Bridge Estimate: Bridge No's. 044/103 & 044/104 Lebanon / Hartford - Contract 16148
Bridge Estimate: Bridge No's. 044/103 & 044/104 Lebanon / Hartford - Contract 16148
SUBTOTAL = $25,386,775
Note: 1) Superstructure Item Payment Breakdown is 76% NHDOT, 24% Vtrans Contingency (5% ) = $1,269,339
2) Substructure Item Payment Breakdown is per Substructure Unit. Abut A, BRIDGE TOTAL = $26,656,114
Piers 1, 2, 3, 4 are Owned by NHDOT. Pier 5 & Abut. B Owned by Vtrans SAY = $ 26,700,000
3) Project Wide Item Payment Breakdown is 76% NHDOT, 24% Vtrans
4) Unit Costs Based on Year 2016 Costs
TOTAL TOTAL
ITEM NO. DESCRIPTION UNIT UNIT PRICE QUANTITY COST
CONSTRUCTION ENGINEERING
** Percentages Estimated from other similar NHDOT projects