Risks in Bandra-Worli Sea Link
Risks in Bandra-Worli Sea Link
The Movement of Vehicles in Mumbai city and the Bandra-Worli Sea link project are like
disease and anti-dote. It is the perfect solution for the site’s endless Movement of Vehicles
issue. The native rail network provides better tracks, AC coaches and transports millions of
travellers. The non-rail components have new roads, over bridges, subways, and signal
system.
The Bandra-Worli Sea Link will only add to the existing issues. Mumbai city is among the
five most polluted cities of the world. The Municipal report insists that to reduce the air
pollution in Mumbai city it is essential to promote public transport viz. Rail network and Bus
service.
Many projects were suggested since 50’s for smooth Movement of Vehicles in Mumbai city.
The project in question was opposed, strongly by fisher men and other alert natives
constantly. However, the CRRI mentioned that these corridors should be implemented only
after detailed native research and the Execution of these projects should be started only after
the research say it is ok to go ahead.
MUMBAI URBAN TRANSPORT PROJECT-I was planned around 1984. There was a
heated brain storming session in the Assembly and the Maharashtra Govt. appointed a high-
level team called the K. G. Paranjape Team to give a list in priority of solutions to Mumbai
city’s Movement of Vehicles issues. The Team submitted its consolidated Report which had
certain projects listed in a priority list.
Kirloskar Consultants and the Operation Research Group made a thorough research of
Movement of Vehicles conditions and submitted their reports in July 1994. This report has
rejected the Bandra-Worli Sea Link Project and the West Island Freeway saying that it will
attract more and more Movement of Vehicles towards South Mumbai city and the congestion
will only get worse in many areas. The report has warned that if the Bandra-Worli Sea Link
Project is implemented it will lead to more congestion and as a consequence more pollution
and therefore affecting the health of Mumbai city’s natives.
The V.M. Lal Team has also suggested restricting automobile Movement of Vehicles
entering the island Site at Sion and Mahim. As per the newspapers it is clear that the Bandra-
Worli Sea Link Project has no scientific basis.
It is disastrous to let the personalised vehicles occupy more space and roads, as it will be
harmful to everyone including the users of private vehicle.
Constitutional Legitimacy of the Bandra-Worli Sea Link Project The project is supposed to
be based on research made by the Central Water and Power Research Institute, Pune. The
research is based on a hydraulic model and not on the actual sea is studied.
It is imperative to note that the Indian Ecological Protection Act came into effect in 1986 and
the CRZ Notice in February 1991. In 1994 the Notice which made it compulsory to make an
Ecological Effect Analysis came into force and in the Notice requiring a public hearing also
came into force. Obviously, these legal requirements were not fulfilled. The Ecological
Clearance cannot be given without doing prior research and observing all the steps of
procedure. Even then on 7th January, 199 the clearance was given. The important clauses of
this clearance were also violated. This attitude shows that there is no respect for
Constitutional clauses. In addition to this the site location of the proposed toll plaza has been
changed after obtaining Ecological clearance.
It is desirable to ensure that the development options under consideration are sustainable. In
doing so, Ecological consequences must be characterized early in the project cycle and
accounted for in the project layout. It integrates the Ecological concerns in Progressive
activities right at the time of initiating the project when preparing the feasibility report; It can
often prevent future liabilities or expensive alterations in project layout.
Prior to January 1994, in India was carried out under administrative headlines which required
the project proponents of major irrigation projects, water body valley project, power stations,
ports and harbours etc., to secure a clearance from the Ministry of Nature and Forest, Govt. if
India. The Ecological appraised team of the Ministry carried out the Ecological appraised. In
January 1994, the Govt. of India notified the Nature Effect Notice under rule 5 of Nature
Protection) Rule, 1986 and 29 designated projects. The Notice made it obligatory for the 29
designated projects to prepare and submit an, and Nature Management Plan (EMP) and a
Project Report to an Effect Analysis Agency for clearance. The Ministry of Nature and
Forests, Govt. of Indian was designated the Effect Analysis Agency.
Sea link project locations should be reviewed based upon various regulatory and non-
regulatory criteria. Project siting restrictions depend on the reception of the surrounding
nature. Sensitivity should be assessed in relation to proximity of the project to the sites/sites
listed in the identified ecologically sensitive zones (ESZ) notified by MoEF.
The siting criteria delineated by MoEF include:
• As far as possible, land retained for agricultural purposes should not be converted into
an industrial site.
• Acquired land must have a green belt area as per regulatory norms.
• Sufficient space and arrangements must be made for storing and disposing solid
waste.
• The design of the project must confirm to the landscape pattern of the area without
unduly affecting the scenic beauties of that site.
• Respective town of the project, if any, to be created must provide for space for a
barrier between the project and the township.
An EIA report should provide clear information to the deciding committee on the different
Ecological scenarios without the project, with the project and with project options. Unknown
elements should be clearly reflected in the EIA report.
Pollution Control Board as per the rules and regulations given forth in the Notices.
This public hearing is not a mere formality. The native population is often more conversant
with the native implications of a project than Govt. agencies and experts exercising their
judgement from outside. Besides, in attempting to get through an attractive project, the
agencies are known to turn a blind, even to obnoxious and harmful implications, and the
hearing in a public court gives an opportunity, though limited, to highlight such
consequences. In addition, public participation is an extremely crucial component of
democratic governance and has to be treated seriously, and respected nationwide. Above all,
the affected population has a right to be informed about any project, which is likely to
influence its quality of life and living.
Also, the notice issued above, for obtaining Ecological Clearance of projects, the applicant
has to obtain a NOC from the State Pollution Control Board. The MPCB should issue this
NOC only after completing the legal proceedings.
In the case being discussed, the public hearing was not held in regard to (BWSLP), nor was
the relevant documents etc. made available for inspection to the IPT panel or other NGOs and
concerned natives. Therefore, the panel concludes that the report is incompletely furnished
before the eyes of the law.
These factors prove that from the very beginning there has been a lack of transparency in the
passing and Execution of the project before the eyes of law.
Ecological clearance notifies that “land reclamation should be kept to the minimum, at any
cost to less than 4.7 hectares and the same should be monitored closely so that it does not
violate the clauses of the CRZ Notice, 1991 or as amended subsequently.” Mrs. Geeta
Pardiwala a native of Shivaji Park deposed before the IPT saying that “initially we were told
that there would be only two pillars on the sea link, one at Bandra and the other at Worli.
However now they are reclaiming more land, as it becomes cheaper for them to build the
bridge. According to the 1994 Notice, any expansion of all existing or new projects requires
that not only a fresh Ecological Effect Analysis is carried out however also fresh permission
for the said project is sought and granted. This has definitely not been adhered to in the case
of the Bandra-Worli Sea Link. The present project is based on the 1992 MMRDA report;
however, there are a number of contradictions to the original recommendations. The
Ecological Effect Section has recommendations by scientist C. V. Kulkarni that no further
reclamation be allowed on the Bandra side, to prevent siltation in the Mahim Bay and the
creek area.
In project such as mentioned above, in case new quarries are to be opened, specific approvals
from the competent authority should be obtained in this regard.” This has been violated by
the Mumbai city Suburban Collector who has issued the quarrying Permit. The quarry on site
falls under a ‘no development zone’, Notified in development control regulation for Greater
Mumbai city, 1991.
Wherever fishing or other marine activities are getting affected, the concerned agency should
be consulted and their concurrence obtained for the project in question.” The fishermen
affected by the project in question were neither consulted nor was their consent obtained.
Mumbai city is geographically positioned to play host to creeks and shallow waters opposite
headlands. In most of the areas, these creeks have been blocked. Mahim Creek is one of the
few sites left where the waves can partially enter the area.
However, the Effect on the marine ecology, flora and fauna, and the possibility of initiating
erosion has not been studied. With Mahim creek getting shallower because of the process of
siltation, there is a greater danger for coast like the Versova beach. The erosion here become
a geological hazard, and has assumed alarming probabilities.
The road network in Mumbai city is based on three north-south corridor routes and there are
very few continuous east-west routes. Therefore, Movement of Vehicles is concentrated on a
few routes that have become congested. Mumbai city road Movement of Vehicles has
worsened by around four hundred percent in the last twenty years. It poses considerable
health issues.
The W. S. Atkins Report (1994) was commissioned by the MSRDC to research the feasibility
of the Bandra-Worli Sea Link. The result of the report is based on a strategic transportation
computer model based on cost and time of travel and calibrated for Mumbai city.
Undesirability of the Project
a) Effect due to Blockage of Mithi Water body
The most insidious aspect of the link, that will endanger the life of every native person, is
related to the outbreak of epidemics. Almost 800 million litres of sewage are discarded every
day in the Mahim Creek, besides the thousands of industries that release effluents that are
located in Dharavi and upstream of the Mithi Water body.
Most experts agree that Socio-economic and financial instruments can help achieve
sustainable development. Issues relating to transportation are so complexly mixed with other
issues, such as agricultural land use and demographic and cultural trends that only a coherent
set of policy measures will work. Obviously, policy recommendations must be made on a
case-by case basis; however, some generalized approaches can be suggested. Transportation
policy strategies should consist of Socio-economic, institutional, technological, information
and land-use reforms. A balanced strategy should set standards that can be used to achieve
full-cost recovery, inform consumers, provide options for them and integrate social and urban
planning.
Conclusions
It is understood from the above discussed report that not one, but several aspects of the
Ecological Regulations of the country have been violated in the proceedings of this project.
The project as is planned will only seek to eliminate the issue of vehicular pollution and
Movement of Vehicles especially in the Worli-Haji Ali Area which is already severely
congested due to lack of space.
The most annoying part of the project is that in depth research using current data have not
been used to estimate the Ecological Effect of the project on the site’s coastline, mangrove
forests and marine ecology, which till date remains a major flaw in the plan.
Lastly as there has been no survey started to elicit how much the natives are willing to pay for
the use of the bridge it should not end up being another white Elephant to the State’s
exchequer.