Proposal For Slope Formation

The document proposes forming slopes and adding greenery on rock fill slopes. It specifies that the rock slope should be finished with a mix of smaller rock particles and soil to a slope no steeper than 1 vertical to 1.5 horizontal. The slope should then be covered with at least 75mm of topsoil and turfed. Payments will be made according to slope formation and embankment turfing items in the bill of quantities.

Uploaded by

Jayaratne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views

Proposal For Slope Formation

The document proposes forming slopes and adding greenery on rock fill slopes. It specifies that the rock slope should be finished with a mix of smaller rock particles and soil to a slope no steeper than 1 vertical to 1.5 horizontal. The slope should then be covered with at least 75mm of topsoil and turfed. Payments will be made according to slope formation and embankment turfing items in the bill of quantities.

Uploaded by

Jayaratne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Proposal for Slope Formation & Greenary Works on Rock Fill Slopes

Minimum 1m Soil Fill

3
1 Rock Fill

Maximum
1V:1.5H slope

1. Rock slope shall be finished with a mix of smaller particles of rock and soil to a slope flatter
than 1V:1.5H.
2. Slope shall be covered with a minimum 75mm layer of top soil.
3. Slope shall be turfed.

Payments shall be made as follows:

Slope formation by BOQ Item 2.5.7

Embankment turfing by BOQ Item 7.1.1


Proposal for Rock Slope Protection in Flood Areas

Minimum 1m Soil Fill

3
1 Rock Fill

Maximum
1V:1.5H slope

1. Rock slope shall be finished with a mix of smaller particles of rock and soil to a slope flatter than
1V:1.5H.
2. Slope shall be covered with a Geotextile.
3. Slope shall be protected with 300mm thick Reno-mat.
4. Fill toe shall be protected with 2m x 1m Gabion.
5. Berm shall be covered with 100mm top soil & be turfed.

Payments shall be made as follows:

Slope formation by BOQ Item 2.5.7

Embankment turfing by BOQ Item 7.1.1

Geotextile by BOQ Item 6.7.1

Gabion by BOQ Item 7.22.2

Reno-mats by BOQ Item 7.22.1