1. Terms of payment
• The terms of payment ) It was not mentioned in the unpriced
commercial offer except for the 15% as an advanced payment).
ARC requests united engineering to submit the terms of
payment mentioned under unpriced commercial offer, so that
it pays 15% of the total contract value as an advance payment
in exchange for opening a bank guarantee letter for the full
value of the contract issued by the Libyan Foreign Bank, and
this credit remains valid Until the issuance of the work
completion certificate, provided that the remaining 85% is
distributed according to the following breakdown:
1.1 Part I (Erection)
o paying 50% of the total value of the erection works
according to the progress monthly works within 30 days
from the date of invoices.
o Paying 5% of the total value of erection works within 30
days from the date of issuance of the initial acceptance
certificate.
o Paying 5% of the total value of erection works after 12
months of issuing the completion certificate for each
tank.
1.2 Part II (supply of material)
o Paying 15% within 30 days of submitting shipping
documents.
o Paying 5 % within 30 days of the receiving materials at
the site and approval by ARC.
o Paying 5% after 12 months of issuing final acceptance
certificate.
• The Acceptance of foreign currency rates will be according to
the bulletin issued by the Central Bank of Libya corresponding
to the closing date of receiving offers on 15/11/2022.
Please accept
• The acceptance of the general conditions contained in the bid
document and the technical and financial requirements it
contains, including a letter of good performance. Please accept
ARC ask United Engineering co. to submit complete technical proposal for tank
preventive maintenance as per tender’s documents and according to API653.
The technical offer shall include the following information including our
amendment in our scope of work, technical specification, BOQ and supply of
materials.
The following required list has been sent to all bidders, the bidder shall submit
the missed ones to fulfil the ARC's requirements, where the final procedures
shall be submitted to ARC for approval prior to commence any work.
1. Tank foundation repair procedure
2. Tank bottom plates replacement and repair procedure
3. Tank shell plates replacement and repair procedure
4. Door sheet opening procedure
5. Welding procedure specification (WPS) and welding procedure
qualification records (PQR) for supporting (WPS)
6. General inspection procedure
7. NDT testing procedures
8. Tank prepare for inspection procedures
9. Reference electrode installation procedure
10. Tank cleaning procedure
11. Surface preparation and coating procedure
12. Painting repair procedure
13. Sphere tank legs replacement procedure
14. Surface preparation and coating inspection procedure
15. Gap filling application procedure
16. Inspection and testing plan (ITP)
➢ To be amend
The following points have been changed in the original scope of work,
technical specification and bills of quantity. Bidders shall amend their
offer accordingly.
4. Materials (ANNEXURE-I)
Materials: Generally, the material used for maintenance of tanks shall
conform to the following Specifications or equivalent as per API 650:
Plates : ASTM A-285 Gr.C / A-283 Gr.C / A-131
Pipes : ASTM A-106 Gr,.B / API 5L / A-53 seamless
Flanges : ASTM A-105 Gr.I
Structural : ASTM A-36
Bolting : ASTM A-193 Gr.B7 and A-194 Gr.2H
Electrodes : Manual Metal Arc Electrodes conforming to
AWS E6010 ER70-3/ E7018
Please confirm amendment accordingly.
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Removal and renewal of tank bottom accessories which is not falling within the
B-6 area of plate replacement such as drain nozzles, bottom sump, roof support To be added
pads and level deck
C- FOUNDATION PAD:
Supply and lay fire proofing (vermiculite cement or equivalent H.D. cement)
C-6.2 including all metal mesh, etc. as detailed in para 4.4.8.4 of section-1 of the M3 40 To be amend
Scope of Work.
C-6.3 Supply and install fire proof coating for 6 hours fire rating M2 498 To be amend
F- FLOATING ROOF:
Partial replacement of existing roof sealing system (HMT stainless steel scissor
F-4 LM 100 30 TO be amend
type).
G- HEATING COILS:
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Complete replacement of heating coils system with all its accessories, with 100%
G-1
radiography of the joints ond hydro test.
including heating
G-1.2 616-SL1 (4) Dia 21.34 m EA 1
element
including heating
G-1.3 616-SL2 (5) Dia 21.34 m EA 1
element
including heating
G-1.8 670S1 A/B & 670 S2B Dia 6.10 m EA 3
element
To be added
G-1.9 615F8(2-6) Dia 42.67 m EA 1 including heating
element
Complete replacement steam trap station unit including steam traps for heating
G-2 EA 10 To be amend
coil system
I PIPING:
Note: The design shall comply with ARC specification and the following Codes
and Standards : (NFPA [11, 15, 25 &30] , API 521 & 2021 and ASQ Q9000)
Note: The design shall comply with ARC specification and the following Codes
and Standards : (NFPA [11, 15, 25 &30] , API 521 & 2021 and ASQ Q9000)
I-5 LPG sphere tanks legs (St33 DIN17100, ASTM/ASME A3553 Gr.B) TO be amend
Replace of LPG spher tank legs pipe Ø 24” Sch.STD40 -(617-LPG 1)& (617-
I-5.1 LM 4222 To be amend
LPG 2) & (617-LPG 3)& (617-LPG 4)
I-5.2 Replace of LPG spher tank legs pipe Ø 12” SCH. 30 (617-LPG3) & (617_LPG4) LM 20 To be added
I-5.23 Replace of LPG spher tank legs pipe Ø 24” Sch.STD40 -(617-LPG 5) LM 36 To be amend
M- PAINTING:
External surfaces of tank shell and all accessories mounted on it such as wind
M-1 girders, ladders, handrail, platforms, external side of foam deflectors and fire M² 18,000
fighting pipes of the tank.
M-3 Internal surfaces of of top 1m portion of tank shell for fixed roof tanks. M² 17,400
M-3 Internal surfaces of tank bottom plates and shell Internal 1ST course M2 800
M-1 External surfaces of fixed roofs including all Accessories mounted on it. M² 8,000
External surfaces of floating roofs including rolling ladder and all other
M-5 M² 13,400
accessories mounted on it
M-6 Loading and unloading lines in the tank boundary wall area. M² 2,300
All internal surfaces of bottom, shell, roof plates and roof supporting structure
M-3 M² 900
of water service tanks.
M-1
External surfaces of spheres including all accessories mounted on it like
M-4 M² 2,400
ladders, platforms, supports, level indicators, hand rails, piping etc.
M-6
M-1 sand papering and cleaning the external surface of tank shell with soap
M-4 solution and water thoroughly and apply one coat of a finish paint as per Para
M² 15,200
M-5 4.12.10 of section 1 of the Scope of Work and painting specifications to match
the colour with the surrounding tanks.
M-6
ESTIM TOTAL
UNIT RATE
DESCRIPTION UNIT AMOUNT REMARKS
QTY (L. D)
(L. D)
Tanks with insulated roofs, the roof plates in these tanks should be coated by (Refer to our
M-4 MASCOAT layer (minimum total thickness of 3mm) instated of the existed M² 1000 notification letter on
mineral wool insulation. 2/11/2022)
The Contractor shall provide training for (20) Owner's Specialist Engineers for a
two weeks period (abroad) at an ASME and API approved training provider,
Including the provision of training materials in various specializations and
T-1 L.S.
accredited certificates (all training expenses shall be included in the
contract price and at the expense of the contractor), provided that ARC
bears travel and accommodation expenses.
UNIT TOTAL
EST.
S.N. DESCRIPTION UNIT RATE AMOUNT Notes
QTY (L.D.) (L.D.)
U-2 Structural:
U- 4 PIPE:
U-8 FLANGES:
U-9 TEE:
U-11 BOLTS: