Environmental Management System
Environmental Management System
Issue No: 1
Issue Date: May 2016
EMS1
CONTENTS
Distribution;
Operations Director
Quality Manager / System co-ordinator
Mill Manager
Transport Manager
Weighbridge control
Production
Engineers
Office File
1. INTRODUCTION
L J Fairburn & Son Ltd Environmental Management System (EMS) covers the manufacture of
compound animal feed. The objective of the system is to operate to the requirements of the
Environment Agency.
The system has been developed by L J Fairburn & Son Ltd.’s personnel who make up the
Environmental Management Team headed up by the Operations Director and assisted by A V
Consultants. The team developed the structure for the Company system. The implementation of the
system was then audited by A V Consultants.
2. SCOPE OF MANUAL
This Manual describes how L J Fairburn & Son Ltd.’s Environmental Management System is controlled
and documented. However it is closely connected with both the Company’s Quality and Health &
Safety Systems. There are areas common to all three systems. For instance Management
Responsibility, Document Control and Training are detailed and controlled within the Quality System;
Contractors are controlled within the Health & Safety System Manual.
L J Fairburn & Son Ltd.’s Environmental Management System currently covers the feed mill only. It
does not extend to our sales/marketing functions or other non-manufacturing operations or to our
customers or suppliers.
The key to the Environmental Management System is the aim for Continuous Improvement as shown
by the Environmental Management System Circle below
ENVIRONMENTAL
POLICY
MANAGEMENT
REVIEW OBJECTIVES
PREVENTATIVE
ACTION
MEASURE
CORRECTIVE
ACTION
ANALYSE
DATA
3. COMPANY PROFILE
Introduction
L J Fairburn & Son Ltd is a major quality egg producer and as part of the strict quality control
approach manufactures all the compound feed required for the laying hens some 80,000 tonnes per
annum.
The Company has a Compound Feed Mill (Huttoft mill) on the site at Huttoft incorporating the latest
feed milling technology. The Mill is strategically located near the centre of farming operations.
L J Fairburn & Son Ltd.’s success stems largely from supply of premium eggs into the UK market. L J
Fairburn & Son Ltd.’s policy is to provide premium feeds to service the company farms, that set the
standard for the industry in terms of nutritional effectiveness.
Organisation
4. MANAGEMENT ORGANISATION/RESPONSIBILITIES
4.1 Objectives
The Company Management organisation ensures that the responsibilities and authorities are clearly
defined within an effective structure. Overall control of the Environmental Management System is
the responsibility of the Operations Director.
4.2 Reference
Policy
Work Instructions
The system was developed using a top-down approach and compiled by the EMS Team:-
The system is held together by a set of System Procedures which ensure a common approach to the
system and which also inter-relate to those within the Company’s Quality and Health & Safety
systems.
These System Procedures are held within the folder ‘Environmental Management System’.
An explanation for the various procedures is given below. Where reference is made to the computer
system the folders are set up as per Appendix IV.
6. ENVIRONMENTAL POLICY
The signed, published policy is held within the Environmental Management System Manual folder
and is displayed on Company notice-boards and on the L J Fairburn & Son Ltd website.
MISSION STATEMENT
L J Fairburn & Son Ltd cares about the environment and is committed to protecting it. Our corporate
strategy is for all of our employees to do all that is practicable to achieve this.
OUR POLICY
Design, operate and maintain all of our operations in an environmentally responsible manner,
complying with all relevant legislation.
Provide adequate training and information to our staff, such that they able to comply with this
policy.
The Company’s Environmental Policy and its implementation is the direct responsibility of the
Operations Director of L J Fairburn & Son Ltd and it will be reviewed on a regular basis to
ensure its continuing relevance.
Environmental Management System Procedures are the procedures developed to implement and
control the Environmental Management System. They cover the following categories:
Environmental Aspects
Legislation
Objectives and Targets
Training
Communication
Documentation and Record Handling
Monitoring and Measurement
Non-Conformance
Audit
Management Review
All Environmental Management System procedures are held on the computer system. A register of
these is detailed in Appendix 1.
These are procedures needed to address the specific environmental aspects identified in the
environmental programme to ensure that activities on site are controlled and managed effectively
and to ensure consistency in operational matters.
The Environmental Policy, Aspects register and Register of Legislation alongside the requirements of
the Sites’ PPC Permits, were used to define the operational procedures required by L J Fairburn & Son
Ltd. These are described in Appendix II.
Company Procedures are held in the Operational Procedures folder within the Environmental
Management System on the computer system. The mill has its own procedures and work instructions
held in local files. Examples of these are held within the Generic Environmental Documents folder.
Template Forms – Templates for recording information arising from the various procedures are held in
a folder within the Generic Environmental Documents folder.
9. EXTERNAL DOCUMENTATION
In addition to internal procedures a folder is also maintained on the computer system which contains
Guidelines and Codes of Practice obtained from External Sources.
The site has been issued with PPC Permit which is held on the computer system and in hard copy.
Permit conditions are included in the Environmental Management System.
APPENDIX I
Procedure Name
EMS SP01 Environmental Aspects Evaluation
EMS SP02 Environmental Legislation
EMS SP03 Environmental Objectives, Targets and Management
Programs.
EMS SP04 Training
EMS SP05 Environmental Communication
EMS SP06 Documentation and Record Procedures
EMS SP07 Monitoring and Measurement
EMS SP08 Non Conformance
EMS SP09 Internal Environmental Audit
EMS SP10 Management Review
Document Name
Environmental Policy
CEAR Company Environmental Aspects Register
EROL Register of Legislation
CEOT Company Environmental Objectives and Targets
CETS Company Environmental Target Monitoring Summary
ETNA Environmental Training Needs Analysis Matrix
APPENDIX II
Environmental Operations Controlled within the EMS.
Operation Level Relevant Procedure Notes
(See Appendix III)
Monitoring of PPC Operations
Requirements Director
Bulk Liquid delivery, Production EMS OP01 Local Work Instructions
Storage and Handling Manager based on this procedure
Drains and Interceptors Production EMS OP02 Local Work Instructions
Manager based on this procedure
Waste Management Quality & EMS OP03 Local Work Instructions
Production based on this procedure
Manager
Bag Filter Operation & Production EMS OP04 Local Work Instructions
Maintenance Manager based on this procedure
Plant & Equipment L J Fairburn & EMS OP05 Local Work Instructions
Change Son Ltd Board based on this procedure
Contractor Control and Production EMS OP06 Local Work Instructions
Training Manager based on this procedure and
Co. Health & Safety Manual
Purchasing – Operations EMS OP07
consideration of Director
environmental issues
Planned Preventative Production EMS OP08 Local Work Instructions
Maintenance Manager based on this procedure
Cooler Abatement Production EMS OP09 Local Work Instructions
Operation & Maintenance Manager based on this procedure
Potential Environmental Operations EMS OP10 Local Work Instructions
Nuisance Director based on this procedure
Ozone Depletors Quality EMS OP11 Local Work Instructions
Manager based on this procedure
Vehicle Movements on Transport & Work Transport Policy Co
Site Production Health & Safety Manual
Manager
Raw and ancillary Material Production Local Work Instructions
delivery, storage and Manager
handling
Emergency Procedure i.e. EMS Team EMS OP12 Contained within Site
- Spillage/Leakage of Emergency Plan and also
Oil/Chemicals. local Work Instructions and
- Failure of abatement Company Health & Safety
equipment. Manual
- Fire
Environmental Emissions Operations EMS OP13
Monitoring Director
APPENDIX III
Form Name
EECF External Environmental Communication/Complaint Form
NCIR Non-conformance & Incident Report Form
APPENDIX IV
Environmental Management
System
System Generic Env Systems Operational External Objectives & Register of MCERTS
Procedures Environmental Manual Procedures Environmental Targets Legislation Monitoring
Waste Documents Documents
DISTRIBUTION
S Hall Operations
Weighbridge
Director control
Quality Manager/ System
co-ordinator
R Clark Mill Manager
Transport Manager
Weighbridge
Control room
Office File
Workshop
Works Canteen
The proposed environmental management system for use by L J Fairburn & Son Ltd
Huttoft Mill installation will be brought into during the determination period of this Part
A Permit application. The EMS is bespoke and independently monitored.
2. Monitoring forms
3. Work instructions
4. System procedures
5. Operational procedures
6. Aspects register
7. Audits
8. Training
9. External documents
EQUIPMENT CHECKS Wk 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Daily Checks Bag Check for leaks, burst
filters bags
Monday
Tuesday
Wednesday
Thursday
Friday
EQUIPMENT CHECKS 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Daily Checks Bag Check for leaks, burst
filters bags
Monday
Tuesday
Wednesday
Thursday
Friday
Week Commencing
Date Time Test Location Intensity Extent Sensitivity Offensiveness Comments Weather Conditions Noise Signed
(0-5) (0-5) (0-5) (0-4) (Internal or external sources) Wind speed/direction etc. (Internal or external sources)
Beyond site perimeter test - Taken from _____________________ Date __________Time ____________ Result ________________________________________
Additional Comments
L J Fairburn & Son Ltd Environmental Management System
ENVIRONMENTAL EXTERNAL COMMUNICATION / COMPLAINT FORM (EECF)
Version No: 1 Issued Date: 30 May 2016 Issued By: Operations Director
Name:
Address:
Contact e-mail:
Brief description of
comment / complaint
Does the complaint / communication impact on our PPC Permit Conditions? Yes No
Follow-up
or
Corrective Action Plan
(as applicable):
Note: For all Complaints a copy must be sent to the Operations Director
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
NON-CONFORMANCE AND INCIDENT REPORTING FORM (NCIR)
Version No: 1 Issue Date: 30 May 2016 Issued By: Operations Director
Report Number:
Date and Time
of Non-conformance/Incident:
Description/Nature of Non-conformance/Incident:
Effects:
Copy To: Operations Director Ref EMS Procedures: SP05 and SP08
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System SEKPI
Site
Units Target Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec YTD
Manufacture Tonnes 0.0
Electricity KWH 0.0
Primary Energy KWH/tonne #DIV/0!
Waste - General Tonnes 200301 0.0
Waste - Special Tonnes 200132 0.0
Waste - Vegetable Oil Tonnes 020304 0.0
Waste - Oil & Lubricants Tonnes 130208 0.0
Waste - Metal Tonnes 200140 0.0
Waste - Light Bulbs Kgs 200121 0.0
Reworks Generation % of NSM Max 2% #DIV/0!
Water Usage - Mixers Tonnes 0.0
Water Usage - Domestic Tonnes 0.0
Water - TOTAL Tonnes 0.0
Environmental Complaints Number 0.0
Environmental Accidents Number 0.0
Water Discharge Samples Number 1/Quarter 0.0
EMS Meetings Number 3/Annum 0.0
SEKPI V1
WORK INSTRUCTION W.I. EMS 1
FATS DELIVERIES
The following checks should be carried out on Tanks, Bunds and Pipe-
work each month to ensure that they are not damaged or filled with
rain water or contaminants.
Bunds
Inspect contents of bund.
Any fats pumped from the bund into an IBC it must be carefully
inspected to ensure it is not contaminated.
Check the condition of the bund walls. Look for signs of cracking,
damage or seepage. Report any adverse findings to the Mill
Manager or Quality Manager.
Dry raw material spillages are a potential environmental pollutant. Care should be
taken to minimise this risk and as such the following instructions are to be
observed.
The Production Operative should follow the UFAS raw material intake procedure
namely:-
The valve on the pipe between the tank and the pump must be
locked shut whilst not in use.
WASTE DISPOSAL
There are several types of waste generated on site and care must be taken to
ensure waste is classified into the correct containers for disposal or recycling to
reduce the environmental impact. Waste storage receptacles are appropriately
marked by category.
Weekly checks of the waste storage receptacles are conducted by the Mill Manager
to ensure the area is tidy and no leakages are occurring.
o Premixes
o Oily rags and soiled spill kits or absorbent granules used for oil and
lubricants
o Any part filled tins of paint for disposal
o Waste Oil and Lubricants – collected for recycling
NUISANCES
The site has potential to produce environmental nuisances; odour, dust and noise
which can affect people and their property outside the site boundary.
An investigation must take place to identify any problems and carry out
corrective actions to eliminate the cause of the nuisance.
All concrete and tarmac roadways and storage areas are to be checked annually to
ensure that they are impervious to liquids and not damaged.
The check should identify any areas which are cracked or sunk and which will
result in liquids including rainwater permeating into ground.
This includes ensuring that sealed construction joints on concrete areas are
sound.
The location of the damage requiring repair action should be noted on a copy
of the site plan (see work transport site plan) in order to assist if others have
to carry out the follow up measures.
In the event that areas are found to be porous, a repair schedule will be
implemented.
Assess that there is space in the vehicle compartment to accept the load and
ensure that the discharge spout to set to centre of compartment to be filled
INTRODUCTION
This procedure describes how L J Fairburn & Son Ltd environmental aspects are defined and evaluated for
significance/priority.
DEFINITIONS
Environmental Aspect
Element of an organisation's activities or products or services that can interact with the environment.
Environmental Impact
Any change to the environment, whether adverse or beneficial, wholly or partially resulting from an
organisation's environmental aspects.
REFERENCES
Company Environmental Aspects Register - held on computer system.
RESPONSIBILITIES
The EMS Team is responsible for completing and updating the Environmental Aspects Register.
ASPECTS METHODOLOGY
The methodology used to determine the significance of L J Fairburn & Son Ltd environmental aspects is
set out in the Environmental Aspects Prioritisation Methodology sheet within the Aspects Register.
In defining the company’s environmental aspects, all Company activities, products and services will be considered
with regard to:
Page 1 of 5
L J Fairburn & Son Ltd Environmental Management System
Past activities, current activities and planned activities – most activities entered in the register will be associated
with current Operations, but the register should also contain environmental impacts connected to planned future
activities and also past activities conducted on site which had the potential to cause contamination of the land.
Each of the following columns within the Aspects Register must be completed:
Reference number
Environmental aspect
Environmental impact
Operating level
Consequence rating of the event
Likelihood rating of the event
SIGNIFICANCE/PRIORITY OF ASPECTS
Aspects are assessed for significance by determining the priority rating as outlined in the Environmental Aspects
Prioritisation Methodology (See overleaf)
Page 2 of 5
L J Fairburn & Son Ltd Environmental Management System
Consequence (Consequence rating of the event): This scores the environmental impact according to the
severity of its effect on the environment. It is possible to assign a 'negative' score to those impacts that are
beneficial to the environment. This is the sites' relative contribution to the overall environmental impact.
Score Consequence Description of Environmental Consequences
Positive environmental improvement, reduced environmental impact
-1 Positive Good for public relations
Proactive use of renewable/sustainable resources.
Noticeable impact on-site only;
No outside complaints;
1 Minor
Small-scale use of renewable resources; and
Negligible environmental damage
Small potential for local adverse publicity;
Minor breach of emission limits, but no environmental harm;
Noticeable but low impact off-site e.g. discernable odours; and
2 Noticeable Low impact on global issues (e.g. ozone depleting substances); and
Small-scale use of non-renewable resources (e.g. oil-based);
Moderate use of renewable resources (e.g. timber-based)
Loss up to £100 and only small likelihood of complaints.
Noticeable environmental impact limited to a small area;
Losses between £100 and £1,000 and complaints possible, litigation
possible;
Moderate use of non-renewable resources or large-scale use of other
3 Significant resources;
Large-scale use of renewable resources;
Severe and sustained nuisance, numerous complaints, e.g. strong
odours / noise disturbance; and
Minor breach of permitted emission limits.
Moderate environmental impact within and outside the facility but no
lasting environmental damage;
Potential for adverse publicity;
4 Severe Losses between £1,000-£10,000 and complaints and litigation possible;
Hazardous substances releases with 1/2 mile effect;
Major breach of emission limits
Large scale use of non-renewable resources.
Damage to land beyond the facility boundary, reversible;
Local media interest, careful public relations required;
5 Major
Losses between £10,000-£50,000 and litigation expected; and
Serious toxic effect on beneficial or protected species in the area.
Severe widespread environmental damage, irreversible;
National media interest and adverse publicity;
6 Catastrophic
Loss of over £50,000 and litigation certain; and
Possible Site Shutdown.
Page 3 of 5
L J Fairburn & Son Ltd Environmental Management System
The overall priority score is calculated by multiplying the consequence score with the likelihood score, this priority
score is then assigned a colour coding based on the following matrix which denotes the significance.
Likelihood Consequence
-1 1 2 3 4 5 6
Positive Minor Noticeable Significant Severe Major Catastrophic
1 - Extremely unlikely -1 1 2 3 4 5 6
2 - Very unlikely -2 2 4 6 8 10 12
3 - Unlikely -3 3 6 9 12 15 18
4 - Somewhat unlikely -4 4 8 12 16 20 24
5 - Fairly probable -5 5 10 15 20 25 30
6 - Probable -6 6 12 18 24 30 36
7 - Frequent -7 7 14 21 28 35 42
8 - Very frequent -8 8 16 24 32 40 48
9 - Almost certain -9 9 18 27 36 45 54
ASPECTS REGISTER
The Aspects Register includes a description of all impacts that L J Fairburn & Son Ltd activities, products and
services may have on the environment. It also includes a note of the significance, based on the colour coding
system, of each aspect, taking into account the legislative or regulatory situation.
The Register includes a cross-reference to relevant legislation and other requirements, associated objectives and
targets and also operational control procedures for significant aspects.
The Register will be reviewed annually by the EMS Team. Once the review is completed the date of revision
and revision number will be updated on the Register, the previous version will be retained for record purposes
and the updated version will be incorporated into the EMS.
Page 4 of 5
L J Fairburn & Son Ltd Environmental Management System
The environmental impacts of any changes (actual or proposed) in our activities or areas of Operations will be
considered by the EMS Team and added to the Register if not already included, or removed if no longer
relevant.
Similarly, any changes in legislation, regulations or codes of practice (which might affect the significance of any
aspect) will also be considered. If there are any such changes to the Aspects Register, then the Operations Director
will bring them to the attention of the EMS Team at the next management review meeting.
Page 5 of 5
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd develops and maintains its Environmental
Register of Legislation (EROL). The purpose of the register is to identify environmental legislation and other
requirements applicable to the environmental aspects and associated impacts of L J Fairburn & Son Ltd activities,
products and services.
All procedures, documentation etc. referred to within this procedure are held on the computer system.
REFERENCES
Environmental Register of Legislation (EROL)
RESPONSIBILITIES
The EMS Team is responsible for completing, updating and communicating the Environmental Register of
Legislation.
All staff are responsible for ensuring their activities are in compliance with legal and other requirements.
THE REGISTER
The Register includes a brief description of all environmental legislation which has a bearing on L J Fairburn & Son
Ltd activities and the ways in which these may have an effect on the environment. It includes a note of all Laws,
Acts, Regulations, Statutory Instruments, Approved Codes of Practice and Guidance Notes as may be issued by
the various governmental bodies in the UK. It also includes any non-regulatory environmental requirements such as
Trade Association Codes of Practice and any customer environmental requirements.
Changes to the Register will be reviewed by the Operations Director to identify the need to modify EMS
documentation (e.g. Environmental Aspects Register, objectives & targets, procedures, training materials etc) to
ensure the EMS reflects legal compliance requirements.
Evaluation of compliance with relevant legislation, regulations and other requirements is achieved via the internal
environmental audit process. This evaluation is recorded via the Internal Environmental Audit Report. See EMS
SP09
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This document describes the procedure for establishing objectives and targets for continual improvement of the
environmental performance of L J Fairburn & Son Ltd operations.
All procedures, documentation etc. referred to within this procedure are held in the Environmental Management
System Folder on the computer system.
DEFINITIONS
Environmental Objective
An overall environmental goal, consistent with the environmental policy, that an organisation sets itself to
achieve.
Environmental Target
A detailed performance requirement, applicable to the organisations, or parts thereof, that arises from the
environmental objectives and that needs to be set and met in order to achieve those objectives.
REFERENCES
RESPONSIBILITIES
EMS Team: responsible for establishing Company objectives and targets, monitoring progress and determining
the schedule of the Management Programme.
PROCEDURE
Setting the Company Objectives
In identifying objectives, the EMS Team will consider:
Legislative requirements as indicated in the L J Fairburn & Son Ltd Environmental Register of Legislation
(EROL).
The views of any interested parties.
The corporate goals of the company.
The need to minimise environmental risk and liability.
Evolution of the Environmental Policy.
Significant/priority aspects that occur across all areas of the business.
Results of internal and external audits.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
Management Review
All objectives and targets are reviewed at the annual Company Management Review. The review will determine the
Environmental Objectives and Targets for the next 12 month period.
If timescales are not being met - or actions are not progressing - the EMS team will review the reasons and
reschedule the completion date, committing additional resources as necessary.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This document describes the procedure for the identification of training needs and effective training of all persons
working on or behalf of L J Fairburn & Son Ltd whose work may create an actual or potential significant impact on
the environment.
All procedures, documentation etc. referred to within this procedure are held in the Environmental System
Folder on the computer system.
REFERENCES
Environmental Training Needs Analysis Matrix (ETNA)
General Environmental Awareness Powerpoint Presentation
Training Records – held locally
RESPONSIBILITIES
L J Fairburn & Son Ltd requires that all persons working on or behalf of the organisation, whose work may create
an actual or potential significant impact upon the environment, receive appropriate training. L J Fairburn & Son
Ltd shall ensure that personnel performing tasks which can cause an actual or potential significant
environmental impact are competent on the basis of appropriate education, training and/or experience. A
competency evaluation of all persons working for or on behalf of L J Fairburn & Son Ltd and therefore requiring
training will be highlighted through completing a training needs analysis.
PROCEDURE
The EMS Team has carried out a training needs analysis to identify training needs and completed a Company
Environmental Training Needs Analysis Matrix. This will be reviewed and updated on an annual basis as part of
the Management Review. Updates to the matrix may arise from incidents, environmental improvement
programmes, personnel changes and requirements for refresher training.
The Site EMS Team will review and update their local Training Needs Analysis Matrix on an annual basis.
Updates to the matrix may arise from updates to the Company Environmental Training Needs Analysis Matrix or
local incidents, environmental improvement programmes, personnel changes and/or requirements for refresher
training.
All personnel will receive general environmental awareness training using the General Environmental
Awareness Powerpoint presentation. The training package will communicate the following:
The importance of conforming with the environmental policy and procedures and to the requirements of the
EMS.
The significant environmental aspects of their work activities and the environmental benefits of improved
personal performance.
Roles and responsibilities in achieving conformance with the environmental policy and procedures and with
the requirements of the EMS, including emergency preparedness and response requirements.
An understanding of the regulatory requirements associated with each site’s IPPC permit and how they
affect their work and responsibilities.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
It is the responsibility of the EMS Team to ensure all personnel receive the general environmental awareness
training.
Where the training needs analysis identifies further training is required in order for employees to be competent
in their roles in regards to the EMS, this will be undertaken. It is the responsibility of the Mill Manager to ensure
all training that is identified is carried out.
All training records of the environmental training are kept in the relevant training files.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes how L J Fairburn & Son Ltd manages internal and external communication regarding
the EMS. The levels of communication include internal communication to various levels within L J Fairburn &
Son Ltd and communication to and from 3rd parties.
All procedures, documentation etc. referred to within this procedure are held in the Environmental Management
System Folder on the computer system.
REFERENCES
NCIR - Non-conformance and Incident Report Form
EECF - External Communication or Complaint Form
EMS SP08 - Non–conformance, Corrective and Preventive Action Procedure
RESPONSIBILITIES
rd
The Operations Director is responsible for internal communication within L J Fairburn & Son Ltd, and to 3
parties from the company. External communications on environmental issues received by the Operations
Director or by Mill Manager will be recorded.
PROCEDURE
Internal communication
Issues will be communicated by the Operations Director via e-mail.
Site issues will be communicated by the Mill Manager via:
External communication
L J Fairburn & Son Ltd has to communicate externally e.g. with regulatory bodies to comply with legal
requirements and to report environmental incidents on site. Communication is also received from external
sources; this may be a complaint or a general enquiry.
The following mechanisms are used to manage external communications regarding the EMS:
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
L J Fairburn & Son Ltd does not communicate its Significant Aspects externally.
All such communications will be reviewed at the Site EMS Management Review meeting.
Where notification of abnormal emissions to the Environmental Agency is required as per Section 5 of the Site
PPC permit, the notification must be made using Schedule 1 of the Site Permit.
All communications on environmental matters to & from Regulatory bodies must be kept on file.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the methods used to control the following documentation within the L J Fairburn & Son
Ltd Environmental System (EMS).
Environmental Manual
Environmental Procedures
Environmental Forms
Records
RESPONSIBILITIES
The Operations Director in conjunction with the Quality Manager is responsible for placing the latest versions of
environmental documents on the computer system, and for recording amendments and identifying as “obsolete”
any of these superseded documents.
CONTROL OF RECORDS
Records include:
All completed Forms
Registers and Logs.
Records should be maintained in such a way that they are readily identifiable, retrievable and secure.
EMS Records
The table below shows specific records that have been identified as part of the EMS, and who is responsible for
their maintenance and disposal.
* Note – the retention time for records is as per the IPPC permits.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes L J Fairburn & Son Ltd processes for monitoring and measurement for the activities,
products and services that can have a significant impact on the environment. All procedures, documentation etc.
referred to within this procedure are held in the Environmental Management System Folder.
REFERENCES
Environmental Aspects Register
Environmental Legislation Register Procedure (EMS SP02)
Environmental Objectives and Targets Procedure (EMS SP03)
PPC permit requirements – permit held on Site
Site Environmental KPI Sheet (SEKPI) – part of Site General KPI sheet held under Site KPIs.
Environmental KPI Sheet (EKPI)
RESPONSIBILITIES
The EMS Team is responsible for ensuring monitoring and measurement systems are in place.
Mill Manager has responsibility for specific monitoring and measuring systems on Site, and for updating the Site
KPI sheets.
PROCEDURE
L J Fairburn & Son Ltd will periodically evaluate its compliance with legal and other requirements which includes
IPPC permit conditions, checks against applicable legislation, checks against other requirements such as UFAS
requirements and compliance with environmental operational controls. Minor problems regarding compliance
shall be dealt with via the site EMS Team meetings, management and shift meetings
L J Fairburn & Son Ltd will periodically assess its progress in meeting its Environmental Objectives and Targets,
through the site EMS Team meetings and EMS Internal audits. The need to review and revise Environmental
Objectives and Targets shall be considered when changes occur to the Register of Environmental Aspects.
L J Fairburn & Son Ltd will periodically monitor environmental data in relation to the identified significant
environmental aspects. Environmental data identified to monitor the environmental performance is recorded via
the Site’s Environmental KPI sheet and includes:
Rework Generation
Water usage
Procedures for monitoring and collecting data on each of the issues are held on site. These procedures are
reviewed in line with monitoring and measurement requirements of the Site IPPC Permit.
It is a condition of the Permit for some sites that other environmental measurements are undertaken on a
regular basis – refer to site Permit.
The KPI sheet (EKPI) is maintained by the Quality Manager, the data being pulled through from the Site KPI
sheets in order to monitor trends.
The performance information will be periodically assessed in the site EMS Team meeting.
Where monitoring equipment is used in relation to the collection of environmental performance information or
the control of environmental impacts, this equipment is maintained and calibrated in line with Site calibration
procedures. Details of environmental monitoring equipment to be calibrated are held in the Site Calibration
Register held by the Mill Manager.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the steps that L J Fairburn & Son Ltd takes to identify and correct actual non-
conformities, as well as potential causes of non-conformity.
All procedures, documentation etc. referred to within this procedure are held on the Server unless stated
otherwise.
DEFINITIONS
Non-Conformity
A situation which does not comply with the requirements of one or more of the following:
The Environmental Policy
An EMS Procedure
Relevant legislation (including the requirement of the Site PPC permit)
Incident
An event which does not conform to normal operational circumstances or conditions.
Complaint
Any expression of dissatisfaction by a customer, member of the public, or other third party whether justified or
not.
Corrective Action
Action taken in the short term to eliminate the cause of a non-conformity and prevent reoccurrence.
Preventative Action
Action taken in the medium to long term to eliminate the cause of a non-conformity and prevent reoccurrence.
REFERENCES
Non-Conformance and Incident Report (NCIR)
Environmental Communication (EMS SP05)
Internal Audit Procedure (EMS SP09)
Site Emergency Action Plan – held at each Site
RESPONSIBILITIES
All staff are responsible for reporting non-conformities and incidents whether they arise through internal audits,
internal or external communication or day to day activities.
The EMS team are responsible for reviewing the non-conformance information, implementing any changes to
the Environmental Management System and checking the corrective action has been completed.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
PROCEDURE
Non-conformities and incidents may be identified and reported by any company employee, internal audit,
contractor, regulatory authority or member of the public.
The appropriate information will be entered on the Non-Conformance and Incident Report Form and submitted to
the Production Manager who will update and copy to the Managing Director.
Where notification of abnormal emissions to the Environment Agency is required as per Section 5 of the Site
PPC permit, the notification must be made by the Production Manager, or nominated deputy, using Schedule 1
of the Site Permit.
All incidences are reviewed at the EMS meetings and any changes required to the EMS system to prevent or limit
recurrence are recorded.
The EMS Team also reviews incidence reports at the Management Review Meetings to identify:
Areas where incidents/non-conformities occur most frequently.
Any changes to the Environmental Management System which may be required to prevent or limit
recurrence.
Preventative Action is based on the premise that the Environmental Management System is preventative in
nature, by causing us to:
These steps help to prevent problems from occurring. However, the pro-active identification of potential non-
conformities and implementation of preventative actions is part of the Management Review process.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the company’s processes for monitoring and evaluating internal compliance with the L
J Fairburn & Son Ltd Environmental Management System, and for identifying areas for potential improvements.
All procedures, documentation etc. referred to within this procedure are held in the Environmental Management
System Folder on the computer system.
REFERENCES
Environmental Audit Pack
Non-conformance and Incident Report Form - NCIR
Environmental Aspects Register - CEAR
Register of Legislation - EROL
RESPONSIBILITIES
The Quality Manager is responsible for planning the audit programme.
The EMS team are responsible for reviewing the audit reports and any non-conformances and making any
changes to the EMS as a result of these via the Management Review (EMS).
Environmental Auditors are responsible for conducting the internal audit and raising any non-conformances.
PROCEDURE
Scope
The audit programme will ensure that all areas of the EMS at the Mill are audited at least twice per year and is
based on the importance of an issue considering the significant aspects, incidents and non-conformities and
audit results.
Planning
When planning an audit, the auditor shall note the following as a minimum:
Any relevant aspect listed on the Environmental Aspects Register so that the significance may be
reviewed.
Compliance with relevant legal, regulatory or other requirements listed in the Register of Legislation.
Those relevant procedures pertinent to the area/activity being audited are still appropriate and are being
followed.
Progress towards appropriate objectives and targets as stated in the Environmental Management System
Programme.
All incidents, non-conformities and corrective actions which have arisen since last internal audit (including
non-conformities raised at the last internal environmental audit).
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
Audit Process
The auditor will undertake the audit through interview, sampling and process area walkover, determining the
degree of compliance to the EMS, and noting any non-conformances. The auditor will use the audit checklist
held in the Auditors pack to aid the process.
Audit findings will be recorded on the Environmental Checklist and the Environmental Internal Audit Report
where additional comments are required. If non-conformances are identified, it is the responsibility of the
auditee to determine a corrective action plan and to ensure it is communicated and implemented appropriately
within an appropriate timescale.
Distribution of Reports *
The completed Internal Environmental Audit Report will be sent to the Operations Director and Quality Manager
as well as the auditee. The Quality Manager then files the report.
Review
The EMS Team will review and analyse audit findings and report within the Management Review.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes L J Fairburn & Son Ltd processes for the Management Review of the Environmental
Management System.
RESPONSIBILITIES
The Operations Director is responsible for ensuring that the EMS is reviewed at planned intervals at least
annually to ensure its continuing suitability, adequacy and effectiveness. The Mill Manager is responsible for
ensuring that Site EMS meetings are held quarterly.
PROCEDURE
EMS Meetings are held quarterly – the agenda for these is held on the computer system.
Minutes of these meetings (including observations, conclusions and agreed actions) are maintained.
Minutes of the Site EMS Review Meetings are copied to the Operations Director.
Audit results.
Evaluations of compliance with legal requirements and other requirements to which the organisation
subscribes.
Measurements of performance against EMS objectives.
Status of preventive and corrective actions.
Actions from previous management reviews.
Incident / non-conformity reports and external communication / complaint reports.
Environmental KPIs via Site Environmental KPI recording.
The review considers:
The continuing suitability of the EMS in relation to changing conditions and information.
The concerns of relevant interested parties.
Whether any changes need to be made to the Environmental Policy.
Whether any changes need to be made to the management system as a result of corrective actions.
The relevance of Environmental Aspects as recorded in the Aspects Register.
Legislation status and any new or impending legislation or regulatory requirements which may have a
bearing on Company activities.
The extent to which objectives and targets are being met.
The Environmental Programme for the period until the next Management Review.
Review of the procedures.
Whether or not the EMS is delivering the required improvement in environmental performance.
Recommendations for improvement.
The EMS Team will make changes to the EMS or initiate actions it deems necessary and communicate changes
to the appropriate parties. This will ensure that the system continues to deliver continual environmental
improvement.
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd manages bulk liquid storage and delivery in
such a way as to prevent spillages and leaks. The main objective of this procedure is to ensure that no liquid is
released to surface water, groundwater or to land. Bulk liquids includes; Vegetable oils and Red diesel.
REFERENCES
This Procedure is implemented by Mill Procedures & Work Instructions.
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The Mill
Manager is responsible for its implementation on site.
HAZARDS
These liquids have a very high potential to pollute land or water. Even small quantities can pollute large volumes of
water and can be difficult and expensive to clear up. Oil can also contaminate land and could result in expensive
remediation/cleanup costs being incurred.
ACTIONS
These will be identified by Work Instructions held on site which will incorporate the following points.
1. All bulk liquid storage tanks must meet the requirements of the Control of Pollution (Oil Storage) (England)
Regulations 2001. Further details are contained in the Register of Legislation (Legislation Register) and
Pollution Prevention Guidelines 02 and 26 held on the computer system.
2. Tanks, bunds and pipework are to be checked monthly to ensure that they are not damaged in any way and
that they are not leaking. Refer also to the section in this procedure for waste oil tanks and for bund water
removal.
1. All deliveries should be supervised wherever possible, in particular where a new contractor is making a
delivery or where an incident has occurred in the past.
2. The date and time for delivery should be booked when there will be a responsible person available to
supervise the delivery and contractors should be informed that they should ask for the relevant person
responsible when they arrive on site.
3. The delivery note provided by the delivery contractor must be checked to ensure it covers the correct
amount ordered.
Page 1 of 3
L J Fairburn & Son Ltd Environmental Management System
4. The delivery contractor will be taken to the correct fill point. Prior to filling, check that the tank(s) have
sufficient spare capacity for the delivery and record the amount already in the tank.
5. Prior to filling, check that the contents of the spill kit are present and that the kit is near to hand.
6. If the fill pipe is outside of the bund, then a drip tray must be placed under the fill point prior to coupling of
the fill pipe.
7. If the tanker driver is unable to see the fill gauge during filling, ensure that the fill gauge will be monitored on
their behalf.
8. Tanker hoses and associated couplings should be checked for leaks during delivery, if any leaks are
detected delivery must stop immediately.
9. In case of spillage all persons following this procedure must refer to the Site Emergency Plan and/or Spill
Procedure.
10. The fill gauge and the amount delivered should be as detailed on delivery note.
6. Before collection, check that the contents of the spill kit are present and that the kit is near to hand.
7. During collection use a drip tray if you think there is a possibility of spillage and cease pumping if any leaks
occur. In the event of a spillage follow the Site Emergency Plan and/or Spill Procedure
8. Ensure a waste transfer note is obtained for the oil which details the correct quantity removed. This note should
then be filed and retained for 3 years. See the Waste Management Procedure EMS OP3.
9. Disposal of bund water
1. All bunded areas are inspected on a weekly basis or more frequently in periods of heavy rain.
2. Where bunded areas are found to contain liquid, then the liquid must be removed as detailed below.
3. If chemical, oil or fuel spillages or residues are found within the bund, or should there be an accumulation of
rainwater in the bund this should be recorded and the appropriate corrective action taken.
4. If the liquid within the bund is an accumulation of uncontaminated rainwater then a manually controlled
positive lift pump should be used to transfer it into suitable storage containers. These containers can then
be drained to a foul drain or surface water via an interceptor. Refer to Drainage and Interceptor Procedure
EMS OP02.
Page 2 of 3
L J Fairburn & Son Ltd Environmental Management System
5. In the event that the spillage within the bund is found to be from oil, chemical or fuel, then a suitably
licensed hazardous waste disposal contractor should be contacted to organise disposal of the bund water in
accordance with Waste Management legislation See the Waste Management Procedure EMS OP3.
6. A waste transfer note should be obtained, filed and kept for 3 years.
7. In the event of other sources of contamination in the bund such as litter and solid debris this can be
removed and disposed of in general waste unless the debris is classified as special/hazardous waste.
Documentation
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation (Legislation
Register) held on the computer system.
CIRIA/Environment Agency Joint Guidelines – Concrete Bunds for Oil Storage Tanks
CIRIA/Environment Agency Joint Guidelines – Masonry Bunds for Oil Storage Tanks
Page 3 of 3
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd will maintain site drainage system in such a
way as to prevent the:
REFERENCES
This is a Procedure which is implemented by local Site Procedures & Work Instructions
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The Mill
Manager is responsible for its implementation on site.
HAZARDS
The discharge of any substance other than clean rainwater to surface waters is against the law.
It is also unlawful to discharge effluent (e.g. vehicle washing) to foul sewer without a consent from the relevant water
authority. If you are in any doubt as to whether you need consent then contact your water authority to discuss.
Damaged drainage or interceptors can lead to the leakage of effluent into the ground. This could lead to
contamination of soils and pollutants may migrate through the soil to pollute groundwater.
ACTIONS
These will be identified by Work Instructions held on site which will incorporate the following points.
Site Drainage
1. The Mill Manager will ensure that a site drainage plan is available for the site and that it is up to date. Oil
interceptors and outfalls to surface water are marked on this plan.
2. Drain gullies and manholes should be colour-coded on site to enable easy identification of surface (blue)
and which are foul (red) drains
3. As a minimum, annual checks of the surface water drainage system must be carried out. This will be done
by inspecting at the point closest to where the surface water drain leaves the site or the final outfall to
surface waters during a period of rainfall. Checks will be conducted to see if water is passing through the
sewer or is coming out of the outfall (if not then the drainage system maybe leaking or blocked) and that the
water appears to be free from pollution. Any issues must be reported to the Quality & Mill Manager. If the
water appears to be contaminated they must contact the Environment Agency.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
4. As a minimum, annual checks of the foul sewer drainage systems must be carried out. This will be done by
inspecting at the point closest to where the sewer leaves the site. Checks will be conducted to see that
effluent is passing through the drain (if not then the drainage system maybe leaking or blocked). Any
suspected leakage or damage must be reported to the Quality & Mill Manager.
1. Access to interceptors must be clear at all times and should be checked regularly to ensure nothing is
obstructing access.
2. All interceptors will be checked at least every six months to see if they need emptying or repair.
3. If the interceptor is full and needs emptying then a suitably licensed waste contractor will be used. A copy
of their licence will be obtained and kept on file.
4. When the interceptor is emptied a waste transfer note is obtained and retained for 3 years as interceptor
waste is classified as special/hazardous waste. See operational procedure relating to waste management –
EMS OP03.
Documentation
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation (Legislation
Register) held on the computer system.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd will store and dispose of its waste in
accordance with UK waste management legislation. It relates to the handling and disposal of all waste arising at
L J Fairburn & Son Ltd mill.
It sets out how waste is identified, how it is stored and handled and how it is disposed of so as to reduce both
environmental and health and safety risks associated with these activities.
REFERENCES
This Procedure is implemented by local Site Procedures & Work Instructions.
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The Mill
Manager is responsible for its implementation on site.
HAZARDS
Under UK legislation any business that produces, imports, carries, keeps, treats or disposes of controlled
wastes must:
DEFINITIONS *
WASTE
Waste is any object or substance that L J Fairburn & Son Ltd discard, irrespective of its toxicity or quantity.
Waste may represent a risk to personnel, external parties or the environment through its:
Toxicity.
Quantity.
Page 1 of 6
L J Fairburn & Son Ltd Environmental Management System
HAZARDOUS WASTE
Hazardous waste is those wastes which are considered hazardous to people and the environment through their
physical and chemical properties i.e. any material which is toxic, corrosive, harmful, irritant, flammable,
carcinogenic or mutagenic. This includes but is not limited to:
Degreasers, paints and solvents (but not empty containers of these materials)
Batteries
The WEEE Regulations apply to electrical and electronic equipment (EEE) in the following categories with a
voltage of up to 1000 volts AC or up to 1500 volts DC.
Automatic dispensers,
Electrical and electronic tools other than those permanently fixed at a given place in industrial machinery
or an industrial location.
GENERAL WASTE
All other waste, e.g. packaging, office waste, waste product and obsolete equipment not included in the above
categories.
Note: If there is any doubt as to how a particular waste should be categorised – this should be discussed with
A V Consultants.
Mill Manager should list the different types of waste on site detailing responsibility and method of
disposal. Every opportunity should be taken to recycle or recover waste to minimise the effect on the
environment.
Page 2 of 6
L J Fairburn & Son Ltd Environmental Management System
2. Evidence of these checks is to be recorded. The Mill Manager is responsible for taking actions arising from
any issues found.
3. Waste storage receptacles (skips, bins etc.) should be checked regularly to ensure they are secure and will
prevent leakage, damage or escape through any means.
4. All waste receptacles are to be clearly labelled to enable easy identification of the waste and its main
hazards should leakage or containment breach occur.
5. Waste chemicals and other hazardous material are to be stored in a marked storage receptacle in a
specified area.
General waste
1. Solid general waste must be stored within specified containers and their location marked.
2. Waste streams should be categorised and receptacles clearly marked and appropriate instructions issued.
3. Waste drums, containers and pallets of waste material are not to be stocked higher than 2 metres to reduce
risk of accident by falling objects and incorrect handling.
4. The site should be checked for any litter and where this is found it is to be removed and put in the
appropriate bin.
Hazardous Waste
1. All hazardous wastes types are to be listed and the receptacles they are to be stored in, identified. The
method of disposal should also be identified, including the details of the person(s) responsible for arranging
disposal.
2. Hazardous waste must not be mixed with general waste. Mixed loads of general and hazardous waste will
be categorised as hazardous.
Page 3 of 6
L J Fairburn & Son Ltd Environmental Management System
2. All WEEE must be stored, recycled and disposed of separately from other waste.
3. WEEE can be returned free of charge if it was sold after 13.08.2005 and/or it is being replaced with new
equivalent EEE. In this case the EEE supplier should be contacted for details of the relevant compliance
scheme.
a. It was purchased before 13.08.2005 and is not being replaced by equivalent EEE.
c. New EEE is purchased and it is decided through negotiation with the producer to accept the future costs
of treating and disposing of it.
CONTRACTORS
1. The Mill Manager is responsible for ensuring that contractors are aware of site emergency procedures,
waste disposal arrangements and the location of spill kits and first aid points. Any incident or near miss
involving a contractor should be reported to the Mill Manager as laid down in the Site Emergency
Procedure.
2. Only licensed waste carriers are permitted to remove waste from L J Fairburn & Son Ltd site and a copy of
their licence (authorisation) or exemption certificate to carry and or dispose of waste should be obtained
prior to any waste removal. Records of these licences are to be kept.
RECORDS
1. Waste consignment notes are to be kept for all waste removed from site as required by legislation.
2. The Mill Manager is responsible for ensuring that the type, quantity and destination of the waste being
disposed of is recorded and total amounts are reported and discussed at the Site EMS meeting.
3. Waste produced must have a written description including the European Waste Catalogue 6 digit codes.
See below.
4. The Standard Industry Classification (SIC) or NACE code for animal feed plants is 15.71.
5. The NASE code for the main polluting process on site is 105.03
Page 4 of 6
L J Fairburn & Son Ltd Environmental Management System
3. The mill manager must obtain confirmation that the receiver is registered to accept the specific waste.
The tables on the following page describe the wastes produced by L J Fairburn & Son Ltd site. In the event that
a site produces a waste not covered by this list, guidance on disposal must be obtained.
DOCUMENTATION
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation held on the
computer system.
www.defra.gov.uk/environment/waste/management/doc/pdf/waste_man_duty_code.pdf
Page 5 of 6
L J Fairburn & Son Ltd Environmental Management System
Waste Categorisation
European Waste
Waste Description Hazardous Catalogue WFD Codes
Page 6 of 6
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd will maintain dust abatement equipment at
each site. The main objective of this procedure is to ensure that dust emissions are kept to a minimum.
REFERENCES
This will be referenced in the Site monitoring and planned preventative maintenance schedules.
HAZARDS
The emission of dust and particulates to atmosphere could cause a nuisance to residents and businesses in the
surrounding area. These emissions may also lead to the deposition of material on land or in watercourses and may
pose a risk to flora and fauna.
ACTIONS
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation (Legislation
Register) held on the computer system.
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
The aim of this document is to ensure that new and modified plant/equipment has been appropriately
commissioned and approved prior to the commencement of Operations in relation to environmental issues.
REFERENCES
This procedure should be read in conjunction with EMS OP07 Environmental Purchasing Procedure and Capital
Approval.
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The Mill
Manager is responsible for its implementation on site.
HAZARDS
If planned changes to plant/equipment on site is not appropriately reviewed and approved then there will be an
increased risk of the following:
Unnecessary financial cost (e.g. excessive packaging requiring waste disposal, purchasing of energy
inefficient equipment incurring increased running costs).
Increase in environmental damage (e.g. increased emissions, equipment containing hazardous
materials).
Damage to L J Fairburn & Son Ltd reputation or environmental credentials.
Non-compliance with PPC Permit.
ACTIONS
2. The above should be reviewed not only for when the modification has been made but also the
associated activities and risks of physically making the modification.
3. The Mill Manager will ensure that the relevant changes are made if required to other documents (i.e.
procedures, inclusion within planned maintenance schedules) will be made.
4. For any plant changes the implications to product quality and/or Health & Safety will also be taken into
account.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
LEGISLATION
There is currently no specific environmental legislation associated with making changes to plant/equipment on
site although depending on the proposed changes prior approval may be required.
Details of the legislation relating to this are contained in the Register of Legislation (Legislation Register) held on
the computer system.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd manages the environmental risks associated
with contractors that work on site.
The main objective of this procedure is to ensure the risk associated with contractors, in terms of environmental
damage and legislative non-compliance, is minimised.
REFERENCES
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The
Production Manager is responsible for its implementation on site.
HAZARDS
Contractors conduct a range of activities on site using an array of materials and produce a variety of wastes. If
contractors activities are not managed on site this increases the risk of the following:
ACTIONS
LEGISLATION
There is no specific environmental legislation associated with contractors work on site but non-compliance with
some could potentially occur from contractors work on site.
Details of the legislation relating to this are contained in the Environmental Register of Legislation held on the
computer system.
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
The aim of this document is to assist L J Fairburn & Son Ltd staff integrate environmental considerations into
purchasing decisions. This document will ensure the company informs/seeks approval from the Environment
Agency when significant changes occur at a site or within the business and when key process and abatement
plant/equipment and/or Raw Materials are purchased.
REFERENCES
L J Fairburn & Son Ltd Capital Procedures
Environmental Equipment Purchasing Checklist (EPC)
Raw Material Purchasing Procedures
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager, Raw Material
Buying team and other nominated persons responsible for procurement on a mill basis. These people are
responsible for its implementation.
HAZARDS
If environmental issues are not considered as part of the procurement progress this increases the risk of:
Unnecessary financial cost (e.g. excessive packaging requiring waste disposal, purchasing of energy
inefficient equipment incurring increased running costs).
Increase in environmental damage (e.g. increased emissions, equipment containing hazardous
materials).
Non-compliance with a site’s PPC Permit.
ACTIONS
Review of purchase/submission
1. The Mill Manager / Relevant Buyer/ Procurement Purchaser will review how the purchase could affect
the environmental impacts/risks at the site(s) and will raise any relevant issues with the Operations
Director who will update the Environmental Aspects Register if required.
2. The Operations Director / appropriate Independent Advisor will review how the purchase could affect
compliance with environmental legislation and impacts on the Company EMS.
3. The Mill Manager will seek approval from the Environment Agency where required if the purchase will
affect the conditions of the site’s PPC Permit.
LEGISLATION
There is no specific environmental legislation associated with purchasing materials other than informing/seeking
approval from the Environment Agency where required under the Pollution Prevention and Control Regulations.
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
The aim of this document is to ensure that all key plant and equipment is regularly maintained to reduce mill down-
time, increase efficiency and reduce/eliminate hazards.
REFERENCES
This procedure should be read in conjunction with procedure EMS OP05 Plant & Equipment Change.
Site Preventative Maintenance Schedule
Site Planned Maintenance Programme
RESPONSIBILITY
The Operations Director is responsible for this procedure and its communication to the Mill Manager. The Mill
Manager is responsible for its implementation on site.
HAZARDS
If planned maintenance is not carried out there will be an increased risk of the following:
ACTIONS
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
LEGISLATION
There is currently no specific environmental legislation associated with preventative maintenance on site
although depending on the proposed changes prior approval may be required.
Page 2 of 2
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd will manage potential environmental
nuisances (odour, dust and noise on site. The main objective of this procedure is to ensure that nuisances are kept
to a minimum.
REFERENCES
EECF – External Environmental Communication/Complaint Form
NCIR - Non-conformance and Incident Report Form
EMS SP08 - Non–conformance, Corrective and Preventive Action Procedure
EMS OP04 – Bag Filter Maintenance
EMS OP08 – Plant Maintenance
EMS SP05 – Environmental Communication
RESPONSIBILITIES
All staff on site are responsible for ensuring that their activities do not cause any environmental nuisance.
HAZARDS
The potential nuisances are noise from process machinery and vehicle movements, odour from process emissions
to atmosphere and dust from process emissions to atmosphere and vehicle loading / unloading activities. These
nuisances could affect human occupation/residences in the surrounding area.
ACTIONS
Day to day Operations
1. The correct Operating and maintenance procedures are covered in other Operating Procedures within the
Environmental System.
2. Abnormal odours, noise and dust emissions must be reported to line managers immediately. An investigation
must take place to identify any problems and carry out corrective actions. Consideration must be given by the
site manager if these abnormalities should be reported to the Regulatory authorities.
3. Site management and shift leaders will check for abnormal noise, dust and odour during daily mill tours.
4. Any complaint registered by a member of the public, customer, supplier or other party will be handled by the
relevant manager using the External Communication or Complaint Form (ECCF- reference EMS SP05).
Documentation
Nuisance observations and reports, both internal and external, must be documented.
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation held on the
computer system.
Page 1 of 1
L J Fairburn & Son Ltd Environmental Management System
INTRODUCTION
This procedure describes the method by which L J Fairburn & Son Ltd will manage emergency procedures (fire,
spillages and abnormal emissions) at each site. The main objective of this procedure is to ensure that emergency
procedures are in place to avoid any environmental impact.
REFERENCES
Health & Safety Manual
Emergency Action Plan
NCIR - Non-conformance and Incident Report Form
RESPONSIBILITIES
The Mill Manager is responsible for the implementation and maintenance of the Emergency Action Plan.
All staff on Site are responsible for implementing emergency procedures to avoid environmental pollution.
HAZARDS
The potential pollutants in an emergency situation are as follows:-
Emissions – particulates
These pollutants could affect human occupation/residences in the surrounding area and contaminate land and
water systems.
ACTIONS
Fire
Fire prevention and control policies are documented in the Company Health & Safety Manual, copy found on the
computer system.
Fire detection equipment must be checked weekly and recorded in Mill Log Book.
Evacuation drills must be conducted annually and recorded in Mill Log Book
The Emergency Action Plan contains instructions on what to do in the event of a fire.
Page 1 of 2
L J Fairburn & Son Ltd Environmental Management System
Spillages
Site work instructions contain detailed instructions on procedures and actions to take in the event of a spillage of
bulk liquids or failure of bunding. Spillages must be reported to the Regulatory authorities
The Emergency Action Plan contains a register of each liquid held on site.
Emissions
In the event of abnormal emissions from abatement plant the process plant must be immediately shut down and
corrective actions taken to prevent further emissions.
Abnormal odour or dust emissions must be reported to line managers. An investigation must take place to identify
any problems and carry out corrective actions. Consideration must be given by the Mill Manager if these
abnormalities must be reported to the Regulatory authorities.
Site management and shift leaders will check for abnormal dust and odour during daily mill tours.
Documentation
After any Emergency e.g. fire, details of the emergency and the action taken must be documented in a specific
report to be held on Site.
LEGISLATION
Details of the legislation relating to this procedure are contained in the Register of Legislation held on the
computer system.
Page 2 of 2
L J Fairburn & Son Ltd
ENVIRONMENTAL AUDITORS PACK
INDEX
4. WORK INSTRUCTIONS
ENVIRONMENTAL
AUDIT REPORT REPORT NO:___________________________
PAGE NO:____________of________________
2. NON CONFORMANCES
3. AUDIT DETAILS
3.1 AUDIT TRAIL - DETAILED ON Checklist and Audit Trail (IEAT) FORM
SIGNED:
_______________________________ _______________________________________
Departmental Head Lead Auditor
_______________________________
Date of Audit
COPIES: Note: It is the Auditor’s responsibility to ensure copies are circulated. Please double side copies of IEAT
DEPARTMENTAL HEAD
OPERATIONS DIRECTOR
QUALITY MANAGER
CLAUSES COVERED
DESCRIPTION PREVIOUS THIS NC REF NOS
VISIT VISIT
4.1 GENERAL REQUIREMENTS
4.2 ENVIRONMENTAL POLICY
4.3 PLANNING
4.3.1 Environmental Aspects
4.3.2 Legal Requirements
4.3.3 Objectives, Targets & Programme
4.4 IMPLEMENTATION AND OPERATION
4.4.3 Communication
4.4.4 Documentation
4.5 CHECKING
SIGNED:
_________________________________ _________________________________
Departmental Head Auditor
_________________________________
Date of Audit
COPIES: Note: It is the Lead Auditor’s responsibility to ensure copies are circulated
DEPARTMENTAL HEAD
OPERATIONS DIRECTOR
QUALITY MANAGER
Authorised: Operations Director Form: IEAS Version 1
ENVIRONMENTAL AUDITORS PACK
Section: 2(iii)
L J Fairburn & Son Ltd
REPORT NO:___________
Details of Non Conformance PAGE NO ____of_______
NON CONFORMANCE REPORT NO:
1. Details of Non Conformance
4. Signatures:
Date of Audit
Auditor Date
DEPARTMENTAL HEAD
OPERATIONS DIRECTOR
QUALITY MANAGER
REPORT NO:______________
Additional Audit Trail
PAGE NO of ___
(Please list brief details of any observations, further information on non-conformances, additional audit areas
and any possible BDPs here)
SIGNED:
_____________________________________ _________________________________
Departmental Head Auditor
_____________________________________
Date
DEPARTMENTAL HEAD
OPERATIONS DIRECTOR
QUALITY MANAGER
Authorised: Operations Director Form: IEAT Version: 1
ENVIRONMENTAL AUDITORS PACK
Section: 3
Environmental Legislation
Register (EMS SP02)
Is it accessible in an emergency?
Does it include accidents e.g.
liquid spillage, cyclone failure,
etc?
Operating Procedures
Site Tour
Compressors – is oil
separated and collected for
disposal?
Site Drains
Are plans of the drain system
available
Are drain covers colour
coded?
Is an authorised waste
contractor used to empty the
interceptor?
Is there an accumulation of
liquids inside the bund areas
and by fill pipes?
Where do they drain to?
OPENING MEETING
5. Logistics: - Lunch
- Facilities for Auditors (office)
- Protective Clothing/ Ear Defenders
9. Confidentiality of Audit
11. Audit as Sample Both acceptable and non conforming aspects of the system will
be seen and missed
Page: 1 of 1
CLOSING MEETING
1. Thanks
2. Objective and Scope Restate as this resets the context of the Audit.
3. Limitations: Remind the auditees that the audit was a sample, therefore deficiencies
may exist in areas not covered.
7. Sign Off Previous Non-conformances i.e. Outstanding: If it has been agreed that
the corrective action for these has been implemented then the auditors should sign
these off in Section 5 and record the relevant non-conformance number(s) on the audit
summary report (IEAS) in Section 2.1. If it has not been possible to sign one off then
the relevant non-conformance number should be recorded under the Outstanding
Section 2.2. and a copy of the nonconformance must be attached to this audit report.
8. Feedback: Please leave blank Audit Assessment form (IEAA) with the auditee.
9. Copies of Reports: The Lead Auditor is responsible for ensuring that copies of the
audit report are circulated as per the circulation listed on the IEAS.
Please return this form to the Quality Manager as soon as possible. Your comments will be used to assess the
auditing procedure and will help in future planning.
Please circle the appropriate response: Comments (please always comment if you have
marked 3 or 4)
1. How would you rate the Auditors' understanding of
the process:
1 2 3 4
Excellent Good Satisfactory Unsatisfactory
1 2 3 4
Entirely Mostly Partly Not at All
1 2 3 4
Entirely Mostly Partly Not at All
1 2 3 4
Entirely Mostly Partly Not at All
1 2 3 4
Entirely Mostly Partly Not at All
1 2 3 4
Entirely Mostly Partly Not at All
Operations Director
Site Management &
Supervision
Office - CSD
Sales
Drivers
Process Operators
Warehouse
Maintenance
Procurement
Logistics Planners
Issued By: The General Manager Page 1 of 1 Date Issued: January 2008
Version1
I understand that L J Fairburn & Son Ltd operates an 'Environmental Management System' (EMS). I understand that the EMS is designed to e
compliance with the IPPC directive. L J Fairburn & Son Ltd holds an Operational Permit under the PPC Regulations enforced by the 'Environ
Agency'.
My Supervisor/Manager has access to all the current systems which make up the 'EMS'. I appreciate that I am freely entitled to refer to these
required.
I certify that I have received training in all the aspects of Environmental Management as they apply to L J Fairburn & Son Ltd. In particular I
I have received individual focused training, and I hold certificates and/or work instructions for my activities which might impact upon the env
Initials Date
General Awareness Presentation
Environmental Management System File
Work Instruction WI EMS 1
Work Instruction WI EMS 2
Work Instruction WI EMS 3
Work Instruction WI EMS 4
Work Instruction WI EMS 5
Work Instruction WI EMS 6
Work Instruction WI EMS 7
Work Instruction WI EMS 8
Work Instruction WI EMS 9
Work Instruction WI EMS 10
Work Instruction WI EMS 11
Work Instruction WI EMS 12
Work Instruction WI EMS 13
Work Instruction WI EMS 14
Work Instruction WI EMS 15
Work Instruction WI EMS 16
Work Instruction WI EMS 17
Work Instruction WI EMS 18
Work Instruction WI EMS 19
Work Instruction WI EMS 20
Work Instruction WI EMS 21
Work Instruction WI EMS 22
Work Instruction WI EMS 23
Work Instruction WI EMS 24
Work Instruction WI EMS 25
Work Instruction WI EMS 26
Work Instruction WI EMS 27
Work Instruction WI EMS 28
Work Instruction WI EMS 29
Work Instruction WI EMS 30
Work Instruction WI EMS 31
DVD Lock, Stop and no leaking barrels
I am satisfied that ________________________________________ is fully aware of L J Fairburn & Son Ltd's EMS and is able to comply w
its requirements.
Section 9
External documents
The targets and monitoring associated with these objectives are recorded on the sheet CETS.
Site targets are monitored and records are held locally.
Issued By: Operations Director Page 1 of 1 Date First Issued: May 16 Last Update:
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Up to date copies of electrical drawings and Drainage plans are stored in Mill &
Office.
CONTENTS
Page
Emergency Contact Numbers 2
Hazards on Site 3
Inventory of tanks and stores 4
Raw Material Type & Description 5
Emergency procedures: 6
Immediate actions 6
Secondary actions 7
Distribution within Company 10
Site plan 11
Page 1 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
An up to date list of all site personnel contact details is held by Operations Director.
Page 2 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
The Accident Management Site Plans include information of relevance for dealing
with accidents that may pose a risk of environmental pollution and pin points the
location of key equipment.
This includes:
HAZARDS ON SITE
HAZARD LOCATION(S)
Vegetable Oils See Site Plan Ref Fat Tank, Tank farm
Lubricating Oils and Grease See Site Fire Plan Ref Flammable
Chemicals (Mill Press Floor & Ground
Floor)
Waste oil See Site Plan Ref Waste Oil
Page 3 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Page 4 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Oil seed products and by-products Natural product: Oil seed products and by-products
Medicated Feeding Stuff – prescription Medicinal feed additives approved for use in the
required (MFS) Medicated Feeding Stuffs – no relevant species category
prescription required (MFSX) - YES
Acidifiers and Antioxidants YES Complexes of dry powder or liquid acids or aldehydes
Premixtures of Vitamins and Trace Elements Mixtures of vitamins (A, D3, E, K and B group), amino
acids (lysine, methionine, threonine), trace elements
(iron, copper, manganese, cobalt, zinc, iodine and
selenium (from sources such as oxides, sulphates,
iodates and selenites) and palatability enhancers.
Probiotics and Natural Extracts YES Complexes of natural plant materials and extracts.
Ancillary Materials
Mineral oils, greases and Food grade complex hydrocarbons with additives
lubricants
Page 5 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Detergent cleaning chemicals Disinfectants approved by DEFRA for the purposes of the Diseases of
Animals (Approved Disinfectants) Order 1978 (as amended) specifying
the dilutions at which they are respectively approved.
EMERGENCY PROCEDURES
1. Immediate Actions
Actions to be taken by the person first at the scene. These procedures should be
posted and trained into all employees.
A detailed list of accident types with their consequences and the actions to be
followed depending on the type of incident/accident.
IMMEDIATE ACTIONS
Page 6 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Any incident or near miss including those involving a contractor must be reported
to the Operations Director.
Page 7 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Page 8 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Fire
Spreading between buildings and Raise alarm on site
Fuels and oils stores Ensure all persons are evacuated from danger area
Chemicals Toxic and polluting smoke If safe to do so, isolate power and fuel sources.
Buildings Wind dispersion of pollutants Summon fire brigade
Surface run off from fire fighting water Contact Site Manager or deputy
Surface run off from failed tanks, If necessary contact Environment Agency
stores or pipe work Liaise and follow instructions of emergency
Exploding gas and fuel canisters services making them aware of risks and hazards.
Dust and fibres from building materials Provide copy of Accident Management Plan
(may contain asbestos). Refer to COSHH data sheets if appropriate
Ensure fire fighting water and other liquids cannot
cause pollution – as above.
Make temporary repairs if appropriate
Arrange for the clean up and removal, of all spilled
liquid, with an approved waste disposal contractor.
Dispose of contaminated materials safely.
Assess cause and take preventative action
Record incident
Abatement Failure Shut down affected plant immediately
Identify cause of pollution
Grinder Exhaust Dust emissions Make temporary repairs if appropriate
Local Exhaust Ventilation System Arrange for the clean up and removal, of all spilled
contaminant, with an approved waste disposal
contractor.
Dispose of contaminated materials safely.
Assess cause and take preventative action
Record incident using NCIR form
Page 9 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
DISTRIBUTION
Page 10 of 11
L J Fairburn & Son Ltd Environmental Management System
Accident Management Plan – Huttoft Mill
Version No: 1 Issued By: Operations Director
Issue Date: May 2016 Review date May 2017
Page 11 of 11
Site Closure Plan
Huttoft Mill
May 2016
1
Site Closure Plan
Contents Page
1. INTRODUCTION Page 3
Table 1 Table 1 - Main Potential Pollution Sources, Pathways and Impacts Page 6
FIGURES
Figure 1.1 Site layout plan showing IED installation boundary and key activities Page 14
2
Site Closure Plan
1. INTRODUCTION
Under Condition 1.4.1 Reference 3 of the IED Permit and in accordance with Section 2.11:
Closure, of the Food and Drink Sector Guidance Note (IPPC S6.10, August 2003), L J Fairburn &
Son Ltd is required to develop and maintain a Site Closure Plan “to demonstrate that, in its
current state, the installation can be decommissioned to avoid any pollution risk and return
the site of operation to a satisfactory state”.
The purpose of the Site Closure Plan is to address environmental pollution risks that may
occur during decommissioning of the site, and outline techniques to plan for and minimise the
effects of these potential risks.
The SITE CLOSURE PLAN draws on and references available information, including:
• Information and site plans included with the IED application submitted in June 2016;
• The Application Site report (ASR) submitted with the IED application;
The SITE CLOSURE PLAN is designed to complement the Application Site Report (ASR) and is
designed to facilitate the Surrender Site report that is required to be submitted in the event
of site decommissioning or closure.
2. SITE ACTIVITIES
The L J Fairburn & Son Ltd Blackdale site installation, operated by L J Fairburn & Son Ltd,
manufactures animal feed.
The installation activity is listed in Schedule 1 of the IED Regulations namely Section 6.8 A
(1)(d)(i):
“Treating and processing of vegetable raw materials intended for the production of food
products with a finished product production capacity of more than 300 tonnes per day”.
3
Site Closure Plan
The activity undertaken at the installation includes 2 main production lines within the main
production building with several associated storage bins and bays.
The site is located in Lincolnshire in the Lincolnshire fens just off the A52 trunk road in the
village of Huttoft.
The installation operates on a 24-hour basis, usually for 5½- 6 days per week and for 52 weeks
per year.
An Application Site Report (ASR) was submitted in support of the IED Application. Whilst
focusing on land and water quality at the site, the ASR is one of the key references for the
purposes of producing this Site Closure Plan.
4
Site Closure Plan
Activities to be operated on the site relate to the treating and processing of grain,
additives and other materials to produce animal feed and associated activities;
The site was purpose built for the treatment and processing of raw materials for
animal feed products and has been operated since 1979. Any contaminants that may
have been released by other historical industrial or agricultural activities may already
be present on site;
Activities identified with a reasonable possibility of future pollution occurring include
delivery of red diesel for forklift trucks and front loader shovels.
There will be a requirement for collection of reference data as part of the Site
Protection & Monitoring Programme for these areas of the site unless improvements
to pollution prevention measures were made in the interim. Improvements were
undertaken and the requirement to collect reference data was
reviewed.
Table 1 summarises the main potential risks relating to sources of pollution on site, pollution
pathways and possible environmental impacts that may occur during decommissioning.
5
Site Closure Plan
Drummed & Internal – stored Good grade liquid Local ground and Infiltration into surface soils Soil contamination
IBC liquid raw in dedicated raw materials groundwater. Migration to and movement Pollution of
drums in a within groundwater groundwater
materials
designated area Migration through drainage Effect on surface
network to surface water water
within the mill on
Direct contact Potential effect on
drip trays or
human health
sump pallets
6
Site Closure Plan
Product Designated areas Local ground and Infiltration into surface soils Soil contamination
within the main groundwater. Migration to and movement Pollution of
Food grade solid within groundwater groundwater
process building Surface waters
and warehouses
raw materials Migration through drainage Effect on surface
network to surface waters waters
Waste oil Internal – stored Contaminated Local ground and Infiltration into surface soils Soil contamination
drums and in dedicated waste groundwater. Migration to and movement Pollution of
waste digest drums on drip hydrocarbons, within groundwater groundwater
trays within a food grade liquid Migration through drainage Potential effect on
network to surface waters human health
designated waste waste raw
Direct contact (including
storage area materials
dermal/ingestion/inhalation of
vapours
Plant Infrastructure
Silos Internal – inside Food grade solid Local populace. Dispersion in air Particulates in air
main production raw materials Local ground and Infiltration into surface soils Soil contamination
Area and (e.g. cereals) groundwater Migration to and movement Pollution of
externally within groundwater groundwater
Migration through drainage Potential impact on
7
Site Closure Plan
8
Site Closure Plan
Demolition
Dust during Site wide Particulates Local populace. Dispersion in air Nuisance to local
demolition Infiltration into surface soils populace
Local ground and Migration to and movement Contamination of
groundwater within groundwater soils
Migration through drainage Pollution of
network to surface waters groundwater
Direct contact (including Deposition on soils
dermal/ingestion/inhalation of
dusts)
Noise and Site wide Noise and Local populace Dispersed in Air Nuisance to local
vibration vibration populace
nuisance
during
demolition
Odour during Site wide Various odours Local populace Dispersed in Air Nuisance to local
demolition populace
9
Site Closure Plan
3. CLOSURE PROCEDURES
The closure and vacation of the L J Fairburn & Son Ltd Huttoft installation may pose
potential impacts on the environment, summarised in Chapter 2 of this report. Under the
conditions of the permit, it is necessary to adopt controls and practices to minimise any
environmental impacts whilst the site is operational. The following general principles will
also be followed during decommissioning.
L J Fairburn & Son Ltd will conduct a comprehensive review of past accidents, incidents and
near misses by consulting incident logs and registers maintained within the Environmental
Management System.
The general principles will be applied for each of the potential pollution sources listed
below.
• Bulk storage bins
• Bulk storage tanks
• Bunds
• Unused materials
• Engineering materials
• Finished products
• Wastes
• Transformers
• Asbestos
• Drainage system
Figure 1 - Site layout plan showing IED installation boundary and key activities, as presented
in the original IED application.
Raw materials are stored in bins located internally and externally within the installation:
These contain materials of vegetable origins, e.g. wheat and soya and minerals e.g.
limestone
10
Site Closure Plan
All storage bins would be emptied by incorporation into finished product and where this is
not possible the materials would be transferred to another mill to minimise waste
generation.
All bagged and IBC ingredients would also be transferred to the nearest compatible
Feed mill for incorporation into product.
Fat & Vegetable Oil; are used as ingredients in the animal feed. Approaching the point of
closure consumption of these materials would be carefully managed to ensure that all liquid
tanks were emptied and the materials used to make feed this will minimise wastage and
energy usage involved in transferring materials elsewhere. It also minimises the potential
for spillages. The empty tanks would be cleaned by approved specialists and any residues
would be disposed of by approved waste disposal contractor. The tanks would be of value to
another producer and would most likely be relocated to another feed mill. The bunds would
be cleaned and associated steel, brick and concrete works would be recycled.
Red Diesel; Diesel is used for the forklift operation and is stored in a self bunded tank, it is
also used to fire the boiler and a second self bunded tank is located in the bunded tank
farm. The fuel is dispensed to the forklifts via a key controlled pump located adjacent to the
tank. In the case of the boiler fuel there is a direct connection to the burner pump. In the
event of closure fuel stocks would be managed to ensure a nil stock on completion. Any
residue remaining in the tank and delivery system would be purged using inert gas and fuel
collected and used to power forklift trucks during the closure process. The tanks and pumps
would be transferred to another site or sold at auction.
Bunds
Decommissioning of bunds will, only occur after the decommissioning of the relevant
vessels they contain.
Bund water will be disposed in accordance with any potential pollutants, either to foul
sewer or as hazardous waste.
Both raw materials and packaging materials which are suitable for their intended purpose
will be transferred to other sites. Materials which are unsuitable for use will be
appropriately disposed as waste.
11
Site Closure Plan
Workshop chemicals such as oils, greases, paints, aerosols, boiler chemicals etc. would be
transferred in their original packaging to other company sites as appropriate.
Any waste oils and solvents (including oily rags and other cleaning materials) would be
disposed of hazardous waste via a registered specialist contractor.
Finished product will be sold. Any finished product that cannot be sold will be disposed of
appropriately depending upon the nature of material and level of any contamination.
3.2.7 Wastes
All waste generated during the closure process will be segregated into streams appropriate
for recycling e.g. paper, cardboard, plastic, metals, oil etc. These waste streams will be
handled by registered contractors and all waste transfer documentation will be maintained
on file.
3.2.8 Asbestos
A full asbestos survey will be carried out on the site in the event of closure, however it is not
anticipated that any asbestos containing materials are present. This is due principally to the
age of the plant and buildings.
If the site was transferred to a new owner for continuing use it is anticipated that they
would take on responsibility for managing the asbestos risk. If the mill was to be demolished
then appropriate techniques would be employed to control the release of fibres from the
cladding sheets (as per HSE guidance HSG210) during the dismantling process. The sheets
would be removed intact and disposed of via a registered waste contractor as hazardous
waste.
L J Fairburn & Son Ltd will ensure that the Asbestos Register and current management plan
are up to date at the time of decommissioning.
The drainage system will be purged with water to clean the system, after all demolition
work is complete. Duty of care documentation and consignment notes will be held centrally
by L J Fairburn & Son Ltd for two years, or a minimum of five years for special waste.
3.3 Decommissioning
12
Site Closure Plan
3.3.1 Noise; the mill is surrounded by a several residential dwellings. All works would be
carried out to minimise disruption to the neighbours. The neighbours would also be
forewarned of any planned works.
3.3.2 Demolition of Buildings and Above Ground Infrastructure; if the mill buildings were
to be demolished then all of the preceding issues would need to be resolved first i.e. the
feed materials, liquids, fuels etc.
The plant would be made safe by isolating electrical, hydraulic and air supplies. The
production plant would be removed and sold/transferred to other sites.
The demolition engineers would be provided with copies of the drainage plans and
instructions not to put any materials into the surface water drains.
Air conditioning units would have their refrigerant recovered by a specialist contractor prior
to any dismantling work taking place.
The site would be handed over to a specialist demolition contractor once all equipment had
been removed and the site made safe and secure. This operation would be controlled by
CDM regulations and the planning would cover all environmental controls required which
would be recorded in the CDM file. The CDM file will include a copy of the Emergency Plan.
4.1 Responsibilities; The Operations Director would have overall responsibility for the site
closure programme.
The Mill Manager would have day to day responsibility for implementation. Guidance and
support would be provided from the other members of the L J Fairburn & Son Ltd
management team and specialists as required.
The workshop facility would be maintained as long as the site was manned in order to
facilitate a controlled closure of the site. The engineering team would be retained
throughout the closure process as they have the necessary skills to ensure safe and
controlled shutdown of the operation.
The workshop is also the centre for specialist control measures such as emergency spill kits.
4.2 Planning; if the site was to be closed a senior management team would oversee the
planning of the process.
Any decision to close the site would take into account the environmental impact of the
closure and any associated demolition etc. that might be required. Technical expertise
13
Site Closure Plan
would be provided by the L J Fairburn & Son Ltd management team. EA, Local Authority,
Parish Council (including neighbours) and Workforce would be consulted on closure plans at
the appropriate stage.
4.3 Review; the Mill Manager will review the Site Closure Plan every 2 years to ensure that
the plan is up to date and additionally if there are related changes to the operation.
Figures
14
Site Closure Plan
15
Site Protection and Monitoring Programme
L J Fairburn & Son Ltd
Hottoft Mill
Version 1
Contents
Page 1 of 16
Executive Summary 3
1. Introduction 3
2. Objectives 4
3. Monitoring Programme 5
5. Environmental Summary 9
Page 2 of 16
Executive Summary
This document represents the Site Protection and Monitoring Programme (SPMP) for L J
Fairburn & Son Ltd, Hottoft submitted to the Environment Agency (EA) in pursuance of
Condition 4.6 of the Permit No EPR/HP3132/RN (the "Permit") authorizing “the treating and
processing of materials intended for the production of food products from vegetable raw
materials at plant with a finished product production capacity of more than 300 tonnes per day
(average value on a quarterly basis)”.
The testing, inspection and maintenance programme for pollution prevention infrastructure at
the site (the Infrastructure Monitoring Programme) has been designed as detailed in Schedule
3. The results of the routine monitoring will be collated into a Monitoring Report and sent to
the EA on the 31st of January each year. The Monitoring Report will also contain
recommendations for changes to the SPMP (if any) to be formally agreed, in writing, by the EA.
An intrusive investigation for benchmarking purposes is not required in this case as no sources
were identified in the Site Condition Report (at the time of PPC application submission) as
having a ‘reasonable likelihood of pollution’. The measures in place plus further refinements
agreed will ensure that no pollution occurs. For the same reason an ongoing Environmental
Monitoring Programme is not proposed.
The potential sources of contamination identified in the Site Condition Report included the
vegetable oil and molasses delivery points; the minerals and salt delivery points; the light fuel
oil delivery point and the lubricating oils storage area which have containment measures
installed thus removing the need for collecting reference data in these locations. The site
drainage system was not identified as an area requiring the collection of reference because the
site run-off only consists of surface water drainage. Foul water associated with the site welfare
facilities is discharged to the public sewer under a trade effluent discharge consent.
1. INTRODUCTION
1.1 Introduction
L J Fairburn & Son Ltd is required to maintain a Site Protection and Monitoring Programme
(SPMP) for their installation Huttoft Mill, Sutton Road, Huttoft, Lincolnshire, LN13 9RA. This
SPMP has been produced by L J Fairburn & Son Ltd & AV Consultants, in accordance with the
conditions of the Permit EPR/HP3132/RN issued under Regulation 10 of the Pollution
Prevention and Control Regulations.
Page 3 of 16
This document is intended to be read in conjunction with the following supporting documents:
Site Condition Report, dated 30 June 2016
Permit, EPR/HP3132/RN dated
Huttoft Mill
Sutton Road
Huttoft
Lincolnshire
LN13 9RA
The site covers an area of approximately 1 hectare and can be seen in the site plan below.
1.3 Details of Installation
The site is located within an area of approximately 1 hectare, with the site boundary comprising
secure fencing and a lockable gate.
The Hottoft installation manufactures compound and blended animal feeds i.e. feeds which are
suitable for consumption by an animal without further processing. The products manufactured
are based upon core formulations of cereals (such as wheat and barley), soya, and rape seed
plus specific additives, such as mineral supplements. The processing is undertaken to a specific
formulation on a batch basis, with the key stages being weighing, grinding & mixing.
Depending upon the specific formulation, the required cereals etc. are pre-ground prior to
being weighed out in a uniform grist size. The blended materials are then transferred to the
mixing stage of the process, where they are mixed with pre weighed supplements and
medicinal feed additives used for prophylactic and therapeutic treatment. Following this, the
mix is now the finished product.
The finished product is then stored in silos prior to being automatically loaded to bulk vehicles
for delivery to customers on an as required basis.
External areas comprise car parking areas, of tarmac & concrete hardstanding, storage areas for
ingredients (bulk and drums), waste, bulk chemicals including fuel/oil, and a small area of soft
ground.
Page 4 of 16
2. OBJECTIVES
2.1.2 There is no requirement for a site investigation to collect reference data as there were
no sources identified as having a ‘reasonable likelihood of pollution’.
The potential sources of contamination identified in the Site Condition Report included the
following:
Vegetable oil delivery points. The fill points outside of the bunded areas are protected by
catch trays under each fill point which would contain any spills and leaks. There are
procedures in place for the regular inspection and emptying of these catch trays and there
has been no staining to the ground since the catch trays were installed. Pneumatic control
valves are fitted on each fill line inside the bund. Sealing lines are also closed on
completion of the delivery and the fill lines have sealed screw caps fitted to the lines when
not in use. Kerbing provided around the liquid intake area contains any spillages and spill
kits are available in the case of an emergency.
Minerals and salt delivery points. Pneumatic control valves are fitted on each fill line. Any
material spilled during filling would be cleaned up immediately as outlined in the
procedure.
Storage of lubricating oils (205 litre drums). The drums have secondary containment
consisting of bunded trays that are designed to hold the capacity of each 205 litre drum.
The need for collecting reference data in this location has therefore been removed.
Site drainage system. The site drainage system was not identified as an area requiring the
collection of reference data because the site run-off only consists of surface water
drainage. Foul water only consists of discharge associated with the site welfare facilities
Therefore it is very unlikely that C J Fairburn’s installation could cause ground
contamination thus eliminating the requirement for the collection of reference data.
3. MONITORING PROGRAMME
Page 5 of 16
To test the integrity of the pollution prevention infrastructure currently in place and evaluate
the monitoring, inspection and testing programme in place to maintain the infrastructure as
detailed in sections 2.2.2 (emissions to water and sewer) and 2.2.5 (Fugitive emissions to
surface water, sewer and groundwater) of the IPPC application.
The maintenance activity is split between planned work and emergent work and coordinated by
the Mill Manager and Operations Director using both an internal site services team and external
resource for specialist testing / inspections.
Routine work includes examination and testing due to appropriate statutory requirements,
regulations, manufacturers and suppliers recommendations and as part of the company
planned maintenance system. Frequency of testing depends upon these criteria.
The Operations Director and the Mill Manager co-ordinate staff and relevant sub contractors.
Competency of external specialists and contractors is reviewed by the Operations Team.
Planned maintenance tasks carried out by maintenance personnel may be subject to a permit
to work. Sub contractors are required to submit a work method statement and in some cases
are issued with a permit to work. Any records of equipment inspected and tested are kept and
maintained in the Engineering Department.
Emergency work is classed as breakdown work and is reviewed on an immediate and daily
basis. Upon discovery of a fault with plant or equipment, parties with an interest, e.g.
Production Manager, will liaise with the Operations Director (or Engineering support) to discuss
details of the work needed.
The infrastructure monitoring programme is summarized in OP08 & SP07 from the
Environmental Management System and comprises the following inspection programmes:
Page 6 of 16
Surfacing
The majority of the operational areas are covered with concrete hardstanding or tarmacadam
that is in good condition. However, outside the installation operations area and outside the
installation boundary there are a number of vegetated areas.
In addition informal inspection is almost continuous by the mill staff. The mill staff are all fully
briefed in the various aspects of the EMS and in the event of a fault of any description to the
integrity of the hard standing, the details will be reported to the appropriate person. The fault
will then be addressed by the appropriate mans whether an incident under the accident
management plan or routine maintenance.
Subsurface Structures
The only other subsurface structures on site are the effluent drains.
Secondary Containment
All of the permanent above ground storage tanks have secondary containment. There is a
procedure in place for the inspection of main containment infrastructure which is linked to the
preventative maintenance programme to maintain integrity.
There is a procedure in place for the inspection of main containment infrastructure which is
linked to the preventative maintenance programme to maintain integrity. This covers the
inspection of tanks and associated pipe work.
The following personnel are responsible for undertaking the infrastructure monitoring
programme:
Page 7 of 16
Inspection Type Frequency Responsibility
Storage tanks, bunds, Visual Monthly Mill Manager
pipework
Outlet to water Visual Monthly Mill Manager
course
W1
Infrastructure and site Visual Annually Mill Manager /
condition Operations Director
Personnel responsible for the inspection, testing and maintenance of pollution prevention
infrastructure are trained to an appropriate level to ensure compliance with the Infrastructure
Monitoring Programme. The site operates an Environmental Management System (EMS) and
all such activities are covered by ‘Work Instructions’.
The assessment and reporting procedure will be carried out within the remit of the site
management systems.
For infrastructure an assessment of the potential for containment infrastructure to fail will be
undertaken. The assessment will be carried out by responsible persons with suitable technical
and operational experience.
Infrastructure monitoring will be recorded as will summaries of any pollution incidents and
failure of containment measures resulting in emissions.
Summaries of the monitoring data and results of the data assessment will be submitted to the
EA on 31st January each year following the initiation of the SPMP together with
recommendations for any amendments to the SPMP.
All assessment sheets used for the infrastructure assessment are stored in a secure location.
4. REFERENCES
4.1 References
Page 8 of 16
Site Report, dated 30 May 2016
Revisions
The SPMP was modified on the following dates as follows; (first issue)
5.1 Topography
The site lies at an elevation of approximately 2-3m above Ordnance Datum (aOD) and is virtually level
and flat.
5.2 Geology
The geological map extract shows the area of installation site and the surrounding area.
Alford (pronounced "Olford") is a town in Lincolnshire, England, It is situated approximately 11 miles (18
km) north-west from the coastal resort of Skegness, and at the foot of the Lincolnshire Wolds,
designated an Area of Outstanding Natural Beauty. Alford population is about 3,500, measured at 3,459
at the 2011.
The Cretaceous sequence begins with the Wealden Group limestones, mudstones, sandstones and
siltstones which occur from Gibraltar Point in a band which narrows northwestwards to the Caistor area.
To their east, and stratigraphically above them, are the sandstones of the Lower Greensand Group and
beyond them the Chalk which gives rise to the Lincolnshire Wolds and extends to the North Sea coast
but is obscured along the coastal margin.
5.3 Hydrogeology
The Lincolnshire Limestone forms an important aquifer in the Lincolnshire area. The groundwater
abstracted is used mainly for public supply, but also supplies agricultural, industrial and private needs.
The Lincolnshire Limestone crops out in the west of the study area, but dips gently eastwards where it is
progressively covered by younger deposits where confined conditions prevail. The direction of
groundwater flow generally follows the direction of dip to the east. The Lincolnshire Limestone aquifer
provides a good case study for examining the geochemical changes in groundwater chemistry which
take place in the direction of groundwater flow and as such the hydro geochemistry of the aquifer has
Page 9 of 16
been well-studied in the past. In addition to the effect of increased residence time permitting greater
water-rock interaction, the geochemical processes of carbonate dissolution and equilibria, ion-
exchange, redox reactions and mixing with old formation water are all significant in determining the
groundwater chemistry in the aquifer.
5.4 Hydrology
The Fens Area: The Fens cover a large area of eastern England, stretching from the Wash out to Lincoln,
Peterborough and Cambridge. Five different rivers, the Witham, Welland, Glen, Nene and Ouse, carry
water from surrounding uplands through the Fens and into the Wash.
Management Plans for the Fens: The Environment Agency has developed Catchment Flood
Management Plans for the Anglian Region with the aim of taking a broad view of flood risk at catchment
level over the next 100 years. Factors such as climate change, future development and changes in land
use and land management were taken into account in developing sustainable policies for managing
flood risk in the future.
5.5 Ecology
The sensitivity of receptors in the vicinity of the site to contamination is summarised in Table 5.2.1.
Page 10 of 16
6.0 Assessment of land pollution potential
6.1 Identification of Potentially Polluting Substances
A list of the major substances used, manufactured and stored within the installation (or waste by-
products from the manufacturing process) is contained in the supporting information Section 5,
elsewhere in this application. An assessment of their pollution potential has been made based upon
their properties, toxicity and the volume stored. This information is recoded in detail in the Aspects
Register of the Environmental Management System (EMS). The materials and substances used within
the installation are also assessed in the environmental risk assessments in supporting information
section 4.
The tables below are taken from the Site Condition Report written by AV Consultants and
submitted in support of the PPC application in June 2016.
Page 11 of 16
Substance Liquid or Volumes Toxicity/ Fate/ Pollute land Considered
(contaminants) Solid Stored Mobility if released? Further?
Pollute land
if released?
Products & Waste Materials
Page 12 of 16
Potentially Relevant Relevant Records Containment Measures Planned Likelihood
Polluting System Activity Of Pollution Testing & Of Pollution?
Substance Inspection
Regime*
Minerals Production Delivery Some Primary: Tanker Delivery is Slight
(bulk tanker & evidence Secondary: None supervised possibility
delivery) processing of minor Tertiary: Concrete hard
leaks and standing and drainage
spills at system
fill point
Vitamins & Production Delivery No evidence Primary: Flat bed lorry Delivery is Little
mineral & or records of Secondary: None supervised Likelihood
additives processing spills/leaks Tertiary: Indoor flooring
(pallet
delivery) Storage No evidence Primary: Plastic/paper Visual checks as Little
or records of bags part of normal Likelihood
spills/leaks Secondary: Pallets operations
Tertiary: Indoor flooring
Waste oil Oils arising Storage No evidence Primary:1,100 Litre Bulk Visual checks as Little
from plant or records of storage part of normal Likelihood
maintenance spills/ leaks tank operations
Secondary: Bunded tank
Tertiary: Concrete
hardstanding and storm
drainage system
Page 13 of 16
Appendix 1 Site Plan
Page 14 of 16
Appendix 2 – Plant Overview
The Hottoft Mill installation manufactures compound animal feeds i.e. feeds which are suitable for
consumption by an animal without further processing. The installation has been in operation as a mill
since 1824 but as a feed mill since the 1050s it produces a wide range of chicken feeds to meet specific
customer demands. Products are manufactured on four process lines. Typical production from the
installation will total up to approximately 100,000 tonnes per year from 2020 of finished product. The
installation typically operates 24 hours a day, 5 or 6 days a week and for 52 weeks a year. There are
some directly associated activities which include storage and handling of raw materials and waste.
The products manufactured are based upon core formulations of cereals, vegetable proteins, oilseed
extraction products, vegetable oils etc, plus specific additives, such as mineral and vitamin supplements.
The processing is undertaken to a specific formulation on a batch basis, with the key stages including
weighing, grinding and mixing.
Depending upon the specific formulation, the required cereals etc. are put in enclosed weighers after
grinding to a uniform grist size. The ground materials are then transferred in enclosed conveyors to the
mixing stage of the process, where they can be mixed with vegetable oils. Following mixing the batch
becomes the finished product. The finished products are then conveyed to storage silos prior to dispatch
to customers. Products are automatically loaded into bulk vehicles for delivery to customers on an as
required basis.
Suitable controls are in place for handling of raw materials, wastes and products such that the potential
for emissions for these activities is minimised. Where appropriate, a range of abatement systems are
employed throughout the process to remove particulate matter.
The installation has a drainage system for surface water, to collect the water from roofs and
hardstanding areas. Surface water is then discharged to a nearby drain to the east of the site.
Page 15 of 16
Page 16 of 16
Huttoft Mills Organisational Structure
MD
Directors
Duty Mill
Manager
Finance / HR Admin
/Admin Support
Drivers Mechanic
Mill Ops
Admin Support
4.8.2016
L J Fairburn & Son Ltd
ENVIRONMENTAL POLICY
MISSION STATEMENT
L J Fairburn & Son Ltd cares about the environment and is committed to protecting it. Our
corporate strategy is for all our employees to do all that is practicable to achieve this.
Produce adequate training and information to our employees to ensure the relevant
knowledge and experience is acquired and maintained for successful implementation
of this policy.
This Environmental Policy can only be effective with the support and efforts of every
member of staff, our suppliers and contractors.
Sarah Hall
Wk
EQUIPMENT CHECKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Monday
Tuesday
Wednesday
Thursday
Friday
EQUIPMENT CHECKS 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Monday
Tuesday
Wednesday
Thursday
Friday