Outline Project Quality Plan (Outline PQP) : 其士建築 (香港) 有限公司 Chevalier Construction (Hong Kong) Limited
Outline Project Quality Plan (Outline PQP) : 其士建築 (香港) 有限公司 Chevalier Construction (Hong Kong) Limited
For
REVISION STATUS
Page 2
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
CONTENT
1 Scope
2 Normative Reference
5 Management Responsibility
6 Resource Management
7 Construction Management
8 Procurement Management
Page 3
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Page 4
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
1.0 Scope:
This Project Quality plan covers required activities for selection, purchasing, delivery of
all materials & equipment complying with the technical specifications, statutory and
regulatory requirements & scope of work for the project.
- Client/Employer
- Engineer
- Consultant
- Contractor
- Sub-Contractor
- Quality System:
Following are the Quality Systems.
1. Organizational Structure.
2. Project Management Process.
3. Construction Work Process.
4. Installation Work Process.
5. Testing & Commissioning Process.
6. Resources.
- Quality Plan: Document Specifying which procedures & associated resources shall be
applied by whom & when to a specific project, product, process or contract.
- Quality Assurance: Part of Quality Management to attain quality requirements of the
contract.
Page 5
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Page 6
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
- Quality Records.
- Planning, Operation & Process Control documentation such as:
i. Inspection, Test Plan (I&TP) - provided by CIMS.
ii. Programme and Work Procedures / method statement.
iii. Records of Internal Reviews.
iv. Test Report (TR) - provided by CIMS.
v. Audit report & Corrective actions.
vi. Other records used to ensure effective planning operation & control.
Page 7
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
The main focus of the contract’s QMS is on the customer satisfaction. To this end, the
contract commits itself to make persistent effort for continual improvement, in order to
sustain and raise the level of performance.
All the staff is requested to join the contract, to provide the best support to the system
implementation.
Page 8
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
5.3.3 Planning
5.3.3.1Quality Objectives:
The top management of Chevalier has identified the following quality objectives for the
project. The objectives are measurable, consistent with the policy & relevant to the
successful completion of the project. Attainment of objectives is considered a part of
Chevalier effort for continual improvement.
- To ensure that approved practices, procedures, I&TPs & audit program are in place
& utilizes as they apply throughout all the phases of the project.
- To minimize the scrap & rework during the life of the project.
- To ensure that safety of the personnel, the facilities & environment have been
carefully considered & that the appropriate measure has been implemented.
- To ensure that quality requirements are determined & satisfied throughout the
phases of contract performance, including as applicable, procurement, construction
& pre-commissioning.
- To provide proper resources to meet construction schedule.
- To provide for early & prompt detection of deficiencies & for timely & effective
correction action, in order not to impair schedule.
mobilizations, titles of individuals, sub-contractor necessary to complete the work & the
integration of quality improvement initiatives.
Planning is conducted to ensure that changes in the quality management system are
conducted in a controlled manner & the integrity of the quality management system is
maintained.
The project manager defines the responsibilities & authorities for the project
management process & inform to all concern within the project organization. QA
Manager shall have organizational authority at least equal to that of the line manager
responsible for the execution of the work. He administrates reports to the Engineer & is
responsible for the auditing of the Quality Management System. Ha has the overall
responsibility to organize the implementation to organize the implementation of the
quality plan. It shall be his responsibility to report any deficiencies in the quality of work
to the Engineer. He or his staff has the authority to stop work in any area where
discrepancies remain uncorrected & subsequently close out any non-conformance report
upon satisfactory correction of noted deficiencies.
QA Manager is responsible for the supervision of the relevant discipline for the
supervision of the relevant discipline inspectors. He shall be responsible for monitoring,
identifying any areas of concern & raising non-conformance reports as necessary. He is
responsible for ensuring that the discipline inspectors have access to the necessary
standards, specifications & drawings to enable them to effectively monitor construction
activities. He shall review activity inspection reports to ensure they are concise &
complete. He is also responsible for the management of the independent Test Agencies
ensuring that they have suitability trained & qualified personnel on-site & that their
equipment is satisfactorily maintained & calibrated.
Page 10
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Project Secretary / Clerk and Document Controller is responsible for the control of all
documents in accordance with the Quality Control Plan. Control and record the
movement of all correspondence, report, specification, drawings and any other
documents to ensure that all such movement are traceable and are carried out without
undue delay.
- At defined intervals & occasions the employer’s requirements are discussed &
communicated to all responsible personnel to increase their commitment in meeting
these requirements.
- Every month a coordination meeting is conducted involving procurement,
construction, QA & members of the management to evaluate & monitor that
customer requirement are adequately met & that customer satisfaction is achieved.
- The MR issues internal communication related to quality Management System &
records of such communications are maintained.
6.1.1 Infrastructure:
Chevalier shall plan, determine & manage the work area, in a manner to satisfy the
project requirements. Chevalier provides the necessary provisions to achieve
non-deficient product in the project sites & office area. Provisions shall include
equipments, transportation, communication & other utilities.
Page 13
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
equipment and facilities such as excavator, ground water control facilities, wastewater
treatment plant and noise monitoring equipment to achieve the productivity, conformity
of product and regulatory requirements.
Chevalier planned staffing shall comply with the contractor approved Quality Plan.
Reduction from required level of quality personnel shall require the Engineer’s approval.
Chevalier shall advise engineer 30 days in advance of quality personnel changes due to
vacation, temporary assignments or resignations. All other changes such as illness &
emergency leaves will be advised to the Engineer as soon as possible.
The Department Manager is responsible to identify training needs & assure training is
performed. Personnel lacking required competencies shall receive training such as
formal, informal or on-the-job training.
Page 14
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Employee needs are identified through job description requirements, employees past
experience & knowledge. The Department Manager/ Supervisor shall establish a training
plan to address these needs.
Management ensures that employees are aware of the relevance & importance of their
work activities & how they contribute to the achievement of the quality objectives.
Management ensures that employees are trained & record should store & maintained in
the Administration Department.
Chevalier will assess the major plant and machinery required for the Contract and
prepares the Plant Schedule, which detailing the capacity, quantity and timing for use.
The selection of plant will subject to efficient performance to achieve the safety,
programme and environmental requirements.
Page 15
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Chevalier will review the contract agreement to determine project requirements. The
engineering manager will evaluate these requirements & determine any additional
requirements, including regulatory & legal ones, which may have not been identified by
the Engineer & need to be implemented to support the delivery of the work.
The Project Manager & the Management Representative are responsible for evaluation of
the Engineer’s feedback/complaints & responding them.
Based upon the key project documents to control the quality of the construction works in
the following ways:
a) The project Manager shall prepare and submit the master programme at
commencement of the project. The project identifies “Key Dates” by which each and
any part of the design works included in the contract are to be achieved and
“Milestone Dates” which related to the completion of major and critical items of the
project. The agreed master programme shall be the controlled document for
monitoring the progress of the project.
Page 16
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
b) Chevalier shall briefs all the subcontractors and Nominated subcontractor (Lift
Installation) the standard and requirements of each particular trades and discussion /
co-ordination the sequence and method for the particular works trades
c). Based on the discussed and agreed sequence and method to prepare the method
statement for architect / engineer approval before carrying out the site installation /
execution of works.
d) Chevalier shall also issues the short term programme to each subcontractor so as to
meet the entire project completion,
e) Chevalier site management control and record work in-progress by subcontractors,
and also main contractor (Chevalier) and co-ordinate with nominated subcontractor
where required by contract and / or other client’s representative.
f) Chevalier site management collect progress and status information which are then
entered into the project master file for works.
g) Chevalier site management controls the construction waste and avoids stock pile in
the site area.
h) Preparation of updated project status according to the planned programme including:
i.) Detailed works programme for the next short-term period.
ii.) Material schedule and advice notice for coming delivery.
iii.) Warehouse and in-house workshop material delivery for next short term period.
iv.) Amendment and variation of works registers and review.
v.) Nominated subcontractor’s work quality plan where necessary.
vi.) Review the statuary requirements (including safety, EPD, Police) to ensure the site
condition in up to the required standard.
vii.) Updated material procurement schedule
viii.) Update material delivery schedule
ix.) Update man power schedule
x.) Update plant schedule
xi.) Update safety plan
xii.) Update waste management plan
xiii.) Update security plan
xiv.) Non-confirming reports from client.
i) The project manager shall brief, where necessary and/ or distributes reports to site
project team and domestic and / or nominated subcontractor.
Page 17
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
j) The site agent or, when necessary the project manager conducts regular site review
meeting with its own project team and all subcontractors on monthly basis to brief the
above mentioned items.
k) The project manager and site agent confirm / rectified amendments / variations.
l) If necessary, site agent issues notification of non-compliance / request for corrective
action and report to project manager.
m) The project manager shall conduct a regular review meeting with client and its
consultant to report the project status.
n) The project manager prepares and attends chevalier head office monitoring review
meeting with the project director / General Manager.
a). Documented work instruction defining the manner of production and installation.
b). Monitoring and control of special process such as temporary works.
c). The approval of processes and equipments.
d). Criteria for workmanship.
e). Handling, package, delivery and storage of materials.
f). Inspection and testing procedure for the quality control.
g). Master programme of works and other sub-programmes as required.
Page 18
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
h). Detail planning in respect to the appointment of sub-contractors, material supply and
plant requirements in form of schedule.
i). Inspection and testing procedure for the quality control.
Regarding the off-site fabricated products, such as structural steel works, regular
inspection at the fabrication yard will be carried out by site engineer for the quality
control and monitoring according to the procedure as specified in the Quality
Management System.
I&TP’s, its issuance & use shall also be controlled so that only revision applicable to the
project is utilized.
A documented procedure has been established to control documents required for the
quality management system. Project documents shall be maintained at the Main Office &
the field offices. Access to these files shall be limited to Chevalier Key Personnel assign
to this project.
Prior to submitting documents to the engineer, these documents are to be reviewed &
approved by the responsible key personnel. This review & approval shall be indicated on
each item by statement & signature of the responsible personnel.
Page 19
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
inspection checklist & test reports forms provided by the engineer, its issuance & use
shall also be controlled so that the revision applicable to the project are utilized.
Upon commencement of the contract, the chevalier will identify the subletting needs and
prepare the sub-contract schedule which includes tentative subletting works, tender
invitation date, tender return date, sub-contract award date, proposed sub-contract types
and sub-contact of awarded sub-contractor.
Page 20
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Chevalier has procedures to ensure that such purchased materials and subcontracted work
conform to the requirements stated or implied in the contract and comply with client’s
quality requirements. The purchasing manager and subletting manager are responsible
to ensure that the procedures at the company’s quality system are being implemented
respectively.
The project manager assisted by the purchasing manager shall ensure that he purchased
materials are complied with the client’s specification. Based upon the project details and
subletting / purchasing schedules of materials and work trades prepared by project
manager, the purchasing and subletting manager shall then call for the relevant suppliers
and subcontractors from the approved list which based upon the supplier and
subcontractor’s previous quality performance.
b.) After award of contract, during the stage of project initiation, a list for material
schedule and material quality requirement is prepared.
c.) Samples and quotations are obtained and approval as necessary.
d.) Suppliers are selected and purchase order shall issue.
e.) Material delivery period shall be agreed with suppliers.
f.) As a part of routine project quality control, site meetings are held in which relevant
informational and reports are reviewed. This includes the material schedule and
requirements.
g.) Retrieval orders from purchaser are issued and/or expedited.
h.) Materials are received on site inspected and/or verified as per material requirements.
i.) Materials are labeled and stored on site as per storage instruction.
j.) Requests for materials distribution on site are processed by site storekeeper.
k.) Records of delivery orders, materials receipts, inspection and distribution are kept
by storekeeper.
l). Where verification is required at the vendor’s premises, verification/inspection
arrangements & methods of material release shall be identified and included in the
supply contract.
Material inspection will be carried out and identified at the time of delivery on site, for
example, mill certificates for steel re-bar and delivery docket for concrete. Color codes
system will be used for differentiating batches of delivery of steel re-bar. The quality
Page 22
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
control registers will be maintained and updated for the delivery batch of steel re-bar and
concrete which will record the certificate of origin, test results and location used etc. in
order to clearly identify and trace of used products.
All the built elements are identified with information, i.e. level, alignment, dimensions,
all the variances and modifications taken place during work; and materials used are
recorded during the course of works, management to team prepares the "as built" data.
Page 23
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
Chevalier has procedure for defining incoming, in-progress and final quality verification
requirement for both materials and workmanship. This is done by means of project
initiation and also Chevalier has procedures for ensuring that materials and workmanship
are verified according to the client’s requirements as per project operation control of
works and materials. These procedures include the procedures for establishing and
maintaining inspection and test records and for ensuring samples of specified materials
are submitted to Architect / Client for approval before incorporation into the work.
a) All the model and reference number of the equipment, the location of use, the
calibration requirements and the acceptance criteria have been properly record.
b) The equipment is capable of the accuracy and precision necessary.
c) The equipment is identified with a suitable indicator or approved identification record
to show the calibration status.
d) Calibration records are properly maintained.
Page 25
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
e) There are ways to resolve the problem when equipments are found to be out of
calibration.
f) The environmental conditions are suitable for the calibration, inspection,
measurement and/or test being carried out.
g) The handling, preservation and storage of equipment is such that the accuracy and
fitness for use is maintained.
h) Inspection, measuring and test facilities, including both test hardware and test
software, are safeguarded from adjustments which would invalidate the calibration
setting.
Page 26
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
9.4.3 Audits:
Chevalier has established & will maintain & implement a quality audit program to verify
that the quality activities & related results comply with planned contractual arrangements
& to determine the effectiveness of the quality program associated procedures. The QP
shall have the following:
- A procedure that addresses the responsibilities & requirements for planning &
conducting audits & for reporting results & monitoring record was developed to
govern these activities.
- Contractor audits shall be carried out in order to monitor the quality system
implementation for procurement & construction work phases for the Project.
- Audits will be executed by the QA Manager in accordance with the approved quality
plan requirements.
- Corrective action shall be monitored & bought to its closure.
- Audit to be conducted by the engineer will be selected by him at any time.
Page 27
其士 (建築) 有限公司 Issue no.: 0
CHEVALIER CONSTRUCTION (HONG KONG) LIMITED Rev. no: 0
Document Title: Outline Project Quality Plan Doc. no: OPQP
The Engineer shall be notified to verify the closure of the NCR. A non-conformance Log
shall be prepared & maintained & included in the weekly progress meetings.
9.5 Improvement
9.5.1 Continual Improvement:
Chevalier continually improves the effectiveness of the QMS through the use of the
quality policy, quality objectives audit results, analysis of data, corrective & preventive
action & management review meetings.
9.5.2 Corrective Action:
Chevalier shall take action to eliminate the cause of non- conformities & to prevent
recurrence. A procedure defining the requirements for corrective action has been
prepared.
Page 28