BL501. Learning Pack 1 - Ground Works
BL501. Learning Pack 1 - Ground Works
Siteworks
This classification is concerned with the removal of trees, tree stumps, bushes, and shrubs as having a
trunk of at least 0.5 m girth at 0.5m above ground level at the top of the stump. The assumption can be
made that anything smaller is a bush.
Guidelines for estimating for the removal of trees and stumps might include the following:
Trees – time for the gang to fell; hire of chain saws; fuel and oil; sharpening; axes; wedges; pince
bars and mauls; protective clothing; time to cut up and burn the slash; disposal of the main limbs
and trunks to a tip.
Stump – Time to excavate around larger stumps by hand, or by machine if numbers or size
warrant; men excavating or hire of machine and operative; disposal of stumps to tip.
Bushes, shrubs and undergrowth can be removed by hand using chain saws and burning the
residue. Machines can also be used to ‘bulldoze’ the shrubs off the ground into piles for burning
or remove from the site and dumped in other locations. The choice depends on the size to be
cleared and density of the growth.
GROUND WORKS
Depth stage (m) To excavate and To throw the soil To clear the sides Totals Hours
get out out
1.0 2.4 0.0 0.0 2.4
> 1.0 to 2.0 2.4 1.4 1.4 5.2
> 2.0 to 3.0 2.4 2.8 1.4 6.6
> 3.0 to 4.0 2.4 5.2 1.4 8.0
Table 2 Multipliers for difficulty due to nature of ground and type of hand excavation
Table 3 – Range of outputs for various classes of hand excavation in ordinary soil (hours per m3).
2|P age
B. Machine Excavation Data
Multiplier
3
Soil type ( x output per hour / m )
Vegetable soil, sand, ordinary soil 1.00
Heavy clay 1.33
Soft rock 2.00
Hard rock 5.00 *
* Low output due to general inability of machines to do the breaking up, which requires pneumatic drills
or explosives.
Table 6 Outputs for a tractor with front shovel (1.24m3) and backhoe (0.06 – 0.28m3), required
for loading of spoil and straight into dumper or tipping lorries alongside excavation.
3|P age
Example 1 Groundworks
1. Site works
1.1 Clearing the site incl. trees ≤ 0.5m girth complete with stumps and roots………….M2
Assume site to clear is 50m x 20m and that we will excavate 1m length and 1m width at any time. Plant
rate of JCB at K410.00/8hr.day and Dump Truck at K250.00/8hr.day
VDMRC
Example 2 Groundworks
1. Site works
1.2 Removal of trees > 0.5m and ≤ 1m girth complete with stumps and roots…………No
Assume site to clear is 50m x 20m having 5 x trees and 3 x stumps > 0.5m girth. Plant rate of Lorry at
K180.00/8hr.day, 2 x chain saws at K100.00/8hr.day, 3 x labourers at K3.60/hr and charges at tip off at
K30.00/load for 3 x loads.
(i) Felling of trees, cutting up, burning, loading onto lorry: LHLC3
3 labourers for 2 days of 8 hours at K3.60/hr ................................................................. K173.28
Hire of chain saw, 2 off for 2 days at K100 per day ................................................... K400.00
Lorry with Mechanical Off- Load and driver for 2 days at K180.00 per day ............ K360.00
Charges at tip: 3 loads at K30.00 per load ................................................................... K90.00
Cost of 5 x trees K1023.28
Cost per tree K204.66
Example 3 Groundworks
2. Surface excavation
2.1 Surface excavation to reduce level 0.25m depth (50m x 20m)……………………...M3
Assume site is 50m x 20m and top soil to be removed. Plant rate of JCB at K500.00/8hr.day and Dump
Truck at K250.00/8hr.day.
Example 4 Groundworks
3. Trench excavation
3.1 Excavate strip footing > 1m total depth from reduce level …………………………M3
Assume strip footing girth at 20m x 8m and 600mm deep and will excavate 1m length and 1m width at
any time. Plant rate of JCB at K500.00/8hr.day and Dump Truck at K250.00/8hr.day.
5|P age
The followings are the two examples of rates for Hand Excavation, using the outputs in Table 1 & 2.
Example 5 Groundworks
3. Trench excavation
3.1 Excavate strip footing at reduce level > 1m ≤ 2m total depth ……………………..M3
UTHC2PU
Using data from Table 1, assuming the excavation dimensions to be 1m by 1 m on plan:
Throw out soil at 2.0m deep: Assume labour rate at K26.50
2.0m3 at 5.2 hours/m3 at K26.50................................................................................. K275.60
Cost to excavate 2m3 …………… K275.60
Cost per m3 ................................................................................................................ K137.80
Profit and on-cost 20% ................................................................................................ K27.56
Unit Rate per M3 ................................................................................................................ K165.36
Example 6 Groundworks
3. Trench excavation
3.1 Excavate strip footing at reduce level ≤ 4m total depth …………………………..M3
UTHC2PU
Using data from Table 1, assuming the excavation dimensions to be 1m by 1m on plan:
Throw out soil at 4.0m deep: Assume labour rate at K26.50
4.0m3 at 8.0 hours/m3 at K26.50................................................................................. K848.00
Cost to excavate 4m3 …………… K848.00
Cost per m3 ................................................................................................................ K212.00
Profit and on-cost 20% ................................................................................................ K42.40
Unit Rate per M3 ................................................................................................................ K254.40
Example 7 and 8, it is closely related to Example 2, however, it will only apply if it is stated in BOQs
that you price ‘backfilling’ as part of Groundworks (refer Example 2). However, if BOQ states
‘backfilling’ is priced separately, then this is the case, part (ii) of Example 2 will be omitted and priced
as in Example 7 or 8 shown below.
Example 7 Groundworks
4. Backfill excavation
4.1 Backfill excavation with previously excavated materials …………………………..M3
BAVPBPU
Backfilling of stumps and roots of trees
Assume root spread approximately 1.50m radius and root depth approximately 1.25m
Volume of excavation approximately 8.84 m3/ tree
Plant rate of JCB at K500.00/8hr.day 8.84m3 x 8 holes for 8stupms in example 1 = 70.72m3
6|P age
Example 8 Groundworks
4. Backfill excavation
4.1 Backfill excavation with previously excavated materials …………………………..M3
BAVPBPU
Backfilling of stumps and roots of trees
Assume root spread approximately 1.50m radius and root depth approximately 1.25m
Volume of excavation approximately 8.84 m3 / tree
Plant rate of JCB at K500.00/8hr.day