SAP Project System - A Ready Reference (Part 1) - SAP Blogs
SAP Project System - A Ready Reference (Part 1) - SAP Blogs
Community
Sheetal Deshmukh
May 9, 2008 | 7 minute read
Follow 29 70 67,177
In my first blog you will find the important terms of the PS module. I have tried to
explain them with the help of an example. Following this is the next blog SAP
Project System – A ready Reference ( Part 2 ) where the technicalities of the
same are covered.
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 1/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
”
You create and manage your project structure in SAP R/3 Project System, by
means of work breakdown structures and networks.The WBS describes individual
phases and functions of a project. Network contains the individual project tasks
and the dependencies between them in the form of activities and relationships
Project Definition
Project Definition is general description of the project that you want to manage. It
is a framework laid down for all the objects created within a project. It contains
organizational data that is binding for the entire project.
Phase
Function
Object
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 2/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Individual tasks required to carry out the project is called WBS elements.
Network
The network describes project processing. Thus the Network contains
instructions on how to carry out activities in a specific way, in a specific order and
in a specific time period.Main elements of network are activities and
relationships. It forms the basis for planning, analyzing and monitoring time
schedules, costs, & resources.
Activities
Activities are used to plan project staffing, capacity, material, PRTs, and service
requirements. When activities are assigned to WBS elements, detailed view of
costs, dates, and capacities at WBS element could be obtained. It’s a task in a
network which has a defined start and finish. An activity can be broken down into
activity elements.Three categories of activities in the Project System:·
Internal Activities
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 3/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
External Activities
General Cost Activities
Activity element
Activity element is an activity which is subordinate to another activity. Activity
elements contain the same information as activities.Three categories of activity
elements in the Project System:
Work elements
External Elements
General Cost Elements
Activity Type
It’s a physical measure of activity output of a cost center .e.g. hours, number of
units produced, machine times, production times.
Milestones
Milestones are the events in the project to which particular importance is
attached Or which trigger predefined functions. In general they indicate
transition between different departments or phases. Milestones are assigned to
activities and WBS elements:In PS milestones are used to:
Relationships
You use relationships to depict chronological and technical dependencies
between activities. The relationship determines the nature of the link between the
individual activities. :
Confirmations
It is a part of network control. It documents the state of processing for the
network activities and activity elements. There are two types of confirmations
Partial & Final.Confirmations are used to record:
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 4/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Settlement
As a rule, projects are used to collect and monitor costs, but are not usually the
final cost object. For this reason the costs in atypical project will be settled at the
end of the period.To this end, you store settlement rules in the activity / WBS
element requiring settlement. They contain information on settlement receivers,
cost apportionment and control data. Settlement receivers could be cost centers,
G/L accounts. Etc.
Budget
The budget is the approved cost structure for an action or project in a particular
period.Budgeting differs from cost plan in that it is binding. In the approval phase
you prescribe your project funds in the form of budget. It is possible to allocate
overall and annual budget in parallel.
Work Centers
Work center represents the resources responsible for executing an activity. In a
work center, you can enter the available capacity and an operating time. You can
arrange the work centers in a hierarchy for capacity evaluation purposes.
Internal activities are assigned to work centers (resources) to be completed.A
work center is a physical unit within a company where an activity is performed.
Profit Center
It is subdivision of business organization which is set up for internal management
control purposes. Profit centers divide business up on a management basis. The
basic aim of profit center accounting is to present areas of the business as
entities operating independently in the market.
The first thing that needs to be created in the system is Project Definition. The
entire activity plan for this project will come under this project definition. Overall
budget needs to be estimated, assigned and get approved for the project. Project
timeline needs to be decided. Project could be then subdivided into separate
parts which are actually WBS elements lets say in this e.g. we have 4 main WBS
elements:
1. Land Acquisition
2. Procurement
3. Construction
4. General
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 5/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Now to take an example we will drill down two WBS elements namely Land
Acquisition and Construction.
Above 4 activities should be done in sequence. As in second activity will start only
after request document for the land is completed and so on. Hence these
activities have FS Relationship between them.
It could be sub divided in to floor wise tasks. Let say, we have four story building
and each floor has 4 flats. So under WBS element ‘Construction’ we may create
separate sub WBS element for each floor. Each sub WBS element of floor may be
divided further into last level of WBS elements one for each flat on the floor. This
way we will have hierarchy of the WBS elements.Finally last level of WBS
elements i.e. WBS elements of the flats will have activities like
1. Plumbing
2. Electrical work
3. Flooring
4. Painting
5. Furniture
Let say Plumbing and Electricity work are the external activities as they are given
to a outside contractor. While the other activities are done by company labor so
they are internal activities. Plumbing and Electrical work could be started
simultaneously.While flooring needs be done once the plumbing and Electrical
work is complete. Hence they have FS relationship and so on…. Now if we talk
about milestones:
As I have said that Work center represents the resources responsible for
executing an activity For the above activities, work centers could be the company
labor required for the construction, labor provided by the external service center
for plumbing and Electricity work. while Profit Centers could be the finally
constructed flats.
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 6/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
3 Activities (Under
Plumbing( external Activities)
3rd WBS)
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 7/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Alert Moderator
Assigned Tags
Retagging required
sheetal deshmukh
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 8/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Related Questions
com.sap.engine.lib.injection.InjectionException
By Former Member May 29, 2008
29 Comments
Aditya Varrier
May 11, 2008 at 7:33 pm
Hi Sheetal,
a good blog to understand the terminologies in PS.
Waiting for Part 2.
Great work.
Regards,
Aditya
Like 0 | Share
Former Member
May 11, 2008 at 8:08 pm
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 9/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Like 0 | Share
Former Member
May 11, 2008 at 8:11 pm
Like 0 | Share
Arpil Gupta
May 11, 2008 at 9:08 pm
Like 0 | Share
Former Member
May 11, 2008 at 10:05 pm
Like 0 | Share
Former Member
May 12, 2008 at 3:52 am
A good one . Will really help beginners to understand the concepts of SAP PS.
Like 0 | Share
Former Member
May 13, 2008 at 5:57 pm
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 10/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Hi
Good job.
Both the parts are very much descriptive and can be used as reference for techies.
Starting point for beginners.
Thanks.
Like 0 | Share
Former Member
May 19, 2008 at 11:58 pm
Hi Sheetal,
This is a very useful blog for all the techis...Very simple language and a lot of useful content...
Keep it up.
Thanks
Nayan
Like 0 | Share
VS G
June 12, 2008 at 7:55 am
hi sheetal i am working on a report in PS and need to pull the last posting date with amount spend on the
project.... where can i those.... thank you.
Like 0 | Share
Amaresh Makal
January 5, 2009 at 9:15 pm
Sheetal,
Wonderful job. Any beginner can understand the concept, terminology, and whole picture of PS.
Amaresh
Like 0 | Share
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 11/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Former Member
February 4, 2009 at 4:55 am
Hi Sheetal,
I am very new to PS, and as per our requirement, i need to send a mail to completion of one step. So i need
to link a workflow to the PS.
Thanks,
Runal
Like 0 | Share
Former Member
June 27, 2010 at 10:24 pm
Good attempt
Regards
Kiran
Like 0 | Share
Former Member
July 2, 2010 at 5:50 pm
Hello Sheetal
Muthu
Like 0 | Share
Former Member
August 23, 2010 at 3:17 am
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 12/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Hi shital,
its very gr8 documentation for PS freash consultant.Hope if you have more documentation ,you will
forwards to sdn forum.
Regards,
Mahesh Amale
Like 0 | Share
Former Member
August 10, 2011 at 9:11 pm
The documents created are excellent and very useful to any PS module user.
Can you throw some ligt on how to import network activites from excel sheet. Similarily can i
import Confirmation from a excel sheet.
Regards
SCSharma
GM_Manufactuing systems (using SAP)
Like 0 | Share
Former Member
June 15, 2012 at 8:53 am
Hi Sheetal,
Regards,
Pranav
Like 0 | Share
Former Member
June 25, 2012 at 10:36 am
Like 0 | Share
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 13/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Former Member
June 26, 2012 at 5:02 pm
Hi Sheetal'
Thank you for giving such a valuable information for easy understanding of PS basics.
Regards'
srikanth.
Like 0 | Share
Like 0 | Share
Former Member
July 3, 2012 at 6:29 am
Its really a great thing.Such an effort to make the jargons and business flow comprehensible is really
commendable!!
Like 0 | Share
Former Member
July 31, 2012 at 9:52 am
Great job!
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 14/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Nandha
Like 0 | Share
Former Member
December 27, 2012 at 10:42 am
Hi Sheetal,
Nice blog , Its very good for a beginner irrespective of Techincal or fuctional.
Thanks a lot.
Shekhar
Like 0 | Share
Former Member
July 31, 2013 at 6:08 am
Hello...
Thanks for this usefull blog..really i don't have any idea about PS but after i read this got a basic idea, the
explanation give with the relation of construction excellent and easy to understand..
Like 0 | Share
Hi,
Extremely good blog. Specially for beginners in PS. Looking forward for more like this.
Like 0 | Share
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 15/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
Manuel Robalinho
May 20, 2016 at 1:20 pm
Excelent.
Like 0 | Share
Former Member
March 16, 2017 at 10:55 pm
This is good information, it made my life easier when trying to explain other people with no PS experience.
Thank you!
Like 0 | Share
Rohan Koul
March 26, 2018 at 11:22 am
Great work
Like 0 | Share
Anjikumar Pasumarthy
February 13, 2019 at 8:05 pm
Great work
Like 0 | Share
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 16/17
4/4/23, 4:00 PM SAP Project System – A ready Reference ( Part 1 ) | SAP Blogs
abhilash reddy
April 26, 2022 at 3:42 am
really great blog , please keep posting the other module which you have worked on .
thank you .
Like 0 | Share
Find us on
Trademark
Newsletter Support
https://blogs.sap.com/2008/05/09/sap-project-system-a-ready-reference-part-1/ 17/17