Proposal For Slope Formation
Proposal For Slope Formation
3
1 Rock Fill
Maximum
1V:1.5H slope
1. Rock slope shall be finished with a mix of smaller particles of rock and soil to a slope flatter
than 1V:1.5H.
2. Slope shall be covered with a minimum 75mm layer of top soil.
3. Slope shall be turfed.
3
1 Rock Fill
Maximum
1V:1.5H slope
1. Rock slope shall be finished with a mix of smaller particles of rock and soil to a slope flatter than
1V:1.5H.
2. Slope shall be covered with a Geotextile.
3. Slope shall be protected with 300mm thick Reno-mat.
4. Fill toe shall be protected with 2m x 1m Gabion.
5. Berm shall be covered with 100mm top soil & be turfed.