SP0509 Circuit Breaker Testing SWP
SP0509 Circuit Breaker Testing SWP
Adequate staffing resources with the competencies to safely ES000901R102. HSECH Risk Control Guide
complete the required tasks as per MN000301R165: 8 Level Field MN000301R165. 8 Level Field Test Competency
Test Competency.
SP0509R01 Circuit Breaker Testing Job Safety Analysis
These competencies can be gained from, but not limited to any or
all of the following:- SP0509C01 Circuit Breaker Test Report
Qualifying as an Electrical Fitter Mechanic SP0509C01R01 Circuit Breaker Sample Test Report
Qualifying as a Technical Service Person SP0509C02 Circuit Breaker HV Withstand Test Report.
Training in the safe use of relevant test equipment SP0509C03 Circuit Breaker Testing Competency Assessment
Requirement for all live work: SP0506 Substation Primary Plant and Secondary Systems Field
Testing SWP
Safety Observer (required for all “live work” as defined in the ESO
Code of Practice for Electrical Work). AS 1931 – 1996 – High Voltage Test Techniques Parts 1 and 2
All resources are required to: AS 2006 – 1986 – High Voltage A.C. Switchgear and Controlgear –
Circuit Breakers for Rated Voltages Above 1,000V
Have appropriate Switching and Access authorisations for the
roles they are required to perform and have the ability to assess AS 2650 – 1986 – High Voltage A.C. Switchgear and Controlgear –
and maintain relevant exclusion zones from exposed live electrical Common Requirements
apparatus AS 2467 – 1981 – Maintenance of Electrical Switchgear
Hold current licences for any vehicles and equipment they may be Test Equipment Manual
required to operate.
Circuit breaker Manual / Manufacturer’s Drawings
Required Training
Staff must be current in all Statutory Training relevant for the task.
SP0509
4. KEY TOOLS AND EQUIPMENT (eg barriers, matting) to prevent inadvertent contact with adjacent
live plant or breaching exclusion zones. Furthermore, the P53
Test Equipment within calibration date, tested and tagged Operate the Network Process is applicable at all times for isolation
and earthing.
Safety Barriers
Careful consideration should be taken with the selection and
HVIA Operating Equipment – PED’s, Live Line Tester, Class 0
placement of test leads. Only use appropriately rated test leads
gloves. All equipment to be inspected and confirmed within test
that are placed to be clearly visible to reduce the risk of them
date prior to use
being not seen and removed prior to placing plant back into
PPE including full-length protective cotton clothing, safety footwear, service. Where possible, use leads that are supplied with the test
helmet. Additional PPE as required: brim for safety helmet, leather equipment since these will have suitable connectors and the
work gloves, class 00 gloves, hearing protection, safety eyewear, correct current and voltage rating. Leads should be selected and
high visibility clothing when working on or near roadways. All PPE used such that it is not possible to leave leads connected to the
to be inspected and confirmed within test date (where applicable) plant under test when the test equipment is removed (for example
prior to use an integrated lead set or trifurcated leads).
5.1. Carry out an on site risk assessment Contact with high voltage at CB primary connections.
5.2. All work to be done with circuit breaker de-energised Plant number;
All of the tests described in this SWP should be carried out with Description, ie. dead tank, live tank etc;
the CB de-energised and appropriate control measures in place
SP0509
Rated voltage and insulation level; Consideration shall be given where electronic components are used
in the auxiliary and control circuitry. Different testing procedures
Rated nominal and short-circuit current and duration; and values maybe adopted subject to agreement by the
Commissioning Engineer.
Rated operating sequence;
5.6. Measure Resistance of the Main Circuit.
Interrupting medium;
Measurement shall be made using D.C. current of at least 50A and
Specialised requirements such as:
less than the nominal current rating of the circuit breaker. The test
Rated Transitional Recovery Voltage envelope, Rated Out of shall be conducted as close as practical to ambient temperature.
Phase Breaking Current, Rated Cable Charging Breaking
A four wire ductor should be used for measuring the resistance of
Current, Rated Capacitor Bank Breaking and Inrush Making
the main contacts.
Currents, Rated Small Inductive Breaking Current.
Measure Insulation Resistance.
5.4. Visual inspection of Circuit Breaker condition.
DC insulation tests are to be carried out between terminals of the
Inspect the circuit breaker for any sign of damage or leaks both
circuit breaker as detailed below. Note that these connection
externally and in the circuit breaker marshalling box. Confirm that
arrangements have been specified for consistency with AS2650 and
the interrupting medium level/pressure is correct before
to allow for future insulation condition diagnostic assessment. The
commencing tests and that assembly is complete and no transport
voltage applied will be as per Table 1 for a duration of 1 minute.
bracing has been left in place.
Inspect the external surfaces and ensure the circuit breaker is clean With the circuit breaker in the closed position:
and dry.
A or a to Earth and all other terminals
Check all connections for adequate labelling. The connections
B or b to Earth and all other terminals
should be unambiguous, legibly and adequately marked.
C or c to Earth and all other terminals
5.5. Auxiliary and Control Circuit Voltage Withstand.
The circuit breakers auxiliary and control circuitry shall be subjected With the circuit breaker in the open position:
to a 1 minute power frequency withstand test at 2kV to confirm
insulation integrity. A to Earth and all other terminals
The circuitry shall be considered to have passed if no disruptive B to Earth and all other terminals
discharge occurs during the test.
C to Earth and all other terminals
SP0509
b to Earth and all other terminals AS 2006 – 1986 specifies that normally no dielectric tests are
performed at site on the main circuit, however AS 2067 – 1984
c to Earth and all other terminals
specifies that a 90% power frequency withstand test be carried out
on site after erection. The level of high voltage testing to be applied
A, B and C refer to one set of CB high voltage terminals (eg fixed
is therefore:
contact – top of CB) and a, b, and c refer to the other set of
terminals (eg moving contact – middle of CB) a) Where no HV testing has been carried out at the manufacturer’s
works – 100%.
Minimum acceptance value for new plant is 1,000M.
b) Where HV testing has been carried out at the manufacturer’s
Table 1. Applied Voltages for IR Tests works but subsequent assembly of the HV chamber / bushings
is required on site – 90%.
Primary Voltage Rating Test Voltage in kV
(D.C.) c) Where HV testing has been carried out at the manufacturer’s
works and no on-site assembly is required – No HV withstand
Up to 1kV 1 test.
Note – test both trip coils. Time travel measurement is required for An insulation resistance test is to be repeated after the HV
110 kV and above CBs or any CBs assembled on site. withstand test to confirm that insulation degradation has occurred.
Measure spring charge time following close operation.
SP0509
SP0509
SP0509