept to support the disruption claim. [15, 17].
Once it has been established that an event (or events) occurred that caused disruption, then the
next step will be to value the disruption. Disruption can be caused by a variety of events such as
late information/approvals, delayed access, variations, inclement weather, suspension of the
works etc. The starting point, as ever, will be to review the Conditions of Contract to determine
the remedy, if any, for the particular Disruptive event.
Typically, disruption will be assessed as loss and/or expense (damages) or valued as a variation,
where the valuation of variation rules will apply. Where a measured mile approach has been used
to measure the disruption caused by a variation, the valuation approach adopted will likely be a
re-rate with the planned allowances or measured mile production levels replaced by actual
production levels demonstrated by records. This will require the affected contract rate(s) to be
broken down into its constituent components (labor, plant, materials and overheads and profit
etc.). Care must be taken to ensure that only the affected elements of the rate are adjusted. For
instance, original plant mobilization and demobilization allowances should not be factored into
the calculation.
Where disruption is to be valued on a loss and/expense basis it will be necessary for the
contractor to provide documentation to prove the costs it has incurred. In such circumstances the
contractor will, where possible, be responsible for mitigating the ongoing losses caused by the
disruption, for example by relocating idling resources to other areas of the project unaffected by
the disruptive events. In circumstances where a contractor lacks sufficient records/documents to
link the costs being claimed to specific events then a disruption claim is sometimes advanced on
a ‘total cost’ basis. In Walter Lilly v Mackay & DMW Developments it was stated that there was
nothing in principle wrong with a ‘total’ or ‘global’ cost claim.
Assignment Page 24
Construction and contract Law
However, there are added evidential difficulties in most cases. In order for a total cost claim to
succeed a contractor must generally demonstrate:
Final thoughts
Disruption claims require thought, detailed investigation and most of all records in order support
the disruption analysis/calculations. Unfortunately, far too often disruption claims are considered
as an afterthought at the end of a project when the losses have been incurred and the opportunity
to collate adequate records and prove the claim to the required standard has gone. Taking the
time to put systems in place at project commencement and proactively collecting
contemporaneous records throughout the duration of the project will greatly improve the chances
of a successful outcome [15, 17]
Assignment Page 25
Construction and contract Law
CHAPTER FIVE
The construction industry often associates or conflates delay and disruption. While they are both
effects of events, the impacts on the works are different, the events may be governed by separate
provisions of the contract and governing law, they may require different types of substantiation
and they will lead to different remedies. Having said that, the monetary consequences of delay
and disruption may overlap and, further, delay can lead to disruption and, vice versa, disruption
can lead to delay.
Assignment Page 26
Construction and contract Law
by which the project must be completed. If the contractor fails to complete the work in the
completion date stated in the contract, the employer would have a claim against the contractor
for damages for breach of contract. As stated in FIDIC MDB (2010) clause 8.7: If the
Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall
subject to notice under Sub-Clause 2.5 [Employer’s Claims] pay delay damages to the
Employer for this default. These delay damages shall be the sum stated in the Contract Data,
which shall be paid for every day which shall elapse between the relevant Time for
Completion and the date stated in the Taking-Over Certificate. However, the total
amount due under this Sub- Clause shall not exceed the maximum amount of delay damages (if
any) stated in the Contract Data. These delay damages shall be the only damages due from the
Contractor for such default, other than in the event of termination under Sub-Clause 15.2
[Termination by Employer] prior to completion of the Works. These damages shall not
relieve the Contractor from his obligation to complete the Works, or from any other duties,
obligations or responsibilities which he may have under the Contract. And also PPA(2011)
clause 27 as liquidated damages the following:
1) A penalty of 0.1% or 1/1000 of the value of undelivered Service for each day of delay until
actual delivery or performance,
2) The cumulative penalty to be paid by the Contractor shall not exceed 10% of the contract
price. If the delay in performing the contract affects its activities, the public Body may
terminate the contract by giving advance notice to the Contractor pursuant to GCC Clause 21
without any obligation to wait until the penalty reaches 10% of the value of the Contract.
3) If the Intended Completion d a t e i s extended after liquidated damages have been paid,
the Engineer shall correct any overpayment of liquidated damages by the Contractor by
adjusting the next payment certificate.
Generally, where there has been delay to a construction project, an employer will generally have
a claim against the contractor for liquidated damages.
Claims concerning the quality of the works: In almost every construction contract, the
contractor’s primary obligation is to deliver the project in accordance with the employer’s
specifications by a specified date. The contractor should complete the work as per specification
and correct the work if it have defect, in the defect liability period.
Assignment Page 27
Construction and contract Law
If a contract does not provide for a defects liability period, or if defects remain un remedied or
other works remain incomplete within a reasonable time of them being identified during the
defects liability period or, in the worst case, at the end of the defects liability period, or if the
employer subsequently identifies further defects, the employer will have a claim against the
contractor for breach of contract. The measure of damages recoverable by the employer will be
the costs of rectifying the defects. as per FIDIC MDB(2010) clause11.1 in order that the Works
and Contractor’s Documents, and each Section, shall be in the condition required by the Contract
(fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as
soon as practicable thereafter, the Contractor shall:
(a) complete any work which is outstanding on the date stated in a Taking-Over Certificate,
within such reasonable time as is instructed by the Engineer, and
(b) Execute all work required to remedy defects or damage, as may be notified by (or on behalf
of) the Employer on or before the expiry date of the Defects Notification Period for the Works or
Section (as the case may be). If a defect appears or damage occurs, the Contractor shall be
notified accordingly, by (or on behalf of) the Employer.
But FIDIC MDB (2010) clause11.4 states that, If the Contractor fails to remedy any defect or
damage within a reasonable time, a date may be fixed by (or on behalf of) the Employer, on or
by which the defect or damage is to be remedied. The Contractor shall be given reasonable notice
of this date. If the Contractor fails to remedy the defect or damage by this notified date and this
remedial work was to be executed at the cost of the Contractor under Sub-Clause 11.2 [Cost of
Remedying Defects], the Employer may (at his option): (a) carry out the work himself or by
others, in a reasonable manner and at the Contractor’s cost, but the Contractor shall have no
responsibility for this work; and the Contractor shall subject to Sub-Clause 2.5 [Employer’s
Claims] pay to the Employer the costs reasonably incurred by the Employer in remedying the
defect or damage; (b) require the Engineer to agree or determine a reasonable reduction in the
Contract Price in accordance with Sub-Clause 3.5 [Determinations]; or (c) if the defect or
damage deprives the Employer of substantially the whole benefit of the Works or any major part
of the Works, terminate the Contract as a whole, or in respect of such major part which cannot be
put to the intended use. Without prejudice to any other rights, under the Contract or otherwise,
the Employer shall then be entitled to recover all sums paid for the Works or for such part (as the
case may be), plus financing costs and the cost of dismantling the same, clearing the Site and
returning Plant and Materials to the Contractor.
Assignment Page 28
Construction and contract Law
b) Artificial obstructions or physical conditions which could not reasonably have been foreseen
by an experienced Contractor;
Assignment Page 29
Construction and contract Law
c) Compensation Event occurs or a change order for modification is issued which makes it
impossible for completion to be achieved by the Intended Completion Date;
d) Administrative orders affecting the date of completion other than those arising from the
Contractor's default;
e) Failure of the Public Body to fulfill his obligations under the Contract;
f) Any suspension of the works which is not due to the Contractor's default
g) Force majeure;
Claim related to Loss and expense: Claims for loss and expense happen when contractors
suffered loss because of an employer breach of contract and if contractor have additional money
under the contract. To successfully claim for loss and expense for breach of contract, a contractor
needs to prove that there was an obligation of employer, things have been breached by the
employer or its representatives, there must be tangible monetary loss [9].
The most common claim for loss and expense are
Prolongation cost
Disruption
Acceleration
When a project is delayed because of an event for which the employer is responsible, the
contractor is entitled to an extension of time, as well as any losses arising from the delay. These
losses are referred to as prolongation costs.
Prolongation costs can include site and office overheads, financing charges arising from money
borrowed to fund the project and loss of profit. To successfully claim for prolongation costs,
contractors need to provide detailed particulars and evidence that each of the claimed costs were
caused by employer delay.
Acceleration claims arise when the employer instructs the contractor to complete the works
within a shorter period than originally required under the contract or because of one or more
events for which the employer is responsible.
Claims for disruption occur from the assumption that contractors arrange the activities required
to complete a project in an efficient sequence. On that assumption, any event that affects the
sequence of the works can lead to inefficient use of plants and manpower, which in turn would
increase the costs of completing the project. When the employer is responsible for such events, a
contractor is entitled to recover those costs.
Assignment Page 30
Construction and contract Law
Claim related to Force majeure: for events beyond parties’ control may arise during a project,
affecting the contractor’s ability to perform his or her contractual duties. Event which are
considered as force majeure are war, terrorism, civil unrest and severe adverse weather
conditions etc.
A force majeure claims act that:
is beyond the reasonable control of the contractor
was not reasonably foreseeable at the time of entering the contract;
could not have been avoided;
is not attributable to the employer; and
prevents the contractor from performing its obligations under the contract
PPA (2011) clause 18 Define, “Force Majeure” shall mean an event or events which
are beyond the reasonable control of a Contractor, and which makes a Contractor’s
performance of its obligations hereunder impossible or so impractical as reasonably to be
considered impossible in the circumstances. And FIDIC MDB (2010) describes Force
Majeure on clause 19.1
5.2 Disruption claim management
Delay and disruption issues that ought to be managed within the contract all too often become
disputes that have to be decided by third parties (adjudicators, dispute review boards, arbitrators,
judges). The number of such cases could be substantially reduced by the introduction of a
transparent and unified approach to the understanding of programmed works, their expression in
records, and the allocation of responsibility for the consequences of delay and disruption event[7]
Delay and disruption are inherently interrelated. A loss of productivity (i.e. disruption) can lead
to delay and, if the impacted activities are on the critical path, that can be critical delay, Hence,
the Contractor may rely upon a disruption analysis to support a critical delay claim in addition to
its delay analysis. It is possible for work to be disrupted and yet for the works still to be
completed by the contract completion date. In this situation, the Contractor will not have a claim
for an EOT, but it may have a claim for the cost of the lost productivity.[7]
As regards a claim for disruption under the contract, most standard forms do not expressly
address recovery for disruption; although they do address some of the specific events that could
lead to disruption, such as unforeseen ground conditions and untimely approvals or instructions
from the CA. Disruption is SCL Delay and Disruption Protocol 2nd Edition: February 2017 44
Assignment Page 31
Construction and contract Law
also not a cause of action at law in its own right. The Contractor must therefore explain in its
claim document the legal basis of its entitlement.
As regards a claim for disruption under the contract, most standard forms do not expressly
address recovery for disruption, although they do address some of the specific events that could
lead to disruption, such as unforeseen ground conditions and untimely approvals or instructions
from the CA. Disruption is SCL Delay and Disruption Protocol 2nd Edition: February 2017 44
also not a cause of action at law in its own right. The Contractor must therefore explain in its
claim document the legal basis of its entitlement.
Compensation may be recovered for disruption only to the extent that the contract
permits or there is an available cause of action at law. The objective of a disruption
analysis is to demonstrate the loss of productivity and hence additional loss and
expense over and above that which would have been incurred were it not for the
disruption events for which the Employee is responsible.
Assignment Page 32
Construction and contract Law
CHAPTER SIX
ROLE OF ENGINEER
The Engineer can be natural or/and juridical person or organization (consultant) who can make
relationship (contract) to provide consultancy or intellectual service to the client.
According to civil code of Ethiopia, proclamation number 165 of 1960, Book V, Hiring of
intellectual work, from Article 2632 to 2638 consider an engineer as “intellectual” entity who has
contract or legal relation with employer.
In regards to PPA 2011, Section 7, General Condition of contract, Definition 1.2, “n” state,”
‘Engineer’ means a person named in the Special Conditions of Contract or appointed as such by
the Public Body and notified in writing to the Contractor to act as the representative of the Public
Body to supervise and inspect works and to test and examine the materials employed and the
quality of workmanship, including any authorized representative of such person;”
likewise, MDB FIDIC 2010, General condition of contract, General provision, definition 1.1.2.4
define Engineer as “’Engineer’ means the person appointed by the Employer to act as the
Engineer for the purposes of the Contract and named in the Contract Data, or other person
appointed from time to time by the Employer and notified to the Contractor under Sub-Clause
3.4 [Replacement of the Engineer].” .
Moreover, From FIDIC white book (client/consultant), fourth edition 2006, general condition of
contract, definition 1.1.8, define engineer in terms of consultant, “consultant means the
provisional firm or individual named in the agreement who is employed by the client to perform
the service and legal successors to the consultant and permitted assignees.”
The objectives of the construction project are to complete the project in the required Time,
quality and cost. To meet these objectives the role of engineer discussed in the MDB FIDIC 2010
and PPA 2011 perspective. In the project life cycle, the engineer participate starting from pre-
construction stage( the feasibility study including inception report, the engineering design and
specification, preparing work program, main role in the procurement process up to contractual
relationship), construction stage(supervision all activities, controlling and monitoring the works,
Assignment Page 33
Construction and contract Law
etc.), final in the post constriction stage (Preparing & addressing the schedule of defects / punch
list, Preparation of project close-out report including learning, Collate and verify all As-built
drawings, Addressing any queries during defects liability period and Co-ordination with the
Contractors to rectify the defects during the defects liability period.). Due to these facts he has
good understanding of the project from starting to closing, therefore, he has a key role to the
project. His role can be observed as administrator(agent and professional assistance to the client)
of the project, these nature of his role will be discuss in relation to MDB FIDIC 2010 and PPA
2011.
Professional Role
The engineer is the professional who use his knowledge and skill to design and administer the
project. According to Civil code, chapter four, Art. 2632, (2) cum art 2616, (1) and (2), the
engineer or the consultant independent to exercise his knowledge and skill to realize the work
based on his professional rules.
The engineer is the designer of the project (MDB FIDIC 2010 clause 17.3,g, PPA2011,clause
52.5), serve as the adviser of the client and the contractor for different issues regarding to the
project MDB FIDIC 2010 clause 3.5, 4.9 and PPA clause 15.4, 15.7, 18.8, 20.4, 69.2 and 73.3.
The engineer has the right for the modification of the work according to PPA clause 15.1. and he
provide approval for drawings, design calculation and other that are requested by the contractor
PPA,2011,clause 42.1, 42.3 designs, drawings, and related – Clause 3 MDB FIDIC 2010,
As Agent Role
Both MDB FIDIC 2010 and PPA 2011 are designed by the employer they have stated engineer
throughout the book. In MDB FIDIC 2010, clause 3.1, Engineer’s Duties and Authority stated as
“The Employer shall appoint the Engineer who shall carry out the duties assigned tohim in the
Contract. The Engineer’s staff shall include suitably qualified engineers and other professionals
who are competent to carry out these duties.(Power of agency-Agent Role derived from Art.
2179 of Civil Code)PPA 2011 state, “
Clause, 1.2 MDB FIDIC The Public Body appoints the Contractor to carry out the Works:
Assignment Page 34
Construction and contract Law
(a) Promptly (and in any event within any time targets as may be set out in the Section 6,
Schedule of Requirements) and in a professional and courteous manner so as to
reflect and promote the image of the Public Body;
(b) Strictly in accordance with the Schedule of Requirements and all provisions of the
Contract; and
(c) In accordance with all applicable laws and regulations of the Federal Democratic
Republic of Ethiopia and Good Industry Practice; and
(d) In accordance with the policies, rules, and procedures of the appropriate Authority as
amended from time to time.
(e) In accordance with the quality standards set by the Ministry of Urban Development
and Construction, Quality and Standards Authority of Ethiopia (QSAE), and
applicable international standards;”
(a) In accordance with the terms and conditions of appointment as provided in this
Clauses in consideration of the Contract Price. Power: - Variation – Clause 13.1
MDB FIDIC 2010, Clause 8.8 MDB FIDIC 2010,
Clause 3.1-3.5 MDB FIDIC 2010, – Clause 3.1-3.5 MDB FIDIC 2010, Clause 3.1-3.5 MDB
FIDIC 2010, Clause 3.1-3.5 MDB FIDIC 2010, Clause 3.1-3.5 MDB FIDIC 2010
(Supervision ,Function, Advising Quantity Surveying ,Clause 3.1-3.5 MDB FIDIC 2010,
Testing, Inspection, respectively)
The Engineer has a very significant project management role under the MDB FIDIC 2010 and
PPA 2011 forms. Examples of the Engineer’s role (and tools for project management) include,
Notifying the Contractor of the Commencement Date not less than 14 days before that date,
Reviewing programs, Measuring the Works; Issuing payment certificates, Issuing instructions
(including for variations), Ensuring that the personnel of the contractor act professionally and
safely and removing them the site if they do not, Inspection and testing of the works, Issuing
notices to correct failures, Issuing Taking-Over Certificate(s), Issuing the Performance
Certificate, Assessing and making a neutral determination.
Assignment Page 35
Construction and contract Law
From MDB FIDIC 1.1.3.3 “’Time for Completion’ means the time for completing the Works or
a Section (as the case may be) under Sub-Clause 8.2 [Time for Completion], as stated in the
Contract Data (with any extension under Sub-Clause 8.4 [Extension of Time for Completion]),
calculated from the Commencement Date.”
PPA 2011 state "’Intended Completion Date’ is the date on which it is intended that the
Contractor shall complete the Works. The Intended Completion Date is specified in the Special
Conditions of Contract. The Intended Completion Date may be revised only by the Engineer by
issuing an extension of time or an acceleration order;”
Time management is important in any construction project. Without proper time management,
many problems will occur such as extension of time or time overrun. time overrun describe as
delay and an effect from the construction delay, time overrun become the most general problem
in construction industry. Time overrun occur when the actual progress of a construction project is
slower than the planned schedule. Delay or time overrun will affect all parties involved in the
project. It will affect the profits which would be obtained if the project can be completed on the
schedule. But due to the time overrun, contractors had to spend more money on labor, plant and
may lose the opportunity to get the next project. Hence, effective time management is very
important and crucial to achieve successful completion of construction projects.
In the pursuit of efficient project performance, time control is one of the most important
functions. Hence, there are numerous time management techniques and software packages used
for project planning and scheduling. Hence, time in construction projects need to be controlled
from the beginning of the construction process until the project is totally completed. Currently,
Gantt Bar and Critical Path Networks/Method Critical path method are the most commonly used
method of scheduling and controlling in construction industry, these tools use for planning and
scheduling projects. , allow assessment on how long a project should take. And determine the
resources needed. Moreover, the above issues are supported by the MDB FIDIC 2010, PPA
2011, etc. MDB FIDIC 2010, Clause 1.9,2. 19.4 a, 20.1 and appendix, 2 an PPA 2011, clause,
5.4 -6.5a, 28.d, 28.4 etc.
Assignment Page 36
Construction and contract Law
Many events may increase the time of performance of the overall project or affect
any given activity. Common examples include contractor/subcontractor management and
performance problems, differing site conditions, changes in requirements or design,
A party defending against a delay claim is not without recourse. And that recourse is usually
found in the form of a contract provision. For example:
No Damages for Delay Clause: These are exculpatory clauses that preclude damages for delay.
Generally, a contract may provide that the contractor’s sole remedy is only a time extension.
These provisions are generally enforceable except in cases of fraud or owner interference or if a
statute prevents it from being enforced.
Assignment Page 37
Construction and contract Law
(SCL) SCL2017, UK, clause 1, Contracting parties should reach a clear agreement on the type of
records to be kept and allocate the necessary resources to meet that agreement. Further, to assist
in managing progress of the works and to reduce the number of disputes relating to delay and
disruption, the Contractor should prepare and the Contract Administrator (CA) should accept a
properly prepared program showing the manner and sequence in which the Contractor plans to
carry out the works. The program should be updated to record actual progress, variations,
changes of logic, methods and sequences, mitigation or acceleration measures and any EOTs
granted. If this is done, then the program can be more easily used as a tool for managing change
and determining EOTs and periods of time for which compensation may be due.
Clause 8.3 requires the Engineer to “Review” the initial as-planned program as well as
subsequent iterations.24 They must do this against a detailed list of requirements, with
emphasis put on early detail to allow a highly effective project and risk management tool to be
created.25 The Engineer must provide notice of any comments on programs submitted by the
Contractor within 21 days after receiving the initial program, or 14 days after receiving a revised
program. If he does not do so, he is deemed to have given a Notice of No-Objection to the
program in question. Again, the Engineer has to be organized and ensure that he responds in the
correct time periods or an important opportunity to put the project on the right footing from the
beginning will be lost.
Assignment Page 38
Construction and contract Law
A contractor’s disruption claim arises when an owner changes the method and/or
sequence of construction from that upon which the contractor based its bid. When the
planned method of completing the project is disrupted, contractors incur increased labor
costs because it takes them more time to complete the task than originally contemplated.
When this occurs, contractors either allege a breach of an express contract provision that
requires cooperation between the owner and the contractor, or a breach of the implied duties of
the owner to cooperate with the contractor or to refrain from hindering the
contractor.
To counter a contractor’s disruption claim, owners often argue that they had the
right in the contract to change the schedule and, therefore, the sequence of construction
because of the terms of the contract. Owners often urge that these express terms trump
the implied duty to cooperate, thereby undermine the legal basis for a contractor’s
disruption claim.
Disruption damages are the result of the timing or sequence of the flow of work
(e.g., lost productivity) and not necessarily an extension beyond the originally anticipated
project completion. Loss of productivity claims are difficult, but vitally important, and
almost always require expert testimony. Productivity is a measurement of rate of output
per unit of time or effort, usually measured in labor hours or equipment hours. A loss of
productivity, also sometimes known as “disruption” or “loss of efficiency,” can have
significant negative effects on a contractor’s bottom line. There can be many causes of
disruption on a project such as differing site conditions, design deficiencies, or lack of
access to the work. Quantifying that loss of productivity is the difficult part.
Knowledgeable construction counsel and knowledgeable experts can guide you through
this difficult process.PPA clause 4.2.
Assignment Page 39
Construction and contract Law
UK(SCL), clause 18, Compensation may be recovered for disruption only to the extent that the
contract permits or there is an available cause of action at law. The objective of a disruption
analysis is to demonstrate the loss of productivity and hence additional loss and expense over and
above that which would have been incurred were it not for the disruption events for which the
Employer is responsible.
Over the years, the construction industry has developed various methods of
contractually allocating the risk of project delay and disruption. Some of these methods
include liquidated damages provisions, “no damages for delay” clauses, mutual waivers
of consequential damages, limitation of liability provisions; claims notice provisions, and
provisions addressing responsibility for the adequacy of the construction plans and
specifications. Parties frequently litigate the sufficiency and enforceability of these risk shifting
efforts in conjunction with the underlying merits of delay and disruption
disputes. Understanding these claims and the contractual provisions that relate to these
claims is critical. All parties should attempt to enter into contracts that clearly and
adequately address the risks imposed by project delays and disruptions.
Assignment Page 40
Construction and contract Law
CHAPTER SEVEN
CASE STUDY
7.1 Background
Water supply project is one of the parts of construction project which is mostly susceptible to
delay because of sensitivity its nature. Water supply project may delayed for a single fitting if
it has not supplied and also, If the layout of the pipe line was not properly executed during
design phase the whole project can be delayed for a single pipe junction.
We have selected Kella Titto Water supply project which found in Oromia Regional state Arsi
zone to examine the project time overrun. The project is signed between Oromia Water and
Energy Bureau and Waika Engineering WWC in January 10/2020 to execute the project in 36
months. The contact type is DB form of contract.
Kella Titto water supply project activities and the total cost quoted by the contractor was
summarized in table below.
Delaying construction projects is a common problem in Ethiopia which results increase in the
project cost. Construction Projects are essential requirements and needed to be done to meet the
population demand and necessities. So when a project is delayed, a huge amount of money is
going to be spent and wasted, however, that amount could be invested for other projects or used
for buying new equipment. Usually, delay in construction projects causes Time overrun and Cost
overrun and if not managed profit loss and employer loss value for money can be occurred.
Specifically, the project we have taken to see the case( Kella Titto water supply project) have
been delayed since the project planned to completed on June 10/2021 still to today(January
Assignment Page 42
Construction and contract Law
20/2023) the project was not completed. The project physical (civil work) progress was on only
around 82%
Depend on the information we have received from the employer representative (engineer) and
the contractor we have identified main cause of Kella Titto water supply delay was:
Most of the time, Electro mechanical equipments such as pumps and Generators were purchased
from abroad. In case of Kella Titto water supply project EM equipment was planned from
abroad. Due to the shortage of foreign currency (LC) this equipment was not purchased on time
the project was delayed for certain period of time as we have got information from the
stakeholder of the project.
Kella Titto water supply was delayed due to Infective Planning and scheduling of the contractor.
Since, Infective Planning and scheduling have significant impact on the delay of the project. The
contractor have not actively planned and scheduled the project as day to day performances of the
contractor were very weak. Weak performance of the project activities by the contractor leads
the project to delay due to infective scheduling activities.
Another cause for the delay of Kella Titto water supply is due to fluctuation of market after the
contract was made. The construction material during the contract formed and this time was
highly differentiated. Since most of the material which water supply serve were industrial
material such as pipe and fitting which share up to 50% of the project cost were escalated on the
market.
Riser pipe, pump and generator some pipes and fitting are purchased in a foreign country these
makes contractor difficulty due to foreign currency gap. And the employer was not also release
payment for contractor on time for executed work.
Assignment Page 43
Construction and contract Law
Even though, the project have consultant on site for contract administration and over all site
supervision which the employer delegate was not actively engaged his responsibility.
Additionally, the decision made by the employer was somewhat weak.
We have can conclude that, the project delay happens due to different reasons which both the
employer and contractor shares. The project we have observed were delay due to: material
import delay, ineffective planning & scheduling of project, slow decision making, inefficient site
management & supervision, financial difficulties of contractor and poor contract management
of owners are guide the project to time overrun and cost overrun.
Effective planning and scheduling is very crucial every project to overcome time overrun.
So for this specific project the contacting parties should enforce and re plan for the
activities which was not still completed.
Timely decision making by the employer (consultant and the decision maker) for
Procurement of water supply goods, effect all progress payment as requested, effective
communication with delegated engineers etc and Review meeting with stakeholder and
deciding how to these projected completed is what we have recommend for these
specific project.
Effective contract management system with experienced & qualified personnel both at
site and office are also the most important and very critical to complete this specific
project.
Assignment Page 44
Construction and contract Law
CHAPTER EIGHT
Programs
MDB- The Contractor shall submit a PPA Completing the work program given
FIDIC detailed time programme to the (2011) as part of the Bid, the Contractor
(2010) Engineer within 28 days after receiving shall within the time stated in the
the notice under Sub-Clause 8.1 Claus SCC provide the Engineer with a
Clause [Commencement of Works]. The e 41 program of implementation of the
8.3 Contractor shall also submit a tasks, broken down by activity and
revised programme whenever the by month and include the following
previous programme is inconsistent information:
with actual progress or with the (a) The order in which the
Contractor’s obligations. Each contractor proposes to carry out
programme shall include: the works;
(a) the order in which the Contractor (b) The time limits within which
intends to carry out the Works, submission and approved of the
including the anticipated timing of each drawings are required
stage of design (if any), Contractor’s (c) the order in which the
Documents, procurement, manufacture Contractor proposes to carry out the
of Plant, delivery to Site, construction, works;
erection and testing, (d)the time limits within which
(b) each of these stages for work by submission and approval of the
each nominated Subcontractor (as drawings are required;
defined in Clause 5 [Nominated (e) an organization chart containing
Subcontractors], the names, qualifications and
(c) the sequence and timing of curricula vitae of the staff responsible
inspections and tests specified in the for the Site,
Contract, and
(f)a general description of the method
(d) a supporting report which includes:
including the sequence, by month and
(i) a general description of the
by nature which the Contractor
Assignment Page 45
Construction and contract Law
methods which the Contractor intends proposes to carry out the works;
to adopt, and of the major stages, in the
(g) a plan for the setting out and
execution of the Works, and
organization of the Site, and
(ii) Details showing the Contractor’s
(h) Such further details and
reasonable estimate ofthe number of
information as the Engineer may
each class of Contractor’s Personnel
reasonably require. The Engineer
and of each type of Contractor’s
shall return these documents to the
Equipment, required on the Site for each
Contractor with his approval or any
major stage. Unless the Engineer, within
relevant remarks within ten days of
21 days after receiving a programme,
receipt, except where the Engineer,
gives notice to the Contractor stating the
within those ten days, notifies the
extent to which it does not comply with
Contractor of his wish for a meeting.
the Contract, the Contractor shall
proceed in accordance with the An update of the program shall be a
programme, subject to his other program showing the actual progress
obligations under the Contract. The achieved on each activity and the
Employer’s Personnel shall be entitled effect of the progress achieved on
to rely upon the program when the timing of the remaining work,
planning their activities. including any changes to the
The Contractor shall promptly give sequence of the activities.
notice to the Engineer of specific The Contractor shall submit to the
probable future events or Engineer for approval an updated
circumstances which may adversely program at intervals no longer than
affect the work increase the Contract the period stated in the SCC. If the
Price or delay the execution of the Contractor does not submit an
Works. The Engineer may require the updated Program within this period,
Contractor to submit an estimate of the the Engineer may withhold the
anticipated effect of the future event or amount stated in the SCC from the
circumstances, and/or a proposal under next payment certificate and
Sub-Clause 13.3 [Variation Procedure]. continue to withhold this amount
If, at any time, the Engineer gives until the next payment after the date
Assignment Page 46
Construction and contract Law
Commencement of time
MDB- Except as otherwise specified in the Particular PPA a) The Public Body
FIDIC Conditions of (2011) shall fix the Start Date
(2010) Contract, the Commencement Date shall be the date at on which execution of
which the following precedent conditions have all Claus the Works is to
Clause been fulfilled and the Engineer’s notification e 71 commence in the SCC
8.1 recording the agreement of both Parties on such or by administrative
fulfillment and instructing to commence the Work is order issued by the
received by the Contractor: Engineer.
(a) signature of the Contract Agreement by both b) The Start Date for
Parties, and if required, approval of the Contract by commencing execution of
relevant authorities of the Country; the works shall be not
(b) delivery to the Contractor of reasonable evidence later than
of the Employer’s Financial arrangements (under Sub- 120 days following
Clause 2.4 [ Employer’s Financial Arrangements]); notification of award of
(c) except if otherwise specified in the Contract Data, Contract unless agreed
effective access to and possession of the Site given to otherwise by the parties.
the Contractor together with such permission(s)
Assignment Page 47
Construction and contract Law
Completion of time
MDB- The Contractor shall complete the PPA a. The period of execution of Works shall
FIDIC whole of the Works, and each (2011) commence on the Start Date fixed in
(2010) Section (if any), within the Time accordance with GCC Clause 71.1 and
for Completion for the Works or Claus shall be as laid down in the SCC, without
Clause Section (as the case may be), e prejudice to extensions of the period which
8.2 including: 72 may be granted under GCC Clause 73.
(a) achieving the passing of the b. The Contractor shall carry out the
Tests on Completion, an Works in accordance with the Program of
(b) Completing all work which is implementation of tasks submitted by the
stated in the Contract as being Contractor, as updated with the approval
required for the Works or Section to of the Engineer, and complete them by
Assignment Page 48
Construction and contract Law
Extension of time
MDB- The Contractor shall be entitled PPA The Contractor may request an extension
FIDIC subject to Sub-Clause 20.1 (2011) of the Intended Completion Date if he is
(2010) [Contractor’s Claims] to an or will be delayed in completing the
extension of the Time for Claus contract by any of the following causes:
Claus Completion if and to the extent that e 73 a) Exceptional weather conditions in
e 8.4 completion for the purposes of Sub- the Federal Democratic Republic of
Clause 10.1 [Taking-Over of the Ethiopia;
Works and Sections] is or will be, b) Artificial obstructions or physical
delayed by any of the following conditions which could not reasonably
causes: have been foreseen by an experienced
(a) a Variation (unless an adjustment Contractor;
to the Time for Completion has been c) Compensation Event occurs or a
agreed under Sub-Clause 13.3 change order for modification is issued
[Variation Procedure]) or other which makes it impossible for
substantial change in completion to be achieved by the Intended
the quantity of an item of work Completion Date;
included in the Contract, d) Administrative orders affecting the
(b) a cause of delay giving an date of completion other than those arising
Assignment Page 49
Construction and contract Law
Assignment Page 50
Construction and contract Law
Delayed Payment
DB- If the Contractor does not PPA 1) Once the time-limit referred to in GCC
FIDIC receive payment in accordance (2011) Clause 59.3 has expired, the
(2010) with Sub-Clause 14.7 [Payment], the Contractor – unless the Contractor
Contractor shall be entitled to Clause is a public body which is partly or
Claus receive financing charges 67 wholly financed by the Federal
e 14.8 compounded monthly on the amount Government Budget – shall upon
unpaid during the period of delay. demand, submitted within two months
This period shall be deemed to of receiving late payment, be entitled
commence on the date for payment to late-payment interest at the
specified in Sub-Clause 14.7 rediscount rate applied by the National
[Payment], irrespective (in the case bank of Ethiopia on the first day of the
of its sub-paragraph (b)) of the month in which the time-limit expired,
date on which any Interim Payment plus three and a half percentage
Certificate is issued. Unless points. The interest shall be payable
otherwise stated in the Particular for the time elapsed between the
Conditions, these financing charges expiry of the payment deadline and
shall be calculated at the annual rate the date on which the Public
of three percentage points above the Body’s account is debited. .
discount rate of the central bank in
the country of the currency of 2) Any default in payment of more than
payment, or if not available, the 120 days from the expiry of the period laid
interbank offered rate, and shall be down in GCC Clause 67.1 shall entitle the
paid in such currency. The Contractor Contractor either not to perform the
shall be entitled to this payment Contract or to terminate it.
without formal notice or certification,
Assignment Page 51
Construction and contract Law
Delay Damage
MDB- If the Contractor fails to comply with PPA Except as provided under GCC Clause
FIDIC Sub-Clause 8.2 [Time for (2011) 18, if the Contractor fails to carry out
(2010) Completion], the Contractor shall any or all of the Works within the
subject to notice under Sub-Clause 2.5 Clause period specified in the Contract, the
Claus [Employer’s Claims] pay delay 27 Public Body may without prejudice to
e 8.7 damages to the Employer for this all its other remedies under the
default. These delay damages shall be Contract, deduct from the Contract
the sum stated in the Contract Data, Price, as liquidated damages the
which shall be paid for following:
every day which shall elapse between 1) A penalty of 0.1% or 1/1000 of the
the relevant Time for value of undelivered Service for each
Completion and the date stated in day of delay until actual delivery or
the Taking-Over Certificate. However, performance,
the total amount due under this Sub- 2) The cumulative penalty to be paid
Clause shall not exceed the maximum by the Contractor shall not exceed 10%
amount of delay damages (if any) stated of the contract price. If the delay in
in the Contract Data. These delay performing the contract affects its
damages shall be the only damages due activities, the public Body may
from the Contractor for such default, terminate the contract by giving
other than in the event of termination advance notice to the Contractor
under Sub-Clause 15.2 [Termination by pursuant to GCC Clause 21 without any
Employer] prior to completion of the obligation to wait until the penalty
Works. These damages shall not reaches 10% of the value of the
relieve the Contractor from his Contract.
obligation to complete the Works, or 3) If the Intended Completion Date is
from any other duties, obligations or extended after liquidated damages
Assignment Page 52
Construction and contract Law
responsibilities which he may have have been paid, the Engineer shall
under the Contract. correct any overpayment of liquidated
damages by the Contractor by adjusting
the next payment certificate.
Contractor’s Claims
Assignment Page 54
Construction and contract Law
Assignment Page 55
Construction and contract Law
Assignment Page 56
Construction and contract Law
may be proposed by the Engineer and approved N.B this clause of PPA
by the Contractor, the Engineer shall respond with (2011) is not exactly
approval, or with disapproval and detailed specifies the contractor’s
comments. He may also request any necessary all claim rather on
further particulars, but shall nevertheless give his payment only.
response on the principles of the claim within the
above defined time period.
Within the above defined period of 42 days, the
Engineer shall proceed in accordance with Sub-
Clause 3.5 [ Determinations ] to agree or determine
(i) the extension (if any) of the Time for
Completion (before or after its expiry) in
accordance with Sub-Clause 8.4 [ Extension of
Time for Completion ], and/or
(ii) The additional payment (if any) to which the
Contractor is entitled under the Contract.
Each Payment Certificate shall include such
additional payment for any claim as has been
reasonably substantiated as due under the relevant
provision of the Contract.
Unless and until the particulars supplied are
sufficient to substantiate the whole of the claim,
the Contractor shall only be entitled to payment
for such part of the claim as he has been able to
substantiate.
If the Engineer does not respond within the
timeframe defined in this Clause, either Party may
consider that the claim is rejected by the Engineer
and any of the Parties may refer to the Dispute
Board in accordance with Sub- Clause 20.4
[Obtaining Dispute Board’s Decision].
Assignment Page 57
Construction and contract Law
Assignment Page 58
Construction and contract Law
CHAPTER NINE
9.1 Conclusion
The study indicates that, completing construction projects within estimated time frame is the
main challenge faced in our country. It is very common to observe that, construction contract
especially public project are completed in an extremely delayed.
The most momentous root of project delay in Ethiopia’s construction industry, which are
improper planning, pitiable work program, poor site management, inadequate experience and
capacity of the contractor, inadequate finance of the client and payments for completed work,
problems related to subcontractors, material shortage, availability and failure of equipment,
lack of communication between parties, luck of LC, failure on contract administration and
mistakes during the construction stage. Such reasons for project delay are usual which need
more attention in minimizing and managing the effect as a whole.
However, legally Construction project time overrun is a breach of a contract which can be lead
to dispute in case delay followed by disruption. Both PPA (2011) and MDB (2010) condition of
contract clearly states the legal remedies for delay and disruption claim for all parties in
contract.
The practical implementation of legal remedies against it is not very common instead,
implementation of termination as a remedy for non-performance obligations is common.
Assignment Page 59
Construction and contract Law
9.2 Recommendation
Construction project behind schedule happens everywhere and it is difficult to totally eliminate
project delay in real life. As civil engineering project most of the time passes through hypothesis
of different phases. This uncertainty may or may not happen so the only option is to be optimal
in different stage of the project especially in design and planning phases. Failure on contractual
obligation leads delay and disruption claim, which include overhead cost, loss of productivity,
loss of profit and loss of value for money.
In general, to reduce extent of Delay and disruption claim in construction projects this study
would like to recommend that the construction stakeholders should be able to:
Producing quality contractual document and managing all the process appropriately
within a time
All the stakeholders should effectively manage contract period and take their
responsibility as per the contractual agreement.
Knowing the scope and relationship of all the parties, good communication,
coordination and collaboration of all the parties are very essential.
Appointing appropriate personnel which performers the contracts
The Engineer should play his crucial role in contract process
The contractor should schedule the work for each and every activity optimum and
perform within a time.
Assignment Page 60
Construction and contract Law
REFERENCES
[1]. Sintayehu D. Kebede Enforcement of legal remedies against construction projects time
overrun in Ethiopia:
[2]. Mishra and Soota (2004)
[3]. The Guide to construction arbitration 3rd edition
[4]. Anwar M. Omar 2007, Delay Claims Management in Construction
[5]. Safw Kawa Abdulkareem 2020 Methods of Project Planning for Construction Projects
[6]. Bennatt(2003) The management of construction
[7]. Mubarek Shittu 2020 how to design program of work for building construction
1. [8]. Liquidated Damages and Extensions of Time: In Construction Contracts, Third Edition.
Brian Eggleston. ISBN: 978-1-405-11815-6
[9]. James J. Sienicki Jeffrey M. Singletary Delay and Disruption Claims: Big Impacts on Your
Bottom Line
[10]. M. Ibrahim, “Risk matrix for factors affecting time delay in road construction projects:
owners’ perspective,” Engineering, Construction and Architectural Management, Emerald
Group Publishing Limited, pp. 609-617, 2011.
[11]. Aftab Hameed Memon 2014, Time Management Practices in Large Construction Projects
[12].Chen, W.F. (2003)The Civil Engineering Hand Book 2ndEd
[13]. Koshe, Werku, Jha, K.N., 2016. Investigating causes of construction project delay in
Ethiopian construction industry. J. Civil Constr. Environ. Eng. 1 (1), 18–
[14]. Assaf, A;-Hejji 2006 causes of delay in large construction project, international journal of
project management
[15]. The Society of Construction Law (“SCL”) 2nd edition
[16]. FIDIC MDB(2010) Condition of contract
[18]. PPA(2011) Condition of contract
[[17] Keating on Construction Contracts 9th Edition, ‘Contractor’ claims,
Assignment Page 61