Christopher Design Building Project
Christopher Design Building Project
Total Float
5
4
0*
5
4
0*
2
7
0*
0*
0*
7
7
7
Total Float
5 35 35
4 28 28
0* 0 0
5 35 35
4 28 28
0* 0 0
2 14 14
7 49 49
0* 0 0
0* 0 0
0* 0 0
7 49 49
7 49 49
Total Float
5 35 35
4 28 28
0* 0 0
5 35 35
4 28 28
0* 0 0
2 14 14
7 49 49
0* 0 0
0* 0 0
0* 0 0
7 49 49
7 49 49
Total Float
5 35 35
4 28 28
0* 0 0*
5 35 35
4 28 28
0* 0 0*
2 14 14
7 49 49
0* 0 0*
0* 0 0*
0* 0 0*
7 49 49
7 49 49
Weeks)
Expected
6.3
4.3
6.8
6
6
29.5
\likely + Pessimistic
Bar chart time schedule for the Christopher Design/Building Project
Activity Weeks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Design building
Critical Bar
Early Bar
Progress Bar
FIGURE 3.8 Bar chart time schedule for the Christopher Design/Building Project
Activity Weeks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
aily Requirements)
SP
-
-
-
-
10
20
-
-
-
-
16
20
-
12
-
ersonnel/Labor
FIGURE 3.5 Tabulated schedule for the Christopher Design/Building Project Bar chart cost schedule f
Activity Time Earliest Latest Estimated
Description
Code (Wks) Start Finish Start Finish Total Float Cost
(1-2) Design structural steel 2 0 2 5 7 5 40,000 1 2
(1-3) Design building 13 0 13 4 17 4 420,000 Design
(1-4) Design mechanical equipment 6 0 6 0 4 0* 120,000 str'l steel
(2-3) Fabricate and erect structural steel 10 2 12 7 17 5 220,000
(3-7) Construct phase I building 6 13 19 17 23 4 420,000 40
(4-5) Design electrical equipment 4 6 10 6 10 0* 80,000 Design building
(4-6) Fabricate mechanical equipment 9 6 15 8 17 2 90,000
(4-8) Design interior items 2 6 8 13 15 7 40,000
(5-6) Procure electrical equipment 7 10 17 10 17 0* 40,000 Design mechanical equip
(6-7) Install mechanical and electrical equipment 6 17 23 17 23 0* 200,000
(7-11) Construct phase II building 6 23 29 23 29 0* 450,000 120
(8-9) Procure interior items 4 8 12 15 19 7 40,000
(9-10) Install interior items 10 12 22 19 29 7 240,000
* Critical path items
Critical Bar
Early Bar
Progress Bar
Bar chart cost schedule for the Christopher Design/Building Project
Weeks
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
220
Design building Construct phase I building
420 420
Design mechanical equipt Des elect'l equipt Procure electrical equipment Install mech'l elect'l equipt Construct phase II building
90
Design
int items Procure intr items Install interior items
40 40 240
Progress Bar