Cost Management Scope & Methodology
Cost Management Scope & Methodology
Renovation Project
Cairo
Client:
ACIHT
1|Page
Table of Content
1. Proposal Outline………….…………………..3
1.1 Introduction……………………………...……..3
1.2 Project Understanding……………………....…3
2. Scope of Work………………………………....5
2.1 General…………………..…………………...…5
2.2 Project Development Cycle…………. .....….7
2.3 Key Determinants of Cost……………………..11
2.4 Cost changing Factors………… ………...…12
2.5 Risk Issues……………………………...…...…13
2|Page
1 Proposal Outline
1.1 Introduction
Artelia has invited Concord Consulting Group to manage the design and tender process
in respect of Cost management Services for Hilton Ramses, Cairo as a Sub-Consultant
to Artelia.
Please find hereafter our Cost Management Scope & Methodology concerning the
Design, Tender & Bidding Phase for the mentioned project.
According to the received RFP, the purpose is to carry out the design and tender
process in respect of the Cost Management Services for the Following areas:
1. Design and tender for the lobby, entrances, reception areas, shops and elevator
cabins
2. Design and tender for the current Garden Court which is to become the Shisha
Lounge and part of the Levantine concept (Standard Hilton F&B concept). The
Shisha Lounge also has an outdoor terrace area which needs to included.
3. Design and tender for a bar/pub concept (Sportsman – Standard Hilton F&B
concept) next to the current Garden Court (currently Sherlock Holmes pub). This
could include a terrace.
4. Design and tender to the current Terrace Café and Citadel restaurants to be
combined into one restaurant area under the Levantine concept.
5. Design and tender for the soft refurbishment to the Maharaja Indian restaurant.
6. Design and tender for all ground floor, restaurant floor and pool floor circulation
areas.
3|Page
7. Design and tender for the meeting rooms and ballroom plus pre function areas.
8. Design and tender for ground floor toilets, restaurant floor toilets and pool floor
toilets.
9. Design and tender for the pool deck and new bar concept around the pool.
10. Design and tender for any miscellaneous areas in the public spaces which
are not captured in the above.
11. Detailed design and tender for questroom floors 23, 24, 25, 26 & 27
including all guestrooms and corridors. This is continuation of an existing scheme
which has already been implemented on floors 28, 29 & 30.
Exclusions:
Gym/fitness areas
4|Page
2 Cost Management Scope
2.1 General
Cost Management plan provides a detailed record of the processes that will be adhered to
ensuring project costs are properly managed. One of these processes that is critical to any
project’s successful completion is the one that defines the actions required when a cost
variance occurs.
Without careful and detailed planning project costs can be miss communicated to
stakeholders and its sponsor. This is because of a poor or lack of explanation as to what the
costs covers and any assumptions that have been made in the process of detailing these
costs. A project manager must have the processes and reporting structure in place to
ensure that costs are accurately monitored and controlled. This arrangement guarantees
that the cost base is well managed throughout the project’s duration and that the final
product is delivered to the approved budget.
The Work Breakdown Structure (WBS) along with the scope and schedule baselines allows
the costs of each activity to be properly estimated. An description of how these figures have
been calculated including what assumptions and where appropriate what constraints have
been made to arrive at this figure. The cost performance baseline is created and forms the
basis for presenting the final project budget to the sponsor and stakeholders for approval.
A project cost management plan has the following elements. Each will relate to the culture
of the organization and the nature of the project being undertaken.
Unit of measure (used to create the estimates)
Level of precision (extent of rounding up or down that has been used)
Level of accuracy (e.g. 10%)
Organizational procedures links (WBS gives the framework & control account for the
plan)
Control thresholds (cost variance that will be tolerated before action is needed)
Rules of performance measurement (e.g. EVM – Earned Value Measurement)
Reporting formats & frequency
Description of all cost processes.
5|Page
Cost management is concerned with the process of planning and controlling the budget of
a project or business. It includes activities such as planning, estimating, budgeting,
financing, funding, managing, and controlling costs so that the project can be completed
within the approved budget. Cost management covers the full life cycle of a project from
the initial planning phase towards measuring the actual cost performance and project
completion. This article will explain the different steps or processes in Project Cost
Management, in line with methods such as the PMBOK.
6|Page
Step 4: Cost control
Cost control is concerned with measuring variances from the cost baseline and taking
effective corrective action to achieve minimum costs. Procedures are applied to monitor
expenditures and performance against the progress of a project. All changes to the cost
baseline need to be recorded and the expected final total costs are continuously
forecasted. When actual cost information becomes available an important part of cost
control is to explain what is causing the variance from the cost baseline. Based on this
analysis, corrective action might be required to avoid cost overruns.
Dedicated cost control software tools can be valuable to define cost control procedures,
track and approve changes and apply analysis. Furthermore, reporting can be enhanced
and simplified which makes it easier to inform all stakeholders involved in the project.
The First stage of the project cycle the definition of what the requirements is and how it
can be satisfied. This includes deciding on the size and quality of facility that is required.
Different options will be discussed at this stage and evaluate d in terms of broad cost
estimated, expected operational performance and economic benefit. Preliminary cost
estimates may be attempted at this stage.
Concept Design
Work will then be undertaken to develop the plans for the project. These plans will
establish the general parameters of a scheme design and will include all the project’s
major components. The function of outline designs is to provide:
The basis for the detailed design and accurate cost estimated of the scheme.
The necessary information for the planning process.
7|Page
The Project Development Cycle
Concept Design
Schematic Design
Procurement Plan
Detailed Design
Finance
Priced Estimated BOQ
Bidding Analysis
8|Page
Schematic Design
This stage seeks to define the general scope and conceptual design of the project
including scale and relationship between building components & materials. This is very
important for the Cost management phase since it outlines the cost regarding the material
selections. During this stage value engineering might be required.
Detailed Design
The detailed design of a project is used to assess the quantities of materials required and
the actual construction works involved in implementing a project. Drawings and lists of
quantities are then used to produce detailed project costs and to establish an
implementation timetable.
Upon concluding the detailed Design Stage and obtaining the material take off and
Quantities, the Cost Management team performs this exercise to give an estimate to the
project cost that should be roughly around 5% above or below to the actual price actually
paid.
Upon completing the Tender package Different contractors are invited in order to bid for
the project execution based on their technical and financial offers, this stage provides cost
alternatives for the project based on the economical market status, Value engineering
maybe needed during this stage.
9|Page
Bidding analysis
Once Contractors have been approved both technically and financially, Priced BOQs are
compared to achieve the best offer and compared to the priced Estimated BOQ done to
achieve the best possible .cost and ensure it is within the expected and approved study
proposed.
After a decision has been reached, and the Owners Consultants, and Project manager
reached a conclusion to the winning bid. The project is awarded to the Contractor, in which
case a LOA is issued depending on the Financial Specifications and offer issued in order
to serve best the project at hand.
10 | P a g e
2.3 Key Determinants of Initial Project Costs
Project Costs are based on the actual costs of materials, equipment, and labour in the
region where the project is being procured. These basic costs will vary depending upon a
number of factors which are summarised in the below diagram
11 | P a g e
2.4 Factors which change Costs over time
Once implementation begins, a project’s costs rarely remains static. As further information becomes
available the costs may be further defined. Yet, even when a cost become firmly fixed, there are
numerous factors that can lead to the cost increasing. Delays are a major factoe. Whatever the
reason, delays almost invariably increase budget cost. Many events may have contributed to the
dely – some which could have been foreseen and others which could not.
The below diagram illustrated some of the factors that result in projects being delayed or costing
more than originally planned.
The Diagram below shows the project development cycle in relation with the Risk Issues.
12 | P a g e
The Project
Development Cycle Risk Issues
Risk Decreases
Has project sponsor experience of this type of projects?