1.4.1 SBM - Production / Released Equipments 12 H Sex 21/04/23 11:00 Sex 21/04/23 23:00 0% 24 Hours

This document outlines the schedule for a N2He leak test on a CO2 compressor over 20 days. It involves several key steps: 1) a contract process including receiving a purchase order and developing procedures, 2) equipment mobilization over 7 days, 3) pre-activities like positioning cleaning equipment and tool preparation over 1 day, and 4) the leak test activities themselves over 9 days. The schedule is broken down into multiple sub-tasks with start and end dates assigned.

Uploaded by

Luis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views1 page

1.4.1 SBM - Production / Released Equipments 12 H Sex 21/04/23 11:00 Sex 21/04/23 23:00 0% 24 Hours

This document outlines the schedule for a N2He leak test on a CO2 compressor over 20 days. It involves several key steps: 1) a contract process including receiving a purchase order and developing procedures, 2) equipment mobilization over 7 days, 3) pre-activities like positioning cleaning equipment and tool preparation over 1 day, and 4) the leak test activities themselves over 9 days. The schedule is broken down into multiple sub-tasks with start and end dates assigned.

Uploaded by

Luis
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Schedule N2He Leak Test _ CDI-23 _ CO2 Comp.

B
Id Nome da Tarefa Duração Início Término Predecessoras
% Calendário Nomes dos
concluída
da tarefa recursos Dom, 09/Abr Seg, 10/Abr Ter, 11/Abr Qua, 12/Abr Qui, 13/Abr Sex, 14/Abr Sáb, 15/Abr Dom, 16/Abr Seg, 17/Abr Ter, 18/Abr Qua, 19/Abr Qui, 20/Abr Sex, 21/Abr Sáb, 22/Abr Dom, 23/Abr Seg, 24/Abr Ter, 25/Abr Qua, 26/Abr Qui, 27/Abr Sex, 28/Abr Sáb, 29/Abr Dom, 30/Abr Seg, 01/Maio Ter, 02/Maio
12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0
1 1 Schedule N2He Leak Test _ CDI-23 _ CO2 Comp. B 20,91 dias Seg 10/04/23 06:00 Seg 01/05/23 03:44 0% 24 Hours 0%
2 1.1 CONTRACT PROCESS 5 dias Seg 10/04/23 06:00 Sáb 15/04/23 06:00 0% 24 Hours 0%
3 1.1.1 Receive PO 3 dias Seg 10/04/23 06:00 Qui 13/04/23 06:00 0% 24 Hours 0%
4 1.1.2 Pre Engineering and Procedure 2 dias Qui 13/04/23 06:00 Sáb 15/04/23 06:00 3 0% 24 Hours Pre Engineering and Procedure 0%
5 1.1.3 Procedure Ready for Comments 1 dia Qui 13/04/23 06:00 Sex 14/04/23 06:00 3 0% 24 Hours Procedure Ready for Comments 0%
6 1.1.4 Procedure Revisions 1 dia Qui 13/04/23 06:00 Sex 14/04/23 06:00 3 0% 24 Hours Procedure Revisions 0%
7 1.2 MOBILIZATION 7,46 dias Qui 13/04/23 06:00 Qui 20/04/23 17:00 3 0% 24 Hours MOBILIZATION 0%
8 1.2.1 EQUIPMENT 7 dias Qui 13/04/23 06:00 Qui 20/04/23 06:00 0% 24 Hours EQUIPMENT 0%
9 1.2.1.1 Equipment Mobilization (Operational test) 5 dias Qui 13/04/23 06:00 Ter 18/04/23 06:00 3 0% 24 Hours 0%
10 1.2.1.2 Equipment Moviment to FPSO from SEA 2 dias Ter 18/04/23 06:00 Qui 20/04/23 06:00 9 0% 24 Hours 0%
11 1.2.2 MANPOWER 0,46 dias Qui 20/04/23 06:00 Qui 20/04/23 17:00 0% 24 Hours 0%
12 1.2.2.1 Embark 6h Qui 20/04/23 06:00 Qui 20/04/23 12:00 3;8 0% 24 Hours 0%
13 1.2.2.2 Manpower Safety Induction 3h Qui 20/04/23 12:00 Qui 20/04/23 15:00 12 0% 24 Hours 0%
14 1.2.2.3 Equipments inspection 2h Qui 20/04/23 15:00 Qui 20/04/23 17:00 13 0% 24 Hours 0%
15 1.3 Pré - Activities 0,83 dias Qui 20/04/23 15:00 Sex 21/04/23 11:00 0% 24 Hours 0%
16 1.3.1 SBM - Positioning of cleaning skid´s 6h Qui 20/04/23 17:00 Qui 20/04/23 23:00 8;11 0% 24 Hours 0%
17 1.3.2 PTW Released 8h Qui 20/04/23 15:00 Qui 20/04/23 23:00 13 0% 24 Hours 0%
18 1.3.3 SBM - electric lighting installation 12 h Qui 20/04/23 23:00 Sex 21/04/23 11:00 17 0% 24 Hours 0%
19 1.3.4 Along the hose 1h Qui 20/04/23 23:00 Sex 21/04/23 00:00 11;17 0% 24 Hours 0%
20 1.3.5 Tools, fittings and connections preparation 4h Qui 20/04/23 23:00 Sex 21/04/23 03:00 16;17 0% 24 Hours 0%
21 1.3.6 Toolbox talk 1h Sex 21/04/23 03:00 Sex 21/04/23 04:00 20;17 0% 24 Hours 0%
22 1.4 N2He LEAK TEST ACTIVITIES 9,2 dias Sex 21/04/23 11:00 Dom 30/04/23 15:44 0% 24 Hours 0%
23 1.4.1 SBM - Production / Released Equipments 12 h Sex 21/04/23 11:00 Sex 21/04/23 23:00 15 0% 24 Hours 0%
24 1.4.2 CO2 COMPR. 4th STAGE Disch. / E-T7544 2,18 dias Sex 21/04/23 23:00 Seg 24/04/23 03:15 0% 24 Hours CO2 COMPR. 4th STAGE Disch. / E-T7544 0%
25 1.4.2.1 DISASSEMBLY GÁS SIDE 0,54 dias Sex 21/04/23 23:00 Sáb 22/04/23 12:00 0% 24 Hours 0%
26 1.4.2.1.1 INLET SPOOL - Torque Break on Upstream flange (8'' x 2500) 1 h Sex 21/04/23 23:00 Sáb 22/04/23 00:00 23 0% 24 Hours 0%
27 1.4.2.1.2 INLET SPOOL - Torque Break on Downstream flange (8'' x 2500)
1h Sáb 22/04/23 00:00 Sáb 22/04/23 01:00 26 0% 24 Hours 0%
28 1.4.2.1.3 Lifting and remove Inlet Spool (8'' x 2500 ) 3h Sáb 22/04/23 01:00 Sáb 22/04/23 04:00 27 0% 24 Hours 0%
29 1.4.2.1.4 Assembly & Bolting o flange to Leak Test on INLET Nozzle 1,5 h Sáb 22/04/23 04:00 Sáb 22/04/23 05:30 28 0% 24 Hours 0%
30 1.4.2.1.5 OUTLET SPOOL - Torque Break on Upstream flange (8'' x 2500)1h Sáb 22/04/23 05:30 Sáb 22/04/23 06:30 29 0% 24 Hours 0%
31 1.4.2.1.6 OUTLET SPOOL - Torque Break on Downstream flange (8'' x 2500)
1h Sáb 22/04/23 06:30 Sáb 22/04/23 07:30 30 0% 24 Hours 0%
32 1.4.2.1.7 Lifting and remove Outlet Spool (8'' x 2500 ) 3h Sáb 22/04/23 07:30 Sáb 22/04/23 10:30 31 0% 24 Hours 0%
33 1.4.2.1.8 Assembly & Bolting of blind flange to Leak Test on OUTLET Nozzle
1,5 h Sáb 22/04/23 10:30 Sáb 22/04/23 12:00 32 0% 24 Hours 0%
34 1.4.2.2 DISASSEMBLY COOLING MEDIUM SIDE 0,31 dias Sáb 22/04/23 12:00 Sáb 22/04/23 19:20 0% 24 Hours DISASSEMBLY COOLING MEDIUM SIDE 0%
35 1.4.2.2.1 INLET SPOOL - Torque Break on Upstream flange (8'' x 150) 40 mins Sáb 22/04/23 12:00 Sáb 22/04/23 12:40 33 0% 24 Hours 0%
36 1.4.2.2.2 INLET SPOOL - Torque Break on Downstream flange (8'' x 150)40 mins Sáb 22/04/23 12:40 Sáb 22/04/23 13:20 35 0% 24 Hours 0%
37 1.4.2.2.3 Lifting and remove Inlet Spool (8'' x 150 ) 2h Sáb 22/04/23 13:20 Sáb 22/04/23 15:20 36 0% 24 Hours 0%
38 1.4.2.2.4 Isolate INLET Nozzle flange with test tape 20 mins Sáb 22/04/23 15:20 Sáb 22/04/23 15:40 37 0% 24 Hours 0%
39 1.4.2.2.5 OUTLET SPOOL - Torque Break on Upstream flange (8'' x 150)40 mins Sáb 22/04/23 15:40 Sáb 22/04/23 16:20 38 0% 24 Hours 0%
40 1.4.2.2.6 OUTLET SPOOL - Torque Break on Downstream flange (8'' x 150)
40 mins Sáb 22/04/23 16:20 Sáb 22/04/23 17:00 39 0% 24 Hours 0%
41 1.4.2.2.7 Lifting and remove Outlet Spool (8'' x 2500 ) 2h Sáb 22/04/23 17:00 Sáb 22/04/23 19:00 40 0% 24 Hours 0%
42 1.4.2.2.8 Isolate OUTLET Nozzle flange with test tape 20 mins Sáb 22/04/23 19:00 Sáb 22/04/23 19:20 41 0% 24 Hours 0%
43 1.4.2.3 N2HE LEAK TEST INSPECTION 0,45 dias Sáb 22/04/23 19:20 Dom 23/04/23 06:07 0% 24 Hours N2HE LEAK TEST INSPECTION 0%
44 1.4.2.3.1 Assembly N2He Leak Test equipments 2h Sáb 22/04/23 19:20 Sáb 22/04/23 21:20 42 0% 24 Hours 0%
45 1.4.2.3.2 Gross leak test with nitrogen 20 bar 40 mins Sáb 22/04/23 21:20 Sáb 22/04/23 22:00 44 0% 24 Hours 0%
46 1.4.2.3.3 Check leaking 30 mins Sáb 22/04/23 22:00 Sáb 22/04/23 22:30 45 0% 24 Hours 0%
47 1.4.2.3.4 Helium Injection 1% of Pressure test (24,03 bar) 20 mins Sáb 22/04/23 22:30 Sáb 22/04/23 22:50 46 0% 24 Hours 0%
48 1.4.2.3.5 Increase the pressure with Nitrogem up to 100,75 bar 45 mins Sáb 22/04/23 22:50 Sáb 22/04/23 23:35 47 0% 24 Hours 0%
49 1.4.2.3.6 Increase the pressure with Nitrogem up to 201,5 bar 50 mins Sáb 22/04/23 23:35 Dom 23/04/23 00:2548 0% 24 Hours 0%
50 1.4.2.3.7 Increase the pressure with Nitrogem up to 302,25 bar 1,5 h Dom 23/04/23 00:25 Dom 23/04/23 01:5549 0% 24 Hours 0%
51 1.4.2.3.8 Increase the pressure with Nitrogem up to 403 bar 1,7 h Dom 23/04/23 01:55 Dom 23/04/23 03:3750 0% 24 Hours 0%
52 1.4.2.3.9 Check Maintenance Pressure 1h Dom 23/04/23 03:37 Dom 23/04/23 04:3751 0% 24 Hours 0%
53 1.4.2.3.10 Check gas inlet nozzle with helium detector 15 mins Dom 23/04/23 04:37 Dom 23/04/23 04:5252 0% 24 Hours 0%
54 1.4.2.3.11 Check gas Outlet nozzle with helium detector 15 mins Dom 23/04/23 04:52 Dom 23/04/23 05:0753 0% 24 Hours 0%
55 1.4.2.3.12 Depressurization process, open the all temporary vent valve
1h Dom 23/04/23 05:07 Dom 23/04/23 06:0753;54 0% 24 Hours 0%
56 1.4.2.4 GAS SIDE _ Reinstantement 0,55 dias Dom 23/04/23 06:07 Dom 23/04/23 19:15 0% 24 Hours GAS SIDE _ Reinstantement 0%
57 1.4.2.4.1 Torque Break of Blind flange on OUTLET Nozzle 40 mins Dom 23/04/23 06:07 Dom 23/04/23 06:4755 0% 24 Hours 0%
58 1.4.2.4.2 Torque Break of Blind flange on INLET Nozzle 40 mins Dom 23/04/23 06:47 Dom 23/04/23 07:2757 0% 24 Hours 0%
59 1.4.2.4.3 Lifting and assembly INLET Spool (8'' x 2500 ) 3,5 h Dom 23/04/23 07:27 Dom 23/04/23 10:5758 0% 24 Hours 0%
60 1.4.2.4.4 INLET SPOOL - Bolting on Upstream flange (8'' x 2500) 1,2 h Dom 23/04/23 10:57 Dom 23/04/23 12:0959 0% 24 Hours 0%
61 1.4.2.4.5 INLET SPOOL - Bolting on Downstream flange (8'' x 2500) 1,2 h Dom 23/04/23 12:09 Dom 23/04/23 13:2160 0% 24 Hours 0%
62 1.4.2.4.6 Lifting and assembly OUTLET Spool (8'' x 2500 ) 3,5 h Dom 23/04/23 13:21 Dom 23/04/23 16:5161 0% 24 Hours 0%
63 1.4.2.4.7 OUTLET SPOOL - Bolting on Upstream flange (8'' x 2500) 1,2 h Dom 23/04/23 16:51 Dom 23/04/23 18:0362 0% 24 Hours 0%
64 1.4.2.4.8 OUTLET SPOOL - Bolting on Downstream flange (8'' x 2500) 1,2 h Dom 23/04/23 18:03 Dom 23/04/23 19:1563 0% 24 Hours 0%
65 1.4.2.5 COOLING MEDIUM SIDE _ Reinstantement 0,33 dias Dom 23/04/23 19:15 Seg 24/04/23 03:15 0% 24 Hours COOLING MEDIUM SIDE _ Reinstantement 0%
66 1.4.2.5.1 Lifting and assembly INLET Spool (8'' x 150 ) 2,5 h Dom 23/04/23 19:15 Dom 23/04/23 21:4564 0% 24 Hours 0%
67 1.4.2.5.2 INLET SPOOL - Bolting on Upstream flange (8'' x 150) 45 mins Dom 23/04/23 21:45 Dom 23/04/23 22:3066 0% 24 Hours 0%
68 1.4.2.5.3 INLET SPOOL - Bolting on Downstream flange (8'' x 150) 45 mins Dom 23/04/23 22:30 Dom 23/04/23 23:1567 0% 24 Hours 0%
69 1.4.2.5.4 Lifting and assembly OUTLET Spool (8'' x 150 ) 2,5 h Dom 23/04/23 23:15 Seg 24/04/23 01:45 68 0% 24 Hours 0%
70 1.4.2.5.5 OUTLET SPOOL - Bolting on Upstream flange (8'' x 150) 45 mins Seg 24/04/23 01:45 Seg 24/04/23 02:30 69 0% 24 Hours 0%
71 1.4.2.5.6 OUTLET SPOOL - Bolting on Downstream flange (8'' x 150) 45 mins Seg 24/04/23 02:30 Seg 24/04/23 03:15 70 0% 24 Hours 0%
72 1.4.3 CO2 COMPR. 3rd STAGE Disch. / E-T7543 2,22 dias Seg 24/04/23 03:15 Qua 26/04/23 08:32 71 0% 24 Hours CO2 COMPR. 3rd STAGE Disch. / E-T7543 0%
73 1.4.4 CO2 COMPR. 2nd STAGE Disch. / E-T7542 2,15 dias Qua 26/04/23 08:32 Sex 28/04/23 12:08 72 0% 24 Hours CO2 COMPR. 2nd STAGE Disch. / E-T7542 0%
74 1.4.5 CO2 COMPR. 1st STAGE Disch. / E-T7541 2,15 dias Sex 28/04/23 12:08 Dom 30/04/23 15:4473 0% 24 Hours CO2 COMPR. 1st STAGE Disch. / E-T7541 0%
75 1.5 Desmobilization 0,5 dias Dom 30/04/23 15:44 Seg 01/05/23 03:44 0% 24 Hours 0%
76 1.5.1 Organization of tools 12 h Dom 30/04/23 15:44 Seg 01/05/23 03:44 74 0% 24 Hours Organization of tools 0%

Crítica Tarefa Tarefa Manual Apenas-duração Divisão da Linha Base Resumo do Progresso Resumo de Projeto Tarefa Inativa Prazo

Divisão Crítica Dividir Apenas início Atrasada Marco da Linha Base Sumário Tarefas Externas Marco Inativo Critical

Progresso Crítico Progresso da Tarefa Apenas-conclusão Linha Base Marco Resumo Manual Marco Externo Resumo Inativo Late

Página 1